HomeMy WebLinkAboutItem 06.g- ]fle Date: 14 March 2013 Item No. FINAL ACCEPTANCE AND APPROVAL OF FINAL PAY ESTIMATE 2011 Street Reconstruction Project, Improvement Project 11 -02 Proposed Action Staff recommends adoption of the following motion: Move to approve final acceptance and final payment to BCM Construction, Inc., for the 2011 Street Reconstruction Project, Improvement Project 11 -02. Overview BCM Construction, Inc. is requesting final acceptance and final payment of Pay Estimate No. 6 in the amount of $30,887.05 for 2011 Street Reconstruction Project, Improvement Project 11 -02. Attached is a summary page of the final estimate. The original contract amount was $1,817,616.40. The final contract amount is $1,825,284.36. Additional work, including a water main lowering where City as -built information for the project area was incorrect, was added to the project. All necessary paperwork, including lien waivers, the IC- 134's, Maintenance Bond and Consent of Surety to Final Payment has been submitted. Primary Issues to Consider • Was all work satisfactorily completed? All work was satisfactorily completed and the contractor has met the administrative requirements for final payment. Supporting Information • Letter recommending final acceptance and payment from the City's consulting engineer, WSB & Associates, Inc., dated March 7, 2013 • Letter from Dan Behrens, BCM Construction, Inc., dated March 7, 2013 • Final Pay Request Public Works Director Financial Impact: $30,887.05 Budgeted Related Documents (CIP, ERP, etc.): Notes: Yes Source: Project 11 -02 W SB Yp B & AY alift - f f , f ' engineering planning• environmental• construction March 7, 2013 Mr. Chris Petree Public Works Director 18400 Ipava Avenue Lakeville, MN 55044 Re: Final Acceptance of Street and Public Utility Improvements 2011 Street Reconstruction Project City Project No. 11 -02 WSB Project No. 1715-72 Dear Mr. Petree: 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763 - 541 -4800 Fax: 763 - 541 -1700 BCM Construction, Inc. is requesting final acceptance of the street and public utility improvements within the 2011 Street Reconstruction Project area. The streets and utilities were constructed and approved in 2011. The utility improvements for the above reference project have been tested and approved by WSB & Associates, Inc. and the City's Public Works Department. All of the necessary paperwork has been submitted. We recommend approval of final acceptance of the public streets and utilities within the 2011 Street Reconstruction Project area. Thank you for the opportunity to provide input into this matter. If I can be of any further assistance, please contact me at 763 - 287 -7187. Sincerely, P tWSB fk4 & AssoZ c. Monica Heil, PE Project Manager Attachments cc: Scott Parker, BCM Construction, Inc. St. Cloud • Minneapolis • St. Paul Equal Opportunity Employer wsbeng.com KA01715- 7ZAdmin \Con9raetion Adanin \3 713 Letter of Recommendation -Final Acceptance.do- t'3i��MDINGa — EXC4 VA �'ING cm March 7, 2013 City of Lakeville 20195 Holyoke Avenue Lakeville, MN 55044 RE: Final Acceptance of Street and Utility Improvements BCM Construction, Inc respectfully requests that the City of Lakeville provide for final acceptance of the street and utility improvements for the 2011 Street Improvement Contract, City Project 11 -02. BCM is requesting final payment and acceptance be authorized at the March 18, 2013 City Council meeting. We believe all documentation required for final acceptance has been submitted and reviewed. If there is anything additional please advise. We would like to thank the City for the opportunity to have the contract on this improvement project and look forward to working for the City again. Sincerely, Dan L. Behrens, P.E. President cc Monica Heil WSB &Associates 15760 Acorn Trail - P.O. Box 37 - Faribault, Minnesota 55021 - Phone: 507 - 333 -1155 - Fax: 507 - 333 -1170 Equal Opportunity Employer A SS iSe Assockdrs, Inc. Pay Voucher LKVL - 2011 Street Reconstruction Project Client Contract No.: Project No.: 01715 -72 Client Project No.: 11 -02 Date: 7/16/2012 Request No.: 6 & FINAL Project Summary 1 Original Contract Amount $1,808,150.90 2 Contract Changes - Addition $9,465.50 3 Contract Changes - Deduction $0.00 4 Revised Contract Amount $1,817,616.40 5 lValue Completed to Date $1,825,284.36 6 Material on Hand $0.00 7 Amount Earned $1,825,284.36 8 Less Retainage $0.00 9 Subtotal $1,825,284.36 10 Less Amount Paid Previously $1,794,397.31 11 Liquidated Damages $0.00 12 AMOUNT DUE THIS PAY VOUCHER NO. 6 & FINAL $30,887.05 I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER. Recommended for Approval by: WSB & dissociates, Iryc. 't A"; Approved by Contra or: BCM Constructio Specified Contract Completion Date: 10/15/2011 Comment: Owner: City of Lakeville 20195 Holyoke Avenue Lakeville, MN 55044 -8339 For Period: 111912012 to 6/3012012 Contractor: BCM Construction, Inc. 15760 Acorn Trail Faribault, MN 55021 Construction Observer: Pace 1