Date: Item No.
CELEBRATION CHURCH PUD AMENDMENT
Proposed Action
Staff recommends adoption of the following motion: Move to approve the Celebration Church
PUD amendment and Site Improvement Performance Agreement (SIPA).
Overview
Celebration Church representatives have submitted an application for a planned unit
development (PUD) amendment to allow the construction of a two level, 18,443 square foot
addition on the south side of the existing church building located at 16655 Kenyon Avenue. The
proposed addition will include space for classrooms, a banquet hall, and relocated space for the
day care/pre-school currently located in the existing building.
The Planning Commission held a public hearing at its March 2, 2017 meeting. The Planning
Commission recommended unanimous approval of the PUD Amendment subject to nine
stipulations. There was no public comment at the public hearing.
Primary Issue to Consider
How does the Site Improvement Performance Agreement (SIPA) language differ from the
stipulations recommended by the Planning Commission? Representatives of Celebration Church
recommended some minor changes to Stipulations 4 and 9, which are reflected in the SIPA, to
clarify all proposed building improvements as shown on the plans as well as clarification as to how
on-site parking will be managed while reserving the City’s right to require additional on-site
parking if there is a demonstrated need.
Supporting Information
• Signed Site Improvement Performance Agreement
• March 3, 2017 Planning Commission minutes
• February 24, 2017 planning report, revised March 23, 2017 and the February 22, 2017
engineering report
Financial Impact: $ Budgeted: Y☐ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: A Sense of Community and Belonging
Report Completed by: Frank Dempsey, AICP, Associate Planner
April 3, 2017
None
Zoning Ordinance
CITY OF LAKEVILLE
PLANNING COMMISSION MEETING MINUTES
March 2, 2017
Chair Swenson called the meeting to order at 6:00 p.m. in the Council Chambers at City
Hall. The pledge of allegiance to the flag was given.
Members Present: Chair Jason Swenson, Vice Chair Brooks Lillehei, Karl Drotning,
Pat Kaluza, Elizabeth Bakewicz
Members Absent: Paul Reuvers, Jason Kelvie, Scott Einck, Ex-officio member Nic
Stevens
Others Present: Daryl Morey, Planning Director; Frank Dempsey, Associate Planner;
Kris Jenson, Associate Planner; and Penny Brevig, Recording Secretary
3. Approval of the Meeting Minutes
The February 16, 2017 Planning Commission meeting minutes were approved as
presented.
The February 16, 2017 Planning Commission work session minutes were approved
as presented.
4. Announcements
Mr. Morey stated the following items were distributed to the Planning Commission at
tonight’s meeting:
Regarding the Caribou Coffee & Einstein Bros. Bagels agenda item:
• Revised color building elevations
• Revised site plan
• Revised trash enclosure plan
Mr. Morey reminded the Planning Commission members of the work session
immediately following tonight’s meeting.
5. Celebration Church
Chair Swenson opened the public hearing to consider the application of Celebration
Church for an amendment to the Celebration Church Planned Unit Development
(PUD) to allow an addition onto the south side of the existing church building,
located at 16655 Kenyon Avenue.
Planning Commission Meeting Minutes, March 2, 2017 Page 2
Pastor Derrick Ross from Celebration Church presented an overview of the project.
He indicated that he is continuing the building plan Lowell Lundstrom started over
ten years ago.
Associate Planner Frank Dempsey presented the planning report. Mr. Dempsey
stated that Celebration Church representatives have submitted an application for a
PUD amendment to allow the construction of a two level addition on the south side
of the existing church building. The proposed addition will include first floor space
for classrooms, relocated space for the day care/pre-school that is now located in
the existing building, and a banquet hall and stage on the upper level with seating for
450 people. Mr. Dempsey indicated that the proposed building addition requires an
amendment to the Celebration Church PUD approved in 2001 when the main
assembly hall and parking lot was constructed.
Mr. Dempsey stated that the proposed building addition will be attached to the
existing building with a 20 foot wide outdoor walkway. An indoor hallway connection
will provide interior access to the new addition.
The majority of the subject property lies within the Shoreland Overlay District of Lee
Lake. Mr. Dempsey explained that the Celebration Church Second Addition PUD
allowed up to 42% impervious surface. The new construction will increase the
impervious surface area to approximately 36%.
Mr. Dempsey reviewed building setbacks, elevations, exterior building materials, and
building height, which all meet the requirements of the Zoning Ordinance. The
parking lot reconstruction will include the removal of 12 parking spaces, which still
leaves the church with enough parking spaces to meet the minimum requirement of
434 parking spaces.
If both the banquet and the church area were being used at the same time, 100
more parking spaces would be required. With that in mind, staff is recommending
that banquet hall events and religious assembly in the main sanctuary hall not be
held at the same time.
A new private sidewalk will be constructed adjacent to the parking lot on the south
side of the building addition and near the new loading area and playground. All
landscaping materials meet the size and species requirements of the Zoning
Ordinance.
Mr. Dempsey stated that an accessory building is proposed along the wall of the
existing church building. A small accessory building currently located on the west
side of the parking lot will be removed.
A roof top mechanical screening plan has been prepared to address the screening of
the equipment from Kenyon Avenue. Mr. Dempsey indicated that a 42 inch tall
parapet wall will be extended above the roof line as an architectural means of
addressing the screening requirement of the Zoning Ordinance.
Planning Commission Meeting Minutes, March 2, 2017 Page 3
Mr. Dempsey stated that staff recommends approval of the PUD amendment subject
to the 9 stipulations listed in the February 24, 2017 planning report.
Chair Swenson opened the hearing to the public for comment.
There were no comments from the audience.
Motion was made by Drotning, seconded by Lillehei to close the public
hearing at 6:10 p.m.
Voice vote was taken on the motion. Ayes – unanimous
Chair Swenson asked for comments from the Planning Commission. Discussion
points included:
• Chair Swenson confirmed that a building permit is required prior to
constructing the proposed accessory building to be sure that the exterior
building materials match the exterior of the church.
• Referring to Stipulation 4, Commissioner Lillehei stated that as long as the
church has enough parking he would not be opposed to concurrent events in
the banquet/assembly hall and main sanctuary. Mr. Dempsey indicated that
the stipulation is being recommended by staff to insure that the church does
not utilize on-street parking to meet their parking demand.
• After a brief discussion, the Planning Commission agreed that the following
changes be made to Stipulations 4 and 9 of the February 24, 2017 planning
report:
4. Events or other assembly in the banquet/assembly hall shall not be
scheduled during times when religious assembly or other events
are being held in the main sanctuary hall in order to ensure
adequate off-street parking.
9. The Minnesota Department of Health child care license shall be
approved by the State of Minnesota prior to occupancy of the
building addition for the day care use.
Pastor Derrick Ross confirmed that he could still use the proposed additional
classrooms for other uses, just not day care until they acquired the day care license.
Motion was made by Drotning, seconded by Lillehei to recommend to City
Council approval of the Celebration Church Planned Unit Development amendment
to allow an addition onto the south side of the existing church building, located at
16655 Kenyon Avenue, subject to the following stipulations, as amended:
1. The recommendations listed in the February 22, 2017 engineering report.
2. The site and building addition shall be developed in accordance with the plans
approved by the City Council.
3. The head-to-head parking stalls in the parking lot west of the building shall be
restriped to meet the minimum stall depth requirement of 20 feet.
Planning Commission Meeting Minutes, March 2, 2017 Page 4
4. Events or other assembly in the banquet/assembly hall shall not be scheduled
during times when religious assembly or other events are being held in the main
sanctuary hall in order to ensure adequate off-street parking.
5. Landscaping shall be installed consistent with the approved landscape plan. A
$10,000 security shall be submitted with the building permit application to
guarantee installation of the approved landscaping and parking lot restriping.
6. The existing accessory building shall be removed from the property.
7. A building permit is required prior to commencing construction of the addition and
accessory building. Construction of the addition and accessory building is
subject to the approval of the Building Official and Fire Marshal.
8. A sign permit is required prior to the installation or modifications of any signs.
9. The Minnesota Department of Health child care license shall be approved by the
State of Minnesota prior to occupancy of the building addition for the day care
use.
Ayes: Bakewicz, Lillehei, Swenson, Kaluza, Drotning
Nays: 0
6. Caribou Coffee & Einstein Bros. Bagels
Chair Swenson opened the public hearing to consider the application of United
Properties Development, LLC for the following, located east of Kenwood Trail
(CSAH 50) and south of 175th Street: A. Conditional Use Permit to allow the
construction of Caribou Coffee & Einstein Bros. Bagels with a drive-through service
window; and B. Amendment to the Hoppe Marketplace PUD to allow a reduction in
the required number of parking spaces and a reduction in the required amount of
green space for a convenience restaurant use.
Keith Ulstad from United Properties presented an overview of their request. Mr.
Ulstad stated that they bought the Hoppe property adjacent to Argonne Village 12
years ago. It’s taken a few years longer to fully develop Hoppe Marketplace due to
the recession. He indicated that representatives from Westwood Engineering,
Reprise Architects and Caribou Coffee were in the audience to answer any
questions.
Associate Planner Kris Jenson presented the planning report. Ms. Jenson stated
that the request is for a CUP to allow the construction of a convenience restaurant
on Lot 2, Block 1, Hoppe Marketplace 3rd Addition, along with an amendment to the
Hoppe Marketplace PUD to allow a reduction in the required number of parking
spaces and a reduction in the required amount of green space for a convenience
restaurant on the subject property.
Ms. Jenson indicated that the applicant is proposing a Caribou Coffee & Einstein
Bros. Bagels restaurant with a drive-through. The proposed restaurant will have 41
seats indoors with an additional 20 seasonal seats on the patio. The applicant is
proposing hours of operation of 5:00 a.m. to 9:00 p.m.
City of Lakeville
Planning Department
Memorandum
To : Planning Commission
From: Frank Dempsey, AICP, Associate Planner
Date: February 24, 2017 (Revised March 23, 2017)
Subject: Packet Material for the March 2, 2017 Planning Commission Meeting
Agenda Item: Celebration Church Planned Unit Development Amendment
Action Deadline: April 4, 2017
INTRODUCTION
Celebration Church representatives have submitted an application for a planned unit
development (PUD) amendment to allow the construction of a two level, 18,443 square foot
addition on the south side of the existing church building located at 16655 Kenyon Avenue.
The proposed addition will include space for classrooms, a banquet hall, and relocated
space for the existing day care/pre-school now located in the existing building. The day
care use was approved by conditional use permit in 2006.
The subject property is zoned PUD, Planned Unit Development subject to the C-3, General
Commercial District uses and performance standards. Section 11-73-7.Q of the Zoning
Ordinance allows religious institution uses in the C-3 District. Section 11-73-7.H. allows day
care facilities in the C-3 District. The proposed building addition requires an amendment to
the Celebration Church PUD approved in 2001 at the time the main assembly hall and
parking lot was constructed.
EXHIBITS
The following exhibits are attached for your reference:
A. Aerial Photo Map
B. Location and Zoning Map
C. Application Narrative
D. Property Survey
E. Demolition Plan
F. Site Plan
G. Grading and Stormwater Plan (2 Pages)
H. Utility Plan
I. Landscape Plan
J. Floor and Roof Plans (5 Pages)
K. Exterior Elevations (2 Pages)
L. Sectional Views (3 Pages)
SITE ANALYSIS
The proposed building addition will be attached to the southwest corner of the existing
building with a 20 foot wide outdoor walkway between the existing building and
proposed addition. An indoor hallway connection will provide interior access to the new
addition. The project includes 9,268 square feet of classroom space and infant to
kindergarten day care. The upper level will be a 9,175 square foot banquet hall and stage
with seating for 450 persons. Two separate outdoor play areas are proposed on the west
side of the church building.
The existing Celebration Church is approximately 50,000 square feet in area and includes
office space and a sanctuary with 700 to 1,086 seats. The conditional use permit approved
in 2006 allowed day care for up to 80 children. Additional license capacity may be added
provided that on-site parking is shown to be adequate and subject to approval of a PUD
Amendment.
Surrounding Land Uses and Zoning
North – Former Jackson Landscape property (PUD)
South – Schneiderman’s Furniture store under construction (C-3)
East – Kenyon Avenue and Interstate 35
West – Single family homes (RS-3)
The proposed building addition was reviewed for conformance with Zoning Ordinance
performance standards as follows:
Shoreland Overlay District. The majority of the property lies within the Shoreland
Overlay District of Lee Lake. The Celebration Second Addition planned unit development
approved in 2001 allowed up to 42% of the property within the Shoreland Overlay District
to be impervious surface. The parking lot was constructed with a slightly different
configuration and fewer parking spaces and less impervious surface area than the original
approved site plan resulting in an impervious surface area of 34.1%. The new construction
will increase the impervious surface area to approximately 36%, which is below the 42%
impervious surface area approved in 2001.
Building Setbacks. The existing building meets the setback requirements of the C-3,
General Commercial District as follows:
Front Yard – 30 feet
Side Yards – 20 feet
Rear Yards – 30 feet
The proposed building addition will have the following setbacks:
2
Front Yard (Kenyon Avenue) – 300 feet
Side Yard (south) –240 feet
Rear Yard (west) – 280 feet
Building Elevations and Exterior Building Materials. The building addition will be
constructed of similar integral colored tan concrete block to that of the existing church
building that was constructed in compliance with Zoning Ordinance requirements in 2002.
Section 11-17-9.F.10.g of the Zoning Ordinance allows building additions less than 50% of
the floor area of the existing building to use the same or similar materials as the existing
building.
The south wall of the new addition will equal approximately 15.5% of the exterior wall area
of the entire church building. Using the same exterior building materials as the existing
church for the proposed addition is in harmony with the existing church building and
other commercial structures in the area.
Building Height. The building addition height is 32 feet, measured as the mean height
between the highest and lowest walls. The maximum allowed height in the C-3 District is
three stories or 35 feet.
Floor Plan. The floor plan for the building addition includes day care/classrooms on the
lower level and a 450 seat banquet/assembly hall on the upper level.
Access and Circulation. The property access from and to Kenyon Avenue will remain
unaffected by the proposed building addition and use. The site is accessed via two
driveways to and from Kenyon Avenue.
Parking. The proposed site work will include demolishing and reconstructing part of the
parking area on the south and west sides of the building to provide loading/unloading
area near the entrance door on the south side of the building. The parking lot
reconstruction will include the removal of 12 parking spaces. The church’s 1,086 seat main
assembly hall approved in 2006 requires 434 parking spaces at a ratio of one space for
each 2.5 seats in the main assembly area. The existing parking lot provides 512 parking
spaces which exceeds the minimum required number of parking spaces.
A review of the site plan identified a non-conforming stall space design in the middle row
head-to-head parking spaces in the south parking lot. The existing stalls are 18 feet deep.
A minimum stall depth of 20 feet is required by the Zoning Ordinance. Both of the two
adjacent drive aisles are approximately three feet wider than required by the Zoning
Ordinance, leaving adequate space to re-stripe the middle spaces to comply with the
minimum stall depth requirements.
Staff recommends that events or other assembly in the banquet/assembly hall not be
scheduled during times when religious assembly or other events are held in the main
sanctuary in order to ensure adequate off-street parking.
Sidewalks. An eight foot wide concrete public sidewalk is located on the west side of
Kenyon Avenue. A private sidewalk is located along the east side of the building and from
the west office exit to the west parking lot. New private sidewalk will be constructed
adjacent to the parking lot on the south side of the building addition and near the new
loading area and playground.
3
Landscaping. A mix of deciduous and evergreen trees and shrubs are proposed along the
foundation of the building addition and the south building entrance. All materials meet
the size and species requirements of the Zoning Ordinance.
Accessory Building. A 720 square foot accessory building is proposed to be constructed
along wall of the existing church building. The new accessory building will be 12 feet in
height and constructed of the same masonry block exterior as the church building with an
asphalt shingled roof. A small accessory building currently located on the west side of the
parking lot. The Zoning Ordinance allows one accessory building per property. The
existing accessory building shall be removed from the property.
Signs. No changes to the building or freestanding signage is proposed with this PUD
Amendment. The church is subject to the C-3 District requirements of the Zoning
Ordinance. A sign permit is required prior to the installation of any signs.
Mechanical Equipment. All mechanical equipment for the building addition is proposed
to be located on the roof. A roof top mechanic screening plan has been prepared to
address screening of the equipment from Kenyon Avenue. A 42 inch tall parapet wall will
be extended above the roof line as an architectural means of addressing the screening
requirement of the Zoning Ordinance.
Lighting. Any exterior lighting shall be downcast in design, shall not glare onto adjoining
properties and shall meet Zoning Ordinance requirements. Plans and an electrical permit
shall be submitted prior to the installation of any exterior lighting.
RECOMMENDATION
Planning Department staff recommends approval of the Celebration Church planned unit
development amendment subject to the following stipulations:
1. The recommendations listed in the February 22, 2017 engineering report.
2. The site shall and building addition shall be developed in accordance with the plans
approved by the City Council.
3. The head-to-head parking stalls in the parking lot west of the building shall be
restriped to meet the minimum stall depth requirement of 20 feet.
4. Events or other assembly in the banquet/assembly hall shall not be scheduled
during times when religious assembly or other events are being held in the main
sanctuary hall in order to meet off-street parking requirements.
5. Landscaping shall be installed consistent with the approved landscape plan. A
$10,000 security shall be submitted with the building permit application to
guarantee installation of the approved landscaping and parking lot restriping.
6. The existing accessory building shall be removed from the property.
7. A building permit is required prior to commencing construction of the addition and
accessory building. Construction of the addition and accessory building is subject
to the approval of the Building Official and Fire Marshal.
8. A sign permit is required prior to the installation or modifications of any signs.
4
9. The Minnesota Department of Health child care license shall be approved by the
State of Minnesota prior to occupancy of the day care space.
5
CELEBRATION CHURCH BUILDING ADDITION
Property Information
February 22, 2017
0 450 900225 ft
0 130 26065 m
1:4,800
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search,appraisal, survey, or for zoning verification.
EXHIBIT A
Lee
Lake
C-3
C-3
P/OS
P/OS
RS-3
PUD
P/OS
RS-3
PUDC-3
§¨¦35
KENORA WAY
1 6 7TH STWKENRICK AVE16 4THST W
KENWOOD TRLKENOSHA AVE
165TH ST W
UPPER 167TH ST W
168THST WKENTTRL
KENMORE DRKENRICK LOOPKENYON AVELOWER 167TH ST W
166TH ST W
ZONING MAP
Ü
EXHIBIT B
Don Kimble - Architect
Don Kimble, AIA
P.O. BOX 41 - ANDOVER, KS 67002
Ph. 316- 651-3324 - Fax 316-613-3484
don.kimble.arch@gmail.com
Date: 02-17-2017
Project: Celebration Church
Project Location: Lakeville, MN
To: Frank Dempsey, City of Lakeville
Mr. Dempsey,
The proposed building addition to Celebration Church consists of two parts; the upper level
Banquet Hall and a lower level children’s area.
The upper level Banquet Halls main purpose is to be used as a new dining facility and large
meeting hall for the church, it seats 450. It will also be used for wedding receptions and similar
functions. This upper level Banquet Hall also has the ability to be broken up into classrooms to
be used by the church for additional Sunday school classroom space.
The lower level children’s area has several uses. On Sundays it will function as Sunday school
classrooms, but during the week five of the rooms will be used for childcare. The church
currently has a functioning childcare, Celebration Academy, and it will move to this new lower
level addition. The new child care facility for Celebration Academy is scheduled to house 72
children in daycare.
Please let us know if you have any questions or need any further information.
Thank you,
Don Kimble, Architect
LOUCKS
W:\2016\16427\CADD DATA\SURVEY\S16427-MASTERPlotted: 10 /13 / 2016 2:38 PM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
16655 KENYON AVENUE
LAKEVILLE MINNESOTA
ROE MESSNER &
ASSOCIATES, INC.
380 EAST LOCH LLOYD PARKWAY
VILLAGE OF LOCH LLOYD,
MICHIGAN 64012
10/13/16 SURVEY ISSUED
License No.
Date
I hereby certify that this survey, plan or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Land Surveyor under the laws of
the State of Minnesota.
VICINITY MAP
Field Crew
Max L. Stanislowski - PLS
48988
Project Lead
Drawn By
Checked By
Loucks Project No.16427
MLS
BJY
MLS
BRS/MJA
10/13/16
SCALE IN FEET
0 30 60
SURVEY LEGEND
SPOT ELEVATION
GATE VALVE
SIGN
LIGHT POLE
SANITARY MANHOLE
HYDRANT
CATCH BASIN
CONTOUR
CONCRETE CURB
STORM SEWER
SANITARY SEWER
CHAIN LINK FENCE
WATERMAIN
UNDERGROUND ELECTRIC
CONCRETE
A/C UNIT
CABLE TV PEDESTAL
ELECTRIC TRANSFORMER
UNDERGROUND GAS
MAILBOX
GUARDPOST
ELM
CATULPA
BIRCH
OAK
TREE (GEN)
EL
CA
BI
OA
TR
DECIDUOUS TREE
ELEV @ THRESHOLDTHSD
ELECTRIC OUTLETEO
TREE LINE
PARKING STALL COUNT
HANDICAP PARKING STALL
TOP OF CURBTC
3
SET 1/2 INCH X 14 INCH
IRON MONUMENT,
MARKED "LS 48988"
FOUND IRON
MONUMENT
SITE
N
DESCRIPTION OF PROPERTY SURVEYED
(Per Dakota County Tax records)
Lot 1, Block 1, CELEBRATION 2ND ADDITION, Dakota County, Minnesota.
Abstract Property
SURVEY REPORT
1. The purpose of this survey is to show partial topography and existing improvements for the requested
area of the property.
2. This survey was performed without the benefit of a Title Commitment. There may or may not be
easements of record encumbering this property. The Surveyor was not provided utility easement
documents for the subject property except for those shown on the Survey.
3. The bearings for this survey are based on the plat CELEBRATION 2ND ADDITION.
4. The address, if disclosed in documents provided to or obtained by the surveyor, or observed while
conducting the fieldwork is 16655 Kenyon Avenue, Lakeville, Minnesota 55044.
5. Benchmark: 1980 W. In Lakeville, 0.7 mile north along Interstate Highway 35 from the junction of Interstate
Highway 35 and County Road 5 and County Road 50 in Lakeville, at Interstate Highway 35 milepoint 86.15, 26.1
feet east of eastbound Interstate Highway 35 fog line, 40.4 feet west of off and on ramp from northbound
Interstate Highway 35 to Metro Transit parking ramp, 1.5 feet north of witness post. Elevation = 1013.96 (NAVD
88)
Site Benchmark: Top Nut Hydrant s ft. southwesterly along the westerly right of way of Kenyon Avenue from
the southeast corner of surveyed property. Elevation = 1025.68 (NAVD 88)
6. A volleyball court lies over the line at the southeast corner of the property.
7. A sidewalk lies over the line along the east side of the property.
8.See sheet 2 of 2 sheets for boundary and easement detail.
9. We have shown underground utilities on and/or serving the surveyed property per Gopher State
One-Call Ticket Nos. 162511709 & 162511762. The following utilities and municipalities were notified:
City of Lakeville 952-985-2740 Dakota County Highway Dept. 952-891-7900
Dakota electric 651-463-6268 Frontier Communications 800-778-9140
Lakeville Public Schools 320-963-2400 Center Point Energy 406-541-9571
Dept. of Transportation 651-366-5750 Charter Communications 800-778-9140
Zayo Bandwidth 952-230-9430
i. Utility operators do not consistently respond to locate requests through the Gopher State One Call
service for surveying purposes such as this. Those utility operators that do respond, often will not
locate utilities from their main line to the customer's structure or facility. They consider those
utilities ßSULYDWHà installations that are outside their jurisdiction. These ßSULYDWHà utilities on the
surveyed property or adjoining properties, may not be located since most operators will not mark
such "private" utilities. A private utility locator may be contacted to investigate these utilities
further, if requested by the client.
ii. The locations of underground utility lines shown hereon is an approximation based on available
maps, unless otherwise noted on the survey.
iii. Maps provided by those notified above, either along with a field location or in lieu of such a
location, are very often inaccurate or inconclusive. EXTREME CAUTION MUST BE EXERCISED
BEFORE AN EXCAVATION TAKES PLACE ON OR NEAR THIS SITE. BEFORE DIGGING, YOU ARE
REQUIRED BY LAW TO NOTIFY GOPHER STATE ONE CALL AT LEAST 48 HOURS IN ADVANCE
AT 811 or (651) 454-0002.
CAST IRON MONUMENT
TELEPHONE PEDESTAL
PARTIAL
TOPOGRAPHIC
SURVEY
1 OF 2
CONTROLLED ACCESS
EXHIBIT D
LOUCKS
W:\2016\16427\CADD DATA\CIVIL\_dwg Sheet Files\C1-2 Demolition PlanPlotted: 01 /20 / 2017 9:54 AM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Professional Engineer under the
laws of the State of Minnesota.
Jeffrey A. Shopek - PE
19624
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
JDK
JAS
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 CHECK SET
1/20/2017 CITY SUBMITTAL
CONSTRUC
T
I
O
N
NOT FOR
DEMOLITION
PLAN
C1-2
SCALE IN FEET
0 20 40
SURVEY NOTE:
1. REFER TO BOUNDARY AND TOPOGRAPHIC SURVEY (SHEETS 1-2) FOR
COMPLETE SITE SURVEY INFORMATION.
REMOVE EXISTING BUILDING, CANOPY, ETC.
COORDINATE WITH ARCHITECTURAL PLANS
REMOVE EXISTING CURB & GUTTER, FENCE,
RETAINING WALLS, ETC.
REMOVE EXISTING MANHOLES, POWER
POLES, LIGHT POLES, BOLLARDS, SIGNS, ETC.
REMOVE EXISTING CONCRETE PAVING,
SIDEWALKS, ISLANDS, ETC.
REMOVE EXISTING TREES
REMOVE EXISTING UTILITIES
REMOVE EXISTING BITUMINOUS PAVING
DEMOLITION LEGEND:
1. CONTRACTOR SHALL REMOVE AND/OR RELOCATE EXISTING PRIVATE UTILITIES
AS NECESSARY. CONTRACTOR TO COORDINATE ACTIVITIES WITH UTILITY
COMPANIES.
2. CONTRACTOR SHALL PROTECT SURFACE AND SUBSURFACE FEATURES NOT
NOTED FOR REMOVAL.
3. CONTRACTOR TO CLEAR AND GRUB EXISTING VEGETATION WITHIN
CONSTRUCTION LIMITS, STRIP TOP SOIL, AND STOCKPILE ON-SITE. REFER TO
GRADING PLAN AND SWPPP FOR SEDIMENT AND EROSION CONTROL
REQUIREMENTS.
4. CLEAR AND GRUB AND REMOVE ALL TREES, VEGETATION AND SITE DEBRIS
PRIOR TO GRADING. ALL REMOVED MATERIAL SHALL BE HAULED FROM THE
SITE DAILY. ALL CLEARING AND GRUBBING AND REMOVALS SHALL BE
PERFORMED PER THE CONTRACT SPECIFICATIONS. EROSION CONTROL
MEASURES SHALL BE IMMEDIATELY ESTABLISHED UPON REMOVAL. SEE THE
STORMWATER POLLUTION PREVENTION PLAN (SWPPP).
5.CONTRACTOR SHALL REMOVE ALL SITE SURFACE FEATURES WITHIN REMOVAL
LIMITS UNLESS OTHERWISE NOTED.
SITE DEMOLITION NOTES
WARNING:
THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALLING FOR LOCATIONS OF ALL
EXISTING UTILITIES. THEY SHALL COOPERATE WITH ALL UTILITY COMPANIES IN
MAINTAINING THEIR SERVICE AND / OR RELOCATION OF LINES.
THE CONTRACTOR SHALL CONTACT GOPHER STATE ONE CALL AT 651-454-0002 AT
LEAST 48 HOURS IN ADVANCE FOR THE LOCATIONS OF ALL UNDERGROUND WIRES,
CABLES, CONDUITS, PIPES, MANHOLES, VALVES OR OTHER BURIED STRUCTURES BEFORE
DIGGING. THE CONTRACTOR SHALL REPAIR OR REPLACE THE ABOVE WHEN DAMAGED
DURING CONSTRUCTION AT NO COST TO THE OWNER.EXHIBIT E
LOUCKS
W:\2016\16427\CADD DATA\CIVIL\_dwg Sheet Files\C2-1 Site PlanPlotted: 01 /20 / 2017 9:55 AM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Professional Engineer under the
laws of the State of Minnesota.
Jeffrey A. Shopek - PE
19624
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
JDK
JAS
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 CHECK SET
1/20/2017 CITY SUBMITTAL
CONSTRUC
T
I
O
N
NOT FOR
1. ALL PAVING, CONCRETE CURB, GUTTER AND SIDEWALK SHALL BE FURNISHED AND INSTALLED
IN ACCORDANCE WITH THE DETAILS SHOWN PER THE DETAIL SHEET(S) AND STATE/LOCAL
JURISDICTION REQUIREMENTS.
2. ACCESSIBLE PARKING AND ACCESSIBLE ROUTES SHALL BE PROVIDED PER CURRENT ADA
STANDARDS AND LOCAL/STATE REQUIREMENTS.
3. ALL CURB DIMENSIONS SHOWN ARE TO THE FACE OF CURB UNLESS OTHERWISE NOTED.
4. ALL BUILDING DIMENSIONS ARE TO THE OUTSIDE FACE OF WALL UNLESS OTHERWISE NOTED.
5. TYPICAL FULL SIZED PARKING STALL IS 9' X 20' UNLESS OTHERWISE NOTED.
6. ALL CURB RADII SHALL BE 5.0' UNLESS OTHERWISE NOTED.
7. BITUMINOUS IMPREGNATED FIBER BOARD TO BE PLACED AT FULL DEPTH OF CONCRETE
ADJACENT TO EXISTING STRUCTURES AND BEHIND CURB ADJACENT TO DRIVEWAYS AND
SIDEWALKS.
8. SEE SITE ELECTRICAL PLAN FOR SITE LIGHTING.
CURRENT ZONING: PUD- PLANNED UNIT DEVELOPMENT
PROPOSED ZONING: PUD- PLANNED UNIT DEVELOPMENT
PROPERTY AREA:16.04 AC
DISTURBED AREA:0.99 AC
PARKING REQUIREMENT: XXXXXX
TOTAL PARKING: XXXXXXX
PAVEMENT TYPES
NOTE:
PAVEMENT SECTIONS TO BE DETERMINED BASED ON SOILS REPORT.
LIGHT DUTY BITUMINOUS PAVEMENT
CONCRETE SIDEWALK
HEAVY DUTY BITUMINOUS PAVEMENT
CONCRETE PAVEMENT
SITE NOTES SITE DATA
SITE PLAN
C2-1
SCALE IN FEET
0 20 40
EXHIBIT F
LOUCKS
W:\2016\16427\CADD DATA\CIVIL\_dwg Sheet Files\C3-1 Grading PlanPlotted: 01 /20 / 2017 9:56 AM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Professional Engineer under the
laws of the State of Minnesota.
Jeffrey A. Shopek - PE
19624
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
JDK
JAS
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 CHECK SET
1/20/2017 CITY SUBMITTAL
CONSTRUC
T
I
O
N
NOT FOR
GRADING
PLAN
C3-1
WARNING:
THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALLING FOR LOCATIONS OF ALL
EXISTING UTILITIES. THEY SHALL COOPERATE WITH ALL UTILITY COMPANIES IN
MAINTAINING THEIR SERVICE AND / OR RELOCATION OF LINES.
THE CONTRACTOR SHALL CONTACT GOPHER STATE ONE CALL AT 651-454-0002 AT
LEAST 48 HOURS IN ADVANCE FOR THE LOCATIONS OF ALL UNDERGROUND WIRES,
CABLES, CONDUITS, PIPES, MANHOLES, VALVES OR OTHER BURIED STRUCTURES BEFORE
DIGGING. THE CONTRACTOR SHALL REPAIR OR REPLACE THE ABOVE WHEN DAMAGED
DURING CONSTRUCTION AT NO COST TO THE OWNER.
GRADING, DRAINAGE & EROSION CONTROL NOTES
1. SPOT ELEVATIONS REPRESENT FINISHED SURFACE GRADES, GUTTER/FLOW LINE, FACE OF BUILDING, OR EDGE
OF PAVEMENT UNLESS OTHERWISE NOTED.
2. CATCH BASINS AND MANHOLES IN PAVED AREAS SHALL BE SUMPED 0.04 FEET. ALL CATCH BASINS IN
GUTTERS SHALL BE SUMPED 0.16 FEET. RIM ELEVATIONS SHOWN ON PLANS DO NOT REFLECT SUMPED ELEVATIONS.
3. ALL DISTURBED UNPAVED AREAS ARE TO RECEIVE MINIMUM OF 4 INCHES OF TOP SOIL AND SEED/MULCH OR
SOD. THESE AREAS SHALL BE WATERED/MAINTAINED BY THE CONTRACTOR UNTIL VEGETATION IS ESTABLISHED.
4. FOR SITE RETAINING WALLS "TW" EQUALS SURFACE GRADE AT TOP FACE OF WALL (NOT TOP OF WALL), "GW"
EQUALS SURFACE GRADE AT WALL GRADE TRANSITION, AND "BW" EQUALS SURFACE GRADE AT BOTTOM FACE OF
WALL (NOT BOTTOM OF BURIED WALL COURSES).
5. REFER TO THE REPORT OF GEOTECHNICAL EXPLORATION AND REVIEW (REPORT NO.20-15031), DATED
DECEMBER 19,2016 AS PREPARED BY AMERICAN ENGINEERING TESTING, INC. FOR AN EXISTING SUBSURFACE SITE
CONDITION ANALYSIS AND CONSTRUCTION RECOMMENDATIONS.
6. STREETS MUST BE CLEANED AND SWEPT WHENEVER TRACKING OF SEDIMENTS OCCURS AND BEFORE SITES ARE
LEFT IDLE FOR WEEKENDS AND HOLIDAYS. A REGULAR SWEEPING SCHEDULE MUST BE ESTABLISHED.
7. DUST MUST BE ADEQUATELY CONTROLLED.
8. SEE SWPPP FOR ADDITIONAL EROSION CONTROL NOTES AND REQUIREMENTS.
9. SEE UTILITY PLAN FOR WATER, STORM AND SANITARY SEWER INFORMATION.
10. SEE SITE PLAN FOR CURB AND BITUMINOUS TAPER LOCATIONS.SCALE IN FEET
0 20 40
EXHIBIT G
LOUCKS
W:\2016\16427\CADD DATA\CIVIL\_dwg Sheet Files\C3-2 SWPPPPlotted: 01 /20 / 2017 9:57 AM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Professional Engineer under the
laws of the State of Minnesota.
Jeffrey A. Shopek - PE
19624
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
JDK
JAS
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 CHECK SET
1/20/2017 CITY SUBMITTAL
CONSTRUC
T
I
O
N
NOT FOR
STORMWATER
POLLUTION
PREVENTION
PLAN
C3-2
WARNING:
THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALLING FOR LOCATIONS OF ALL
EXISTING UTILITIES. THEY SHALL COOPERATE WITH ALL UTILITY COMPANIES IN
MAINTAINING THEIR SERVICE AND / OR RELOCATION OF LINES.
THE CONTRACTOR SHALL CONTACT GOPHER STATE ONE CALL AT 651-454-0002 AT
LEAST 48 HOURS IN ADVANCE FOR THE LOCATIONS OF ALL UNDERGROUND WIRES,
CABLES, CONDUITS, PIPES, MANHOLES, VALVES OR OTHER BURIED STRUCTURES BEFORE
DIGGING. THE CONTRACTOR SHALL REPAIR OR REPLACE THE ABOVE WHEN DAMAGED
DURING CONSTRUCTION AT NO COST TO THE OWNER.
SCALE IN FEET
0 20 40
ESTIMATED QUANTITIES
DESCRIPTION UNIT
TEMPORARY ROCK CONSTRUCTION ENTRANCE EA
PREFABRICATED CONCRETE WASHOUT EA
SILT FENCE (STANDARD)LF
BIOROLL LOGS LF
INLET PROTECTION EA
QUANTITY
1
1
170
200
18
SEEDING AC 0.XX
INLET PROTECTION
SWPPP LEGEND
SILT FENCE
EXISTING DRAINAGE PATTERN
PROPOSED DRAINAGE PATTERN
LOUCKS
W:\2016\16427\CADD DATA\CIVIL\_dwg Sheet Files\C4-1 Utility PlanPlotted: 01 /20 / 2017 9:58 AM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision and that
I am a duly Licensed Professional Engineer under the
laws of the State of Minnesota.
Jeffrey A. Shopek - PE
19624
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
JDK
JAS
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 CHECK SET
1/20/2017 CITY SUBMITTAL
CONSTRUC
T
I
O
N
NOT FOR
UTILITY
PLAN
C4-1
WARNING:
THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALLING FOR LOCATIONS OF ALL
EXISTING UTILITIES. THEY SHALL COOPERATE WITH ALL UTILITY COMPANIES IN
MAINTAINING THEIR SERVICE AND / OR RELOCATION OF LINES.
THE CONTRACTOR SHALL CONTACT GOPHER STATE ONE CALL AT 651-454-0002 AT
LEAST 48 HOURS IN ADVANCE FOR THE LOCATIONS OF ALL UNDERGROUND WIRES,
CABLES, CONDUITS, PIPES, MANHOLES, VALVES OR OTHER BURIED STRUCTURES BEFORE
DIGGING. THE CONTRACTOR SHALL REPAIR OR REPLACE THE ABOVE WHEN DAMAGED
DURING CONSTRUCTION AT NO COST TO THE OWNER.
SCALE IN FEET
0 20 40
UTILITY PLAN GENERAL NOTES
1. ALL SANITARY SEWER, STORM SEWER AND WATERMAIN UTILITIES SHALL BE FURNISHED AND INSTALLED PER THE REQUIREMENTS OF THE SPECIFICATIONS,
THE CITY AND THE STANDARD UTILITIES SPECIFICATION OF THE CITY ENGINEERS ASSOCIATION OF MINNESOTA (CEAM), 1999 EDITION. ALL HDPE
CONNECTIONS TO CONCRETE MANHOLES SHALL BE CONNECTED WITH AN INTERNAL RUBBER GASKET OR BY USING ADS WATERSTOP GASKET. ALL
SANITARY SEWER MAIN LINE SHALL BE SDR 35. ALL SANITARY SEWER SERVICES SHALL BE SDR 26.
2. SEE SHEET C8-1 AND THE CONTRACT SPECIFICATIONS FOR SPECIFIC UTILITY DETAILS AND UTILITY SERVICE DETAILS.
3. ALL UTILITY PIPE BEDDING SHALL BE COMPACTED SAND OR FINE GRANULAR MATERIAL PER THE REQUIREMENTS OF THE CITY. ALL COMPACTION SHALL BE
PERFORMED PER THE REQUIREMENTS OF THE CEAM SPECIFICATION.
4. ALL CONNECTIONS TO EXISTING UTILITIES SHALL BE PERFORMED PER THE REQUIREMENTS OF THE CITY. THE CITY DEPARTMENT OF ENGINEERING AND
BUILDING INSPECTIONS DEPARTMENT AND THE CONSTRUCTION ENGINEER MUST BE NOTIFIED AT LEAST 48 HOURS PRIOR TO ANY WORK WITHIN THE
PUBLIC RIGHT OF WAY, OR WORK IMPACTING PUBLIC UTILITIES.
5. ALL SANITARY SEWER AND WATER SERVICES SHALL TERMINATE AT THE PROPERTY LINE UNLESS OTHERWISE NOTED.
6. THE CONTRACTOR SHALL NOTIFY GOPHER STATE ONE CALL AT 651-454-0002 AT LEAST 48 HOURS PRIOR TO PERFORMING ANY EXCAVATION OR
UNDERGROUND WORK.
7. THE CONTRACTOR SHALL FIELD ADJUST WATERMAIN TO AVOID CONFLICTS WITH SANITARY SEWER, STORM SEWER, AND SERVICES AS REQUIRED.
INSULATION OF WATER AND SANITARY SEWER LINES SHALL BE PROVIDED WHERE 7.5 FEET MINIMUM DEPTH CAN NOT BE ATTAINED.
8. ALL STREET REPAIRS AND PATCHING SHALL BE PERFORMED PER THE REQUIREMENTS OF THE CITY. ALL TRAFFIC CONTROL SHALL BE PROVIDED BY THE
CONTRACTOR AND SHALL BE ESTABLISHED PER THE REQUIREMENTS OF THE MINNESOTA MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (MUTCD) AND
THE CITY. THIS SHALL INCLUDE ALL SIGNAGE, BARRICADES, FLASHERS AND FLAGGERS AS NEEDED. ALL PUBLIC STREETS SHALL BE OPEN TO TRAFFIC AT ALL
TIMES. NO ROAD CLOSURES SHALL BE PERMITTED WITHOUT THE EXPRESSED AUTHORITY OF OF THE CITY.
9. ALL NEW WATERMAIN MUST HAVE A MINIMUM OF 7.5 FEET OF COVER.
10. ADJUST ALL EXISTING STRUCTURES, BOTH PUBLIC AND PRIVATE TO THE PROPOSED GRADES WHERE DISTURBED AND COMPLY WITH ALL REQUIREMENTS OF
THE UTILITY OWNERS. STRUCTURES BEING RESET TO PAVED AREAS MUST MEET OWNERS REQUIREMENTS FOR TRAFFIC LOADING.
11. PROPOSED PIPE MATERIALS:
STORM SEWER HDPE 12" " DIAMETER.
STORM SEWER PVC SCH 40 8" DIAMETER
EXIBIT H
LOUCKS
W:\2016\16427\CADD DATA\LANDSCAPE\_dwg Sheet Files\L1-1Plotted: 01 /16 / 2017 12:3 PM7200 Hemlock Lane, Suite 300
Maple Grove, MN 55369
763.424.5505
www.loucksinc.com
PLANNING
CIVIL ENGINEERING
LAND SURVEYING
LANDSCAPE ARCHITECTURE
ENVIRONMENTAL
SUBMITTAL/REVISIONS
PROFESSIONAL SIGNATURE
QUALITY CONTROL
CADD files prepared by the Consultant for this project are
instruments of the Consultant professional services for use solely
with respect to this project. These CADD files shall not be used
on other projects, for additions to this project, or for completion
of this project by others without written approval by the
Consultant. With the Consultant's approval, others may be
permitted to obtain copies of the CADD drawing files for
information and reference only. All intentional or unintentional
revisions, additions, or deletions to these CADD files shall be
made at the full risk of that party making such revisions, additions
or deletions and that party shall hold harmless and indemnify the
Consultant from any & all responsibilities, claims, and liabilities.
CADD QUALIFICATION
CELEBRATION
CHURCH
ADDITION
LAKEVILLE, MN
CELEBRATION
CHURCH
16655 KENYON AVE
LAKEVILLE, MN 55044
C1-1 EXISTING CONDITIONS
C1-2 DEMOLITION PLAN
C2-1 SITE PLAN
C3-1 GRADING PLAN
C3-2 SWPPP
C3-2 SWPPP NOTES
C4-1 UTILITY PLAN
C8-1 DETAILS
L1-1 LANDSCAPE PLAN
11/16/2016 Check Set
LANDSCAPE
PLAN
L1-1
SCALE IN FEET
0 20 40
GENERAL NOTES
CONTRACTOR SHALL VISIT SITE PRIOR TO SUBMITTING BID. HE SHALL INSPECT SITE AND BECOME FAMILIAR WITH EXISTING
CONDITIONS RELATING TO THE NATURE AND SCOPE OF WORK.
VERIFY LAYOUT AND ANY DIMENSIONS SHOWN AND BRING TO THE ATTENTION OF THE LANDSCAPE ARCHITECT ANY
DISCREPANCIES WHICH MAY COMPROMISE THE DESIGN AND/OR INTENT OF THE PROJECT'S LAYOUT.
ASSURE COMPLIANCE WITH ALL APPLICABLE CODES AND REGULATIONS GOVERNING THE WORK OR MATERIALS SUPPLIED.
CONTRACTOR SHALL PROTECT ALL EXISTING ROADS, CURBS/GUTTERS, TRAILS, TREES, LAWNS AND SITE ELEMENTS DURING
PLANTING OPERATIONS. ANY DAMAGE TO SAME SHALL BE REPAIRED AT NO COST TO THE OWNER.
CONTRACTOR SHALL VERIFY ALIGNMENT AND LOCATION OF ALL UNDERGROUND AND ABOVE GRADE UTILITIES AND
PROVIDE THE NECESSARY PROTECTION FOR SAME BEFORE CONSTRUCTION / MATERIAL INSTALLATION BEGINS (MINIMUM 10'
- 0" CLEARANCE).
ALL UNDERGROUND UTILITIES SHALL BE LAID SO THAT TRENCHES DO NOT CUT THROUGH ROOT SYSTEMS OF ANY
EXISTING TREES TO REMAIN.
EXISTING CONTOURS, TRAILS, VEGETATION, CURB/GUTTER AND OTHER EXISTING ELEMENTS BASED UPON INFORMATION
SUPPLIED TO LANDSCAPE ARCHITECT BY OTHERS. CONTRACTOR SHALL VERIFY ANY AND ALL DISCREPANCIES PRIOR TO
CONSTRUCTION AND NOTIFY LANDSCAPE ARCHITECT OF SAME.
THE ALIGNMENT AND GRADES OF THE PROPOSED WALKS, TRAILS AND/OR ROADWAYS ARE SUBJECT TO FIELD ADJUSTMENT
REQUIRED TO CONFORM TO LOCALIZED TOPOGRAPHIC CONDITIONS AND TO MINIMIZE TREE REMOVAL AND GRADING.
ANY CHANGE IN ALIGNMENT MUST BE APPROVED BY LANDSCAPE ARCHITECT.
WARNING:
THE CONTRACTOR SHALL BE RESPONSIBLE FOR CALLING FOR LOCATIONS OF ALL
EXISTING UTILITIES. THEY SHALL COOPERATE WITH ALL UTILITY COMPANIES IN
MAINTAINING THEIR SERVICE AND / OR RELOCATION OF LINES.
THE CONTRACTOR SHALL CONTACT GOPHER STATE ONE CALL AT 651-454-0002 AT
LEAST 48 HOURS IN ADVANCE FOR THE LOCATIONS OF ALL UNDERGROUND WIRES,
CABLES, CONDUITS, PIPES, MANHOLES, VALVES OR OTHER BURIED STRUCTURES BEFORE
DIGGING. THE CONTRACTOR SHALL REPAIR OR REPLACE THE ABOVE WHEN DAMAGED
DURING CONSTRUCTION AT NO COST TO THE OWNER.
Review Date
SHEET INDEX
License No.
Date
I hereby certify that this plan, specification or
report was prepared by me or under my direct
supervision and that I am a duly Licensed
Landscape Architect under the laws of the State of
Minnesota.
Douglas D. Loken - LA
45591
Project Lead
Drawn By
Checked By
Loucks Project No.16427
JAS
DDL
DDL
01/16/17
-
EXHIBT I
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017CODE DATALOWER LEVELAINTERIOR WALL & CEILING FINISHES PROPOSED BUILDING ADDITIONBUILDING CODE INFORMATION FIRE RESISTANCE RATINGSGENERAL NOTES.MINIMUM REQUIRED PLUMBING FIXTURES- PROPOSED BUILDINGLOWER LEVELEXISTING BUILDING CODE INFORMATION PROPOSED BUILDING MODIFICATIONS TO EXISTING BLDG308.5.2 Child care facilityException:BUILDING DIAGRAMBUILDING STATISTICSSQ. FT.UPPER LEVEL ADDITION LOWER LEVEL ADDITION9,1759,268TOTAL18,4432017-01-10LOWER LEVEL PEDESTRIAN CANOPY372EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 244 OCC x .15" = 36.6"WIDTH PROVIDED = 2 DOOR x 36" = 72"EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 422 OCC x .15" = 63.3"WIDTH PROVIDED = 2 DOOR x 36" = 72"EXITEXITEXITEXIT WIDTH CALCULATIONSWIDTH REQUIRED = 132 OCC x .15" = 19.8"WIDTH PROVIDED = 2 DOOR x 36" = 72"EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 288 OCC x .15" = 43.2"WIDTH PROVIDED = 4 DOOR x 36" = 144"125200111300272282814728224224147132200712883716130200244535232323126272122150EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 150 OCC x .15" = 22.5"WIDTH PROVIDED = 1 DOOR x 36" = 36"EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 130 OCC x .15" = 19.5"WIDTH PROVIDED = 1 DOOR x 36" = 36"EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 200 OCC x .15" = 30"WIDTH PROVIDED = 1 DOOR x 36" = 36"EXHIBIT J
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017CODE DATAUPPER LEVELUPPER LEVEL ABUILDING STATISTICSSQ. FT.UPPER LEVEL ADDITION LOWER LEVEL ADDITION9,1759,268TOTAL18,4432017-01-10LOWER LEVEL PEDESTRIAN CANOPY372BANQUET HALL LAYOUT2CLASSROOM LAYOUT3ADA CLEARANCES1111274150565550EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 274 OCC x .15" = 41.1"WIDTH PROVIDED = 2 DOOR x 36" = 72"EXIT WIDTH CALCULATIONSWIDTH REQUIRED = 274 OCC x .15" = 41.1"WIDTH PROVIDED = 2 DOOR x 36" = 72"274274
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017LOWER LEVELLOWER LEVEL ABUILDING STATISTICSSQ. FT.UPPER LEVEL ADDITION LOWER LEVEL ADDITION9,1759,268TOTAL18,4432017-01-10LOWER LEVEL PEDESTRIAN CANOPY372
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017UPPER LEVEL AUPPER LEVELBUILDING STATISTICSSQ. FT.UPPER LEVEL ADDITION LOWER LEVEL ADDITION9,1759,268TOTAL18,4432017-01-10LOWER LEVEL PEDESTRIAN CANOPY372FUTURE OFFICE ENTRYB
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017ROOF PLANROOF PLANA12345678910MCU-1RTU-1RTU-2RTU-3RTU-6RTU-6RTU-7ROOF & OVERFLOW DRAIN DTLSANCTUARY ROOFTOP CURB DETAILMEMBRANE DETAILMEMBRANE FLASHINGROOF ACCESS LADDERCOPING CAPCOPING CAPCOPING CAPCOPING CAPROOF DETAIL
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017ELEVATIONSEXTERIOREAST ELEVATIONAELEVATIONBELEVATIONCEXTERIOR FINISH KEYCMU MASONRY PREFINISHED METAL/ALUMGLAZING SYSTEMEIFSEXHIBIT K
ISSUE DATES:REVISIONS:NO.DATE:CLIENT REVIEW07-17-16JOB NO:16655 KENYON AVE, LAKEVILLE, MN 55044
PASTOR DERRICK ROSS
AN ADDITION TO:CLIENT REVIEW10-28-16CLIENT REVIEW12-15-16CLIENT REVIEW01-11-201675% REVIEW DRAWINGS 01-31-2017SECTIONSBUILDINGSECTIONCSECTION / ELEVATIONASECTION / ELEVATIONBEXTERIOR FINISH KEYCMU MASONRY PREFINISHED METAL/ALUMGLAZING SYSTEMEIFSELEVATIOND
EXHIBIT L
City of Lakeville
Public Works – Engineering Division
Memorandum
To: Frank Dempsey, Associate Planner
From: Matt Decur, Project Engineer
McKenzie L. Cafferty, Environmental Resources Manager
John Hennen, Parks and Recreation Director
Copy: Zach Johnson, City Engineer
Jerilyn Erickson, Finance Director
Gene Abbott, Building Official
Date: February 22, 2017
Subject: Celebration Church Building Addition – Lot 1, Block 1, Celebration 2nd Addition
• Planned Unit Development Amendment Review
• Site Plan Review
• Sediment, Erosion Control, and Restoration Plan Review
BACKGROUND
Celebration Church has submitted an application for an amendment to the Planned Unit
Development approved in 2001 to add a two story addition to the existing church building on
Lot 1, Block 1, Celebration 2nd Addition. The property is located west of and adjacent to
Kenyon Avenue, south of 162nd Street (CSAH 46). The parcel is zoned PUD, Planned Unit
Development.
The proposed site plan application will be completed by:
Applicant: Celebration Church
Engineer/Architect: Loucks
SSIITTEE CCOONNDDIITTIIOONNSS
Lot 1, Block 1, Celebration 2nd Addition currently contains a church building and parking lot
occupied by Celebration Church. The property generally drains from south to north and from
east to west. Existing utility services connect the building to utilities within Kenyon Avenue.
Street lights are located along Kenyon Avenue adjacent to site, and there is private interior
lighting within the parking lot.
CCEELLEEBBRRAATTIIOONN CCHHUURRCCHH AADDDDIITTIIOONN –– LLOOTT 11,, BBLLOOCCKK 11,, CCEELLEEBBRRAATTIIOONN 22NNDD AADDDDIITTIIOONN SSIITTEE PPLLAANN
FFEEBBRRUUAARRYY 2222,, 22001177
PPAAGGEE 22 OOFF 44
EEAASSEEMMEENNTTSS
The subject parcel contains existing drainage and utility easements, per the plat of Celebration
2nd Addition. These easements will remain and will not be impacted with the proposed site
plan.
SSIITTEE PPLLAANN RREEVVIIEEWW
Celebration Church proposes to construct a two story, 18,443 square foot addition, a 744
square foot accessory building and make modifications to the surrounding parking lots. The
addition will connect to existing church building and will contain daycare classrooms and a
banquet hall. Private storm sewer will be extended around the proposed building addition.
Private sidewalk on the site will be extended to connect the proposed addition to the
surrounding parking lot. Existing full access driveways on Kenyon Avenue will remain.
PPUUBBLLIICC SSTTRREEEETTSS AANNDD AACCCCEESSSS
Kenyon Avenue
The subject parcel is located west of and adjacent to Kenyon Avenue, a major collector roadway
as identified in the City’s Comprehensive Transportation Plan. Currently, Kenyon Avenue is
constructed as a 44-foot wide three-lane urban roadway with a shared center left turn lane
adjacent to the church site. An 8-foot wide sidewalk is located along the west side of Kenyon
Avenue south of Celebration Church’s north driveway. An 8-foot wide trail is located along the
east side of Kenyon Avenue north of Celebration Church’s south driveway.
Kenyon Avenue adjacent to the parent parcel was reconstructed in 2001 to a three lane
roadway with City Project No. 00-21/Dakota County Project No. 05-35. Right of way was
dedicated with the Celebration 2nd Addition plat.
CCOONNSSTTRRUUCCTTIIOONN AACCCCEESSSS
Construction traffic access and egress for site grading, utility and building construction shall be
restricted to the existing entrances off of Kenyon Avenue.
PPAARRKKSS,, TTRRAAIILLSS AANNDD SSIIDDEEWWAALLKKSS
The park dedication fee has been collected on the subject parcel with the Celebration plat.
There is no public trail or sidewalk construction as a part of this application.
UUTTIILLIITTIIEESS
SSAANNIITTAARRYY SSEEWWEERR
The subject parcel is located within OL-51200 of the Orchard Lake sanitary sewer district as
identified in the City’s Comprehensive Sanitary Sewer Plan. Wastewater will be conveyed via
existing trunk sanitary sewer to the MCES Farmington Interceptor and continue to the Empire
Wastewater Treatment Facility. The downstream facilities have sufficient capacity to serve the
proposed building addition.
An existing public sanitary sewer extends through the site. A sanitary sewer service is
extended from this main to serve the existing building. Service for the building addition will be
from within the existing building.
CCEELLEEBBRRAATTIIOONN CCHHUURRCCHH AADDDDIITTIIOONN –– LLOOTT 11,, BBLLOOCCKK 11,, CCEELLEEBBRRAATTIIOONN 22NNDD AADDDDIITTIIOONN SSIITTEE PPLLAANN
FFEEBBRRUUAARRYY 2222,, 22001177
PPAAGGEE 33 OOFF 44
The Sanitary Sewer Availability Charge was paid for the parent parcel.
WWAATTEERRMMAAIINN
Existing 16-inch public watermain extends through the subject parcel north of the existing
building. A 6-inch private watermain service is extended to the existing building. Service for
the building addition will be provided from within the existing building.
DDRRAAIINNAAGGEE AANNDD GGRRAADDIINNGG
The subject parcel is located within subdistrict CL-12 of the Crystal Lake Stormwater District,
as identified in the City’s Water Resources Management Plan.
The subject parcel was previously graded and improved with Celebration 2nd Addition. The site
drains to the north, eventually to Lee Lake. Parking lot and roof runoff is conveyed via a private
storm sewer system to public storm sewer, which outlets to an existing regional stormwater
basin.
The proposed site adds under an acre of impervious surface which is under the threshold of the
permitting requirements of the MPCA Construction General Permit with respect to the water
quality volume. The proposed stormwater management plan consists of two existing publicly
owned and maintained stormwater basins which drain through Farmington to the Vermillion
River.
The final grading plan must indicate any proposed borrow areas in which the building footings
will be placed on fill material. The grading specifications must indicate that all embankments
meet FHA/HUD 79G specifications. A final certificate of occupancy shall not be issued until an
as-built certified grading plan has been submitted and approved by the City Engineer.
The proposed site plan and improvements contain more than one acre of site disturbance. A
National Pollution Discharge Elimination System General Stormwater Permit for construction
activity is required from the Minnesota Pollution Control Agency.
SSTTOORRMM SSEEWWEERR
No public storm sewer is proposed to be constructed in conjunction with the site plan
improvements. A private storm sewer system will be installed to convey the discharge from the
roof of the new building to the existing private storm sewer within the site. Runoff eventually
drains to the public storm sewer within Kenyon Avenue and to a public stormwater basin north
of the site.
The Trunk Storm Sewer Area Charge has been collected on the subject parcel and will not be
required with the site plan improvements.
WWEETTLLAANNDDSS
There are no wetlands on Lot 1, Block 1, Celebration 2nd Addition.
CCEELLEEBBRRAATTIIOONN CCHHUURRCCHH AADDDDIITTIIOONN –– LLOOTT 11,, BBLLOOCCKK 11,, CCEELLEEBBRRAATTIIOONN 22NNDD AADDDDIITTIIOONN SSIITTEE PPLLAANN
FFEEBBRRUUAARRYY 2222,, 22001177
PPAAGGEE 44 OOFF 44
TTRREEEE PPRREESSEERRVVAATTIIOONN
There are several trees on Lot 1, Block 1, Celebration 2nd Addition. Several trees will be
removed and replaced with construction of the building addition. Any other trees damaged or
removed due to utility or site construction must be replaced by the developer.
EERROOSSIIOONN CCOONNTTRROOLL
The Developer is responsible for obtaining a MPCA Construction Permit for the site as well as
developing and maintaining the SWPPP throughout construction phase. The permit requires
that all erosion and sediment BMPs be clearly outlined in a site’s SWPPP. Changes made
throughout construction should be documented in the SWPPP.
Additional erosion control measures may be required during construction as deemed
necessary by City staff or the Dakota County Soil and Water District. Any additional measures
required shall be installed and maintained by the Developer.
RREECCOOMMMMEENNDDAATTIIOONN
Engineering recommends approval of the site plan, sediment, erosion control, and restoration
plan for the Celebration Church building addition, subject to the requirements and stipulations
within this report.
1. The Applicant shall submit the final construction drawings in an electronic format. The
electronic format shall be in either .dwg (AutoCAD) or .dxf format.