Date: Item No.
AWARD CONTRACT TO FITZGERALD EXCAVATING & TRUCKING
FOR 205TH STREET CHANNEL STABILIZATION IMPROVEMENTS
Proposed Action
Staff recommends adoption of the following motion: Move to award contract to Fitzgerald
Excavating & Trucking Incorporated for 205th Street Channel Stabilization Improvements.
Overview
On December 19, 2016, the Lakeville City Council approved plans and specifications for City
Project 16-15.
On Tuesday, January 10, 2017 at 10:00 a.m. the City received five bids for City Project 16-15.
The bids ranged from a low bid of $197,860 submitted by Fitzgerald Excavating & Trucking
Incorporated to a high bid of $276,665. The Engineer’s Estimate of the construction cost was
$227,690. City, Vermillion River Watershed Joint Powers Organization and Wenck Associates
staff reviewed the bids and recommend approval.
Primary Issues to Consider
• The City’s funding source is the Utility Fund – Environmental Resources. The
Vermillion River Watershed Joint Powers Organization will reimburse the City up to
$100,000 for construction costs.
• Construction is anticipated to begin in February, 2017 and be completed by August, 2017.
Supporting Information
• Bid Tabulation
• Letter of Recommendation dated February 2, 2017, from Wenck Associates
• Agreement
Financial Impact: $ Budgeted: Y☒ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Notes: Additional funding provided by Vermillion River Watershed Joint Powers Organization
Report Completed by: McKenzie Cafferty, Environmental Resources Manager
February 6, 2017
197,860 Utility Fund – Env. Resources
CITY OF LAKEVILLE
RESOLUTION NO. ____
RESOLUTION AWARDING CONTRACT FOR
205TH STREET CHANNEL STABILIZATION IMPROVEMENTS
WHEREAS, the City of Lakeville received sealed bids on Tuesday, January 10, 2017 at 10:00 a.m.
for 205th Street Channel Stabilization Improvements, City Project 16-15; and
WHEREAS, the lowest responsible bid was from Fitzgerald Excavating & Trucking
Incorporated.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Lakeville,
Minnesota:
Hereby awards the contract to the lowest responsible bidder that meets all the bid requirements,
Fitzgerald Excavating & Trucking Incorporated, with a bid in the amount of $197,860. The
construction is proposed to be completed as specified in the contract documents.
ADOPTED by the Lakeville City Council this 6th day of February, 2017.
______________________________
Douglas P. Anderson, Mayor
_________________________________
Charlene Friedges, City Clerk
Wenck Associates, Inc. | 1800 Pioneer Creek Center | P.O. Box 249 | Maple Plain, MN 55359-0249
Toll Free 800-472-2232 Main 763-479-4200 Email wenckmp@wenck.com Web wenck.com
CM 105 (Revised 10/26/2015) T:\5895 Lakeville\0003 - 205th Channel Reconstruction\Bidding\CM105 Bid Opening Tabulation.Docx
Bid Opening Tabulation
Bids were opened on January 10, 2017 at 10:00 a.m.
For 205th Street Channel Reconstruction Project
City Project No. 16-15
Pre-Bid Estimate $227,690.00
Contractor Bid Amount
1. Fitzgerald Excavating $197,860.00
2. Friedges Contracting, Inc. $276,665.00
3. MNL Inc. $199,442.00
4. Rachel Contracting $228,011.80
5. Standard Contracting $228,793.57
Signed:
Date: February 2, 2017
Wenck Associates, Inc. | 1800 Pioneer Creek Center | P.O. Box 249 | Maple Plain, MN 55359-0249
Toll Free 800-472-2232 Main 763-479-4200 Email wenckmp@wenck.com Web wenck.com
-
February 2, 2017
Mr. McKenzie Cafferty
Environmental Resources Manager
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044-8339
RE: 205th Street Channel Reconstruction Project
City Project No. 16-15
Dear Mr. Cafferty:
I reviewed the five bids received for this project following the bid opening on Tuesday, January
10, 2016, at 10:00AM, at the City of Lakeville City Hall. The low bidder is Fitzgerald Excavating
& Trucking Inc. at $197,860.00. The Engineer’s estimate for this project is $227,690.00.
There are no math errors in the bid, and the unit prices are within an acceptable range.
Wenck does not have experience working with Fitzgerald Excavating & Trucking Inc. so we
checked with one of the listed references that we work directly with, the City of Woodbury
engineer. The City of Woodbury has worked with the contractor and continues to work with
them on pond maintenance/clean out projects. The City of Woodbury did not express concern
about the Contractor’s ability to complete the work as we described and commented that they
know the Contractor does work on streams for the MN DNR. The contractor did list MN DNR
contacts and projects as three additional references. Based on the feedback, Wenck does not
have any reason to believe Contractor is not capable of completing this project as designed and
specified. We recommend that the City of Lakeville award Fitzgerald Excavating & Trucking Inc.
the 205th Street Channel Reconstruction Project, City Project No. 16-15.
Sincerely,
Ed Matthiesen, P.E.
Principal, Wenck Associates, Inc.
AGREEMENT
THIS AGREEMENT, made this 6th day of February, 2017 by and between the City of Lakeville, hereinafter
called “Owner” and [ ], doing business as a Minnesota corporation, hereinafter called “Contractor.”
WITNESSETH: That for and in consideration of the payments and agreements hereinafter mentioned:
1. The Contractor will commence and complete the construction of: 205th Street Channel Restoration
Project, City of Lakeville Improvement Project No. 16-15.
2. The Contractor will furnish all of the material, supplies, tools, equipment, labor and other services
necessary for the construction and completion of the project described herein.
3. The Contractor will complete the work required by the Contract Documents within the specified
completion dates unless the period for completion is extended by the Contract Documents.
4. The Contractor agrees to perform all of the work described in the Contract Documents for the sum of
$ .
5. The term “Contract Documents” means and includes the following: (A)
Notice to Bidders
(B) Information for Bidders
(C) Bid Proposal Form
(D) Affidavit of Non-Collusion
(E) Bid Bond
(F) Agreement
(G) General Conditions
(H) Supplementary Conditions to the General Conditions
(I) Payment Bond and Performance Bond
(J) Notice of Award
(K) Notice to Proceed
(L) Change Order(s)
(M) Drawings prepared by the City of Lakeville
(N) Specifications prepared or issued by the City of Lakeville
6. The Owner will pay to the Contractor in the manner and at such times as set forth in the General
Conditions such amounts as required by the Contract Documents.
7. This Agreement shall be binding upon all parties hereto and their respective heirs, executors,
administrators, successors and assigns.
IN WITNESS WHEREOF, the parties hereto have executed, or caused to be executed by their duly authorized
officials, this Agreement in duplicate, each of which shall be deemed an original on the date first above written.
OWNER: CITY OF LAKEVILLE
By: Attest:
Doug Anderson, Mayor (Seal) Charlene Friedges, City Clerk
ATTEST: (SEAL)
CONTRACTOR:
ADDRESS:
BY:
TITLE:
BY:
TITLE:
NOTE: Two (2) corporate officers are to sign, if applicable.
STATE OF MINNESOTA
COUNTY OF DAKOTA
The foregoing instrument was acknowledged before me this 6th day of February, 2017, by
of the corporation.
and of [ ], a Minnesota corporation, on behalf
Notary Public,
My commission expires:
County, MN