HomeMy WebLinkAboutItem 06.m
Date: Item No.
FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
BERRES RIDGE 1ST ADDITION
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
streets and utilities installed with Berres Ridge 1st Addition.
Overview
Berres Ridge Development Company, LLC requests final acceptance of the public street and
utility improvements installed with the development of Berres Ridge 1st Addition. The prime
contractor responsible for the public improvement work was Friedges Contracting Company,
LLC.
The public utilities, curb and gutter, and bituminous base-course pavement were constructed in
2015. The bituminous wear-course pavement was constructed in 2016. The public street and
utility improvements were tested and inspected by WSB and Associates and the City’s Public
Works Department.
Primary Issues to Consider
• The public street and utility improvements installed with the development of Berres
Ridge 1st Addition were completed consistent with the City’s construction standard
specifications and the administrative requirements for final acceptance.
Supporting Information
• None
Financial Impact: $ Budgeted: Y☐ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer
July 17, 2017
0 N/A