HomeMy WebLinkAboutItem 06.kDate: 29 July 2013 Item No. 6k
APPROVAL OF AN OVERHANG ELECTRIC EASEMENT WITH NORTHERN STATES
POWER COMPANY, OUTLOT A, RIDGEVIEW 2ND ADDITION
Proposed Action
Staff recommends adoption of the following motion: Move to approve the rg anting of an
overhang electric easement with Northern States Power Company in Outlot A Ridgeview 2 nd
Addition.
Passage of this motion provides an additionai 10 foot easement for Northern States Power
Company for the upgrading of power lines in Lakeville.
Overview
Northern States Power Company, dba Xcel Energy, is in the process of upgrading both its
power poles and power lines on a section of line that runs northeast /southwest through
Lakeville. Part of the line running through the Ridgeview 2nd Addition has one of the longest
spans it the line and as such has the potential to sway in high winds outside the current
easement.
This creates a possible blow down problem in this area. Two possible solutions exist to solve
the blow down problem; one is to install another power pole; the other is to acquire an
addition to the existing easement. Installing another power pole has not been favorably
received by the affected property owners.
As a result, Northern States Power Company is seeking to acquire an additional 10 feet of
easement to meet the blow down requirements in this area. Staff has reviewed the easement
grant agreement and recommends its approval.
Primary Issues to Consider
• Does the easement affect any City facilities? The additional 10 foot easement does not
affect any City facilities.
Supporting Information
• A copy of the easement agreement and property description are attached.
Chr pher etree
Public Works Director
Financial Impact:
Related Documents (CIP, ERP, etc.):
Notes:
Budgeted: Source:
OVERHANG ELECTRIC EASEMENT
KNOW ALL BY THESE PRESENTS, That the undersigned, hereinafter called "Grantor ", in
rnn6deratinn of the ciim of $1.00 and other good and valuable -- 4 deratEen ir. hand paid 1 -- U
NORTHERN STATES POWER COMPANY, a Minnesota Corporation, d /b /a Xcel Energy, the receipt
and sufficiency whereof is hereby acknowledged, do hereby, grant unto said Company its successors and
assigns, hereinafter called "Grantee ", an overhang easement with the right, privilege and authority to
maintain its facilities for the transmission and distribution of electrical energy, including the necessary
wires, electric cables, and facilities related and appurtenant thereto, over, across, and upon said easement
on the following described Land situated in the County of Dakota, State of Minnesota, described on the
attached Exhibit A (the "Premises ").
Except for the right of access tree trimming and temporary working area, said easement shall be limited to
that part of the Premises (hereinafter called "Easement Area ") described the "Easement Area" on the
attached Exhibit A .
The grant of easement herein contained shall also include the right of reasonable access to said
easement across the Premises for the purpose of exercising the rights granted herein, together with the
right to remove from Easement Area any structure, trees, shrubbery, or other object or obstruction which
in Grantee's opinion interferes with said facilities or the removal of which may be reasonably necessary
for the construction or maintenance thereof. The grant of easement herein contained shall also include the
right of reasonable use of the Premises adjacent to the Easement Area by Grantee for tree trimming
purposes and for temporary construction area during construction, repair or replacement of said electric
facilities.
Except as otherwise provided herein or in any Underground Distribution Agreement between the
Grantor and Grantee covering the above described Premises, Grantee shall, after installation of the above
described electrical facilities, or after the exercise of any rights granted herein, restore the lands subject to
this easement to as near their original condition as is reasonably possible and remove therefrom all debris,
spoils, and equipment resulting from or used in connection with said installation.
Grantor further agrees that no structure or obstruction will be erected or permitted or any trees
planted on or within said Easement Area, that he will not change the ground elevation thereof without the
written consent of Grantee, or perform any act which will interfere with or endanger said electrical
facilities.
Page 1 of 3
Rev(1): 10 -4 -04
The grant herein contained shall also include the right of Grantee to permit the joint use of
overhead facilities and joint undergrounding with public utility and cable television companies.
Grantor covenants with Grantee, its successors and assigns, that Grantor is the owner of the above
described premises and has the right to sell and convey an easement in the manner and form aforesaid.
This instrument and the covenants and agreements contained herein are binding upon the Grantor,
his personal representatives, heirs, successors and assigns.
The Grantor agrees to execute and deliver to NSP, at NSP's cost, without additional
compensation any additional documents needed to correct the legal description of the easement area to
conform to the right of way actually occupied by the electric lines.
It is mutually understood and agreed that this instrument covers all the agreements and
stipulations between the parties and that no representation or statements, verbal or written, have been
made modifying, adding to or changing the terms hereof.
This instrument is exempt from the Minnesota Deed Tax.
IN WITNESS WHEREOF, the undersigned have caused this instrument to be duly executed as
of the day of 1 2013.
City of Lakeville, a municipal corporation
By
Matt Little
Its: Mayor
By
Char Friedges
Its: City Clerk
Page 2 of 3
Rev(1): 10 -4 -04
STATE OF MINNESOTA
COUNTY OF
SS.
The foregoing instrument was acknowledged before me this day of 20013,
by City of Lakeville, a municipal corporation.
Notary Public
This instrument was drafted by: TSM
Northers! States Power Company
414 Nicollet Mall, Minneapolis, MN 55401
Page 3 of 3
Rev(l): 10 -4 -04
NORTHERN STATES POWER
MINNESOTA
EXHIBIT A SHEET 1 OF 2
Easement Exhibit
Location: City of Lakeville, Dakota County, Minnesota
Grantor: City of Lakeville
See Sheet 2 of 2 for descriptions.
NE COR.
OUTLOT A, RIDGEVIE
SECOND ADDITION
POB
E. LINE OUTLOT A
wi
N (�
I�
<I�
y�
I�
/
DESCRIPTION LINE x.00, / i� D LS CRIF
& `/ G
NW'LY LINE OF
NSP EASEMENT PER
DOC NO. 26946
y / I
SEC. 7, T.114N., R20W., 5TH P.M.
CO.: DAKOTA
I HEREBY CERTIFY THAT THIS SURVEY, PLAN, OR
REPORT WAS PREPARED BY ME OR UNDER MY DIRECT
SUPERVISION AND THAT I AM A DULY LICENSED LAND
SURVEYOR UNDER THE LAWS OF THE STATE OF
MINNESOTA.
ERIC A. ROESER LIC. NO. 47476
DATE: 6) "7 1aZ //I
N
Scale: 11"= 60'
NORTHERN STATES POWER
MINNESOTA
EXHIBIT A SHEET 2 OF 2
Easement Exhibit
Location: City of Lakeville, Dakota County, Minnesota
Grantor: City of Lakeville
See Sheet 2 of 2 for descriptions.
Premises
Outlot A, Ridgeview Second Addition, according to the recorded plat thereof.
Easement Area:
A in nn F...4 -Ads easement ver ... der a n-1 .........., 11-at part _ s1b_ 1___: �_<_.__ _�. �'n._. .. 110
r ,v. vv rvut rnuc caacn,cm wc�, uuuci, an a,dvao Mal Pa,t VI UDC IjWj W;f1 UUJUJU ae5Gribea - YremlSeS,� lying 7U.UU
to the right of and abutting the following described line; said line also being the northwesterly line of that easement
reserved and described in document number 26946:
Commencing at the northeast corner of Outlot A, Ridgeview Second Addition, according to the recorded plat
thereof; thence South 00 degrees 45 minutes 25 seconds East on an assumed bearing along the east line of said
Outlot A, a distance of 178.36 feet to the intersection of the northwesterly line oft] let easement described in
document number 26946 and said east line of Outlot A, also being the point of beginning; thence South 41 degrees
57 minutes 59 seconds West along said northwesterly line of that easement described in document number 26946,
a distance of 367.67 feet to the southerly line of said Outlot A, and said line there terminating.
The sidelines of said easement are to be prolonged or shortened to terminate at the east and southerly lines of said
Outlot A.
Containing 3,755 square feet, or 0.09 acres, more or less.
SEC. 7, T.114N., R20W., 5TH P.M.
CO.: DAKOTA
Dakota County, MN
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a Map Scale
legal document and should not be substituted for a title search,appraisal, survey, or for zoning 1 inch = 126 feet
verification. Dakota County assumes no legal responsibility for the information contained in this data. 7/15/2013
Xce/ L�rtc�rc�►ysM
Line 0832 Rebuild Project
Easement Compensation Worksheet for:
Parcel: NIA
Citv of Lakeville
Residential Land
Property Value
Value
Acres
Easement
Easement Compensation
per acre
Adjustment
From Survey
Compensation
New Easement Payment: $7,545.00 40% 0.09 $271.62
Summary of Payments:
Easement Payment
Total Payments $750.00