HomeMy WebLinkAboutItem 06.kLakes
Date: 27 January 2015 Item No.
RESOLUTION ACCEPTING BIDS AND AWARDING THE CONTRACT FOR THE
WATER TREATMENT FACILITY IMPROVEMENT PROJECT TO
GRIDOR CONSTRUCTION
Proposed Action
Staff recommends adoption of the following motion: Move to accept bids and award the
contract for the Water Treatment Facility Improvement Project to Gridor Construction.
Passage of this motion enables the facility modifications, equipment installation, and
reservoir construction necessary for the Water Treatment Facility to meet water use demands.
Overview
This improvement project for the Water Treatment Facility (WTF) is based on the outcomes of
the 2013 WTF expansion study. It will expand the capacity of the facility to handle increased
water production to meet expected residential, commercial, industrial, institutional, and
emergency demands.
The project adds a fifth high service pump, expands the chlorine system, installs a larger
fluoride day tank, adds a second air wash blower, updates chemical feed pumps, and
constructs a 1 million gallon reservoir expansion. The engineer's estimate for the project was
$3.735 million.
The City received four bids with a bid range of $3.087 to $3.737 million. Gridor Construction
submitted the lowest responsible bid at $3.087 million, approximately 17 percent below the
engineer's estimate. Staff, along with the consulting engineer, reviewed the bids and
recommend award of the contract to Gridor Construction.
Primary Issues to Consider
• Are these improvements necessary? The comprehensive water system study showed that
the City was unable to ymeet near-term demand for water with the current facility
configuration. These improvements expand facility capacity to meet those peak demands
and avoid costly expansion of the facility over the next five to eight years.
Supporting Information
• A copy of the letter of recommendation from Black & Veatch, the bid tabulation and
c e at d.
Christo J. Petree
Public Works Director
Financial Impact: $3,087,700.00 Budgeted: Yes Source: Water Trunk Fund
Related Documents (CIP, ERP, etc.):
Community Values: Good Value for Public Services
CITY OF LAKEVILLE
RESOLUTION NO:
RESOLUTION ACCEPTING BIDS AND AWARDING THE CONTRACT FOR THE
WATER TREATMENT FACILITY IMPROVEMENT PROJECT TO
GRIDOR CONSTRUCTION
WHEREAS, invitations to bidders for the Water Treatment Facility Improvements
Project were officially published on 12 December 2014, and
WHEREAS, sealed bids for the project were opened at 11:00 a.m. on
16 January 2015, and
WHEREAS, the lowest responsible bidder for the project at a total cost of
$3,087,700.00 was Gridor Construction, 3990 27d' Street SE, Buffalo Minnesota.
NOW, THEREFORE, BE IT RESOLVED, that the bids are accepted for the Water
Treatment Facility Improvement Project and the contract is awarded to Gridor
Construction.
APPROVED AND ADOPTED this 2nd day of February 2015 by the City Council
of the City of Lakeville.
CITY OF LAKEVILLE
Matt Little, Mayor
ATTEST:
Charlene Friedges, City Clerk
BLACK&VEATCH
Building a world of diffarenca;
January 27, 2015
City of Lakeville, MN
Water Treatment Facility Improvements
Christopher Petree
City of Lakeville
Public Works Director
18400 Ipay a Avenue
Lakeville. ,MN 55044
Subject: Bid Results and Recommendation
Dear Mr, Petree;
SCOTT FRONEK
Project Manager, Water Division
7760 MANCE AVENUE SOUTh, SUITE .300.
af40%EAPOI S, %1% SFA35
u95v n -0500 j FRixV`u imD; By ckmi
Bids for general construction work were received and opened on January 16, 2015, at
Lakeville City Hall. for the Water Treatment Facility (WTF) Improvements Project A
review of the low bid received was completed as well as a limited review of the
apparent low bidder. A summary of the Bid Tabulation is included as an attachment.
The following is list of the lump suns base bids, in ascending value. The Engineer's
Estimate for the project was estimated at $3„735,000.
Construction Company
lump Sum Bid
Gridor Construction
$3.087,700
Rice Lake Construction Group
$3.109.600
Magney Construction
$3,457,300
Lakehead -Construction
$3,737.000
This letter provides a review on a number of topics related to the bidding process.
We have performed a limited review of Gridor Construction to assist the City in
evaluating and establishing that Gridor has the technical experience and practical
knowledge to perform the WTF Improvements work. Black & Veatch reviewed the
following items in regard to Gridor Construction:
• Similar Project Experience
Project Manager and Superintendent
Other Information
_ BID RESULT', AND PAGE 3
PECQ FFNIENDATIGN
;ANVAP? 27. 2025
OTHER INFORMATION
Black & Veatch reviewed the Bid Form. List of Subcontractors, and the Equipment
Questionnaire. At this time. we believe that all listed equipment manufacturers are
acceptable.
For major subcontractors. Gridor has listed EIM and Automatic Systems as their
electrical and I&C subcontractors. EIM completed the previous electrical work for the
City of Lakeville's WTF expansion in 2002. and are familiar with the facility.
Automatic Systems is also familiar with the WTF, having previously worked at the
facility and more recently provided configuration services for ongoing plant control
issues.
The equipment questionnaire for Gridor, indicated they plan to use Capital for the Gas
Chemical Feed Systems, Blue White pumps for fluoride pumps. Pratt for Butterfly
Valves. and Siemens for a Variable Frequency Drive. The City is familiar with most of
this equipment already since many are already utilized within the City's WTF.
Additionally, Black & Veatch has had successful experiences with each of these
manufacturers.
Gridor also indicated a $25,000 potential deduct should the City choose to use
Continental blowers in lieu of the Hoffman Blower which was base bid. The City can
consider this change and if adopted would be implemented as a credit change order
following execution of the contract with Gridor.
SUMMARY
Based on the information reviewed and our evaluation, we recommend that the City
award the WTF Improvements Project Gridor Construction Inc.
Please contact me if you have any questions.
Sincerely,
BLAC_K& VVEATCH f
Scott D. Fronek P.E.
Project Manager
Enclosures
row
ll
5
log
ull
>1
41
Le)
(D
0
Q
la
en
ca
co
'o
CG
.2
E
E
I
tr,
cn
cz
ea
Lo
ci
FA
O
Ix
W
O '43
10
15-
o
fn
c
LL
wo
r_
ri
C
U.
8X
CL
CL
0)
Iry
iz
Section 00500
AGREEMENT
This Agreement is by and between the City of Lakeville, Minnesota (herein called Owner)
and Gridor Construction, Inc. (herein called Contractor).
Owner and Contractor, in consideration of the mutual covenants herein set forth, agree
as follows:
ARTICLE 1 - WORK.
1.01. Contractor shall complete all Work as specified or indicated in the Contract
Documents based on the acceptance by Owner of Contractor's Bid.
The Work is generally described as follows:
This project is an improvements project to the Lakeville Water Treatment Facility (WTF)
which will increase the capacity of the WTF and provide redundant backup equipment.
To increase the capacity of the WTF, a fifth High Service Pump will be installed to
provide additional capacity to the existing High Service Pump Station. An existing
reservoir will be expanded by 1 million gallons to provide additional storage at the WTF.
The chlorine system will be expanded by installing scales and manifold piping for two
additional gaseous chlorine cylinders and the chlorine feeders will be increased in size.
The fluoride day tank will be replaced with a larger tank. In addition to the items listed
above to increase the capacity of the WTF, the existing fluoride metering pumps will be
replaced and a redundant air wash blower and wash water supply pump for the backwash
system will be provided.
ARTICLE 2 - ENGINEER.
2.01. The Project has been designed by Black & Veatch Corporation, 7760 France Avenue
South, Suite 1200, Minneapolis, Minnesota 55435, who is referred to in the Contract
Documents as Engineer. Engineer, and its duly authorized agents, are to act as Owner's
representatives, assume all duties and responsibilities, and have the rights and authority
assigned to Engineer in the Contract Documents in connection with completion of the
Work in accordance with the Contract Documents.
ARTICLE 3 - CONTRACT TIMES, LIQUIDATED DAMAGES, DELAYS AND
DAMAGES, DELAY COMPENSATION.
3.01. Time of the Essence.
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -1-
012715
A. All time limits for Substantial Completion, and completion and readiness for final
payment as stated in the Contract Documents are of the essence of the Contract.
3.02. Contract Times.
A. The Contract Times shall be as indicated in the Contractor's Bid. The Work
shall be substantially completed within the number of days indicated in the Contractor's
Bid after the date when the Contract Times commence to run as provided in Paragraph
2.03 of the General Conditions, and completed and ready for final payment in accordance
with Paragraph 14.07.13 of the General Conditions within the number of days indicated in
the Contractor's Bid after the date when the Contract Times commence to run.
3.03. Liquidated Damages.
A. Owner and Contractor recognize that time is of the essence of this Agreement
and that Owner will suffer financial loss if the Work is not completed within the times
specified in Paragraph 3.02 above, plus any extensions thereof allowed in accordance with
Article 12 of the General Conditions. The parties also recognize the delays, expense, and
difficulties involved in proving in a legal or arbitration proceeding the actual loss suffered
by Owner if the Work is not completed on time. Accordingly, instead of requiring any
such proof, Owner and Contractor agree that as liquidated damages for delay (but not as
a penalty) Contractor shall pay Owner $2,500 for each day that expires after the time
specified in Paragraph 3.02 for Substantial Completion until the Work is substantially
completed. After Substantial Completion, if Contractor shall neglect, refuse, or fail to
complete the remaining Work within the Contract Times or any proper extension thereof
granted by Owner, Contractor shall pay Owner $2,500 for each day that expires after the
time specified in Paragraph 3.02 for completion and readiness for final payment until the
Work is completed and ready for final payment.
B. The liquidated damages set forth herein shall not be accumulative. If
Substantial Completion of the Work is not met within the time specified for final
completion of all Work, the liquidated damages shall continue to be at the rate or rates
specified for default on Substantial Completion until Substantial Completion is attained.
If the Work is not then finally completed, the rate or rates specified for default on final
completion shall apply until final completion is attained.
C. Owner shall have the right to deduct the liquidated damages from any money in
its hands, otherwise due, or to become due, to Contractor, or to initiate applicable dispute
resolution procedures and to recover liquidated damages for nonperformance of this
Contract within the time stipulated.
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -2-
012715
3.04. Delays and Damages.
A. In the event Contractor is delayed in the prosecution and completion of the
Work because of any delays caused by Owner or Engineer and, except as set forth in
Paragraph 4.01 of the General Conditions, Contractor shall have no claim against Owner
or Engineer for damages or contract adjustment other than an extension of the Contract
Times and the waiving of liquidated damages during the period occasioned by the delay.
ARTICLE 4 - CONTRACT PRICE.
4.01. Owner shall pay Contractor in current funds, for completion of the Work
designated in Article 1 in accordance with the Contract Documents, a Lump Sum amount
of: $3,087,700 , as indicated in Contractor's Bid.
ARTICLE 5 - PAYMENT PROCEDURES.
5.01. Submittal and Processing of Payments.
A. Contractor shall submit Applications for Payment in accordance with Article
14 of the General Conditions. Applications for Payment will be processed by Engineer as
provided in the General Conditions.
5.02. Progress Payments; Retainage.
A. Owner shall make progress payments on account of the Contract Price on the
basis of Contractor's Applications for Payment as recommended by Engineer, on or about
the 1st day of each month during performance of the Work. All progress payments will
be on the basis of the progress of the Work measured by the Schedule of
Values established in Paragraph 2.07.A of the General Conditions (and in the case of Unit
Price Work based on the number of units completed) or, in the event there is no Schedule
of Values or cost loaded Progress Schedule, as provided in Division 1, General
Requirements.
B. Prior to Substantial Completion, Owner will retain from progress payments,
less the aggregate of payments previously made and less such amounts as Engineer shall
determine or Owner may withhold in accordance with Paragraph 14.02.B.5 of the
General Conditions, an amount equal to the following percentages:
1. Until the Work is 50 percent completed, retainage will be 10 percent of
Work completed.
2. If the Work is 50 percent completed as determined by Engineer, and if the
character and progress of the Work are satisfactory to Owner and Engineer,
Owner, on recommendation of Engineer, may determine that as long as the
character and progress of the Work remain satisfactory to them, there will
be no additional retainage on account of Work subsequently completed.
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -3-
012715
C. Upon Substantial Completion, Owner may release a portion of the retainage to
Contractor, retaining at all times an amount sufficient to cover the cost of the Work
remaining to be completed.
D. The reduction or termination of additional retainage will not be initiated at
any time if the Work is behind schedule; and, subsequent to reducing retainage, the full
retainage of payments authorized may be reinstated any time the Work falls behind
schedule.
E. Consent of the Surety shall be obtained before any retainage is paid by Owner.
Consent of the Surety, signed by an agent, must be accompanied by a certified copy of
such agent's authority to act for the Surety.
5.03. Final Payment.
A. Upon completion and acceptance of the Work in accordance with Paragraph
14.07.A of the General Conditions, Owner shall pay the remainder of the Contract Price
as recommended by Engineer as provided in Paragraph 14.07.B.
ARTICLE 6 - CONTRACTOR'S REPRESENTATIONS.
6.01. In order to induce Owner to enter into this Agreement, Contractor makes the
following representations:
A. Contractor has examined and carefully studied the Contract Documents and
the other related data identified in the Bidding Documents.
B. Contractor has visited the Site and become familiar with and is satisfied as to
the general, local, and Site conditions that may affect cost, progress, and performance of
the Work.
C. Contractor is familiar with and is satisfied as to all Federal, state, and local
Laws and Regulations that spay affect cost, progress, and performance of the Work.
D. Contractor has studied all reports of explorations and tests of subsurface
conditions at or contiguous to the Site and all drawings of physical conditions in or
relating to existing surface or subsurface structures at or contiguous to the Site (except
Underground Facilities) which have been identified in the. Supplementary Conditions as
provided in Paragraph 4.02 of the General Conditions and reports and drawings of a
Hazardous Environmental Condition, if any, at the Site which has been identified in the
Supplementary Conditions as provided in Paragraph 4.06 of the General Conditions.
E. Contractor has obtained and carefully studied (or assumes responsibility for
having done so) all additional or supplementary examinations, investigations,
explorations, tests, studies, and data concerning conditions (surface, subsurface, and
Underground Facilities) at or contiguous to the Site which may affect cost, progress, or
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -4-
012715
performance of the Work or which relate to any aspect of the means, methods,
techniques, sequences, and procedures of construction to be employed by Contractor,
including application of the specific means, methods, techniques, sequences, and
procedures of construction, if any, expressly required by the Contract Documents to be
employed by Contractor, and safety precautions and programs incident thereto.
F. Contractor does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance of the Work at the
Contract Price, within the Contract Times, and in accordance with the other terms and
conditions of the Contract Documents.
G. Contractor is aware of the general nature of work to be performed by Owner
and others at the Site that relates to the Work as indicated in the Contract Documents.
H. Contractor has correlated the information known to Contractor, information
and observations obtained from visits to the Site, reports and drawings identified in the
Contract Drawings, and all additional examinations, investigations, explorations, tests,
studies, and data with the Contract Documents.
I. Contractor has given Engineer written notice of all conflicts, errors,
ambiguities, or discrepancies that Contractor has discovered in the Contract Documents,
and the written resolution thereof by Engineer is acceptable to Contractor.
J. The Contract Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for performance and furnishing of the Work.
ARTICLE 7 - CONTRACT DOCUMENTS.
A. The Contract Documents which comprise the entire agreement between
Owner and Contractor concerning the Work consist of the following:
1. This Agreement.
2. Performance and Payment Bonds.
3. General Conditions.
4. Supplementary Conditions.
5. Specifications.
6. Drawings consisting of 44 sheets, with each sheet bearing the following
general title:
City of Lakeville, Minnesota
Water Treatment Facility Improvements Project
Sheet titles are listed on Sheet 1 in the section entitled Drawings.
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -5-
012715
7. Addendum 1.
8. Exhibits to this Agreement, enumerated as follows:
a. Contractor's Bid.
b. Notice to Proceed.
9. The following, which may be delivered or issued after the Effective Date of
the Agreement and are not attached hereto:
a.Work Change Directives.
b. Change Orders.
c.Field Orders.
B. There are no Contract Documents other than those listed in this Article.
C. The Contract Documents maybe amended, modified, or supplemented only
as provided in Paragraph 3.04 of the General Conditions.
ARTICLE 8 - MISCELLANEOUS.
8.01. Terms.
A. Terms used in this. Agreement will have the meanings indicated in the General
Conditions and Supplementary Conditions.
8.02. Assignment of Contract.
A. No assignment by a party hereto of any rights under or interests in the
Contract will be binding on another party hereto without the written consent of the party
sought to be bound; and specifically, but without limitation, moneys that may become
due and moneys that are due may not be assigned without such consent (except to the
extent that the effect of this restriction may be limited by law); and unless specifically
stated to the contrary in any written consent to an assignment, no assignment will release
or discharge the assignor from any duty or responsibility under the Contract Documents.
8.03. Successors and Assigns.
A. Owner and Contractor each binds itself, its partners, successors, assigns, and
legal representatives to the other party hereto, its partners, successors, assigns, and legal
representatives in respect to all covenants, agreements, and obligations contained in the
Contract Documents.
8.04. Severability.
A. Any provision or part of the Contract Documents held to be void or
unenforceable under any Law or Regulation shall be deemed stricken, and all remaining
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -6-
012715
provisions shall continue to be valid and binding upon Owner and Contractor, who agree
that the Contract Documents shall be reformed to replace such stricken provision or part
thereof with a valid and enforceable provision that comes as close as possible to
expressing the intention of the stricken provision.
8.05. Business Addresses.
A. The business address of Contractor given herein is hereby designated as the
place to which all notices, letters, and other communication to Contractor will be mailed
or delivered. The address of Owner appearing herein is hereby designated as the place to
which all notices, letters, and other communication to Owner shall be mailed or
delivered. Either party may change its address at any time by an instrument in writing
delivered to Engineer and to. the other party.
IN WITNESS WHEREOF, Owner and Contractor have signed this Agreement. One
counterpart each has been delivered to Owner, Contractor, Surety, and Engineer.
This Agreement will be effective on
Owner:
City of Lakeville, Minnesota
I:
And:
Matt Little, Mayor
Charlene Friedges, City Clerk
Address for giving notices:
20195 Holyoke Avenue
Lakeville, MN 55044
Contractor:
Gridor Construction, Inc.
37
Title:
Address for giving notices:
End of Section
3990 27th Street SE
Buffalo, MN 55313
City of Lakeville, MN 00500 Agreement
WTF Improvements Project -7-
012715