AGREEMENT WITH BLACKSTONE CONTRACTORS, LLC FOR
LAKE MARION SHORELINE RESTORATION
Proposed Action
Staff recommends adoption of the following motion: Move to approve Agreement with Blackstone
Contractors, LLC. for Lake Marion Shoreline Restoration.
Overview
The Lake Marion Shoreline Restoration project, City Project 17-20, includes reconstructing and
stabilizing a section of Lake Marion shoreline that is experiencing erosion. The design
incorporates the installation of large retaining wall blocks and a flagstone pathway to support
recreational fishing activities.
The City received two quotes for the Lake Marion Shoreline Restoration project. The quotes
ranged from a low quote of $30,665 submitted by Blackstone Contractors, LLC to a high quote of
$35,961. Three contractors declined to provide a quote. The Engineer’s Estimate was $30,835.
The attached Agreement provides the scope of work, cost and schedule for completing the project.
Primary Issues to Consider
• Why is this project necessary? The project will stabilize eroded Lake Marion shoreline and
improve water quality of surface water draining to the lake.
• Construction is anticipated to begin in Fall, 2017 and substantially complete by the end of
this year.
Supporting Information
• Agreement
Financial Impact: $ Budgeted: Y☒ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Notes:
Report Completed by: Mac Cafferty, Environmental Resources Manager
September 18, 2017
30,665 Utility Fund – Env. Res.
1
194133v1
FORM OF AGREEMENT
BETWEEN CITY OF LAKEVILLE AND CONTRACTOR
FOR NON-BID CONSTRUCTION CONTRACT
THIS AGREEMENT made this _____ day of _____________, 2017, by and
between the CITY OF LAKEVILLE, a Minnesota municipal corporation (“Owner” or
“City”) and BLACKSTONE CONTRACTORS, LLC, a Minnesota limited liability
company (“Contractor”). Owner and Contractor, in consideration of the mutual
covenants set forth herein, agree as follows:
1. CONTRACT DOCUMENTS. The following documents shall be referred to as
the “Contract Documents”, all of which shall be taken together as a whole as the contract
between the parties as if they were set verbatim and in full herein:
A. This Agreement.
B. Standard General Conditions of the Construction Contract, EJCDC C-700,
2013 Edition.
C. Drawings (City of Lakeville Lake Marion Fishing Access Project),
prepared by Wenk Associates, date 08/2017.
D. MnDOT Standard Specifications for Construction, 2016 Edition.
E. City of Lakeville Utility and Street Construction Standard Specifications,
May, 2014.
F. Contractor’s Quote.
In the event of a conflict among the provisions of the Contract Documents, the order in which
they are listed above shall control in resolving any such conflicts. Contract Document “A” has
the first priority and Contract Document “F” has the last priority.
2. OBLIGATIONS OF THE CONTRACTOR. The Contractor shall provide the
goods, services, and perform the work in accordance with the Contract Documents and Drawings
(City of Lakeville Lake Marion Fishing Access Project) prepared by Wenk Associates, dated
08/2017). The Contractor shall refer to the Drawings for construction access location. Access for
the work shall be as shown on the plans. Contractor shall not begin any work until the City has
received the signed contract and has reviewed and approved the insurance certificates and has
given the Contractor a written notice to proceed.
3. CONTRACT PRICE. Owner shall pay Contractor for completion of the Work,
in accordance with the Contractor’s quote.
4. PAYMENT PROCEDURES.
A. Contractor shall submit Applications for Payment. Applications for
Payment will be processed by the City Engineer.
2
194133v1
B. Progress Payments; Retainage. Owner shall make 95% progress payments
on account of the Contract Price on the basis of Contractor’s Applications
for Payment during performance of the Work.
C. Payments to Subcontractors.
(1) Prompt Payment to Subcontractors. Pursuant to Minn. Stat.
§ 471.25, Subd. 4a, the Contractor must pay any subcontractor
within ten (10) days of the Contractor’s receipt of payment from
the City for undisputed services provided by the subcontractor.
The Contractor must pay interest of 1 ½ percent per month or any
part of a month to the subcontractor on any undisputed amount not
paid on time to the subcontractor. The minimum monthly interest
penalty payment for an unpaid balance of $100.00 or more is
$10.00. For an unpaid balance of less than $100.00, the Contractor
shall pay the actual penalty due to the subcontractor.
(2) Form IC-134 (attached) required from general contractor. Minn.
Stat. § 290.92 requires that the City of Lakeville obtain a
Withholding Affidavit for Contractors, Form IC-134, before
making final payments to Contractors. This form needs to be
submitted by the Contractor to the Minnesota Department of
Revenue for approval.
The form is used to receive certification from the state that the
vendor has complied with the requirement to withhold and remit
state withholding taxes for employee salaries paid.
D. Final Payment. Upon final completion of the Work, Owner shall pay the
remainder of the Contract Price as recommended by the City Engineer.
Final completion of the Work, including final restoration and
establishment of permanent cover (“Restoration”), occurs upon
completion of all work under the Contract Documents as determined by
the City Engineer.
5. COMPLETION DATE. All Work, except restoration, must be completed by
December 31, 2017 and final completion by June 15, 2018.
6. CONTRACTOR’S REPRESENTATIONS.
A. Contractor has examined and carefully studied the Contract Documents
and other related data identified in the Contract Documents.
B. Contractor has visited the Site and become familiar with and is satisfied as
to the general, local, and Site conditions that may affect cost, progress, and
performance of the Work.
3
194133v1
C. Contractor is familiar with and is satisfied as to all federal, state, and local
laws and regulations that may affect cost, progress, and performance of
the Work.
D. Contractor has carefully studied all: (1) reports of explorations and tests
of subsurface conditions at or contiguous to the Site and all drawings of
physical conditions in or relating to existing surface or subsurface
structures at or contiguous to the Site (except Underground Facilities)
which have been identified in the General Conditions and (2) reports and
drawings of a Hazardous Environmental Condition, if any, at the site.
E. Contractor has obtained and carefully studied (or assumes responsibility
for doing so) all additional or supplementary examinations, investigations,
explorations, tests, studies, and data concerning conditions (surface,
subsurface, and Underground Facilities) at or contiguous to the Site which
may affect cost, progress, or performance of the Work or which relate to
any aspect of the means, methods, techniques, sequences, and procedures
of construction to be employed by Contractor, including any specific
means, methods, techniques, sequences, and procedures of construction
expressly required by the Bidding Documents, and safety precautions and
programs incident thereto.
F. Contractor does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance of
the Work at the Contract Price, within the Contract Times, and in
accordance with the other terms and conditions of the Contract
Documents.
G. Contractor is aware of the general nature of work to be performed by
Owner and others at the Site that relates to the Work as indicated in the
Contract Documents.
H. Contractor has correlated the information known to Contractor,
information and observations obtained from visits to the Site, reports and
drawings identified in the Contract Documents, and all additional
examinations, investigations, explorations, tests, studies, and data with the
Contract Documents.
I. The Contract Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for performance and furnishing
of the Work.
J. Subcontracts:
4
194133v1
(1) Unless otherwise specified in the Contract Documents, the
Contractor shall, upon receipt of the executed Contract Documents,
submit in writing to the Owner the names of the Subcontractors
proposed for the work. Subcontractors may not be changed except
at the request or with the consent of the Owner.
(2) The Contractor is responsible to the Owner for the acts and
omissions of the Contractor's subcontractors, and of their direct
and indirect employees, to the same extent as the Contractor is
responsible for the acts and omissions of the Contractor's
employees.
(3) The Contract Documents shall not be construed as creating any
contractual relation between the Owner and any subcontractor.
(4) The Contractor shall bind every subcontractor by the terms of the
Contract Documents.
7. WORKER’S COMPENSATION. The Contractor shall obtain and maintain for
the duration of this Contract, statutory Worker’s Compensation Insurance and Employer’s
Liability Insurance as required under the laws of the State of Minnesota.
8. COMPREHENSIVE GENERAL LIABILITY. Contractor shall obtain the
following minimum insurance coverage and maintain it at all times throughout the life of the
Contract, with the City included as an additional name insured on a primary and noncontributory
basis. The Contractor shall furnish the City a certificate of insurance satisfactory to the City
evidencing the required coverage:
Bodily Injury: $2,000,000 each occurrence
$2,000,000 aggregate products and
completed operations
Property Damage: $2,000,000 each occurrence
$2,000,000 aggregate
Contractual Liability (identifying the contract):
Bodily Injury: $2,000,000 each occurrence
Property Damage: $2,000,000 each occurrence
$2,000,000 aggregate
Comprehensive Automobile Liability (owned, non-owned, hired):
Bodily Injury: $2,000,000 each occurrence
$2,000,000 each accident
5
194133v1
Property Damage: $2,000,000 each occurrence
9. WARRANTY. The Contractor warrants all work to be performed by it pursuant
to this Agreement against poor material and faulty workmanship. The warranty period is one
year or until 80% of the permanent cover is established as determined by the City Engineer
whichever first occurs. The Contractor shall post a warranty bond in the amount of twenty-five
percent (25%) of final certified project costs to secure the warranty. The bond must be furnished
the City prior to final payment to the Contractor.
The Contractor shall be held responsible for any and all defects in workmanship and
materials which may develop in any part of the contracted service, and upon proper notification
by the City shall immediately replace, without cost to the City, any such faulty work.
10. INDEMNITY. The Contractor agrees to indemnify and hold the City harmless
from any claim made by third parties as a result of the services performed by it. In addition, the
Contractor shall reimburse the City for any cost of reasonable attorney’s fees it may incur as a
result of any such claims.
11. PERFORMANCE AND PAYMENT BONDS. Performance and Payment
Bonds are not required.
12. MISCELLANEOUS.
A. Terms used in this Agreement have the meanings stated in the General
Conditions.
B. Owner and Contractor each binds itself, its partners, successors, assigns
and legal representatives to the other party hereto, its partners, successors,
assigns and legal representatives in respect to all covenants, agreements,
and obligations contained in the Contract Documents.
C. Any provision or part of the Contract Documents held to be void or
unenforceable under any law or regulation shall be deemed stricken, and
all remaining provisions shall continue to be valid and binding upon
Owner and Contractor, who agree that the Contract Documents shall be
reformed to replace such stricken provision or part thereof with a valid and
enforceable provision that comes as close as possible to expressing the
intention of the stricken provisions.
D. Data Practices/Records.
(1) All data created, collected, received, maintained or disseminated
for any purpose in the course of this Contract is governed by the
Minnesota Government Data Practices Act, Minn. Stat. Ch. 13, any
6
194133v1
other applicable state statute, or any state rules adopted to
implement the act, as well as federal regulations on data privacy.
(2) All books, records, documents and accounting procedures and
practices to the Contractor and its subcontractors, if any, relative to
this Contract are subject to examination by the City.
E. Patented devices, materials and processes. If the Contract requires, or the
Contractor desires, the use of any design, devise, material or process
covered by letters, patent or copyright, trademark or trade name, the
Contractor shall provide for such use by suitable legal agreement with the
patentee or owner and a copy of said agreement shall be filed with the
Owner. If no such agreement is made or filed as noted, the Contractor
shall indemnify and hold harmless the Owner from any and all claims for
infringement by reason of the use of any such patented designed, device,
material or process, or any trademark or trade name or copyright in
connection with the Project agreed to be performed under the Contract,
and shall indemnify and defend the Owner for any costs, liability,
expenses and attorney's fees that result from any such infringement.
F. Assignment. Neither party may assign, sublet, or transfer any interest or
obligation in this Contract without the prior written consent of the other
party, and then only upon such terms and conditions as both parties may
agree to and set forth in writing.
G. Waiver. In the particular event that either party shall at any time or times
waive any breach of this Contract by the other, such waiver shall not
constitute a waiver of any other or any succeeding breach of this Contract
by either party, whether of the same or any other covenant, condition or
obligation.
H. Governing Law/Venue. The laws of the State of Minnesota govern the
interpretation of this Contract. In the event of litigation, the exclusive
venue shall be in the District Court of the State of Minnesota for Dakota
County.
I. Severability. If any provision, term or condition of this Contract is found
to be or become unenforceable or invalid, it shall not affect the remaining
provisions, terms and conditions of this Contract, unless such invalid or
unenforceable provision, term or condition renders this Contract
impossible to perform. Such remaining terms and conditions of the
Contract shall continue in full force and effect and shall continue to
operate as the parties’ entire contract.
J. Entire Agreement. This Contract represents the entire agreement of the
parties and is a final, complete and all inclusive statement of the terms
7
194133v1
thereof, and supersedes and terminates any prior agreement(s),
understandings or written or verbal representations made between the
parties with respect thereto.
K. Permits and Licenses; Rights-of-Way and Easements. The Contractor
shall give all notices necessary and incidental to the construction and
completion of the Project. The City will obtain all necessary rights-of-
way and easements. The Contractor shall not be entitled to any additional
compensation for any construction delay resulting from the City’s not
timely obtaining rights-of-way or easements.
L. If the work is delayed or the sequencing of work is altered because of the
action or inaction of the Owner, the Contractor shall be allowed a time
extension to complete the work but shall not be entitled to any other
compensation.
OWNER: CONTRACTOR:
CITY OF LAKEVILLE
BY: ____________________________ BY: ____________________________
Douglas P. Anderson, Mayor Its: _______________________
AND ___________________________
Charlene Friedges, City Clerk
Vice President