FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
utilities installed with Spirit of Brandtjen Farm 16th Addition, and final acceptance of public
streets and utilities installed with Summerlyn 1st and 2nd Additions and Tullamore 2nd, 3rd and 4th
Additions.
Overview
Tradition Development requests final acceptance of the public utility improvements installed
with the development of Spirit of Brandtjen Farm 16th Addition (SBF 16th). The prime contractor
responsible for the public improvement work on SBF 16th was Enebak Construction Company.
The public utilities for SBF 16th were constructed in 2016.
Lennar requests final acceptance of the public street and utility improvements installed with the
development of Summerlyn 1st and 2nd Additions and Tullamore 2nd, 3rd and 4th Additions. The
prime contractor responsible for the public improvement work on these developments was
Nodland Construction Company. The public utilities, curb and gutter, and bituminous base-
course pavements for these developments were constructed in 2013-2014. The bituminous wear-
course pavements for these developments were constructed in 2015.
The public street and utility improvements for the above-referenced developments were tested
and inspected by WSB & Associates and the City’s Public Works Department.
Primary Issues to Consider
• The public street and utility improvements installed with the above-referenced
developments were completed consistent with the City’s construction standard
specifications and the administrative requirements for final acceptance.
Supporting Information
• None.
Financial Impact: $ Budgeted: Y☐ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer