HomeMy WebLinkAboutItem 06.dJuly 24, 2014 Item No. APPROVE CHANGE ORDER NO. 1, FINAL ACCEPTANCE AND FINAL PAYMENT TO MINNESOTA DIRT WORKS, INC. FOR KENYON AVENUE EROSION IMPROVEMENTS August 4, 2014 City Council Meeting Proposed Action Staff recommends adoption of the following motion: Move to approve Change Order No. 1 final acceptance and final payment to Minnesota Dirt Works Inc. for the Kenyon Avenue Erosion Improvements project, City Project 13-17. Passage of this motion will result in an adjustment to the contract price, final acceptance of the project and final payment to the contractor. Overview The contractor is requesting final acceptance and final payment for City Project 13-17. The original contract amount was $51,307.50 with one change order in the amount of $6,663.00, resulting in a total contract amount of $57,970.50. Change Order No. 1 is for work related to unforeseen field conditions encountered during construction. During construction, the City's geotechnical engineering consultant recommended additional clay fill to reconstruct and stabilize the slopes to reduce the risk of future slope instability and erosion. The final construction cost is $65,989.20 as a result of changed field conditions and necessary item overruns. The contractor has met the administrative requirements for final payment. Primary Issues to Consider Why was the change order work completed? The work was within the project scope and required a quick response to allow construction to continue in consideration of the weather. Any delay increased the risk of further erosion, which could have undermined Kenyon Avenue or entered into Lee Lake, and potentially extra costs. A lower unit price was negotiated resulting in overall project savings. Supporting Information Letter of Recommendation from WSB & Associates dated July 11, 2014 Change Order No. 1, Pay Estimate No. 1 and Final Za,Jo on City er Financial Impact: $65,989.20 Reiated Documents (CIP, ERP, etc.): Notes: Budgeted: Yes Source: Utility Fund — Env. Resources 7­4.rha'." hu. B? it?Gei!? ` planning, environmentaP construction 701 Xenia Avenue South Suite 300 M'€nneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541.1700 July 11, 2014 Mr. McKenzie Cafferty City of Lakeville 20195 Holyoke Avenue Lakeville, MN 55044 Re: Construction Pay Voucher No. I (Final) Kenyon Avenue Erosion Improvements City of Lakeville Project No. 13-17 WSB Project No, 2109-44 Dear Mr, Cafferty: Please find enclosed three copies Construction Pay Voucher No. 1 and final for the above -referenced project in the amount of $65,989.20. This amount includes a change order in the amount of $6,663.00. This change order was necessary to allow for additional clay fill to be hauled in and graded, providing additional stabilization of the erosion prone banks, at the direction of Braun Intertec. Also enclosed find the following documentation required for releasing final payment to the contractor: 1. Satisfactory showing that the contractor has complied with the provisions of Minnesota Statutes 290.92 requiring withholding state income tax (IC 134 forms). 2. Evidence in the form of an affidavit that all claims against the contractor by reasons of the contract have been fully paid or satisfactorily secured (lien waivers). I recommend payment and closeout of this project at this time. Please make payment in this amount to Minnesota Dirt Works at your earliest convenience. Let me know if you have any questions, Sincerely, WSB & Associates, Inc. Je Newhall, PE Project Manager Enclosures cc: Tom Berrrtel, Minnesota Dirt Works, Inc. Equal Opportunity Employer wsbeng.com K!1U21U934f31Adaa;n}L'onsrrnerion 1d.A.O.; ['R VO i FNL CTY 071014.du Owner: City of Lakeville 20195 Holyoke Avenue Lakeville, MN 55044-8339 For Period: 313/2014 to 6/3/2014 Contractor: Minnesota Dirt Works, Inc. 2500 West County Road 42 Burnsville, MN 65337 Pay Voucher LKVL - Kenyon Avenue Washout Client Contract No.: Project No.: 02109-44 Client Project No.: � —1'7 Date: 613/2014 Request Pio.: 1 & FINAL Project Sutvttnary 1 Original Contract Amount $51 307,501 2 Contract Changes -Addition $6,663,00 3 Contract Changes - deduction $0.00 4 Revised Contract Amount $57,970 501 5 Value Completed to Date $65,98920 6 Material on Hand $0.00 7 Amount Earned $65,989.20 8 Less Retainage $0.00 9 Subtotal I $65989.203 10 Less Amount Paid Previously $0:00 11 Liquidated Damages $0.00 =AMOUNT DUE THIS PAY VOUCHER NO. 1 & FINAL $65,989.20 I HEREBY CERTIFY THAT A FINAL EXAMINATION HAS BEEN MADE OF THE ABOVE NOTED CONTRACT, THAT THE CONTRACT HAS BEEN COMPLETED, THAT THE ENTIRE AMOUNT OF WORK SHOWN IN THE FINAL VOUCHER HAS BEEN PERFORMED AND THE TOTAL VALUE OF THE WORK PERFORMED IN ACCORDANCE WITH, AND PURSUANT TO, THE TERMS OF THE CONTRACT IS AS SHOWN IN THIS FINAL VOUCHER. Recommended for Approval by: WSB &Associates, Inc. e Z/7M Ap ed by Contractor: Minnesota Dirt Worms, Inc. Specified Contract Completion Date: 611/2014 Comment: Construction Observer: Approved by Owner: City of Lakeville Project Material Status Item No item Description I I Uri its Unit Price Contract Quantity Quantity to Date Current Quantity Amount to Date SCHEDULE A - BASE BID 1 2021.501 IMOBILIZATION LS $2,550.00 1 1 1 $2,550.00 2 2104.501 IREMOVE SEWER PIPE (STORM) L F $15.00 60 54 54 $810.00 3 2104.509 REMOVE DRAINAGE STRUCTURE EACH $525.00 1 1 1 $525.00 4 12105,601 SITE. GRADING LS $18,500.06 1 1 1 $18,500.00 5 21D5.603 JCLAY BORROW CU YD $25.45 501 200 200 $5,090.00 6 2105.604 GEOTEXTILE FABRIC TYPE IV S Y $2.00 120 90 90 $180.00 7 2501.515 30" RC APRON WITH T. G. AND SHEET PILED END SECTION EACH $5,600.00, 1 1 1 $5,600.00 8 2503.511 30" RC PIPE SEWER CLASS III L F $64.30 150 159 159 $10,223.70 g 2506.502 CONST DRAINAGE STRUCTURE DES 60-4020 EACH $6,125.00 1 1 1 $6,125.D0 10, 12511.501 RANDOM RIPRAP CLASS III (FIELDSTONE) CU YD $97.50 40 70 70 $6.825.D0 11 2563.601 TRAFFIC CONTROL ILS 1 $250.00 1 1 1 $250.00 12 2573.502 SILT FENCE, TYPE HEAVY DUTY LIN FT $3.00 150 250 250 $750.00 13 2575.523 JEROSION CONTROL BLANKETS CATEGORY 2 ISY $1:50 9001 1265 1265 $1.897.50 Totals For Section SCHEDULE A - BASE BID: $59,326.20 Change Order 1 14 12105.607 CLAY FILL CU YD $13.50 388 388 388 $5;238.00 15 2101:511 CLEARING AND GRUBBING LUMP SUM $925.00 1 1 1 $925:00 16 2506:602 CLEAN OUT FES LUMP SUM $300.00 1 1 1 $300.0 17 97078 REMOVE WOOD FENCE LUMP SUM $2D0.00 1 1 1 $200.00 Totals Far Change Order 1: $6,663.00, Project Tote Is: 1 $65,982.20 Project Payment States Owner: City of Lakeville Client Project Pio.: Client Contract No.: Project No.: 02109-44 Contractor: Minnesota Dirt Works, Inc. dontract Chars es No.Type JDate JDescription Amount COI Change Order 16/3/2014 lAddition of line items 14-17. $6.663.00 Change Order Totals: $6,663.00 Pavmant Sura rary No. From To Date Payment Total Retainage Total Total Work JTotal Work Date Payment Per Retainage Payment Certified Per Certified Payment Retainage Payment 1 & FINAL 31312014 , 6/3/2014 $65,989.20 $65,989.20 $0.00 $0.00 $66,989.20 $65,98920 $65,989.20 Payment Totals: $65,989.201 $0.,OOL $65,989.20 $65,988.20. Ppjest Summary Material On Flared: Total Payment to Date: Total Retainage: Total Amount Earned: $0.00 $66,989.20 Original Contract: $0.00 Contract Changes: $65,989.20 Revised Contract: $51,307:50 $6,663.00 $57,470.50