HomeMy WebLinkAboutItem 06.jDate: 18 August 2014 Item No. APPROVAL OF THE 2014 MISCELLENEOUS ROADWAY REPAIRS PROJECT CITY PROJECT 14-01 CHANGE ORDER NO. 1 PrgMr&d Action Staff recommends adoption of the following motion: Move to approve the 2014 Miscellaneous Roadwaypairs Project Change Order No,1 increasing the contract sum in the amount of $23.860.00 Passage of this motion acknowledges the installation of two additional catchbasin structures at the low point of the King Park parking lot and additional grading work between the existing trail along Dodd Boulevard and the new curb section to be installed along the west side of the parking lot to better facilitate drainage in the area. OyerAew This change order adds two new drainage structures at the low point of the King Park parking lot, adjacent to the concession building. Prior to paving the parking lot and installing these two new drainage structures, water would overtop the existing curb along the east side of the parking lot and flow down the paved trail adjacent to the concession building. The installation of the new storm sewer structures will assist with conveying the runoff generated by the newly paved parking lot into the underground storm sewer system prior to overtopping the curb in this location. Additional grading work was also required along the west side of the parking lot, between the existing Dodd Boulevard trail and the new concrete curb and gutter. This grading work will sere to better drain this area of the parking lot and extend the useful life of the new parking lot pavement. Staff has reviewed the change order and recommends approval. Primary Issues to Consider • What is the impact to the contract? This change order increased the contract by $23,860.00 to a total of $1,325,326.49. • How important was this change to the project? Without the addition of the new storm sewer structures and the grading work, drainage issues within the King Park parking lot would have resulted in the premature deterioration of the new pavement surface, and created standing water issues near the concession building and the newly constructed playground. Supportmg Information • Copies of Change Order No. 1, Change Order No.1 detail are attached. &M YV' Lo' ga :2zeAO�---� Monica Heil Brett Altergott Operations and Maintenance Engineer Parks and Recr ' n Director Financial Impact: $23,860.00 Budgeted: Related Documents (CIP, ERP, etc.): Notes: Increases the contract amount of C.P Yes Source: Park Dedication 14-01 to $1,325,326.49. CHANGE ORDER NO. 1 Owner: City of Lakeville Project No.: 2014 Miscellaneous Roadway Repairs Project: Project Contractor: McNamara Contractinq, Inc. 14-01 Contract Date: April 21, 2014 Original Contract Amount: $1,301,466.49 To: McNamara Contracting, Inc. (Contractor), you are hereby directed to make the changes noted below in the subject Contract: Owner: City of Lakeville By: Date: August 18, 2014 By: Matt Little, Mayor Charlene Friedges, City Clerk Nature of the Changes: See the attached Change Order for a description of the change and supporting information. These changes result in the following adjustment of Contract Price and Contract Time: Contract Price Prior to this Change Order $ 1,301,466.49 Net Increase/Decrease Resulting from this Change Order 23,860.00 Current Contract Price, Including this Change Order $ 1,325,326.49 The above changes are approved: The above changes are accepted: CITY OF LAKEVILLE .12 Monica Heil Operations and Maintenance Engineer Date: 19 August 2014 LU Date: AcNamaird CAmtractins. Inc. +44cNamaral Ccntracthile, t®lic 16700 Chippendale Aire_ Rosemount, Iv>N 55068 Phone: 651.322.5500 Fax: 651.322.5550 Plant: 651.322.3939 www.rncnamaracontractiinj%.com To: LAKEVILLE CITY OF Address: 20195 HOLYOKE AVENUE LAKEVILLE, MN 55044 Contact: Phone: Fax: Project Name: 2014 - King Park Additional Work Project Location: Bid Number: Bid Date: $3,805.00 $7,610.00 Line # Item Description Estimated Quantity Unit Unit Price Total Price 1 Mobilization 2 F & 148" CB/MH on top of existing 18" RCP 3 Catch Basin Casting Assembly (3067) 3 Salvage & Reinstall Existing Catch Basin Casting 4 Remove and Replace Curb for modified storm sewer 5 Remove and Replace Bituminous Trail for storm sewer construction 6 Grade between Dodd Road bituminous trail and new curb on the west portion of the lot to drain 1.00 LS $3,500.00 $3,500.00 2.00 EACH $3,805.00 $7,610.00 2.00 EACH $1,000.00 $2,000.00 1.00 EACH $600.00 $600.00 30.00 LF $60.00 $1,800.00 300.00 SF $10.00 $3,000.00 1.00 LS $5,350.00 $5,350.00 Total Bid Price: $23,860.00 Notes: • Quantities are estimates, billing will be based on actual quantity installed • All turf establishment in green areas affected by extra work to be paid at contract prices. • Grading quoted assumes a straight grade between Dodd Blvd bituminous trail and new back of curb; due to design there may be areas that will still hold water. Payment Terms: Payment due within 10 days after payment is made by Owner or within 30 days of invoice; whichever is sooner ACCEPTED: The above prices, specifications and conditions are satisfactory and are hereby accepted. Buyer: Signature: Date of Acceptance: 8/7/2014 2:47:05 PM CONFIRMED: McNamara Contracting, Inc. Authorized Signature: Estimator: Mike McNamara (612) 363-8191 m.mcnamara@mcnamaracontracting.com Page 1 of 1