Loading...
HomeMy WebLinkAboutItem 05.dPositioned to Thrive Public Works January, February, March 2016 Public Works January, February, March 2016 2 Holyoke Water Tower Work on the tower continued throughout the winter, most noticeably with the construction of the 2 million gallon tank that will hold the water. Crews have completed metal fabrication of the tank and will begin painting both the interior and exterior. Early this summer, the tank will be hoisted up the shaft and set in place. The project remains on schedule and is expected to be online in early fall. Well 20 All of the underground work on Well 20 was completed before the end of 2015. Early in 2016, the contractor installed the pitless adaptor and completed connection to the collection pipe. As the ground thaws, a concrete slab will be poured to support the well controls. This well will be online and serving customers later this spring. 3