Loading...
HomeMy WebLinkAboutItem 05.b4p L- Project Updates Water Treatment Facility Improvements. The new section of reservoir passed Rs leak test. The contractor is installing drain tile and back filling around the reservoir. The Utilities Division will drain the reservoir on October 5 to allow the contractor to begin demolition of the wall between the existing and new halves of the reservoir. Additional work that will be starting in October includes installation of a high service pump, the electrical work and piping for installation of the backwash blower, and upgrades to the fluoride system. with completion of all items by January 2016. LAKEVILLE PUBLIC WORKS Christopher Petree, Director September 2015 2015 Street Reconstruction. Restoration work is underway in both project areas as road reconstruction reaches its final phases for the year. Utility installation is complete in all areas. The remaining curb and gutter were completed in mid-September along 16911 Street and portions of 168th Street. Final grading for the remaining areas was completed during the week of September 28 in preparation for the base course of The project is on schedule asphalt. The project is on schedule. Holyoke Avenue Water Tower. Pours for the shaft and dome panels continue, though recent rain has slowed work on the shaft. Pours are anticipated to continue at a rate of three pours per week, weather permitting, until the shaft is completed in early November. In total, they will pour 12 ring walls and 16 dome panels. Fabrication of the tank will begin once the shaft is complete and carry on through the winter. The tower is expected to be online in the fall of 2016. Well 20 Construction. Drilling and development of the well are complete and worked focused on removing sand that sloughed into the hole during development. Over 175 tons of sand was removed from the hole. The drilling rig and other equipment have been removed from the park and the contractor is working on removing the remaining sand and restoring the site. Finalizing pumps, motors, and controls will continue into the fall with the well expected to be online by the end of the year and fully available in the summer of 2016. Kensington Boulevard Improvement Project. Paving is complete along Kensington Boulevard with the application of the asphalt wear course on Wednesday, September 30, and new LED street lights have been installed. E Miscellaneous Roadway Repairs. Rain delayed the final grading and preparation of the City Hall north parking lot for its first layer of asphalt. Work continued on September 28 in anticipation of application of the asphalt base layer that week, followed by the wear course for the entire parking lot. The base layer of asphalt was applied at Fire Station 2 in mid- September. CA Cathodic Protection A key component of the Kensington Boulevard l improvements was buried along the roadway. -r¢ Cathodic protection was installed along the length of the Kensington Boulevard water = main in an effort to protect the existing ductile% iron water main pipe from corrosion. With cathodic protection, sacrificial anodes were installed along the length of the water main. These anodes will work to "protect" the water main pipe, as the sacrificial metal will corrode instead of the ferrous material to which it is attached. Manufacturers of cathodic protection technology suggest that; the typical life expectancy for a sacrificial anode is 20 -years, however, there are many cathodic protection systems that have functioned in excess of 30 -years. While installation of cathodic protection does not guarantee the complete absence of water main breaks, research has shown that the installation of sacrificial anodes will significantly reduce the number of breaks over the life of the pipe. The installation of cathodic protection will help to maintain the integrity of the existing water main pipe until such time as the roadway is completely reconstructed and the water main pipe is replaced. 3 OA East Lake Fish Survey The fish population in East Lake has rebounded dramatically after a severe winterkill in 2012. Based on the latest fish survey from 2015, the number of black crappies is off the charts. Black bullheads and carp numbers are also extremely high and these bottom feeding fish could be contributing to poor water in East Lake. Because East Lake is susceptible to winterkills, dissolved oxygen should be monitored over winter. Mother Nature may, very well, rebalance the fish community in the next year or two. Valve Repair Utilities Division staff were out WF exercising hydrants near Schneiderman's furniture when water starter bubbling out of a gate valve in the middle of the intersection. Shutting water off to y. that valve resulted in several" businesses without water for the , duration of the repair. Temporary water service was arranged for the adjacent motel. Equipment was brought in and the area around the valve excavated. Corrosive soils had weakened several of the bolts around the valve cover and the change in water pressure during hydrant exercising caused the bolts to release enough to displace the gasket and allow water to flow up to street level. The bolts were replaced and the water main put back in service. The entire process took about two hours. 4 East Lake (20July2010) Standard Trapnets Fish/net East Lake (14-15 Sept 2015) Standard Trapnets Fish/net MN DNR Normal Range for Similar Type of Lakes Fish/net Black bullhead 42.3 347 1.1-25.2 Black crappie 8.9 467 1.2-4.8 Bluegill 1.4 34.5 4.9-49.8 Ca rp 1 5.8 0.4-1.6 Goldfish 0.3 1 NA Golden shiner 4.1 -- NA Green sunfish 6.8 0.3 0.2-2.1 Hybrid sunfish 0.5 -- NA Largemouth bass -- 6.4 0.3 - 1.3 Northern Pike - 0.3 NA Pumpkinseed -- 1 1.7- 10.3 White sucker 0.7 14.3 0.2-2.2 Yellow perch 0.6 13.4 0.4-3.5 Fathead minnow 2 -- NA Turtle - painted 2.6 2.1 0 Turtle - snapper 1.4 1.4 0 Valve Repair Utilities Division staff were out WF exercising hydrants near Schneiderman's furniture when water starter bubbling out of a gate valve in the middle of the intersection. Shutting water off to y. that valve resulted in several" businesses without water for the , duration of the repair. Temporary water service was arranged for the adjacent motel. Equipment was brought in and the area around the valve excavated. Corrosive soils had weakened several of the bolts around the valve cover and the change in water pressure during hydrant exercising caused the bolts to release enough to displace the gasket and allow water to flow up to street level. The bolts were replaced and the water main put back in service. The entire process took about two hours. 4