HomeMy WebLinkAbout12-003CITY OF LAKEVILLE
RESOLUTION NO. 12 -03
RESOLUTION OF SUPPORT
DAKOTA COUNTY 2012 -2016 CAPITAL IMPROVEMENT PROGRAM (CIP)
WHEREAS, Dakota County has asked cities and townships to request projects for
inclusion in the Dakota County 2012 -2016 Transportation CIP; and
WHEREAS, the following transportation projects contained in the County CIP are
important to the City of Lakeville:
Project
Year
CSAH 9 (Dodd Blvd.) - CSAH -46/2 (Scott Co.) to 215 St. (CSAH -70) (Design)
DCP 9 -46 - 2012
CSAH 9 (Dodd Blvd.) — 185 St. (CSAH -60) to Hayes Ave. (Design /ROW Acquisition)
DCP 9 -42 - 2012
CSAH -50 (Kenwood Tr.) /Dodd Blvd. (CSAH -9) - Signal Projects (Construction)
DCP xx -xx — 2012
CSAH 9 (Dodd Blvd.) - CSAH -46/2 (Scott Co.) to 215 St. (CSAH -70) (ROW Acquisition)
DCP 9 -46 - 2013
CSAH 9 (Dodd Blvd.) — 185 St. (CSAH -60) to Hayes Ave. (Construction)
DCP 9 -42 - 2013
CSAH 50 (Kenwood Tr.) - Roundabout at CSAH 60 (185 St.) (Design /ROW Acquisition)
DCP 50 -17 - 2013
CSAH 9 (Dodd Blvd.) - CSAH -46/2 (Scott Co.) to 215 St. (CSAH -70) (Construction)
DCP 9 -46 - 2014
CSAH 50 (Kenwood Tr.) - Roundabout at CSAH -60 (185 St.) (Construction)
DCP 50 -17 - 2014
CSAH 9 (Dodd Blvd.) -Hayes Ave. to CSAH -23 (Cedar Ave.) (Design)
DCP 9 -43 - 2016
CSAH 70 (21 0 St.) — W. Co. Line to Laredo Path (Bike /Ped Trail - Design)
DCP 70 -xx - 2016
County participation contingent upon receipt of Federal Funding.
3 Assumes full or partial right -of -way dedication through platting. Right -of -way dedication must occur prior to roadway
construction.
and
WHEREAS, in the last five years the City of Lakeville has financed its share of costs
for several County roads and State interchanges; and
WHEREAS, the City of Lakeville has issued debt in the form of general obligation
bonds, street reconstruction bonds, and municipal state aid bonds and has raised property
taxes to cover its share of costs.
NOW, THEREFORE, BE IT RESOLVED that the City of Lakeville hereby supports
these projects and requests that these projects be included in the Dakota County 2012 -2016
Transportation CIP for construction in the year indicated and financed with county, state or
federal funding sources as follows:
• The County will request payment of the City's share of the project costs (i.e.
design, right -of -way acquisition, construction) once the project is completed rather
than periodic payments; and
The City will advance encumber $1.1 million of Municipal State Aid Street Funds
(MSA) in 2014. If the Minnesota Department of Revenue does not grant the
advance encumbrance, the County will defer payment from the City until 2017.
APPROVED this 3 day of January, 2012.
ATTEST:
6 4�UJ 1 57
Charlene Friedges, ty Clerk
By: rv'e"
Mark Bellows, Mayor