HomeMy WebLinkAboutItem 06.gOctober 3, 2011 CHANGE ORDER NO. 2 WITH FRIEDGES LANDSCAPING, INC. FOR CONSTRUCTION OF STONEBOROUGH PARK — CITY IMPROVEMENT PROJECT #11 -05 Proposed Action Staff recommends adoption of the following motion: Move to authorize Mayor and City Clerk to execute Change Order No. 2 with Friedges Landscaping, Inc. for construction of Stoneborough Park. Overview On May 2, 2011 the Mayor and City Clerk executed an Agreement with Friedges Landscaping, Inc. for the construction of Stoneborough Park at a cost of $188,857.50. On July 5, the Mayor and City Clerk executed Change Order #1 in the amount of $6,606.33. Over the past several months, Friedges Landscaping, Inc. has completed over 90% of the construction of the park, including installation of trail, curb for playground, shelter construction, landscaping, ballfield and backstop along with seeding on the site. A separate contractor has also installed the playground. At this time staff is recommending approval of Change Order No. 2 equaling $1,500.00. This change order is a result of additional black dirt, grading and repair of erosion control measures required after a torrential rain of over 4" in July, which flooded the entire park and segment of trail behind the homes in area. The new contract price is as follows: Contract price prior to Change Order Net increase resulting from Change Order No. 1 Net increase resulting from Change Order No. 2 Current contract price including Change Order No. 1 & 2 Primary Issues to Consider 0 Is the cost of Change Order No. 2 fair and reasonable? Yes, $1,500.00 cost to re- grade the site, add some additional black dirt and repair the erosion control measures on the site along with re- grading the baseball infield is a reasonable price. Supporting Information a Change,Order No. 2 ohn Hennen ark Maintenance & Operations Mgr Item No. $188,857.50 6,606.33 1,500.00 $196,963.83 Financial Impact: $196,963.83 Budgeted: YIN Y Source: Park Ded Fund Related Documents (CIP, ERP, etc.): Notes: # DESCRIPTION ADD DEDUCT 1 Storm Damage: Additional work related to large, but brief, storm damage that required repair work to the park and erosion control measures. 1,500.00 Total Contract Sum (Including all Change Orders to Date):1 $196,963.83 TOTAL CHANGE ORDER ADDS AND DEDUCTS: 1,500.00 - NET CHANGE ORDER TOTAL: $1,500.00 Contract Summary to Date Original Contract Sum: 188,857.50 Net Change by Previously Authorized Change Orders: 6,606.33 Net Change of this Change Order: 1,500.00 Total Contract Sum (Including all Change Orders to Date):1 $196,963.83 Change Order #2 Contract Change Order for: Stoneborough Park Development City of Lakeville, MN 20195 Holyoke Avenue Lakeville, MN 55044 To j Contractor): Friedges Landscaping, inc. 9380 - 202nd Street West Lakeville, MN 55044 Consultant: Brauer & Associates, Ltd. 10417 Excelsior Blvd. - Suite One Hopkins, MN 55343 Contractor: Friedges Landscaping, Inc. 9380 - 202nd Street West Lakeville, MN 55044 Owner: City of Lakeville, MN 20195 Holyoke Avenue Lakeville, MN 55044 CHANGES TO THE CONTRACT (The contractor shall make the following changes to the contract) City Clerk Page 1 of 1 Distribution To: ❑ Owner ❑ Consultant ❑ Contractor ❑ Field ❑ Other Initiation Date: 22 -Aug -11 Consultants Protect: #11 -02 Date Mayor Signature Date Dpe Date