Date: Item No.
FINAL ACCEPTANCE AND FINAL PAYMENT TO
INSITUFORM TECHNOLOGIES USA, LLC
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
utility improvements and final payment to Insituform Technologies USA, LLC for 2016 Sanitary
Sewer Improvement Project.
Overview
Insituform Technologies USA, LLC requests final acceptance of public utility improvements and
final payment in the amount of $10,388.02 for City Project 16-13. The original contract amount
was $214,462.70. No change orders were processed for this project. The final construction cost
is $207,760.50.
Primary Issues to Consider
• The public utility improvements were tested and inspected by the City’s Public Works
Department. All work was completed consistent with the contract and the administrative
requirements for final payment.
Supporting Information
• None.
Financial Impact: $ Budgeted: Y☒ N Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Notes: Additional funding provided by Metropolitan Council of Env. Services (MCES) Grant
Report Completed by: Zach Johnson, City Engineer
March 6, 2017
10,388.02
2
San . Sewer Operating Fund