HomeMy WebLinkAboutItem 06.gDate: 16 April 2012 Item No. RESOLUTION ACCEPTING BIDS AND AWARDING THE CONTRACT FOR THE 2012 LAKE MARION TRUNK SANITARY SEWER REHABILITATION TO VISU -SEWER INC. Proposed Action Staff recommends adoption of the following motion: Move to accept bids for 2012 Lake Marion trunk sanitary sewer rehabilitation, City Project 12 -08, and award the contract to Visu- Sewer, Inc. Passage of this motion enables the relining of approximately 5,664 feet of sanitary sewer main. Overview This project involves a 27 -inch sanitary sewer trunk line that runs along Jasper Terrace and Kenwood Trail to Ipava Avenue. This particular section of pipe is subject to the deteriorating effect of hydrogen sulfide gas which forms a weak acid and, over time, softens the walls of the concrete pipe. Relining the pipe with cured in place pipe will reinforce the existing pipe and eliminate the effects of the gas. Cured in place pipe is a resin impregnated felt liner that is inserted in the pipe and expanded with hot water against the pipe walls and cured until it hardens. The City solicited bids on February 23, 2012 and opened bids on Friday, April 6. Six companies submitted bids; the lowest responsible bid was received from Visu -Sewer Inc. in the amount of $564,244.00. The scope of work includes the sewer relining and the sealing of manholes to eliminate potential sources of inflow and infiltration. Funding is available within the Sanitary Sewer operating budget to meet the full cost. Primary Issues to Consider • Is pipe relining necessary? Yes, if left alone the acid from the hydrogen sulfide gas will cause the concrete pipe to fail. Supporting Information • A copy of the bid - .1-- ' and contract are attached. Air i C r stoph :.I. l etree Public Works Director Financial Impact: $564,244.00 Budgeted: Yes Source: 7714.6295 and 7710.6295 Related Documents (CIP, ERP, etc.): Notes: RESOLUTION ACCEPTING BIDS AND AWARDING THE CONTRACT FOR THE 2012 LAKE MARION TRUNK SANITARY SEWER REHABILITATION TO VISU -SEWER INC. WHEREAS, the advertisement for bids for the 2012 Lake Marion trunk sanitary sewer rehabilitation, City Project 12 -08, was officially published on 23 February 2012, and WHEREAS, sealed bids for water treatment chemicals were opened at 2:30 p.m. on 6 April 2012, and WHEREAS, the lowest responsible bidder for the trunk sanitary sewer rehabilitation was Visu- Sewer, Inc., 7905 Beech Street NE, Fridley, Minnesota 55432. NOW, THEREFORE, BE IT RESOLVED, that the bids are accepted for the 2012 Lake Marion trunk sanitary sewer rehabilitation, City Project 12 -08, and the contract is awarded to Visu- Sewer, Inc. APPROVED AND ADOPTED this 16 day of April 2012 by the City Council of the City of Lakeville. ATTEST: Charlene Friedges, City Clerk CITY OF LAKEVILLE RESOLUTION NO: CITY OF LAKEVILLE Mark Bellows, Mayor Grand Total Bid c ,0'ega '799 I pD ' / J4 .. 1 - 'rib oo'fIbr ; 00 "7'66 7- 9J6 QQ LGZ8 Addendum No. 1 Received 547 F 572 9 / v(,L ( %s) puo8 p!9 a c s. 0/ Th © S Contractor 'Sak Construction 'Michels Corporation 'Insituform Technologies, LLC 'Visu -Sewer Clean & Seal, Inc. 'Lametti & Sons, Inc. Veit Companies o • n V c 6 a u d v 0 a 2012 Lake Marion Trunk Sanitary Sewer Rehabilitation Project No. 12-08 Contractor Count: 6 Owner: City of Lakeville, MN City Project No. 12-08 Bidders List CONTRACT AGREEMENT THIS AGREEMENT, made and entered into as of the 16 day of April, 2012, by and between the City of Lakeville, hereinafter called "Owner" and Visu- Sewer, Inc., doing business as a corporation, hereinafter called "Contractor." WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned: 1. The Contractor will commence and complete the construction of the 2012 Lake Marion Trunk Sanitary Sewer Rehabilitation, City of Lakeville, Minnesota Improvement Project No. 12 -08. 2. The Contractor will furnish all of the material, supplies, tools, equipment, labor and other services necessary for the construction and completion of the project described herein. 3. The Contractor will complete the work required by the Contract Documents within the specified completion dates unless the period for completion is extended by the Contract Documents. 4. The Contractor agrees to perform all of the work described in the Contract Documents for the sum of $565,244.00. This sum includes all applicable taxes. 5. The term "Contract Documents" means and includes the following: (A) Instructions to Bidders (B) Bid Form (C) Affidavit of Non - Collusion (D) Notice of Award (E) Notice to Proceed (F) Contract Agreement (G) Bid Bond (H) Performance Bond (I) Payment Bond (J) Withholding Affidavit (K) General Conditions (L) Supplementary Conditions to General Conditions (M) Supplementary General Requirements (N) Supplementary Special Provisions (0) Addendum 6. The Owner will pay to the Contractor in the manner and at such times as set forth in the General Conditions such amounts as required by the Contract Documents. 7. This Agreement shall be binding upon all parties hereto and their respective heirs, executors, administrators, successors and assigns. COPYRIGHT. Contractor shall defend actions or claims charging infringement of any copyright by reason of the use or adoption of any designs, drawings or specifications supplied by it, and it shall hold harmless the City from loss or damage resulting there from. PATENTED DEVICES, MATERIALS, AND PROCESSES. If the contract requires, or the Contractor desires, the use of any design, devise, material or process covered by letters, patent or copyright, trademark or trade name, the Contractor shall provide for such use by suitable legal agreement with the patentee or owner and a copy of said agreement shall be filed with the City. If no such agreement is made or filed as noted, the Contractor shall indemnify and hold harmless the City from any and all claims for infringement by reason of the use of any such patented designed, device, material or process, or any trademark or trade name or copyright in connection with the services agreed to be performed under the contract, and shall indemnify and defend the City for any costs, liability, expenses and attorney's fees that result from any such infringement. 2012 LAKE MARION TRUNK SANITARY SEWER REHABILITATION Contract Agreement CITY OF LAKEVILLE PROJECT NO. 12 -08 IN WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized officials, this Agreement in triplicate, each of which shall be deemed an original on the date first above written. OWNER: CITY OF LAKEVILLE STATE OF MINNESOTA COUNTY OF DAKOTA: BY: AND: The foregoing instrument was acknowledged before me this 16th day of April, 2012 by Mark Bellows and by Charlene Friedges, respectively the Mayor and the City Clerk of the City of Lakeville, a Minnesota municipal corporation, on behalf of the corporation and pursuant to the authority granted by its City Council. CONTRACTOR: BY Mark Bellows, Mayor Charlene Friedges, City Clerk NOTARY PUBLIC Its STATE OF MINNESOTA COUNTY OF The foregoing instrument was acknowledged before me this day of , 2012, by the corporation, on behalf of the corporation. NOTARY PUBLIC 2012 LAKE MARION TRUNK SANITARY SEWER REHABILITATION Contract Agreement CITY OF LAKEVILLE PROJECT NO. 12 -08