RESOLUTION APPROVING FEASIBILITY REPORT AND CALLING PUBLIC HEARING FOR
THE 2017 HOLYOKE AVENUE IMPROVEMENT PROJECT
Proposed Action
Staff recommends adoption of the following motion: Move to approve a resolution approving
the feasibility report and calling a public hearing for the 2017 Holyoke Avenue Improvement
Project. These improvements constitute City Improvement Project 17-04.
Overview
On November 21, 2016, the City Council authorized WSB & Associates, Inc. to prepare a
feasibility report for the 2017 Holyoke Avenue Improvement Project. That feasibility report
has been completed.
Based on information in the feasibility report, the estimated cost for the 2017 Holyoke Avenue
Improvement Project is $2,348,205. Funding for the 2017 Holyoke Avenue Improvement
Project, based on the City’s Street Assessment Policy, is recommended as follows: $456,800
City issuance of debt which is repaid with Streetlight Utility Fund revenues; $65,000 Dakota
County CDA CDBG/RIG Funds; $78,144 Communication Fund; $1,137,756 City issuance of
debt which is repaid with property tax levies; and $610,505 City issuance of debt which is
repaid through special assessments to benefitting property owners for the street, storm sewer
and signage improvements.
Included in the estimated project cost is the cost of replacing the street light system and
installing miscellaneous wayfinding and gateway signage.
Not included in the proposed project financing is a grant from the Dakota County Community
Development Agency. Staff has submitted a request for $250,000 through their
Redevelopment Incentive Grant program, but the amount received and how it is applied to
the project has yet to be determined.
Primary Issues to Consider (see attached)
• Citizen Comments
• Project Cost and Financing Summary
Supporting Information
• The Project Location Map is attached and complete feasibility report is available.
Financial Impact: $ Budgeted: Y☒ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Chris Petree, Public Works Director
2,348,205 Bonds, Grants, Various Funds
CIP & 2017 Budget
2
PRIMARY ISSUES TO CONSIDER
• Citizen Comments: Multiple meetings since August 2015 were held with
DLBA members and at the neighborhood meeting held on December 8, 2016,
there was no significant opposition to project. There were many questions
about the scope of the roadway improvements, the amount of the estimated
assessments, and questions regarding access during construction.
• Project cost and financing summary:
Total Street/Storm Sewer
Streetlight
Replacement Signage
Debt - repaid with:
Property taxes 1,137,756 1,137,756
Special assessments 610,505 593,845 16,660
65,000 65,000
78,144 78,144
456,800 456,800
TOTAL 2,348,205$ 1,731,601$ 456,800$ 159,804$
Streetlight Operating Fund*
Project Financing
Project Cost
Communication Fund
CDBG/RIG Funds
Feasibility
Estimate Budgeted
Debt - repaid with:
Property taxes 1,137,756$ 916,568.00$
Special assessments 610,505$ 557,046.00$
65,000$ -$
78,144$ -$
456,800$ 400,000.00$
TOTAL 2,348,205$ 1,873,614.00$
Streetlight Operating Fund*
Project Financing
Communication Fund
CDBG/RIG Funds
*Debt will be issued for streetlight portion, as well.
3
CITY OF LAKEVILLE
RESOLUTION NO:
RESOLUTION APPROVING FEASIBILITY REPORT AND CALLING PUBLIC
HEARING FOR THE 2017 HOLYOKE AVENUE IMPROVEMENT PROJECT
WHEREAS, on February 6, 2017, the City Council received the feasibility report
for the proposed improvements to Holyoke Avenue between CSAH 70 and Heritage Dr.,
City Improvement Project 17-04.
NOW, THEREFORE, BE IT RESOLVED, by the Lakeville City Council:
1. The Feasibility Report for Project 17-04 is hereby approved.
2. A public hearing is hereby called for March 6, 2017 at 7:00 p.m. at the
Council Chambers of the City Hall and the Clerk shall give mailed and
published notice of such hearing and improvement as required by law.
ADOPTED by the Lakeville City Council this 6th day of February, 2017.
CITY OF LAKEVILLE
________________________________
Douglas P. Anderson, Mayor
ATTEST:
________________________________
Charlene Friedges, City Clerk
211TH S T W
209TH ST W
IDAHOAVEHOLYOKE AVE212TH ST W HEATH AVE208THST
W IDALIA AVEH ERITAGEDRHOLT AVEIDAHOAVEHUGHES AVE207TH ST W
HOLLINS AVEHOLIDAY AVE205TH ST W
210TH ST W
214TH ST W
208TH ST W
UPPER 209THST W
HE R ITAGEDRHAYES AVE208THST W
HYDRA CT
ILAVISTAWAY HIGHVIEW AVEI LAVISTAWAY IDAHO AVEHOLIDAYAVEHUNTERC T
HUMBOLDTCT
HYA LITEDRH
YTRAILCIRICENICTRL HONEYCOMBPATHILLINOISPATH213TH ST WICELAND AVEIBISAVEIBEX AVEID E A L WAY
HUMMINGBIRD LN HULLAVE202ND ST W
HEYWOOD AVE215TH ST W
IDAHOAVE
H U N TSVILL E TRL HOWLAND AVEHOWLAND AVEHYTRAILCIRHYTRAILCIRH
A
R
T
F
O
R
DWAY
HARTFORD WAY
HURLEY AVE
208TH ST W
H
E
L
ENALNHAZE LWOO D TRLIBERIA AVEHOLT AVELOWER208THST
WHYSONPATH
HEMLOCKAVE207THC
TWHERON WAY
0 900Feet¯Project LoactionHolyoke Ave Improvement ProjectCity of Lakeville Document Path: K:\03199-310\GIS\Maps\Project Location.mxd Date Saved: 1/16/2017 3:47:55 PM1 inch = 900 feet
Project Location
Positioned to Thrive
Holyoke Avenue Improvement Project
City Council Meeting
February 6, 2017
Positioned to Thrive
Project Scope
•Mill and Overlay
•Complete Sidewalk
Replacement (Business
District)
•Streetscape
Improvements
•Streetlight
Replacement
Positioned to Thrive
Projected Costs/Financing
Estimated Project Costs $2,348,205
City CIP Funds $1,137,756
City Streetlight Operating Funds $456,800
City Communications Funds $78,144
CBD TIF Funds $65,000
Street and Storm Sewer Assessments $593,845
Signage Assessments $16,660
Positioned to Thrive
Streetscape Analysis
•Business District
•Sidewalks
•Streetscape
•Streetlight
replacement
•Gateway signage
Positioned to Thrive
Streetscape Improvements
Positioned to Thrive
Street Lights
•Replace existing
fixtures with the City’s
current standard
fixtures
•Acorn (pictured)
•Cobra
•Intersections
Positioned to Thrive
Signage
•City Message Sign
•Wayfinding Sign
•Gateway Signs
•County approved
Wayfinding Sings
Positioned to Thrive
City Message Sign & North Wayfinding
Sign
•City Message Sign: City Communication Funds
•North Wayfinding Sign: Dakota County CDBG/RIG
Funds
Positioned to Thrive
North & South Gateway Signs
•CBD TIF Funds and Special Assessments
Positioned to Thrive
County Approved Wayfinding Signs
•City Funds
Positioned to Thrive
Neighborhood Meeting
•All property owners were invited
•Discussed
•Sidewalks
•Streetlights
•Based on feedback received
•Spot sidewalk replacement
•Replacement of existing streetlights in current
locations
Positioned to Thrive
Estimated Assessments
•Single Family Unit
Rate
•North of 210th Street
•$1,948.64
Positioned to Thrive
Estimated Assessments
•Single Family Unit
Rate
•South of 210th Street
•$1,053.84
Positioned to Thrive
Estimated Assessments
•Front Foot
Assessment Rate –
Surface
Improvements
•Upper 206th Street to
210th Street
•$155.53
Positioned to Thrive
Estimated Assessments
•Front Foot
Assessment Rate –
Gateway Signage
Improvements
•Upper 206th Street to
210th Street
•$5.56
Positioned to Thrive
Estimated Assessments
•Front Foot
Assessment Rate
•South of 210th Street
•$11.02
Positioned to Thrive
Project Schedule
Receive Feasibility Report/Set Public Hearing February 6, 2017
Project Public Hearing/Order Project March 6, 2017
Open Bids/Compute Assessments May 3, 2017
Declare Costs/Set Assessment Hearing May 15, 2017
Assessment Hearing June 19, 2017
Award Construction Contract June 19, 2017
Construction Mid/Late July, 2017 – Sept., 2017
Certify Assessments December, 2017
Positioned to Thrive
Next Steps
•Accept the feasibility report
•Set the Public Hearing date for March 6, 2017