HomeMy WebLinkAboutItem 06.l® / D
January 14, 2015
ROSE CREEK
FINAL ACCEP'T'ANCE OF PUBLIC STREETS
January 20, 2015 City Council Meeting
Proposed. Action
Item No.
Staff recommends adoption of the following motion: Move to approve final acceptance of
public streets _within Rase Creek.
Passage of this motion will result in approval and acceptance of the developer -installed
public street improvements constructed with the Rose Creek subdivision.
Overview
Rose Lake Development is requesting final acceptance of the public street improvements that
were constructed with the development of Rose Creek. The prime contractor responsible for
work on this project was Friedges Contracting.
The curb and gutter, and first lift of bituminous pavement were constructed in 2013. The final
bituminous wear course was constructed in 2014. The street improvements for the above -
referenced project have been tested and inspected by WSB and Associates and the Public
Works Department.
Primary Issues to Consider
• Do the completed improvements meet City standards? All work was satisfactorily
completed consistent with the City's construction standard specifications and the
developer has met the administrative requirements for final acceptance.
Supporting -Information
® None.
Zach oh on
City nginee
Financial Impact: $0 Budgeted: N/A Source:
Related Documents (CIP, ERP, etc.):
Notes: