HomeMy WebLinkAboutItem 06.hJanuary 12, 2016 Item No.
Contract with Choice Electric, Inc. for construction of
King Park Baseball Complex Lighting
(January 19, 2016 City Council Meeting)
Proposed Action
Staff recommends adoption of the following motion: Move to approve contract with Choice
Electric. Inc. for the construction of King Park Baseball Complex Lighting.
Overview
The approved 2016 - 2020 CIP includes the lighting of 9 baseball fields at King Park including the
parking lot and trail lighting. The first phase, which is to commence in 2016, consists of lighting
fields 2, 3 (Miracle Field), 4, and the parking lot. At the August 17, 2015 City Council Meeting,
Lakeville Baseball Association (LBA) donated $150,000 towards the lighting project, and on
December 7, 2015 the Mayor and City Council approved a purchase agreement with Musco
Sports Lighting, LLC for the lighting system equipment.
On Monday, January 11, 2016, bids were received and opened for the structural, underground,
and miscellaneous electrical installation for the fields and parking lot. Six bids were received
ranging from a low bid of $246,499, to a high bid of $348,720. The low bid was submitted by
Choice Electric, Inc., and is within budget.
At this time, Staff and Barr Engineering are recommending that the Mayor and City Council
approve a contract with Choice Electric, Inc. for the King Park Ballfield lighting project in the
amount of $246,499. Staff will not issue the Notice to Proceed to the contractor until we are in
receipt of the required Performance and Payment Bond and Certificate of Insurance which is
currently being obtained by the contractor.
Primary Issues to Consider
• Are the lights at the complex needed?
The installation of the lights will allow for additional games to be played at the facility,
ultimately preventing the need to acquire land for additional fields.
Supporting Information
• Barr Engineering bid acceptance recommendation memorandum dated January 12,
2016 which includes the results of the six bids.
• Contract with Choice Electric, Inc.
)im Parks & Recreation Director
Financial Impact: $246,499 Budgeted: Y/N _Y_ Source: 2016 CIP
Related Documents (CIP, ERP, etc.):
Community Values: Good value for public services
resourceful. naturally.
engineering and environmental consultants BARR
Memorandum
To: City of Lakeville
Attn: John Hennen, Interim Parks and Recreation Director
From: Stuart Stephens, P.E.
Subject: King Park Ballfield Lighting Project — Bid Acceptance Recommendation
Date: January 12, 2016
Bids were opened on January 11, 2016 for the planned ballfield lighting project at King Park. Six bids
were received, the results were as follows:
$246,499 Choice Electric
$266,505 Laketown Electric
$274,085 Gunnar Electric
$279,995 Muska Electric
$322,178 A & J Electric
$348,720 Killmer Electric
Choice Electric was the apparent low bidder at $246,499, which compares favorably with the City's
construction cost estimate of $245,800.
We checked with Craig Gallop at Musco Lighting. He reported that he has worked with Choice Electric
on several similar projects and was satisfied with their work.
We also checked with Choice Electric to make sure their bid was accurate. They reviewed their numbers
after the bid opening and said they were comfortable with their submitted bid price.
Therefore, we recommend accepting the low bid of $246,499 from Choice Electric for the King Park
ballfield lighting project.
Barr Engineering Co. 4700 West 77th Street, Suite 200, Minneapolis, MN 55435 952.832.2600 www.barr.com
FORM OF AGREEMENT
This Agreement is by and&IM between Qc,
And 0��4 63`UQ0 11 t P---
("Ownee') 1tP--
Owner and Contractor hereby agree as follows:
ARTICLE 1— WORK
("Owner")
("Contractor").
1.01 Contractor shall complete all Work as specified or indicated in the Contract Documents. The
Work is generally described in Division 01 of the Technical Specifications.
ARTICLE 2 — THE PROJECT
2.01 The Project, of which the Work under the Contract Documents may be the whole or only a part, is
generally described in Article 1.
ARTICLE 3 — ENGINEER
3.01 The Project has been designed by Barr Engineering Company
3.02 Owner has retained Barr Engineering Company (`Engineer") to act as Owner's representative,
assume all duties and responsibilities, and have the rights and authority assigned to Engineer in
the Contract Documents in connection with the completion of the Work in accordance with the
Contract Documents. The duties and responsibilities and rights and authority of Engineer cannot
be extended without written consent of Owner and Engineer.
ARTICLE 4 — CONTRACT TIMES
4.01 Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness
for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Contract Times: Dates
A. The Work will be substantially completed on or before July 29, 2016, and completed and
ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or
before August 19, 2016.
4.03 Liquidated Damages
A. Contractor and Owner recognize that time is of the essence as stated in Paragraph 4.01 above
and that Owner will suffer financial and other losses if the Work is not completed and
Milestones not achieved within the times specified in Paragraph 4.02 above, plus any
extensions thereof allowed in accordance with the Contract Documents. The parties also
recognize the delays, expense, and difficulties involved in proving in a legal or arbitration
proceeding the actual loss suffered by Owner if the Work is not completed on time.
Accordingly, instead of requiring any such proof, Owner and Contractor agree that as
liquidated damages for delay (but not as a penalty):
e_ City of Lakeville
King Park Baseball Complex Lighting 0052.00-1
Form of Agreement
1. Substantial Completion: Contractor shall pay Owner $100 for each day that expires
after the time (as duly adjusted pursuant to the Contract) specified in Paragraph 4.02.A
above for Substantial Completion until the Work is substantially complete.
2. Completion of Remaining Work: After Substantial Completion, if Contractor shall
neglect, refuse, or fail to complete the remaining Work within the Contract Time (as
duly adjusted pursuant to the Contract) for completion and readiness for final payment,
Contractor shall pay Owner $100 for each day that expires after such time until the
Work is completed and ready for final payment.
3. Liquidated damages for failing to timely attain Substantial Completion and final
completion are not additive and will not be imposed concurrently.
4. Milestones: Contractor shall pay Owner $100 for each day that expires after the time (as
duly adjusted pursuant to the Contract) specified above for achievement of Milestone 1,
until Milestone 1 is achieved.
ARTICLE 5 — CONTRACT PRICE
5.01 Owner shall pay Contractor for completion of the Work in accordance with the Contract
Documents the amounts that follow, subject to adjustment under the Contract:
A. Contract Price: $ . U 6 .
All specific cash allowances are included in the above price in accordance with Paragraph
13.02 of the General Conditions.
B. The Bid prices for Unit Price Work set forth as of the Effective Date of the Contract are
based on estimated quantities. As provided in Paragraph 13.03 of the General Conditions,
estimated quantities are not guaranteed, and determinations of actual quantities and
classifications are to be made by Engineer as provided in Paragraph 10.06 of the General
Conditions.
C. For all Work, at the prices stated in Contractor's Bid, attached hereto as an exhibit.
ARTICLE 6 — PAYMENT PROCEDURES
6.01 Submittal and Processing of Payments
A. Contractor shall submit Applications for Payment in accordance with Article 15 of the
General Conditions, as may be modified by the Supplemental Conditions. Applications for
Payment will be processed by Engineer as provided in the General Conditions.
6.02 Progress Payments; Retainage
A. Owner shall make progress payments on account of the Contract Price on the basis of
Contractor's Applications for Payment on or about the first day of each month during
performance of the Work as provided in Paragraph 6.02.A.1 below, provided that such
Applications for Payment meet the requirements of the Contract. All such payments will be
measured by the Schedule of Values established as provided in the General Conditions (and
in the case of Unit Price Work based on the number of units completed) or, in the event there
is no Schedule of Values, as provided elsewhere in the Contract. The amount of retainage
with respect to all progress payments shall be as defined in the Supplementary Conditions.
6.03 Final Payment
A. Upon final completion and acceptance of the Work in accordance with Paragraph 15.06 of
the General Conditions, Owner shall pay the remainder of the Contract Price as
recommended by Engineer as provided in said Paragraph 15.06.
BAR: City of Lakeville Form of Agreement
King Park Baseball Complex Lighting 00 52 00-2
ARTICLE 7 — INTEREST
7.01 All amounts not paid when due as provided in Article 13 of the General Conditions shall bear
interest at a maximum rate equal to the sum of the prevailing "Prime Rate" in the geographical
area of the Project plus 2 percent (2%).
ARTICLE 8 — CDI`fIrRAC T OR'S REPRESENTATIONS
8.01 In order to induce Owner to enter into this Contract, Contractor makes the following
representations:
A. Contractor has examined and carefully studied the Contract Documents and the other related
data and reference items identified in the Bidding Documents.
B. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site
and adjacent areas, and become familiar with and is satisfied as to the general, local, and Site
conditions that may affect cost, progress, and performance of the Work.
C. Contractor is familiar with and is satisfied as to all Laws and Regulations that may affect
cost, progress, and performance of the Work.
D, Contractor has carefully studied all: (1) reports of explorations and tests of subsurface
conditions at or adjacent to the Site and all drawings of physical conditions relating to
existing surface or subsurface structures at the Site (except Underground Facilities), if any,
that have been identified in the Supplementary Conditions, especially with respect to
Technical Data in such reports and drawings, and (2) reports and drawings relating to
Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been
identified in the Supplementary Conditions, especially with respect to Technical Data in
such reports and drawings.
E. Contractor has considered the - information known to Contractor itself; information
commonly known to contractors doing business in the locality of the Site; information and
observations obtained from visits to the Site; the Contract Documents; and the Site -related
reports and drawings identified in the Contract Documents, with respect to the effect of such
information, observations, and documents on (1) the cost, progress, and performance of the
Work; (2) the means, methods, techniques, sequences, and procedures of construction to be
employed by Contractor; and (3) Contractor's safety precautions and programs.
F. Based on the information and observations referred to in the preceding paragraph, Contractor
agrees that no further examinations, investigations, explorations, tests, studies, or data are
necessary for the performance of the Work at the Contract Price, within the Contract Times,
and in accordance with the other terms and conditions of the Contract.
G. Contractor is aware of the general nature of work to be performed by Owner and others at
the Site that relates to the Work as indicated in the Contract Documents.
H. Contractor has given Engineer written notice of all conflicts, errors, ambiguities, or
discrepancies that Contractor has discovered in the Contract Documents, and the written
resolution thereof by Engineer is acceptable to Contractor.
I. The Contract Documents are generally sufficient to indicate and convey understanding of all
terms and conditions for performance and furnishing of the Work.
J. Contractor's entry into this Contract constitutes an incontrovertible representation by
Contractor that without exception all prices in the Agreement are premised upon performing
and furnishing the Work required by the Contract Documents.
M
s— _,of Lakeville
King Park Baseball Complex Lighting 00 52 00-3
Form of Agreement
ARTICLE 9 — CONTRACT DOCUMENTS
9.01 Contents
A. The Contract Documents consist of the following:
1. This Agreement (pages 1 to k inclusive).
2. Performance bond (pages _ to inclusive).
3. Payment bond (pages _ to _, inclusive).
4. Other bonds.
a. A17T (pages _ to ___, inclusive).
5. General Conditions (pages to, inclusive).
6. Supplementary Conditions (pages / to 9, inclusive).
7. Specifications as listed in the table of contents of the Project Manual.
8. Drawings (not attached but incorporated by reference) consisting of LL sheets with .
each sheet bearing the following general title: dil/j IG -)V Aek &T&6e// &m ale t.
9. Addenda (numbers / to �L inclusive).
10. Exhibits to this Agreement (enumeratedasfollows):
a. Contractor's Bid (pages / to inclusive).
b. Documentation submitted by Contractor prior to Notice of Award (pages AR to
L inclusive).
11. The following which may be delivered or issued on or after the Effective Date of the
Contract and are not attached hereto:
a. Notice to Proceed.
b. Work Change Directives.
c. Change Orders.
d. Field Orders.
B. The documents listed in Paragraph 9.01.A are attached to this Agreement (except as
expressly noted otherwise above).
C. There are no Contract Documents other than those listed above in this Article 9.
D. The Contract Documents .may only be amended, modified, or supplemented as provided in
the General Conditions.
ARTICLE 10 —MISCELLANEOUS
10.01 Terms
A. Terms used in this Agreement will have the meanings stated in the General Conditions and
the Supplementary Conditions.
10.02 Assignment of Contract
A. Unless expressly agreed to elsewhere in the Contract, no assignment by a party hereto of any
rights under or interests in the Contract will be binding on another party hereto without the
written consent of the party sought to be bound; and, specifically but without limitation,
W
BARR City of Lakeville Form of Agreement
King Park Baseball Complex Lighting 00 52 00-4
money that may become due and money that is due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by law), and
unless specifically stated to the contrary in any written consent to an assignment, no
assignment will release or discharge the assignor from any duty or responsibility under the
Contract Documents.
10.03 Successors and Assigns
A. Owner and Contractor each binds itself, its successors, assigns, and legal representatives to
the other party hereto, its successors, assigns, and legal representatives in respect to all
covenants, agreements, and obligations contained in the Contract Documents.
10.04 Severability
A. Any provision or part of the Contract Documents held to be void or unenforceable under any
Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to
be valid and binding upon Owner and Contractor, who agree that the Contract Documents
shall be reformed to replace such stricken provision or part thereof with a valid and
enforceable provision that comes as close as possible to expressing the intention of the
stricken provision.
10.05 Contractor's Certifications
A. Contractor certifies that it has not engaged in corrupt, fraudulent, collusive, or coercive
practices in competing for or in executing the Contract. For the purposes of this Paragraph
10.05:
1. "Corrupt practice" means the offering, giving, receiving, or soliciting of anything of
value likely to influence the action of a public official in the bidding process or in the
Contract execution;
2. "Fraudulent practice" means an intentional misrepresentation of facts made (a) to
influence the bidding process or the execution of the Contract to the detriment of
Owner, (b) to establish Bid or Contract prices at artificial non-competitive levels, or (c)
to deprive Owner of the benefits of free and open competition;
3. "Collusive practice" means a scheme or arrangement between two or more Bidders,
with or without the knowledge of Owner, a purpose of which is to establish Bid prices
at artificial, non-competitive levels; and
4. "Coercive practice" means harming or threatening to harm, directly or indirectly,
persons or their property to influence their participation in the bidding process or affect
the execution of the Contract.
10.06 Other Provisions
A. Owner stipulates that if the General Conditions that are made a part of this Contract are
based on EJCDC® C-700, Standard General Conditions for the Construction Contract,
published by the Engineers Joint Contract Documents Committee®, and if Owner is the
party that has furnished said General Conditions, then Owner has plainly shown all
modifications to the standard wording of such published document to the Contractor,
through a process such as highlighting or "track changes" (redline/strikeout), or in the
Supplementary Conditions.
B. This Agreement shall be governed by the laws of the State of Minnesota.
C. This contract may be terminated by the Owner at any time upon discovery by the Owner that
the Contractor or subcontractor has submitted a false statement under oath verifying
compliance with any of the minimum criteria set forth in Minn. Stat. § 16C.285, subd. 3.
BARR City of Lakeville
King Park Baseball Complex Lighting 00 52 00-5
Form of Agreement
IN WITNESS WI HEREOF, Owner and Contractor have signed this Agreement.
This Agreement will be effective on on. IVO(which is the Effective Date of the Contract).
OWNER:
LM
Title:
CONTRACTOR:
ice, L�e��L
M.
Title: V i ee, 1t I
If Contractor is a corporation, a partnership, or
joint venture, attach evidence of authority to sign.
Attest: Attest:
Title:
Address for giving notices:
Title:
Address for giving notices:
.30,�Z) 4t` fgve.
License No.: 002-(Lo2-0
(where applicable)
END OF FORM OF AGREEMENT
B..„,R..R„ City of Lakeville Form of Agreement
King Park Baseball Complex Lighting 00 52 00-6