HomeMy WebLinkAbout03-26-12 WSMinutes
Lakeville City Council Work Session
March 26, 2012
In attendance: Mayor Mark Bellows
Council Member Laurie Rieb
Council Member Kerrin Swecker
Council Member Matt Little
Council Member Colleen LaBeau
Staff: Steve Mielke, City Administrator
Dennis Feller, Finance Director
Steve Michaud, Parks and Recreation Director
Chris Petree, Public Works Director
John Hennen, Park Maintenance and Operations Manager
Zach Johnson, Interim City Engineer
Judi Hawkins, Deputy City Clerk
The meeting was called to order at 6:00 pm.
ITEM #3 — Highview Avenue/ 190 Street Traffic Study Update.
Public Works Director Chris Petree stated that in order to promote a strong
transportation system for the City, SRF had been retained to conduct a traffic study and
analysis of Highview /Holyoke Avenue and the area of 190 Street. Interim City
Engineer Zach Johnson stated that the purpose of the study was to identify whether
the existing configuration allows traffic to function at a high level and to determine if
there are any traffic control improvements that are required today or in the future. The
study coincided with the development of the Crescent Ridge Third Addition plat and
looked at current and anticipated traffic counts. The existing conditions analysis
determined that the area functions well today with an "A" rating.
The second part of the study was a future conditions analysis, based on a full build -out
anticipated in 2030. This model predicts that with the current roadway layout the
intersection will function poorly and forecasts long traffic delays. Based on that
information, two design options were presented which would ensure that improved
intersections would operate at an A or B level of service. The first option would be to
install a traffic signal and designated turn lanes at the Highview Avenue and 190
Street intersection and construct a concrete median on 190 Street so the future 190
Street and Harappa Avenue intersection will be restricted to right in /right out. The
second option is to relocate the Highview Avenue 'S' curve to the north and create a
roundabout intersection at Highview Avenue/ 190 Street, in order to eliminate the off-
set "T" intersections. Both options show improved, and acceptable levels of service in
2030.
City Council Work Session
March 26, 2012
Page -2-
Council Member Swecker asked if realigning Highview would push the issue off to
future years when those areas to the north are developed. Johnson stated that the
existing layout could be utilized which would lessen the impact or implications for
developers of the adjacent property. The City would incur maintenance costs for the
traffic signal and the T' intersections, which are less desirable in the transportation
system, would still exist. Because Crescent Ridge Third developed earlier than the
surrounding areas, it was added as a future traffic generator. The project is anticipated
in approximately 2025.
In response to some residents' questions staff looked at other improvement
opportunities. Some ROW clearing has been done to improve sight lines. For improved
safety staff is also proposing to extend the bituminous pavement by about 200 feet to
the east and west of the 190 Street intersection so gravel does not spill onto the
bituminous of Highview Avenue.
Council Member LaBeau stated that she has lived in this area for about 20 years and in
that time there have been six deaths on that curve. New developments will generate
additional traffic on 190 Street cutting through from Highview Ave. to Cedar. Mr.
Mielke stated that improvements on that section of 190 Street will be completed in
conjunction with development and there are currently no development plans.
Development proposals could be explored for a small portion of the adjoining
(Schweich) property which is within the MUSA. LaBeau suggested the roundabout to
be constructed at Dodd Blvd. and Highview Avenue will mean more continuous traffic
in the area, which will also have an impact. She believes it is important to get this
project accomplished due to the number of accidents. Johnson stated that the traffic
analysis did take the number of accidents and potential causes into consideration, and
the existing configuration meets minimum requirements.
LaBeau stated that she understood that several years ago the previous developer of
Crescent Ridge had been required to straighten the curves in Highview Avenue
through the plat. She wondered what has changed and why there is not a similar sense
of urgency to get the project done now. Mielke explained that the initial plat for
Crescent Ridge included moving the curve into the development. Under the original
plan the developer, Joe Miller, agreed to pay for the road project but as the economy
declined, it was not financially feasible for him to do so. The City dropped the
requirement at that time. Swecker stated that straightening the curves on Highview
has been discussed for a long time. She is not convinced that either of these proposed
options are the perfect solution. Johnson agreed that the Highview Avenue roadway
situation is challenging.
Little asked if staff is concerned that the desired land might not be available in the future
for the proposed roadway. Mielke stated that if the project can be designed and
approved, the City can work with future developers on implementation. Funding
options need to be addressed, since policies may be changed for sharing the cost of
collector road improvements. LaBeau asked about future traffic signals at 185 Street.
City Council Work Session
March 26, 2012
Page -3-
Mielke stated that 185 St. is proposed to be a very busy road and traffic signals will
likely be needed.
Staff is recommending that the two connections of 190 Street to Highview Avenue will
be upgraded in 2012 with additional bituminous pavement for safety purposes. Council
had no further questions.
ITEM #4 — Ipava Avenue Pedestrian Crossing near Century Middle School
Public Works Director Chris Petree stated that the pedestrian crossing was installed in
2011 as part of the Safe Routes to School (SRTS) Federal Aid program. The crossing
meets the minimum requirements for pedestrian crossings in the Manual on Uniform
Traffic Control Devices (MUTCD), however, following the installation there were several
requests from the school district and residents to further improve the safety of the
crossing. An analysis of the crossing found that sight line obstructions exist for vehicles
traveling northbound on Ipava as they approach the intersection. Staff recommends
removal of five crabapple trees from the median and seven ash trees from the boulevard
in an effort to improve motorists' view of the crossing. Relocating the crabapple trees to
a park or another location in the city might be possible. Staff also recommends
installation of a push- button activated pedestrian flasher system. Total cost of
implementing both recommendations is approximately $36,000.
Funding is available as a result of favorable bids on other projects. Council Member Rieb
asked if the school district has been approached to share in the cost. Petree stated that
he had suggested this to CMS principal but has not received a return call. He is
prepared to proceed regardless of whether the school district chooses to participate.
LaBeau asked about ongoing maintenance costs. Petree stated that because the flasher
system is solar powered, there is no monthly electrical operating expense; the LED lights
would be energy efficient, and the equipment would last about 20 -25 years. The
project could be completed in the summer of 2012.
Mielke added that the police have increased their presence and enforcement to improve
safety at the crossing. Little suggested that a policy be implemented to always ask the
school district for cost sharing in these situations. Council members directed staff to
proceed with the project and request cost sharing assistance from the school district.
ITEM # 1 — Heritage Center Update
John Hennen presented the results of the Heritage Center bids that were opened on
March 20 The construction manager re- packaged the bid categories into what he felt
would result in the best possible bids. Hennen stated that over 75 contractors' bids
were received and based on the apparent low bids, the revised estimated cost of the
project is $1,095,524, a decrease of approximately $24,000 from the estimated budget.
City Council Work Session
March 26, 2012 Page -4-
Mielke stated that the construction manager re- packaged the categories of work
compared with what had been reviewed previously may have created some confusion
with the description of the work; however, the scope of work to be accomplished is the
same. The same improvements are included, but some of the configurations and
terminology were changed for bidding purposes. Additional background work will be
completed before the apparent low bids are brought to Council on April 2 for
consideration. Some revisions in the bids are still possible.
LaBeau stated that some items' costs that she would expect to be straightforward, such
as concrete, heating, etc., vary significantly from earlier estimates, while other bids such
as electrical and plumbing seem to have been underestimated originally. She is
concerned that all the funding mechanisms for the project are not in place. She asked if
additional restrooms or showers would be installed and if there would be funds
available in the contingency fund to repair the roof. Mielke stated that nothing in the
plan has changed. The bids were not underestimated, but the inconsistencies were due
to the packaging of the bids. He suggested that the packaging could be reviewed by
Council prior to considering approval of the bids. The construction manager will be at
the April 2 meeting and will be able to answer Council's questions.
Michaud stated that there are several factors that could cause a deviation in bids and is
encouraged that bids on the total project are under estimates. LaBeau is disappointed
that the bids are not even lower, and she wants to be able to provide an explanation to
those who have been asking her about the estimates.
Dennis Feller stated that the favorable bids reduced the total project budget by
$24,000, down to $1,095,000. In addition, the City's reimbursement to the CDA from
the original CDBG Senior Center grant will be reduced. Due to these factors, the overall
total fundraising goal has dropped from $337,000 to $260,000. With $55,000 already
raised, plus a total commitment of $15,000 from the Rotary and Lions, total fundraising
of $190,000 remains.
An interim financing source is needed for cash flows until the sale of the senior center is
complete and final fundraising goals are met. Staff had recommended using either the
Park Dedication Fund or the Liquor Fund, however, Council had expressed concern
about using Park Dedication funds. Council was asked to consider use of liquor
operation funds or the general fund. There are adequate balances in both funds.
Swecker believes that the past practice of using the Liquor Fund balance for building
purposes makes it the appropriate choice. She would not be in favor of using the Park
Dedication Fund. Rieb asked about park dedication funds from the Hosanna senior
project. Feller stated that those funds are already included in this financing package.
LaBeau stated that she does not support borrowing from either liquor fund or park
dedication fund. She believes the project is not self - sustaining and there will be
additional operating expenses for the new building. She does not support borrowing
the funds and was hoping the bids would be lower.
City Council Work Session
March 26, 2012
Page -5-
Little acknowledged that there were concerns about selling the Senior Center before
going ahead with the project, but believes that a better offer could come later on as the
economy improves. He would choose to use Liquor Funds as interim financing.
LaBeau asked if there had been any interest from potential buyers. Mielke stated that
there had been a few people who had looked at it, but no offers had been received.
LaBeau asked the cost to leave the building vacant. Feller estimated about $ 7,000 a
year. It was suggested that the building could be converted for a rental, if the Council
desired.
LaBeau asked what building projects the Liquor Fund has been used for and the criteria.
Feller mentioned fire stations, city hall additions, ice arenas, park improvements, and
many other building projects. Mielke stated that there are no statutory limitations on
what the funds can be used for; it is at the discretion of the Council.
Mayor Bellows stated that the former police station is a monument to government
ineptness and inefficiency. Taxpayer money has been used to maintain the building for
the last several years when those funds could have been used to pay down debt. He
believes the police station should have been sold years ago, and that the senior center
should be sold before the project proceeds. Swecker agreed that it should have been
put on the market when the police moved out of it.
Little asked LaBeau if there was another option for financing that she would be
amenable to, other than the Liquor Fund. He would like to have the most support
possible from the Council and asked if there was another option that she would find
acceptable. LaBeau stated that she continues to oppose the project. She doesn't
believe the seniors or the community are totally engaged in the project and would like
the funding to be clearer.
Michaud stated that in the last six months there has been just over $100,000 raised,
including several commitments which will be received in increments. Other initiatives,
including a program to sell chairs, will be announced soon. Grant applications have
been submitted to various agencies and Council will be kept informed of any
procurements. The possibility of room sponsorships was discussed. Michaud stated that
there will be several methods of recognizing sponsors with plaques. Little suggested
engaging the public through social media.
In summary, staff recommends the revised estimated project budget as a result of the
apparent low bids. A majority of the Council supports using Liquor Funds for interim
financing. Fundraising and grant writing efforts will continue. The construction
manager will be at the Council meeting on April 2 to answer Council's questions.
City Council Work Session
March 26, 2012
ITEM #2 - Kenrick Trail Project/ Grant
Page -6-
Michaud stated that the City of Lakeville has worked with the Bury family for many years
in an attempt to purchase the Lake Marion bluffs and 3,500 feet of shoreline for the
purpose of extending the Kenrick Avenue trail; however an agreement has not been
reached. Dakota County also attempted to assist with the purchase without success.
Staff has concluded that the best alternative is to relocate the trail to the south side of
195 Street while waiting to secure the desired trail segment when the Bury property is
developed. In 2009 the City of Lakeville was successful in securing a $1 M federal grant
for the Kenrick Avenue trail project. Because the trail is being relocated from the
original proposed location for which the grant was awarded, staff is working with the
MNDOT and the Metropolitan Council and anticipates final approval soon.
The original project was programmed in the State Transportation Improvement Plan for
FY 2014, however since the plans are approved and the project is ready to go, a request
was made for advance funding so construction can begin in 2012. Trail Improvement
Funds are proposed to finance the project until the City receives reimbursement from
the federal grant. The required matching grant of $460,000 is available through Park
Dedication Funds and Dakota County has tentatively agreed to contribute a minimum
of $22,000. The earliest grant reimbursement would be in July 2013.
Council is being asked to authorize staff to move the project forward with the interim
funding from the Trails Capital Improvement Program.
Swecker asked if there was any reason that the grant funding would not come through
as scheduled. Chuck Rickart, WSB & Associates Project Manager, stated that the project
has been approved and funds have been allocated for 2014; however, reimbursements
could possibly be available sooner. Rickart stated that soil removals and grading might
be accomplished in 2012 but most likely not any of the actual construction items.
Swecker expressed concerns for the interference this project might have on traffic along
205 which will increase with the opening of the Walmart. Rickart stated the project
would have little impact on traffic this year since work will be off -road, but perhaps more
next year with gravel hauling and paving. Bids for this project were 6% under the
engineer's estimate.
LaBeau asked how bidders are held to their bids for asphalt when petroleum and labor
costs are going up so rapidly. Rickart stated that bids have been favorable, but there is
no guarantee. LaBeau suggested offering a discount to the contractor to offset future
price increases. Rickart stated an alternate bid might be possible for doing the project
earlier; however, whether there would be a cost savings is speculative. A mandatory
fuel escalation clause is in the bid package. Mielke stated that using the bid alternate
will include a financial analysis to see if further advance funding would be
advantageous.
City Council Work Session
March 26, 2012
Page -7-
Mielke clarified to Council that even though the estimated cost for the 205 Street
roundabout was higher than anticipated, the project has not been cancelled. This item
will be added to the April work session for discussion and Council direction.
ITEM #5 — Other
Lakeville Arenas
The Lakeville Arenas Board will pay for some fencing around the parking lot at the
Ames Arena to discourage illegal parking on school grounds. The school district
has authorized split rail fence to be placed in strategic locations.
ITEM #7 — Adjourn
The meeting adjourned at 7:40 p.m.
Respectfully submitted,
J i Hawkins
Deputy Clerk
Mark Bellows
Mayor