Loading...
HomeMy WebLinkAboutItem 05Positioned to Thrive Public Works July 2015 Public Works July 2015 2 50/60 Roundabout. The roundabout has changed dramatically over the last 30 days. Piles of dirt that marked the roundabout are gone and the basic outline of the roundabout is plainly visible. Crews are pouring curb and gutter and the first layers of asphalt have been paved at the western and northern approaches. Remaining work includes storm sewer installation, curb and gutter installation, and grading and paving of the eastern and southern approaches. The project is scheduled to be complete by the end of August. Holyoke Avenue Water Tower. The foundation has been poured and a crew has been working on setting the forms and pouring the ring wall. It is on the ring wall that the shaft will be set. Crews will be on site in the next two weeks to begin setting up forms and preparing to start pouring the shaft. Toward the end of the year, crews will begin to work on building the bowl. The project remains on schedule with work on the shaft and bowl continuing throughout the summer and into next year. The tower is expected to be online in the fall of 2016. 3 Well 20 Construction. Construction of the well has been underway for just over a month. They continue to work on the open hole, completing approximately 3 feet per hour, with the finished depth of the well at more than 500 feet. Nest, the crew will set the casing and follow with grouting the well. Drilling of the well is progressing rapidly; drilling equipment should be removed from the park area by the end of summer. Finalizing pumps, motors, and controls will continue into the fall with the well expected to be online by the end of the year and fully available in the summer of 2016. Kensington Boulevard Improvement Project. Preliminary work on the project has started. Lane shifts went into effect last week and reclamation began on July 31. Kensington Boulevard will remain open to traffic throughout the project. Miscellaneous Roadway Repairs. This project encompasses a variety of smaller projects to include catch basin repair, curb, gutter, and sidewalk replacement, asphalt patching, and trail paving. Work to replace the trails along 165th Street east of Ipava Avenue and south of 165th Street along Ipava Avenue has started with new trail pavement being placed during the week of August 3. Catch basin repairs have been completed in a number of locations along 183rd Street and along Glacier Way. Parking lot rehabilitation at City Hall, Fire Station 1, the Heritage Center, and Fire Station 2 will begin in late August. 4 Commercial Meter Replacement. As water meters reach the end of their service life, they develop problems. Commonly, the meter just stops providing accurate readings for the water that passes through it. This situation occurred recently with the meter that feeds Ardmore Village. The City provides Ardmore Village with a 6-inch line to the entrance of the community and they distribute it to the residents. In troubleshooting the problem, Utilities Division staff determined that the water meter had stopped working correctly. Due to the age of the meter, no parts were available to make the repairs, so a new one was installed. This particular meter is designed as a fire service meter to measure the large volume demands of a fire as well as domestic water use. Installation of the meter necessitated turning off the water to Ardmore Village for several hours while the old meter was removed and the new meter installed by the Utilities Division. Water service was returned in the early afternoon.