HomeMy WebLinkAboutItem 06.n Date: July 5, 2016 Item No. RESOLUTION TO AUTHORIZE THE PREPARATION OF A FEASIBILITY REPORT FOR THE 2017 STREET RECONSTRUCTION PROJECT, CITY PROJECT NO. 17-02 Proposed Action Staff recommends adoption of the following motion: Approve a resolution authorizing WSB & Associates to prepare an engineering feasibility report for the 2017 Street Reconstruction Project, City Improvement Project 17-02. Overview The City has an established Pavement Management Program to rate pavement condition and guide long-term infrastructure management. From the pavement ratings, the City has developed an annual street reconstruction plan as part of its 5-year Capital Improvement Plan. The streets recommended for reconstruction in 2017 show significant surface distresses and failures in the asphalt. The estimated project cost is $9,381,850. Staff conducted a neighborhood meeting for the project on Thursday, June 23, 2016. Approximately 71 property owners attended this first meeting. Proposed project financing is through bonds issued under Minnesota Statutes, Chapter 429, for local improvements. A portion of the total project cost will be assessed to the property owners abutting the identified streets. The engineering feasibility report is required under Chapter 429 prior to adopting a resolution ordering the improvement. Primary Issues to Consider • Could some property owners oppose the proposed assessments for the street reconstruction project, and question the need for the proposed improvements? Yes, and City Staff has worked to address all questions and concerns from residents regarding the timing of and the need for the project. Supporting Information • Attached is a copy of the presentation from the June 23, 2016 Neighborhood Meeting, a summary of the comment cards received and a Project Location Map. Financial Impact: $ Budgeted: Y☒ N☐ Source: Related Documents: (CIP, ERP, etc.): Envision Lakeville Community Values: Good Value for Public Services Report Completed by: Monica Heil, Operations and Maintenance Engineer 9,381,850 429 and Utility Bonds 2 CITY OF LAKEVILLE RESOLUTION NO: RESOLUTION TO AUTHORIZE WSB & ASSOCIATES TO PREPARE A FEASIBILITY REPORT FOR THE 2017 STREET RECONSTRUCTION PROJECT WHEREAS , the pavement within portions of Argonne Estates, Argonne Estates 2 nd Addition, Argonne Farms, Barrett 1 st – 3rd Additions, Forest Hills, Lakeville MotoPrimo, Lynwood North, Lynwood North 4th, 5th and 7th Additions, Lynwood South, Ridgeview First Addition, Ridgeview Second Addition, Rock Ridge First Addition, Rock Ridge Second Addition, Rock Ridge Third Addition, Rolling Knolls, Rolling Knolls Plat Two, Rolling Oaks South, Rolling Oaks South Plat Two, Rolling Oaks South Plat Three, Rolling Oaks South Plat Four, Rolling Oaks South Plat Five, Rolling Oaks South Plat Six, Rolling Oaks South Plat Seven, Rolling Oaks South Plat Eight, Stonebriar, Stonebriar 2 nd Addition, Timber Ridge, and Timber Ridge South has reached the end of its lifespan and is programmed to be reconstructed in the City’s 2016-2020 Capital Improvement Plan; and WHEREAS , the City of Lakeville wishes to finance a portion of the project through special assessments; and WHEREAS, a feasibility report is required under MN Stat. Chapter 429 for this local improvement; NOW THEREFORE BE IT RESOLVED , by the City Council of the City of Lakeville, that WSB & Associates, Inc. is hereby authorized to prepare an engineering feasibility report for the 2017 Street Reconstruction Project, City Improvement Project 17- 02. ADOPTED by the Lakeville City Council this 5th day of July, 2016. CITY OF LAKEVILLE ______________________________ Matt Little, Mayor ATTEST: _____________________________ Charlene Friedges, City Clerk Item #Resident Name Resident Address Phone/E-mail Date Received Comment Response 1 Mary Jo Schmit 17370 Jonquil Avenue 952-435-3483 6/23/2016 Resident is questioning whether or not retaining wall adjacent to the roadway is public or private. Resident believes wall is starting Monica Heil to research original wall construction and follow-up with 2 Tim Folley 10424 166th Str W tim-Folley@hotmail.com 6/23/2016 Resident is requesting additional curb replacement along his street because he believes vehicles bottom out of driveways Staff to evaluate with feasibility report. 3 Sharon Zell 17200 Jasper Trail sharon.zell@charter.net 6/23/2016 "Please check drainage at the end of our driveway. After a rain we get some standing water. Staff to evaluate with feasibility report. 4 Amy Klimpke 10426 169th Street W amysue0124@yahoo.com 6/23/2016 "A river runs through our backyard when it rains. Not sure if anything can be done." Staff to evaluate with feasibility report. Comment Log Po s i t i o n e d t o Th r i v e 20 1 7 S t r e e t R e c o n s t r u c t i o n P r o j e c t Ne i g h b o r h o o d M e e t i n g Ju n e 2 3 , 2 0 1 6 Po s i t i o n e d t o Th r i v e To n i g h t ’ s M e e t i n g • I n t r o d u c e t h e p r o j e c t t o a r e a p r o p e r t y o w n e r s • S o l i c i t c o m m e n t s f r o m p r o p e r t y o w n e r s • P r o v i d e a n u p d a t e t o t h e C i t y C o u n c i l • B e g i n w o r k o n t h e f e a s i b i l i t y s t u d y f o r t h e p r o j e c t Po s i t i o n e d t o Th r i v e Pr o j e c t B a c k g r o u n d • L a k e v i l l e ’ s P a v e m e n t M a n a g e m e n t P r o g r a m • C i t y s t r e e t s a r e r a t e d b a s e d o n t h e i r c o n d i t i o n • P u r p o s e i s t o i d e n t i f y r o a d w a y s i n n e e d o f re c o n s t r u c t i o n • I n f o r m a t i o n w a s u s e d t o d e v e l o p t h e C i t y ’ s C a p i t a l Im p r o v e m e n t P l a n ( C I P ) Po s i t i o n e d t o Th r i v e Pr o j e c t Lo c a t i o n Po s i t i o n e d t o Th r i v e Pa v e m e n t M a n a g e m e n t A p p r o a c h • T o p r o v i d e r e c o m m e n d a t i o n s o n a c a s e - b y - ca s e b a s i s f o r e a c h a r e a o f t h e p r o j e c t • P a v e m e n t c o n d i t i o n s • U t i l i t y n e e d s • M a i n t e n a n c e h i s t o r y • C o u p l i n g u t i l i t y p r o j e c t s w i t h s t r e e t r e c o n s t r u c t i on pr o j e c t s t o b e c o s t e f f i c i e n t Po s i t i o n e d t o Th r i v e Ex i s t i n g C o n d i t i o n s – J e r s e y W a y Po s i t i o n e d t o Th r i v e Ex i s t i n g C o n d i t i o n s – 1 6 7 th St r e e t Po s i t i o n e d t o Th r i v e Pr o p o s e d I m p r o v e m e n t s • S t r e e t re c o n s t r u c t i o n • S p o t c u r b a n d g u t t e r re p l a c e m e n t • S t o r m s e w e r im p r o v e m e n t s Po s i t i o n e d t o Th r i v e Pr o p o s e d I m p r o v e m e n t s • S t o r m D r a i n a g e • P r o a c t i v e l y i d e n t i f y i s s u e s t o r e d u c e f u t u r e ma i n t e n a n c e c o s t s a n d p r o l o n g t h e l i f e o f t h e pa v e m e n t • R e p l a c e / a d d s t o r m s e w e r t o i m p r o v e d r a i n a g e an d a d d r e s s i s s u e s s u c h a s : • S t a n d i n g w a t e r / i c i n g i n t h e s t r e e t • A c c e l e r a t e d p a v e m e n t d e t e r i o r a t i o n Po s i t i o n e d t o Th r i v e Ut i l i t y E v a l u a t i o n s • T e l e v i s e s a n i t a r y s e w e r m a i n l i n e s • I n s p e c t a l l m a n h o l e s • I n s p e c t s t o r m s e w e r f a c i l i t i e s • I n s p e c t w a t e r m a i n a n d r e v i e w m a i n t e n a n c e hi s t o r i e s Po s i t i o n e d t o Th r i v e Ut i l i t y N e e d s • W a t e r m a i n • E x i s t i n g i r o n p i p e s • S o i l s w e r e d e t e r m i n e d to b e c o r r o s i v e • I d e n t i f y a r e a s w i t h ma i n t e n a n c e h i s t o r i e s fo r p o t e n t i a l re p l a c e m e n t Po s i t i o n e d t o Th r i v e St r e e t a n d U t i l i t y I m p r o v e m e n t s • C o u p l e p a v e m e n t re c o n s t r u c t i o n w i t h ef f o r t s t o e x t e n d t h e us e f u l l i f e o f e x i s t i n g ut i l i t i e s Po s i t i o n e d t o Th r i v e Wa t e r m a i n I m p r o v e m e n t s • I n s t a l l c o r r o s i o n pr o t e c t i o n • R e d u c e f r e q u e n c y o f wa t e r m a i n b r e a k s • E x t e n d t h e u s e f u l l i f e of t h e w a t e r m a i n pi p e Po s i t i o n e d t o Th r i v e Sp e c i a l A s s e s s m e n t s • S t r e e t / S t o r m S e w e r I m p r o v e m e n t s • S t r e e t a n d s t o r m s e w e r c o s t s a r e 4 0 % a s s e s s e d • A s s e s s e d o n p e r u n i t b a s i s f o r p r o p e r t i e s z o n e d fo r s i n g l e f a m i l y u s e • C o r n e r L o t s • O n l y o n e u n i t i s a s s e s s e d f o r e i t h e r t h e f r o n t o r si d e s t r e e t Po s i t i o n e d t o Th r i v e Pr o j e c t S c h e d u l e Ne i g h b o r h o o d M e e t i n g June 23, 2016 Fi n a l i z e F e a s i b i l i t y R e p o r t October, 2016 Pr e s e n t F e a s i b i l i t y R e p o r t O c t o b e r 1 7 , 2 0 1 6 Pu b l i c H e a r i n g No v e m b e r 2 1 , 2 0 1 6 Pr e p a r e P l a n s a n d S p e c i f i c a t i o n s N o v e m b e r , 2 0 1 6 – F e b r u ary, 2017 Op e n B i d s March, 2017 As s e s s m e n t H e a r i n g April, 2017 Co n s t r u c t i o n Ap r i l – N o v e m b e r , 2 0 1 7 Po s i t i o n e d t o Th r i v e Ne x t S t e p s • G a t h e r f e e d b a c k f r o m t h e n e i g h b o r h o o d • P r o v i d e a n d u p d a t e t o t h e C i t y C o u n c i l • C o m p l e t e t h e f e a s i b i l i t y r e p o r t a n d p r e l i m i n a r y co s t e s t i m a t e s Po s i t i o n e d t o Th r i v e Pr o j e c t C o m m u n i c a t i o n s • V i s i t t h e C i t y ’ s w e b s i t e f o r c o m p l e t e p r o j e c t st a t u s u p d a t e s ww w . l a k e v i l l e m n . g o v LynwoodHeights Park Goose LakeConservation Area RollingOaks Park Rolli n g O a k s Cons e r v a t i o n Area HosannaChurch JA L I S C O T E R E JASP E R P A T H 16 9 T H S T W K E N R I C K A V E JO N Q U I L A V E 172ND ST W J A S P E R L N J A S P E R L N K E NRI CK AVE JAVELIN A V E J O N Q U I L T R L JASP E R C T JASPER CIR JON Q U I L A V E JA C A N A C T JA C K P I N E C T I X O N I A P A T H JAGU A R C T JA C O B I T E C T J A C K P I N E W AY ISLAND AVE 173RD ST W ITALY C T IT H A C A C T JA Y B E L L C T 173RDSTW JU N E L L E P A T H IX O N I A C T 1 6 6 T H S T W JAZ Z C T 177TH CIR W JEFFERSON CT J A V E L I N A V E 175TH ST W 165TH ST W 176 T H S T W JE R S E Y C T 171ST ST W I P S W I C H W A Y J A R R A T T C T JAD E C T J A S M I N E A V E 1 6 7 T H C T W I S O S C E L L E S A V E J A C A R A N D A W A Y J A C K D A W P A T H J AVACIR 170TH C T W 17 1 S T S T W 173RD ST W 170TH ST W JON A T H A N C T J E F F E R S O N A V E 173RD ST W J O N R A Y C T UPPER 173RD CT W J A D E T E RJOY AVE J O R D A N C T 163RD ST W 1 7 6 T HCIRW 1 7 0 T H S T W I X O N I A A V E JA G U A R A V E 1 6 9 T H S T W 167 T H S T W J A VARIC T J A C K S O N V I L L E C T J A RREAU CT JASPER P A T H 175TH ST W J A G U A R P L J O Y C T J A C K S O N T R L J A V A C T S JA V A C T N J O P L I N A V E I S L E T O N A V E J E R S E Y A V E J A S M I NE CT J A C A M A R W A Y I T H A C A L N I S L E T O N A V E JAT O S C I R J O N Q U I L A V E 176TH S T W JONQUI L A V E J A C K R A B B I T P A T H JA L I S C O T E R W J A C K S O N T R LJONQUIL TRL 1 7 3 R D C T W J A S P E R T R L J A V E L I N C T ITALY PATH JALI S C O L N JAVA LN JO N Q U I L A V E J A S P E R L N JA C K P I N E T R L JA G U A R P A T H J OPLIN PATH J A M I S O N P A T H 166TH ST W J E R S E Y W A Y I S L A N D T E R K E N T U C K Y A V E JO P L I N W A Y P R I V A T E R D PRI V A T E R D IRWINDA L E W A Y P R I V A T E R D PR I V A T E R D Goose Lake Project Area City Parks ² 0 500 1,000250Feet 2017 Street Reconstruction Project Area