Loading...
HomeMy WebLinkAboutWS Item 05Memorandum To: From: Copy: Date: Subject: Background• Mayor, City Council & City Administrator Brett Altergott, Parks & Recreation Director -VQ Zach Johnson, City Engineer John Hennen, Parks & Operations Manager September 11, 2014 Kenrick Ave. Trail Slope Erosion City of Lakeville Parks & Recreation The slope north of Marek's Towing is experiencing erosion issues. Since the spring the slope has eroded twice, once following the record rainfalls in the spring after which it was reconstructed and again following the heavy rains Father's Day weekend. Why is the slope eroding? The primary reason for erosion is the steep slopes and granular soils that make up the embankment. Why is the slope so steep? In late 2011, WSB was directed by staff to design this section of the trail without affecting the snowmobile trail at the bottom of the embankment and there is an existing box culvert within the slope that was not extended. In mid-June, staff directed WSB to propose the City with options and cost estimates for solutions that reduce the likelihood of future slope erosion issues like the ones experienced in 2014. Included with this packet is a memo from WSB outlining the options considered, cost estimates of the recommended solution and photos of the current condition of the slope. There is approximately $44,000 remaining in the project contingency fund, any additional costs would be funded through Park Dedication. Don Sterna of WSB will be in attendance at the City Council Work Session to make a brief presentation and answer any questions. Recommendation: Staff concurs with WSB recommendation to flatten the slopes to at least 1:2 by the construction of a Prefabricated Modular Block Wall (PMBW), seeding, blanketing, and other erosion measures as outlined in the WSB memo dated August 21. WSB & Aaurrintati, brr, enquieering• planning- environmental• construction 701 Xenia Avenue South Suite 300 Minneapolis, MN 55416 Tel: 763-541-4800 Fax: 763-541-1700 Technical Memorandum To: BrettAltergott - Lakeville Parks & Recreation From: Don Sterna, P.E. - WSB & Associates, Inc. Date: August 21, 2014 Re: Retaining Wall Comparison Kenrick Avenue Trail WSB Project No. 01715-84 The purpose of this memo is to document existing conditions along the Kenrick Avenue Trail and to present alternatives, along with a preferred recommendation to address slope stability concerns. Summary of Existing Conditions Currently a section of approximately 200 feet of the embankment along the Kenrick Trail (Figure 1) is experiencing erosion. Erosion is occurring primarily as a result of the steep slopes and in-place granular embankment material which is not able to remain in place after heavy rain events. Post roadway construction slopes along Kenrick Avenue where approximately 1:2 and remained stable for a number of years with no signs of erosion. In 2013, the Kenrick Trail project was designed to maintain a 20 -foot wide snowmobile path at the toe of the slope and a 10 -foot wide trail along the east side of Kenrick Avenue. Guardrail was placed between the roadway and trail to provide vehicular safety and a fence was placed along the trail for pedestrian safety. In order to construct the trail, the embankment slope needed to be steeper than the in place embankment. For a stretch of approximately 200 feet, the slope was steeped beyond the in place 1:2 slopes. The area of erosion is occurring mainly in this 200 -foot stretch which the contractor has been unable to stabilize, even with using heavy duty erosion control blankets and bio -rolls. There are several factors contributing to the continued erosion. These factors include: ■ Slopes steeper than 1:2 ■ Granular embankment fill ■ An increase in impervious surface ■ Heavier than normal rainfall events The interaction plan between the granular embankment and the topsoil layer are not holding when the topsoil becomes saturated. Once the top soil becomes saturated, the increased weight is enough that the topsoil slides down the hill, which opens up the granular material to further erosion. The use of geosythetic matting (erosion control blankets) over the slope does not prevent the topsoil from becoming saturated. Equal Opportunity Employer vtsbeng.com K:'.01715-8401..dmin\Docs.altagott Tech Memo 8-21-14.docx Brett Altergott August 21, 2014 Page 2 Alternatives Considered There are a several wall types that could be utilized to address slope stability. These alternatives vary in construction methods and costs. We reviewed several wall types and made an in-depth analysis of three wall options along the corridor, along with evaluating the opportunity to extend the existing box culvert. The option to extend the culvert was eliminated early in the process since the original culvert is a cast in place structure. It would be technically challenging and extremely expensive to construct. This alternative would still require some type of wall along the toe of the slope and the stream would have to be diverted for construction. The three wall options considered to stabilize the embankment included: 1. Prefabricated Modular Block Wall (PMBW) 2. Reinforced Soil Slope Wall (RSS) 3. Sheet pile wall The preferred means of construction for the wall is one that requires minimal excavation and utilizes smaller and more maneuverable equipment that can be used within tight constraints. The intent would be to avoid impacts to the trail. Alternatives Evaluation Preliminary designs for the three retaining wall types listed in the previous section were developed to determine construction costs and the associated construction limit impacts. Associated impacts include constructability, material delivery, working limits, costs and avoid temporary or permanent easement costs. Evaluation criteria include: ■ Cost o Constructability o Right of way and easements o Avoid impacts to existing trail ■ Construction Limit Impacts o Overhead power line o Material delivery o Quick construction methods K:101715-840`AdminlDoa 4ltergott Tech Memo 8-21-14.docx Brett Altergott August 21, 2014 Page 3 PMBW with Soil Reinforcement A PMBW could be constructed without the use of geosythetic grids up to heights of 8 feet. Heights above that require the use of geosythetic grids. The lower height walls can be constructed by excavating for the footing and then placing the precast wall units. Heights above 8 feet will require excavation IM on some of the in place embankment to install the grid and then the wall is back filled with granular material. The excess material can be placed along the base of the in place embankment to flatten the slopes, thereby reducing the need to haul any material off site. This method requires less fill to flatten the slopes outside the wall area. Reinforced Soil Wall (RSS) The RSS would require a significant amount of the embankment to be excavated in order to install the many layers of geosythetic grid necessary to would develop the strength to support the embankment. This alternative requires the in-place embankment material to be removed from the grid area and be replaced with granular borrow. This alternative was rejected due to the challenges associated with constructing the wall around the existing box culvert and the amount of granular material required. It would also take longer to construct than other alternatives. K. 01715-840\Admin\Dom\AItergott Tech Memo 21-14.dom Brett Altergott August 21, 2014 Page 4 Sheet Pile Wall The sheet pile alternative would require driving sheeting vertically into the ground. Approximately 12 feet would be above ground, with another 24 feet extending below ground to provide the needed stabilization. Constructing this wall would require the use of a crane to drive the sheeting and would require the relocation of existing overhead power lines. This alternative was rejected due to the types of construction equipment needed, ability to fit and maneuver equipment in the area, the conflict with the overhead power lines and the time needed to get the sheeting material. Recommendation The only long-term solution to the existing problem is to flatten the slopes to at least a 1:2 and then reseed and cover the slopes with heavy duty erosion control blankets with bio -rolls firmly staked along the slope to assist in dissipating heavier rain fall events. After reviewing the wall options, costs, constructability, material delivery schedules, working area, and ability to meet long-term needs, WSB recommends the use of the Prefabricated Modular Block Wall (PMBW). The PMBW alternative allows for the construction of flatter slopes which is needed for long-term stabilization. This alternative keeps construction limits within existing right of way, allows for the use of smaller equipment and can be done with minimal disruption to the existing area and trail. Attached to this memo are the proposed plans and cross section showing the limits of the work required to construct the preferred alternative. Ki,01715•i46 AdminlDocsW ltergott Tech Memo 8-21-14.doc- Y�� 28* of c V ev ol k4L. UI I mI1 .4 »1044) §` �| | E�eq 10 < w 0 | !m• _®§/ \}kcc . "§§ §0 ; 0 \| � m; 1; 14 N$ p w r n a F H m .. O N n F F °� g •+ N ❑ p r O� m u Pi n a N M � p [� o n N �J+ N F b p O E W Fg m y V1 �oF� H o a H H x C.ILn cF m Q B 8 6OD N H r -I W P, o 1 N Ei z H m a H U � � ❑ '� W � V F n m )am z � r u U C �• � s ¢H¢ pl t0 Gi •Lmll ip&C N hWY u V L N 2 0 0 F �a�y .p] W� h d pN m N a1 z 7 £ 3 m U 1 u U v o a V v 0 41 N Intl m 3 x W a m = a F IL as�� � r _t LL r ,✓ 5 as�� \ , ■ - . .i rj � , v iM •'� A.0" a 'a ;^'S r ':,, TR •` �''`C�., n }�sl. � .• � S� ,{ "^��'�+�+hNN �- C' q9,�� - r \� ' � ! _ �' 711 � �(' k. f � ► . 1 . r �;;�,A1:` 'Q r- c -,xs ���. ,{,.•r fir^}t, y y LrTICv! i1 ION, •:,' -ON1 , �v+r'►ti -�� Jr dry . �� • � � �� �� �� ` � � TM, + i.,, r�. ,4 +' •. tip, e rc� t� i � iM IT .01 Ji- Jvat e t • +., Ohl. • r y+ • t It 06 40 i t _ 'tel - � ♦ # -