HomeMy WebLinkAboutItem 3.dJ�ukevi��e
Memorandum
To: Justin Miller, City Administrator
From: Monica Heil, Operations and Maintenance Engineer
Copy: John Hennen, Interim Parks and Recreation Director
Chris Petree, Public Works Director
Date: November 17, 2015
Subject: North Creek Greenway Trail Project Status Update
Background
City of Lakeville
Public Works
The proposed North Creek Greenway Trail Project in Lakeville is a 1.05 -mile trail extension
proposed to connect the existing regional greenway trails located at 173rd Street in Lakeville
to the shared City of Lakeville/City of Farmington limits (see attached figure). The City of
Lakeville and Dakota County applied for Federal Transportation Enhancement Funds to
construct the trail, and were awarded $899,410 in 2012. Current 2015 budgeted revenue
sources to construct the trail include:
Source
Federal Grant
$
899,410
Dakota County (Construction Contribution)
$
224,857
Park Dedication Fund (Engineering)
$
112,210
$
1,236,477
In addition to the aforementioned 2015 budgeted revenue sources, $100,000 of Park
Dedication Funds were allocated in 2014 for preliminary engineering and design of the
project.
With the grant application, the City agreed to pay the costs associated with engineering and
design of the trail, while the County had agreed to acquire the easement necessary to
construct the trail and to also contribute up to 20% of the trail construction costs not
otherwise funded by grant dollars.
Both the City and the County have spent much time working to assemble a preliminary trail
alignment and to acquire the necessary easements. To -date, the City has spent $116,278.75
in preliminary design and geotechnical engineering services.
To complete the final design of the trail and take the project through construction, the total
engineering fees are estimated to be:
Engineering Task
Geotechnical Evaluation
$7,898
Preliminary Engineering*
$119,153
Esmt., Grant Ext., Wetlands
$25,740
Project Memorandum Update
$7,000
Final Design
$36,600
Construction Admin. & Insp.
$142,340
Materials Testing
$17,500
$356,231
*$116,278.75 of the estimated $119,153 preliminary engineering fees have already been
incurred.
The estimated construction costs for the project are $1,186,157.50 (see attached). Of that
$1,186,157.50 in estimated construction costs, $899,410 will be funded using Federal
Transportation Enhancement Funds and $237,231.50 will be funded by Dakota County (20%
of the estimated construction costs). This leaves $49,516.00 in presently un -funded estimated
construction costs associated with the project. It should be noted, that both the construction
costs and the estimated final engineering design and construction inspection costs are
subject to change based on final design of the bridge crossing North Creek.
At this time, engineering and construction costs for the project exceed $1.54M, and $1.24M
has been budgeted. Additional funding sources must be identified in order to continue work
on the project.
Dakota County has indicated they will assume all easement acquisition costs associated with
the project, which are currently estimated at $138,000 plus closing costs.
Options
In December of 2014, the City did submit to MnDOT State Aid Offices an extension request for
the project. This extension request was approved, but with the requirement that
construction begin on the project by 2016. Construction of the trail using federal trail grant
dollars will require all of the amenities proposed within the original grant application,
including a trailhead facility in East Community Park. Should the City desire to move with
construction of the trail in 2016, it will require funding sources be identified to accommodate
a $356,231 in total engineering and inspection services, as well as the potential to absorb
$49,516.00 in estimated construction costs for a total of $405,747. With $100,000 in Park
Dedication Funds budgeted for the project in 2014 and $112,000 budgeted in 2015, $193,747
of the estimated engineering and construction costs remains unfunded at this time.
The City can also consider the possibility of constructing the trail with development
throughout this area. In this scenario, the City would be responsible for 3/8t" of the trail
material costs and, depending on the development plans for the area, some portion of the
costs associated with the trail crossing the creek. City staff has conservatively evaluated what
those costs might look like at the time of development, and have estimated those costs at
approximately $395,000. It should be noted, however, that in the event the trail is
constructed as development occurs in the area, the estimated City -share of the project costs
does not include the costs associated with constructing a trailhead facility within East
Community Park.
Variables
At this time, Dakota County is still working with two property owners to secure the necessary
easements to construct the project. While the deadline to have these easements in-place is
March of 2016, the City would need to authorize the production of final plans and
specifications ahead of the easements being acquired in order in order to have plans and
specifications submitted to State Aid for review and approval by May of 2016.
The construction cost estimate for the bridge crossing over North Creek is still in its
preliminary stages. A more accurate cost estimate to construct the bridge cannot be derived
until final plan production has been completed. The costs associated with the bridge
construction, and in -turn, inspection services, are subject to change.
Finally, looking at the current status of the project and the work that remains, City staff would
anticipate a bid opening for the project in mid -Summer of 2016. Contractor workloads at that
time may affect the bidding climate, and could adversely impact the construction costs we
hope to see for the project.
Staff is seeking to discuss with the Council the options available to the City for constructing
this Greenway Corridor Trail.
$1,186,157.50
02109580 Preliminary OPC
WSB Project: NORTH CREEK GREENWAY TRAIL
Pr ject Lomtion: CITY OF LAKEVILLE
City Project No::
WSBhoj-No: 02109-580
Design By:
(,'flecked By:
Date..
11/11/2014
11/112014
ENGINEER'S OPINION OF PROBABLE COST
ITEM
NUMBER
MN UM ITEM
NUMBER
DESCRIPTION
UNITS
UNIT PRICE
PROJECT
TOTAL
ESTIMATED
QUANTITY
TRAIL
PEDESTRIAN
BRIDGE
ESTIMATED COST - Trail
ESTIMATED COST -Bndge
1
2021.501
MOBILIZATION
LUMPSUM
$43000.00
1
1
$43,100.09
$8,30000
2
2100.601
PEDESTkU07 BRIDGE
LS
$165,00000
1
1
$165,000.00
3
2101.501
CLEARING
ACRE
$10,000.00
2
2
$20,000.00
4
2101.502
CLEARING
TREE
$500.00
5
5
$2,500.00
5
2101.506
GRUBBING
ACRE
$10,000.00
2
2
$20,000.00
6
2101.507
GRUBBING
TREE
$50000
5
5
$2,500.00
7
2104.501
REMOVE CURB AND GUTTER
LIN FT
$10.00
50
50
$500.00
8
2104.513
SAWING BITUMINOUS PAVEMENT (FULL DEPTH)
LIN IT
$20.00
60
60
$1,200.00
9
REMOVE BITUMINOUS PAVEMENT
SY
$10.00
20
20
$200,00
10
BITUMINOUS PAVEMENT PATCH
SY
$75.00
20
20
$1,590.00
11
2105.501
COMMON EXCAVATION
CU YD
$16.00
3,450
3,450
$55.200,00
12
2105.507
SUBGRADE EXCAVATION
CU YD
$12.00
1,750
1,750
$21,00000
13
SUBGRADE GRANULAR BORROW ICY)
CUYD
$20.00
2,460
2,460
$49,200.00
12
MUCK EXCAVATION
CU YD
$20.00
225
225
$4,500.00
14
2105.523
COMMMON BORROW
CU YD
$20.00
5.900
5,900
$118,000.00
15
2105604
GEOGIUD
SY
$5.00
225
225
$1,125.00
16
2105,607
WOODCHIPS
CY
$35.00
225
225
$7,875.00
17
2123.610
STREET SWEEPER
HOUR
$200.00
6
6
$1,200.00
18
2211.503
AGGREGATE BASE(CV) CLASS 5
CU YD
$35.00
1,125
1,125
$39,375.00
19
CURB AND (:LITTER
IF
$50.00
50
50
$2,500.00
20
2360.502
TYPE SP 95 WEARING COURSE MIX (21H
TON
$90.00
1,175
1,175
$105,750,00
21
2501-511
24" CS PIPE CULVERT
LF
$60.00
360
360
$21,600.00
22
2501.02
24" PIPE APRON
EACH
$400.00
24
24
$9,600.0
23
2511.501
RANDOM REPLAP, CLASS III
CU YD
$12500
500
500
$62,50000
24
2521.501
CONCRETE WALK, 6" -PED RAMP
SF
$15.00
265
265
$3,975.00
25
2531.618
TRUNCATED DOMES
SQ FT
$45.00
20
20
$900,00
26
2563.901
TRAFFIC CONTROL
LUMPSUM
$3,000.00
1
1
$3,000.0
27
2572.502
CLEAN ROOT CUTTING
IF
$6.00
1,000
1,000
$6,000.00
28
2573.502
SILT FENCE
LIN FT
$2.00
5,500
5,500
$11.000.00
29
2573.535
STABILIZED CONSTRUCTION ENTRANCE
EACH
$1,000.00
2
2
$2,000.00
30
2575.501
SEED & FERTILIZER
ACRE
$3,000,00
3
3
$9,000.00
31
2575.523
EROSION CONTROL BLANKETS CATEGORY 2
SQ YD
$1.50
14,550
14,550
$21,82500
32
2582.503
CROSSWALK MARKING-EPDXY
SQ FT
$5.00
120
120
$960.00
33
SIGNAGE
LS
$10,0(10.00
1
1
$10,000.00
34
BENCHES
LS
$18,000.00
1
1
$18,000.00
35
TRAILHEAD /BATHROOM
LS
$150,000.00
1
1
$150,000.00
36
TRAILHEAD SITE PREPARATION
LS
$10,000.00
1
1
$10,000.00
37
TRAILHEAD UTILITIES
LS
$45,000.00
1
1
$45,000.00
38
TRAILHEAD PARKING LOT -BIT
TON
$90.00
170
170
$15,300.00
39
TRAILHEAD PARKING LOT- CL5
CY
$51.00
140
140
$7,14000
40
SUBTOTAL- CONSTRUCTION COST-
$905,025.00
$173,300.00
CONSTRUCTION CONTINGENCIES(10!}
$90,50250
$17,33000
GRAND TOTAL-
$995,527.50
$190.630.00
$1,186,157.50
02109580 Preliminary OPC