RESOLUTION ACCEPTING AND APPROVING THE GRANT AGREEMENT BETWEEN
THE CITY OF LAKEVILLE AND THE MINNESOTA DEPARTMENT OF
TRANSPORTATION FORTHE CONSTRUCTION OF BRIDGE NO. 19565,
THE 168TH STREET BRIDGE
(S.A.P.188- 594 -001)
Proposed Action
Staff recommends adoption of the following motion: Move to approve a resolution accepting
and approving the grant agreement between the City of Lakeville and the Minnesota
Department of Transportation for the construction of Bridge No 19565 the 168 Street
Bridge, S.A.P. 188-594-001.
Overview
On January 9, 2012 the City Council approved a resolution seeking State Aid Bridge Bonds
funds to replace the 168th Street Bridge over North Creek, which had been found to be
structurally deficient. It was originally estimated that the City of Lakeville would be eligible
for $240,000 in State Aid Bridge Bond Funds to replace the 168th Street Bridge. Based upon
the bid prices received, the final Bridge Bonding Grant amount has been determined to be
$282,926.00. The required local match to replace the bridge will be $25,660.00.
Primary Issues to Consider
What improvements are proposed that qualified for Bridge Bond Funds? Bridge Bond
funds will cover the costs associated with installing the new bridge. In accordance with
Bridge Bond policies, local funds shall fund removal of the existing bridge and
construction of the roadway approaches to the new bridge.
Supporting Information
Minnesota Department of Transportation Local Bridge Bond Grant Agreement
Christo . Petree
Public orks Director
Financial Impact: $308,586.00
Related Documents (CIP, ERP, etc.):
Notes:
Budgeted: Yes Source: Bridge Bonds and Local Funds
CITY OF LAKEVILLE
RESOLUTION NO:
A RESOLUTION ACCEPTING AND APPROVING THE GRANT AGREEMENT
BETWEEN THE CITY OF LAKEVILLE AND THE
MINNESOTA DEPARTMENT OF TRANSPORTATION FORTHE
CONSTRUCTION OF BRIDGE NO. 19565, THE 168TH STREET BRIDGE
(S.A.P. 188- 594 -001)
WHEREAS, The City of Lakeville has applied to the Commissioner of
Transportation for a grant from the Minnesota State Transportation Fund for
construction of Bridge No. 19565; and
WHEREAS, the Commissioner of Transportation has given notice that funding
for this bridge is available; and
WHEREAS, the amount of the grant has been determined to be $282,926.00 by
reason of the lowest responsible bid;
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of
Lakeville:
Does hereby agree to the terms and conditions of the grant consistent with
Minnesota Statutes, section 174.50, subdivision 5, clause (3), and will pay any
additional amount by which the cost exceeds the estimate, and will return to the
Minnesota State Transportation Fund any amount appropriated for the bridge but
not required. The proper City officers are authorized to execute a grant
agreement with the Commissioner of Transportation concerning the above -
referenced grant.
APPROVED AND ADOPTED this 20 day of May 2013.
CITY OF LAKEVILLE
Matt Little, Mayor
ATTEST:
Charlene Friedges, City Clerk
2
Mn/DOT Agreement No. 03780
LOCAL BRIDGE REPLACEMENT PROGRAM (LBRP)
GRANT AGREEMENT
This Agreement between the Minnesota Department of Transportation ( "MnDOT ") and
the Grantee named below is made pursuant to Minnesota Statutes Section 174.50. The provisions
in that section and the Exhibits attached hereto and incorporated by reference constitute this
Agreement and the persons signing below agree to fully comply with all of the requirements of
this Agreement.
Effective date of this Agreement: 5 20
2. Public Entity (Grantee) name, address and contact person:
City of Lakeville
18400 I ava Avenue
Lakeville, MN 55044
Contact: Chris Petree, Public Works Director
3. Project(s):
Naive of Project
(See Exhibit C for
location )
Amount of
LBRP Funds
Amount of Required
Matching Funds
Completion Date
168 Street Bridge
Replacement
Project, Old Bridge
No. L5772, S.A.P.
188 -594 -001
$282,926.00
$25,660.00
Sept. 30, 2013
Exhibit E
Grantee Resolution Approving Grant Agreement
Exhibit F
General Terms and Conditions
4. Total Amount of LBRP Grant for all projects under this Agreement:
$ $282,926.00
5. The following Exhibits for each project are attached and incorporated by reference as part
of this Agreement:
Exhibit A
Completed Sources and Uses of Funds Schedule
Exhibit B
Project Completion Schedule
Exhibit C
Bond Financed Property Certification
Exhibit D
Grant Application
Exhibit E
Grantee Resolution Approving Grant Agreement
Exhibit F
General Terms and Conditions
Mn/DOT Agreement No. 03780
6. Additional requirements, if any: NONE
7. Any modification of this Agreement must be in writing and signed by both parties.
(The remaining portion of this page was intentionally left blank.)
2
Mn,DOT Agreement No. 03780
PUBLIC ENTITY (GRANTEE)
.0
Title: Mavor
Date:
By:
Title: City Clerk
Date:
DEPARTMENT OF TRANSPORTATION
By:
Title:
Date:
OFFICE OF CONTRACT MANAGEMENT
By:
Contract Administrator
Date:
MniDOT Agreement No. 03780
EXHIBIT A
SOURCES AND USES OF FUNDS SCHEDULE
(Complete a different schedule for each project. For the first project
label it A-1; for the second project label it A-2; etc.)
SOURCES OF FUNDS
Subtotal
$282926.00
USES OF FUNDS
Expenses Amount
Public Entity Funds:
Matching $25,660.00
Other:
Subtotal $25,660.00
TOTAL FUNDS $308,586.00 = TOTAL PROJECT $ 308,586.00
COSTS
3
WDOT Agreement No. 03780
EXHIBIT B
PROJECT COMPLETION SCHEDULE
(Provide a different schedule for each project. Label each project
to correspond with the project as listed in Exhibit A; e.g., B -1, B -2, etc.)
168 Street Bridge Replacement Project, S.A.P. 188 -594 -001:
• Contract Award Date: May 20, 2013
• Construction Commences: June, 2013
• Substantial Completion: September 30, 2013
4
Mn/DOT Agreement No. 03780
EXHIBIT C
BOND FINANCED PROPERTY CERTIFICATION
(Complete only one Certification for all projects)
State of Minnesota
General Obligation Bond Financed Property
The undersigned states that it has a fee simple, leasehold and/or easement interest in the
real property located in the County(ies) of Dakota, State of Minnesota that is generally described
or illustrated graphically in Attachment 1 attached hereto and all improvements thereon (the
"Restricted Property") and acknowledges that the Restricted Property is or may become State
bond - financed property. To the extent that the Restricted Property is or becomes State bond -
financed property, the undersigned acknowledges that:
A. The Restricted Property is State bond - financed property under Minn. Stat.
Sec. 16A.695, is subject to the requirements imposed by that statute, and
cannot be sold, mortgaged, encumbered or otherwise disposed of without the
approval of the Commissioner of Minnesota Management and Budget; and
B. The Restricted Property is subject to the provisions of the Local Bridge
Replacement Program Grant Agreement between the Minnesota Department
of Transportation and the undersigned dated May 20, 2013; and
C. The Restricted Property shall continue to be deemed State bond - financed
property for 37.5 years or until the Restricted Property is sold with the written
approval of the Commissioner of Minnesota Management and Budget.
Date: _9 2 0
City of Lakeville, a political subdivision of the
State of Minnesota
By:
Name: Matt Little
Title: Mayor
By:
Name: Char Fried es
Title: Ci Clerk
Mn/DOT Agreement No. 03780
Attachment 1 to Exhibit C
GENERAL DESCRIPTION OF RESTRICTED PROPERTY
(Insert a narrative or graphic description of the Restricted Property for each project. Label each
project to correspond with the project as listed in Exhibit A; e.g., C -1, C -2, etc. It need not be a
legal description if a legal description is unavailable.)
See Attachment 1, for a graphic description of the Restricted Property for the 168 Street
Bridge Replacement Project, S.A.P. 188- 594 -001.
F
r
d
C
IU
t
Q
'D
C
I N
ga g s il
� � Jill 4 1 1 $ r as s
cg
y ,
9a Villa
t 3g g
1 P 11
' � ggg 3 ` � qq g gpppppp j i E $a
8y «. �gk 8` EadS �'.L� E �C { �i Y a �Yi3 f` `Y ` i � i � •°I" ,p
1; li
•rte ' •, �, �r,r
e q eewra -- frttt —- ws reu ro rra ,H• _ _ §:ti ;�.i
° \ �rP�iw °e » ,Rr+w f °j . 3 y r , 'harsh as•a �M
cr \ t Y '4
Y III �. XFi Ag N + y� q N F N N aj I \1
IM
M - ' AA
Z
LL
W o \ w `, � cr � � m `•�, I r e +�'" a rR o
�/� y e \ 7 \�\ F `a F f m in � r, -s's� "` P • :�F �
V/
de
$.N"i"ce \ \\\ v •e + s , c . \ \ g ` n
Z Q S �
Ar
-1 6 -i
n �\
\L
or
'� 6 ez vfe•7.veyer cuss h m � ! .�• -'- F
�T e -
1� Zxuei '� a
L_
Mn'DOT Agreement No. 03780
EXHIBIT D
GRANT APPLICATION
(Attach the grant application for each project and label each application to correspond with the
projects listed in Exhibit A; e.g., D -1, D -2, etc.)
See Attached Grant Application for the 168 Street Bridge Replacement Project in
Lakeville, S.A.P. 188- 594 -001.
UNDOT SIMM t"
APPLICATION FOR BRIDGE i UNDS
State Transportation Fund Grants and Town Bridge Funds
State of Minnesota - Department of Transportation
State Aid for Local Transportation
QF
Project Number _$ Lff �- , oyVV .401 old Bridge Number 45 7 7 2
New Bridge No. ' tog, Over y ® �
County of Aa. Road or Street No.
Municipality of - ZaAemoY o Road or Street Name
Township of � 1A Proposed Const Year
rM
- Bridge sufficiency Rating /• Is this bridge hydraulically deficient? O Yes A No
Adequacy Status from Structure Inventory I.Structurally Deficient O Functionally Obsolete 0 Adequate
Date of Coundl/Board action prioritizing this bridge
M Is this a road-in -lieu of bridge project? d Yes A No
Is the bridge on a private approach and within the public right -of -way? p Yes IN No
Will completion of this project effectively eliminate a deficiency In the transportation system? A Yes 0 No
How many people are affected by this deficiency? 2 ifl What is the ADT on this bridge? 7 .00
Describe the eoonorl inyrtarwe of_repll Ong this b ridge. &6! 1. �i r •l ,
Will this project adversely affect optimum land use or cause other planning concerns?
Have federal -aid funds been applied for on this project?
Is the road designated or planned to be designated as a Minimum Maintenance road?
W addflional sheets for explanation If neoessao
Stricture Costs
$
Approach Costs
$
Engineering Costs
$
Total Costs
$
Total Project Cost
DISTRICT STATE AID ENGINEER RECOMMENDATION
Replace Defer
STATE AID USE ONLY
SR < 80 and FO or SD? O Yes 0 No
OR
Hydraulically deficient? 0 Yes 0 No
District State Aid Ermine
Federal -Aid
State -Aid
Local/Other
Town Bridge
Unallocated Town Bridge
State Bridge Funds
Total
P
0 Yes UL No
0 Yes AL No
0 Yes i$ No
.)' 3 cr as
$
$
Date
WDOT Agreement No. 03780
EXHIBIT E
GRANTEE RESOLUTION APPROVING GRANT AGREEMENT
See Attached Resolution Approving the Grant Agreement for the 168 Street Bridge
Replacement Project in Lakeville, S.A.P. 188 -594 -001.
Mn/DOT Agreement No. 03780
EXHIBIT F
GENERAL TERMS AND CONDITIONS FOR
LOCAL BRIDGE REPLACEMENT PROGRAM (LBRP) GRANTS
(Applicable to each project.)
Article I
DEFINITIONS
Section 1.01 Defined Terms. The following terms shall have the meanings set out respectively
after each such term (the meanings to be equally applicable to both the singular and plural forms of the
terms defined) unless the context specifically indicates otherwise:
"Advance(s)" - means an advance made or to be made by MnDOT to the Public Entity and
disbursed in accordance with the provisions contained in Article VI hereof.
"Agreement" - means the Local Bridge Replacement Program Grant Agreement between the
Public Entity and the Minnesota Department of Transportation to which this Exhibit is attached.
"Certification" - means the certification, in the form attached as Exhibit C, in which the Public
Entity acknowledges that its interest in the Real Property is bond financed property within the meaning of
Minn. Stat. Sec. 16A.695 and is subject to certain restrictions imposed thereby.
"Code" - means the Internal Revenue Code of 1986, as amended, and all treasury regulations,
revenue procedures and revenue rulings issued pursuant thereto.
"Commissioner" - means the Commissioner of Minnesota Management & Budget.
"Commissioner's Order" - means the "Third Order Amending Order of the Commissioner of
Minnesota Management & Budget Relating to Use and Sale of State Bond Financed Property" dated
August 26, 2010, as it may be amended or supplemented.
"Completion Date" - means the projected date for completion of the Project as indicated in the
Agreement.
"Construction Contract Documents" - means the document or documents, in form and substance
acceptable to MnDOT, including but not limited to any construction plans and specifications and any
exhibits, amendments, change orders, modifications thereof or supplements thereto, which collectively
form the contract between the Public Entity and the Contractor(s) for the completion of the Construction
Items on or before the Completion Date for either a fixed price or a guaranteed maximum price.
"Construction Items" - means the work to be performed under the Construction Contract
Documents.
"Contractor" - means any person engaged to work on or to furnish materials and supplies for the
Construction Items including, if applicable, a general contractor.
"Draw Requisition" - means a draw requisition that the Public Entity, or its designee, submits to
MnDOT when an Advance is requested, as referred to in Section 4.02.
Mn/DOT Agreement No. 03780
"G.O. Bonds" - means the state general obligation bonds issued under the authority granted in
Article XI, Sec. 5(a) of the Minnesota Constitution, the proceeds of which are used to fund the LBRP
Grant, and any bonds issued to refund or replace such bonds.
"Grant Application" - means the grant application that the Public Entity submitted to MnDOT
which is attached as Exhibit D.
"LBRP Grant" - means a grant from MnDOT to the Public Entity under the LBRP in the amount
specified in the Agreement, as such amount may be modified under the provisions hereof.
"LBRP" - means the Local Bridges Replacement Program pursuant to Minn. Stat. Sec. 174.50 and
rules relating thereto.
"MnDOT" - means the Minnesota Department of Transportation.
"Outstanding Balance of the LBRP Grant" - means the portion of the LBRP Grant that has been
disbursed to the Public Entity minus any amounts returned to the Commissioner.
"Project" - means the Project identified in the Agreement to be totally or partially funded with a
LBRP grant.
"Public Entity" - means the grantee of the LBRP Grant and identified as the Public Entity in the
Agreement.
"Real Propert)" - means the real property identified in the Agreement on which the Project is
located.
Article II
GRANT
Section 2.01 Grant of Monies. MnDOT shall make the LBRP Grant to the Public Entity, and
disburse the proceeds in accordance with the terms and conditions herein.
Section 2.02 Public Ownership. The Public Entity acknowledges and agrees that the LBRP Grant
is being funded with the proceeds of G.O. Bonds, and as a result all of the Real Property must be owned
by one or more public entities. The Public Entity represents and warrants to MnDOT that it has one or
more of the following ownership interests in the Real Property: (i) fee simple ownership, (ii) an easement
that is for a term that extends beyond the date that is 37.5 years from the Agreement effective date, or
such shorter term as authorized by statute, and which cannot be modified or terminated early �a ithout the
prior written consent of MnDOT and the Commissioner; and /or (iii) a prescriptive easement for a term
that extends beyond the date that is 37.5 years from the Agreement effective date.
Section 2.03 Use of Grant Proceeds. The Public Entity shall use the LBRP Grant solely to
reimburse itself for expenditures it has already made, or will snake, to pay the costs of one or more of the
following activities: (i) constructing or reconstructing a bridge, (ii) preliminary engineering and
environmental studies authorized under Minn. Stat. Sec. 174.50, subdiv. 6a, (iii) abandoning an existing
bridge that is deficient and in need of replacement, but where no replacement will be made, or (iv)
constructing a road to facilitate the abandonment or removal of an existing bridge determined to be
deficient. The Public Entity shall not use the LBRP Grant for any other purpose, including but not
limited to, any work to be done on a state trunk highway or within a trunk highway easement.
0
Mn/DOT Agreement No. 03780
Section 2.04 Operation of the Real Property. The Real Property must be used by the Public
Entity in conjunction with or for the operation of a county highway, county state -aid highway, town road,
or city street and for other uses customarily associated therewith, such as trails and utility corridors, and
for no other purposes or uses. The Public Entity may have no intention on the effective date of the
Agreement to use the Real Property as a trunk highway or any part of a trunk highway. The Public Entity
must annually determine that the Real Property is being used for the purposes specified in this Section
and, upon written request by either MnDOT or the Commissioner, shall supply a notarized statement to
that effect.
Section 2.05 Sale or Lease of Real Property. The Public Entity shall not (i) sell or transfer any
part of its ownership interest in the Real Property, or (ii) lease out or enter into any contract that would
allow another entity to use or operate the Real Property without the written consent of both MnDOT and
the Commissioner. The sale or transfer of any part of the Public Entity's ownership interest in the Real
Property, or any lease or contract that would allow another entity to use or operate the Real Property,
must comply with the requirements imposed by Minn. Stat. Sec. 16A.695 and the Commissioner's Order
regarding such sale or lease.
Section 2.06 Public Entity's Representations and Warranties. The Public Entity represents and
warrants to MnDOT that:
A. It has legal authority to execute, deliver and perform the Agreement and all documents
referred to therein, and it has taken all actions necessary to its execution and delivery of such
documents.
B. It has the ability and a plan to fund the operation of the Real Property for the purposes
specified in Section 2.04, and will include in its annual budget all funds necessary for the
operation of the Real Property for such purposes.
C. The Agreement and all other documents referred to therein are the legal, valid and binding
obligations of the Public Entity enforceable against the Public Entity in accordance with their
respective terms.
D. It will comply with all of the provisions of Minn. Stat. Sec. 16A.695, the Commissioner's
Order and the LBRP.
E. All of the information it has submitted or will submit to MnDOT or the Commissioner
relating to the LBRP Grant or the disbursement of the LBRP Grant is and will be true and
correct.
F. It is not in violation of any provisions of its charter or of the laws of the State of Minnesota,
and there are no actions or proceedings pending, or to its knowledge threatened, before any
judicial body or governmental authority against or affecting it relating to the Real Property, or
its ownership interest therein, and it is not in default with respect to any order, writ,
injunction, decree, or demand of any court or any governmental authority which would
impair its ability to enter into the Agreement or any document referred to herein, or to
perform any of the acts required of it in such documents.
G. Neither the execution and delivery of the Agreement or any document referred to herein nor
compliance with any of the provisions or requirements of any of such documents is prevented
7
Mn/DOT Agreement No. 03780
by, is a breach of, or will result in a breach of, any provision of any agreement or document
to which it is now a party or by which it is bound.
H. The contemplated use of the Real Property will not violate any applicable zoning or use
statute, ordinance, building code, rule or regulation, or any covenant or agreement of record
relating thereto.
I. The Project will be completed and the Real Property will be operated in full compliance with
all applicable laws, rules, ordinances, and regulations of any federal, state, or local political
subdivision having jurisdiction over the Project and the Real Property.
All applicable licenses, permits and bonds required for the performance and completion of
the Project and for the operation of the Real Property as specified in Section 2.04 have been,
or will be, obtained.
K. It reasonably expects to possess its ownership interest in the Real Property described in
Section 2.02 for at least 37.5 years, and it does not expect to sell such ownership interest.
L. It does not expect to lease out or enter into any contract that would allow another entity to use
or operate the Real Property.
M. It will supply whatever funds are needed in addition to the LBRP Grant to complete and fully
pay for the Project.
N. The Construction Items will be completed substantially in accordance with the Construction
Contract Documents by the Completion Date and all such items will be situated entirely on
the Real Property.
O. It will require the Contractor or Contractors to comply with all rules, regulations, ordinances,
and laws bearing on its performance under the Construction Contract Documents.
P. It shall furnish such satisfactory evidence regarding the representations and warranties
described herein as may be required and requested by either MnDOT or the Commissioner.
Section 2.07 Event(s) of Default. The following events shall, unless waived in writing by
MnDOT and the Commissioner, constitute an Event of Default under the Agreement upon either MnDOT
or the Commissioner giving the Public Entity 30 days' written notice of such event and the Public
Entity's failure to cure such event during such 30 -day time period for those Events of Default that can be
cured within 30 days or within whatever time period is needed to cure those Events of Default that cannot
be cured within 30 days as long as the Public Entity is using its best efforts to cure and is making
reasonable progress in curing such Events of Default; however, in no event shall the time period to cure
any Event of Default exceed six (6) months unless otherwise consented to, in writing, by MnDOT and the
Commissioner.
A. If any representation, covenant, or warranty made by the Public Entity herein or in any other
document furnished pursuant to the Agreement, or to induce MnDOT to disburse the LBRP
Grant, shall prove to have been untrue or incorrect in any material respect or materially
misleading as of the time such representation, covenant, or warranty was made.
B. If the Public Entity fails to fully comply with any provision, covenant, or warranty contained
herein.
Mn/DOT Agreement No. 03780
C. If the Public Entity fails to fully comply with any provision, covenant or warranty contained
in Minn. Stat. Sec. 16A.695, the Commissioner's Order, or Minn. Stat. Sec. 174.50 and all
rules related thereto.
D. If the Public Entity fails to use the proceeds of the LBRP Grant for the purposes set forth in
Section 2.03, the Grant Application, and in accordance with the LBRP.
E. If the Public Entity fails to operate the Real Property for the purposes specified in Section
2.04.
F. If the Public Entity fails to complete the Project by the Completion Date.
G. If the Public Entity sells or transfers any portion of its ownership interest in the Real Property
without first obtaining the written consent of both MnDOT and the Commissioner.
H. If the Public Entity fails to provide any additional funds needed to fully pay for the Project.
I. If the Public Entity fails to supply the funds needed to operate the Real Property in the
manner specified in Section 2.04.
Notwithstanding the foregoing, any of the above events that cannot be cured shall, unless waived in
writing by MnDOT and the Commissioner, constitute an Event of Default under the Agreement
immediately upon either MnDOT or the Commissioner giving the Public Entity written notice of such
event.
Section 2.08 Remedies. Upon the occurrence of an Event of Default and at any time thereafter
until such Event of Default is cured to the satisfaction of MnDOT, MnDOT or the Commissioner may
enforce any or all of the following remedies.
A. MnDOT may refrain from disbursing the LBRP Grant; provided, however, MnDOT may
make such disbursements after the occurrence of an Event of Default without waiving its
rights and remedies hereunder.
B. If the Event of Default involves a sale of the Public Entity's interest in the Real Property in
violation of Minn. Stat. Sec. 16A.695 or the Commissioner's Order, the Commissioner, as a
third party beneficiary of the Agreement, may require that the Public Entity pay the amounts
that would have been paid if there had been compliance with such provisions. For other
Events of Default, the Commissioner may require that the Outstanding Balance of the LBRP
Grant be returned to it.
C. Either MnDOT or the Commissioner, as a third party beneficiary of the Agreement, may
enforce any additional remedies it may have in law or equity.
The rights and remedies specified herein are cumulative and not exclusive of any rights or remedies that
MnDOT or the Commissioner would otherwise possess.
If the Public Entity does not repay the amounts required to be paid under this Section or under any other
provision contained herein within 30 days of demand by the Commissioner, or any amount ordered by a
court of competent jurisdiction within 30 days of entry of judgment against the Public Entity and in favor
Mn/DOT Agreement No. 03780
of MnDOT and /or the Commissioner, then such amount may, unless precluded by law, be offset against
any aids or other monies that the Public Entity is entitled to receive from the State of Minnesota.
Section 2.09 Notification of Event of Default. The Public Entity shall furnish to MnDOT and the
Commissioner, as soon as possible and in any event within seven (7) days after it has obtained knowledge
of the occurrence of each Event of Default, a statement setting forth details of each Event of Default and
the action which the Public Entity proposes to take with respect thereto.
Section 2.10 Effect of Event of Default. The Agreement shall survive Events of Default and
remain in full force and effect, even upon full disbursement of the LBRP Grant, and shall only be
terminated under the circumstances set forth in Section 2.11.
Section 2.11 Termination of Agreement and Modification of LBRP Grant.
A. If the Project is not started within five (5) years after the effective date of the Agreement or
the LBRP Grant has not been disbursed within four (4) years after the date the Project was started,
MnDOT's obligation to fund the LBRP Grant shall terminate. In such event, (i) if none of the LBRP
Grant has been disbursed by such date, MnDOT shall have no obligation to fund the LBRP Grant and the
Agreement will terminate, and (ii) if some but not all of the LBRP Grant has been disbursed by such date,
MnDOT shall have no further obligation to provide any additional funding for the LBRP Grant and the
Agreement shall remain in force but shall be modified to reflect the amount of the LBRP Grant that was
actually disbursed and the Public Entity is still obligated to complete the Project by the Completion Date.
B. The Agreement shall terminate upon the Public Entity's sale of its interest in the Real
Property and transmittal of the required portion of the proceeds of the sale to the Commissioner in
compliance with Minn. Stat. Sec. 16A.695 and the Commissioner's Order, or upon the termination of the
Public Entity's ownership interest in the Real Property if such ownership interest is an easement.
Article III
COMPLIANCE WITH MINN. STAT. SEC. 16A.695
AND THE COMMISSIONER'S ORDER
Section 3.01 State Bond Financed Property. The Public Entity acknowledges that its interest in
the Real Property is, or when acquired by it will be, "state bond financed property", as such term is used
in Minn. Stat. Sec. 16A.695 and the Commissioner's Order and, therefore, the provisions contained in
such statute and order apply, or will apply, to its interest in the Real Property, even if the LBRP Grant
will only pay for a portion of the Project.
Section 3.02 Preservation of Tax Exempt Status. In order to preserve the tax - exempt status of
the G.O. Bonds, the Public Entity agrees as follows:
A. It will not use the Real Property or use or invest the LBRP Grant or any other sums treated as
"bond proceeds" under Section 148 of the Code (including "investment proceeds," "invested
sinking funds" and "replacement proceeds ") in such a manner as to cause the G.O. Bonds to
be classified as "arbitrage bonds" under Code Section 148.
B. It will deposit and hold the LBRP Grant in a segregated non - interest - bearing account until
such funds are used for payments for the Project.
10
Mn/DOT Agreement No. 03780
C. It A ill, upon written request, provide the Commissioner all information required to satisfy the
informational requirements set forth in the Code, including Sections 103 and 148, with
respect to the G.O. Bonds.
D. It will, upon the occurrence of any act or omission by the Public Entity that could cause the
interest on the G.O. Bonds to no longer be tax exempt and upon direction from the
Commissioner, take such actions and furnish such documents as the Commissioner
determines to be necessary to ensure that the interest to be paid on the G.O. Bonds is exempt
from federal taxation, which such action may include: (i) compliance with proceedings
intended to classify the G.O. Bonds as a "qualified bond" within the meaning of Code Section
141(e), or (ii) changing the nature of the use of the Real Property so that none of the net
proceeds of the G.O. Bonds will be deemed to be used, directly or indirectly, in an "unrelated
trade or business" or for any "private business use" within the meaning of Code Sections
141(b) and 145(a).
E. It will not otherwise use any of the LBRP Grant or take, permit or cause to be taken, or omit
to take, any action that would adversely affect the exemption from federal income taxation of
the interest on the G.O. Bonds, and if it should take, permit or cause to be taken, or omit to
take, as appropriate, any such action, it shall take all lawful actions necessary to correct such
actions or omissions promptly upon obtaining knowledge thereof.
Section 3.03 Changes to G.O. Compliance Legislation or the Commissioner's Order. If Minn.
Stat. Sec. 16A.695 or the Commissioner's Order is amended in a manner that reduces any requirement
imposed against the Public Entity, or if the Public Entity's interest in the Real Property becomes
exempted from Minn. Stat. Sec. 16A.695 and the Commissioner's Order, then upon written request by the
Public Entity, MnDOT shall execute an amendment to the Agreement to implement such amendment or
exempt the Public Entity's interest in the Real Property from Minn. Stat. Sec. 16A.695 and the
Commissioner's Order.
Article IV
DISBURSEMENT OF GRANT PROCEEDS
Section 4.01 The Advances. MnDOT agrees, on the terms and subject to the conditions set forth
herein, to make Advances of the LBRP Grant to the Public Entity from time to time in an aggregate total
amount not to exceed the amount of the LBRP Grant. If the amount of LBRP Grant that MnDOT
cumulatively disburses hereunder to the Public Entity is less than the amount of the LBRP Grant
delineated in Section 1.01, then MnDOT and the Public Entity shall enter into and execute whatever
documents MnDOT may request in order to amend or modify this Agreement to reduce the amount of the
LBRP Grant to the amount actually disbursed. Provided, however, in accordance with the provisions
contained in Section 2.11, MnDOT's obligation to make Advances shall terminate as of the dates
specified in Section 2.11 even if the entire LBRP Grant has not been disbursed by such dates.
Advances shall only be for expenses that (i) are for those items of a capital nature delineated in
Source and Use of Funds that is attached as Exhibit A, (ii) accrued no earlier than the effective date of
the legislation that appropriated the funds that are used to fund the LBRP Grant, or (iii) have otherwise
been consented to, in writing, by the Commissioner.
It is the intent of the parties hereto that the rate of disbursement of the Advances shall not exceed the rate
of completion of the Project or the rate of disbursement of the matching funds required, if any, under
Section 5.13. Therefore, the cumulative amount of all Advances disbursed by the State Entity at any
point in time shall not exceed the portion of the Project that has been completed and the percentage of the
11
Mn,DOT Agreement No. 03780
matching funds required, if any, under Section 5.13 that have been disbursed as of such point in time.
This requirement is expressed by way of the following two formulas:
Fonnula #1:
Cumulative Advances < (Program Grant) x (percentage of matching funds, if any, required under
Section 5.13 that have been disbursed)
Formula #2:
Cumulative Advances < (Program Grant) x (percentage of Project completed)
Section 4.02 Draw Requisitions. Whenever the Public Entity desires a disbursement of a portion
of the LBRP Grant the Public Entity shall submit to MnDOT a Draw Requisition duly executed on behalf
of the Public Entity or its designee. Each Draw Requisition with respect to construction items shall be
limited to amounts equal to: (i) the total value of the classes of the work by percentage of completion as
approved by the Public Entity and MnDOT, plus (ii) the value of materials and equipment not
incorporated in the Project but delivered and suitably stored on or off the Real Property in a manner
acceptable to MnDOT, less (iii) any applicable retainage, and less (iv) all prior Advances.
Notwithstanding anything herein to the contrary, no Advances for materials stored on or off the
Real Property will be made by MnDOT unless the Public Entity shall advise MnDOT, in writing, of its
intention to so store materials prior to their delivery and MnDOT has not objected thereto.
At the time of submission of each Draw Requisition, other than the final Draw Requisition, the
Public Entity shall submit to MnDOT such supporting evidence as may be requested by MnDOT to
substantiate all payments which are to be made out of the relevant Draw Requisition or to substantiate all
payments then made with respect to the Project.
The final Draw Requisition shall not be submitted before completion of the Project, including any
correction of material defects in workmanship or materials (other than the completion of punch list
items). At the time of submission of the final Draw Requisition the Public Entity shall submit to MnDOT:
(i) such supporting evidence as may be requested by MnDOT to substantiate all payments which are to be
made out of the final Draw Requisition or to substantiate all payments then made with respect to the
Project, and (ii) satisfactory evidence that all work requiring inspection by municipal or other
governmental authorities having jurisdiction has been duly inspected and approved by such authorities
and that all requisite certificates and other approvals have been issued.
If on the date an Advance is desired the Public Entity has complied with all requirements of this
Agreement and MnDOT approves the relevant Draw Requisition, then MnDOT shall disburse the amount
of the requested Advance to the Public Entity.
Section 4.03 Additional Funds. If MnDOT shall at any time in good faith determine that the sum
of the undisbursed amount of the LBRP Grant plus the amount of all other funds committed to the Project
is less than the amount required to pay all costs and expenses of any kind which reasonably may be
anticipated in connection with the Project, then MnDOT may send written notice thereof to the Public
Entity specifying the amount which must be supplied in order to provide sufficient funds to complete the
Project. The Public Entity agrees that it will, within 10 calendar days of receipt of any such notice,
supply or have some other entity supply the amount of funds specified in MnDOT's notice.
Section 4.04 Condition Precedent to Any Advance. The obligation of MnDOT to make any
Advance hereunder (including the initial Advance) shall be subject to the following conditions precedent:
12
Mn/DOT Agreement No. 03780
A. MnDOT shall have received a Draw Requisition for such Advance specifying the amount of
funds being requested, which such amount when added to all prior requests for an Advance
shall not exceed the amount of the LBRP Grant set forth in Section 1.01.
B. No Event of Default under this Agreement or event which would constitute an Event of
Default but for the requirement that notice be given or that a period of grace or time elapse
shall have occurred and be continuing.
C. No determination shall have been made by MnDOT that the amount of funds committed to
the Project is less than the amount required to pay all costs and expenses of any kind that
may reasonably be anticipated in connection with the Project, or if such a determination has
been made and notice thereof sent to the Public Entity under Section 4.03, then the Public
Entity has supplied, or has caused some other entity to supply, the necessary funds in
accordance with such section or has provided evidence acceptable to MnDOT that sufficient
funds are available.
D. The Public Entity has supplied to MnDOT all other items that MnDOT may reasonably
require.
Section 4.05 Processing and Disbursement of Advances. The Public Entity acknowledges and
agrees as follows:
A. Advances are not made prior to completion of work performed on the Project.
B. All Advances are processed on a reimbursement basis.
C. The Public Entity must first document expenditures to obtain an Advance.
D. Reimbursement requests are made on a partial payment basis or when the Project is
completed.
E. All payments are made following the "Delegated Contract Process or State Aid Payment
Request" as requested and approved by the appropriate district state aid engineer.
Section 4.06 Construction Inspections. The Public Entity shall be responsible for snaking its
own inspections and observations regarding the completion of the Project, and shall determine to its own
satisfaction that all work done or materials supplied have been properly done or supplied in accordance
with all contracts that the Public Entity has entered into regarding the completion of the Project.
Article V
MISCELLANEOUS
Section 5.01 Insurance. If the Public Entity elects to maintain general comprehensive liability
insurance regarding the Real Property, then the Public Entity shall have MnDOT named as an additional
named insured therein.
Section 5.02 Condemnation. If, after the Public Entity has acquired the ownership interest set
forth in Section 2.02, all or any portion of the Real Property is condemned to an extent that the Public
Entity can no longer comply with Section 2.04, then the Public Entity shall, at its sole option, either: (i)
use the condemnation proceeds to acquire an interest in additional real property needed for the Public
Entity to continue to comply with Section 2.04 and to provide whatever additional funds that may be
13
Mn/DOT Agreement No. 03780
needed for such purposes, or (ii) submit a request to MnDOT and the Commissioner to allow it to sell the
remaining portion of its interest in the Real Property. Any condemnation proceeds which are not used to
acquire an interest in additional real property shall be applied in accordance with Minn. Stat. Sec.
16A.695 and the Commissioner's Order as if the Public Entity's interest in the Real Property had been
sold. If the Public Entity elects to sell its interest in the portion of the Real Property that remains after the
condemnation, such sale must occur within a reasonable time period after the date the condemnation
occurred and the cumulative sum of the condemnation and sale proceeds applied in accordance with
Minn. Stat. Sec. 16A.695 and the Commissioner's Order.
If MnDOT receives any condemnation proceeds referred to herein, MnDOT agrees to or pay over to the
Public Entity all of such condemnation proceeds so that the Public Entity can comply with the
requirements of this Section.
Section 5.03 Use, Maintenance, Repair and Alterations. The Public Entity shall not, without the
written consent of MnDOT and the Commissioner, (i) permit or allow the use of any of the Real Property
for any purpose other than the purposes specified in Section 2.04, (ii) substantially alter any of the Real
Property except such alterations as may be required by laws, ordinances or regulations, or such other
alterations as may improve the Real Property by increasing its value or which improve its ability to be
used for the purposes set forth in Section 2.04, (iii) take any action which would unduly impair or
depreciate the value of the Real Property, (iv) abandon the Real Property, or (v) commit or permit any act
to be done in or on the Real Property in violation of any law, ordinance or regulation.
If the Public Entity fails to maintain the Real Property in accordance with this Section, MnDOT may
perform whatever acts and expend whatever funds necessary to so maintain the Real Property, and the
Public Entity irrevocably authorizes MnDOT to enter upon the Real Property to perform such acts as may
be necessary to so maintain the Real Property. Any actions taken or funds expended by MnDOT shall be
at its sole discretion, and nothing contained herein shall require MnDOT to take any action or incur any
expense and MnDOT shall not be responsible, or liable to the Public Entity or any other entity, for any
such acts that are performed in good faith and not in a negligent manner. Any funds expended by
MnDOT pursuant to this Section shall be due and payable on demand by MnDOT and will bear interest
from the date of payment by MnDOT at a rate equal to the lesser of the maximum interest rate allowed by
law or 18% per year based upon a 365 -day year.
Section 5.04 Recordkeeping and Reporting. The Public Entity shall maintain books and records
pertaining to Project costs and expenses needed to comply with the requirements contained herein, Minn.
Stat. Sec. 16A.695, the Commissioner's Order, and Minn. Stat. Sec. 174.50 and all rules related thereto,
and upon request shall allow MnDOT, its auditors, the Legislative Auditor for the State of Minnesota, or
the State Auditor for the State of Minnesota, to inspect, audit, copy, or abstract all such items. The
Public Entity shall use generally accepted accounting principles in the maintenance of such items, and
shall retain all of such books and records for a period of six years after the date that the Project is fully
completed and placed into operation.
Section 5.05 Inspections by MnDOT. The Public Entity shall allow MnDOT to inspect the Real
Property upon reasonable request by MnDOT and without interfering with the normal use of the Real
Property.
Section 5.06 Liability. The Public Entity and MnDOT agree that each will be responsible for its
own acts and the results thereof to the extent authorized by law, and neither shall be responsible for the
acts of the other party and the results thereof. The liability of MnDOT and the Commissioner is governed
by the provisions of Minn. Stat. Sec. 3.736. If the Public Entity is a "municipality" as that term is used in
Minn. Stat. Chapter 466, then the liability of the Public Entity is governed by the provisions of Chapter
14
Mn/DOT Agreement No. 03780
466. The Public Entity's liability hereunder shall not be limited to the extent of insurance carried by or
provided by the Public Entity, or subject to any exclusion from coverage in any insurance policy.
Section 5.07 Relationship of the Parties. Nothing contained in the Agreement is to be construed
as establishing a relationship of co- partners or joint venture among the Public Entity, MnDOT, or the
Commissioner, nor shall the Public Entity be considered to be an agent, representative, or employee of
MnDOT, the Commissioner, or the State of Minnesota in the performance of the Agreement or the
Project.
No employee of the Public Entity or other person engaging in the performance of the Agreement or the
Project shall be deemed have any contractual relationship with MnDOT, the Commissioner, or the State
of Minnesota and shall not be considered an employee of any of those entities. Any claims that may arise
on behalf of said employees or other persons out of employment or alleged employment, including claims
under the Workers' Compensation Act of the State of Minnesota, claims of discrimination against the
Public Entity or its officers, agents, contractors, or employees shall in no way be the responsibility of
MnDOT, the Commissioner, or the State of Minnesota. Such employees or other persons shall not
require nor be entitled to any compensation, rights or benefits of any kind whatsoever from MnDOT, the
Commissioner, or the State of Minnesota, including tenure rights, medical and hospital care, sick and
vacation leave, disability benefits, severance pay and retirement benefits.
Section 5.08 Notices. In addition to any notice required under applicable law to be given in
another manner, any notices required hereunder must be in writing and personally served or sent by
prepaid, registered, or certified snail (return receipt requested), to the address of the party specified below
or to such different address as may in the future be specified by a party by written notice to the others:
To the Public Entity: At the address indicated on the first page of the Agreement.
To MnDOT at: Minnesota Department of Transportation
Office of State Aid
395 John Ireland Blvd., MS 500
Saint Paul, MN 55155
Attention: Patti Loken, State Aid Programs Engineer
To the Commissioner at: Minnesota Management & Budget
400 Centennial Office Bldg.
658 Cedar St.
St. Paul, MN 55155
Attention: Commissioner
Section 5.09 Assignment or Modification. Neither the Public Entity nor MnDOT may assign any
of its rights or obligations under the Agreement without the prior written consent of the other party.
Section 5.10 Waiver. Neither the failure by the Public Entity, MnDOT, or the Commissioner, as a
third party beneficiary of the Agreement, in one or more instances to insist upon the complete observance
or performance of any provision hereof, nor the failure of the Public Entity, MnDOT, or the
Commissioner to exercise any right or remedy conferred hereunder or afforded by law shall be construed
as waiving any breach of such provision or the right to exercise such right or remedy thereafter. In
addition, no delay by any of the Public Entity, MnDOT, or the Commissioner in exercising any right or
remedy hereunder shall operate as a waiver thereof, nor shall any single or partial exercise of any right or
remedy preclude other or further exercise thereof or the exercise of any other right or remedy.
15
Mn/DOT Agreement No. 03780
Section 5.11 Choice of Law and Venue. All matters relating to the validity, interpretation,
performance, or enforcement of the Agreement shall be determined in accordance with the laws of the
State of Minnesota. All legal actions arising from any provision of the Agreement shall be initiated and
venued in the State of Minnesota District Court located in St. Paul, Minnesota.
Section 5.12 Severability. If any provision of the Agreement is finally judged by any court to be
invalid, then the remaining provisions shall remain in full force and effect and they shall be interpreted,
performed, and enforced as if the invalid provision did not appear herein.
Section 5.13 Matching Funds. Any snatching funds as shown on Page 1 of the Grant Agreement
that are required to be obtained and supplied by the Public Entity must either be in the form of (i) cash
monies, (ii) legally binding commitments for money, or (iii) equivalent funds or contributions, including
equity, which have been or will be used to pay for the Project. The Public Entity shall supply to MnDOT
whatever documentation MnDOT may request to substantiate the availability and source of any matching
funds.
Section 5.14 Sources and Uses of Funds. The Public Entity represents to MnDOT and the
Commissioner that the Sources and Uses of Funds Schedule attached as Exhibit A accurately shows the
total cost of the Project and all of the funds that are available for the completion of the Project. The
Public Entity will supply any other information and documentation that MnDOT or the Commissioner
may request to support or explain any of the information contained in the Sources and Uses of Funds
Schedule. If any of the funds shown in the Sources and Uses of Funds Schedule have conditions
precedent to the release of such funds, the Public Entity must provide to MnDOT a detailed description of
such conditions and what is being done to satisfy such conditions.
Section 5.15 Project Completion Schedule. The Public Entity represents to MnDOT and the
Commissioner that the Project Completion Schedule attached as Exhibit B correctly and accurately sets
forth the projected schedule for the completion of the Project.
Section 5.16 Public Entity Tasks. Any tasks that the Agreement imposes upon the Public Entity
may be performed by such other entity as the Public Entity may select or designate, provided that the
failure of such other entity to perform said tasks shall be deemed to be a failure to perform by the Public
Entity.
Section 5.17 Data Practices. The Public Entity agrees with respect to any data that it possesses
regarding the G.O. Grant or the Project to comply with all of the provisions and restrictions contained in
the Minnesota Government Data Practices Act contained in Minnesota Statutes Chapter 13, as such may
subsequently be amended or replaced from time to time.
Section 5.18 Non - Discrimination. The Public Entity agrees to not engage in discriminatory
employment practices regarding the Project and it shall fully comply with all of the provisions contained
in Minnesota Statutes Chapters 363A and 181, as such may subsequently be amended or replaced from
time to time.
Section 5.19 Worker's Compensation. The Public Entity agrees to comply with all of the
provisions relating to worker's compensation contained in Minn. Stat. Secs. 176.181 subd. 2 and 176.182,
as they may be amended or replaced from time to time with respect to the Project.
Section 5.20 Antitrust Claims. The Public Entity hereby assigns to MnDOT and the
Commissioner of MMB all claims it may have for over charges as to goods or services provided with
16
Mn/DOT Agreement No. 03780
respect to the Project that arise under the antitrust lass of the State of Minnesota or of the United States
of America.
Section 5.21 Prevailing Wages. The Public Entity agrees to comply with all of the applicable
provisions contained in Minnesota Statutes Chapter 177, and specifically those provisions contained in
Minn. Stat. Secs. 177.41 through 177.435 as they may be amended or replaced from time to time with
respect to the Project. By agreeing to this provision, the Public Entity is not acknowledging or agreeing
that the cited provisions apply to the Project.
Section 5.22 Entire Agreement. The Agreement and all of the exhibits attached thereto embody
the entire agreement between the Public Entity and MnDOT, and there are no other agreements, either
oral or written, between the Public Entity and MnDOT on the subject matter hereof.
Section 5.23 E- Verification. The Public Entity agrees and acknowledges that it is aware of
Governor's ExecutiN a Order 08 -01 regarding e- verification of employment of all newly hired employees
to confirm that such employees are legally entitled to work in the United States, and that it will, if and
when applicable, fully comply with such order.
(The remaining portion of this page was intentionally left blank.)