APPROVE PLANS AND SPECIFICATIONS AND SET A BID DATE FOR
SOUTH CREEK HYDRODYNAMIC SEPARATOR
Proposed Action Staff recommends adoption of the following motion: Move to approve a resolution approving plans and specifications and setting a bid date for the South Creek Hydrodynamic Separator, City Project 17-06.
Overview City Project 17-06 includes the installation of a hydrodynamic separator at a location approximately ¼ mile southeast of the Holyoke Avenue/210th Street intersection. The proposed storm water management structure is designed to remove sediment and pollutants from storm water before it enters South Creek. The City and Vermillion River Watershed Joint Powers Organization are partnering on this water quality improvement project. The estimated construction cost is $216,000. Construction is anticipated to begin in November 2017 with substantial completion by December 2017. Restoration will be completed in Spring, 2018. A copy of the plans and specifications are available for review in the Engineering Division.
Primary Issues to Consider
• The anticipated funding source is the Trunk Storm Sewer Fund. Additional funding will be provided by the Vermillion River Watershed Joint Powers Organization as established by an existing Joint Powers Agreement, and a Clean Water Fund grant from the Minnesota Board of Water and Soil Resources. The City’s estimated net cost for the project is $55,000.
Supporting Information
• Resolution
Financial Impact: $ Budgeted: Y☒ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Access to a Multitude of Natural Amenities and Recreational Opportunities
Notes: Additional funding provided by Vermillion River Watershed Joint Powers Organization
Report Completed by: McKenzie Cafferty, Environmental Resources Manager
55,000
September 5, 2017
Trunk Storm Sewer Fund
Joint Powers Agreement (Contract No. C0028877)
CITY OF LAKEVILLE
RESOLUTION NO. 17-
RESOLUTION APPROVING PLANS AND SPECIFICATIONS AND SETTING A BID
DATE FOR THE SOUTH CREEK HYDRODYNAMIC SEPARATOR PROJECT
WHEREAS, Wenck Associates prepared plans and specifications for the South Creek Hydrodynamic Separator project (City Project 17-06).
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Lakeville, Minnesota: That the plans and specifications for City Project 17-06 are hereby approved by the City Council of the City of Lakeville, Minnesota;
BE IT FURTHER RESOLVED, that bids will be advertised as required and opened at 10:30 a.m. on Monday, September 25, 2017 at City Hall, 20195 Holyoke Avenue, Lakeville, Minnesota.
ADOPTED by the Lakeville City Council this 5th day of September 2017.
______________________________ Douglas P. Anderson, Mayor _________________________________ Charlene Friedges, City Clerk