Date: December 18, 2017 Item No.
FINAL ACCEPTANCE AND FINAL PAYMENT TO
FITZGERALD EXCAVATING & TRUCKING, INC. FOR
205TH STREET CHANNEL STABILIZATION IMPROVEMENTS
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
improvements and final payment to Fitzgerald Excavating & Trucking, Inc. for 205th Street
Channel Stabilization Improvements, City Project 16-15.
Overview
Fitzgerald Excavating & Trucking, Inc. requests final acceptance of public improvements and
final payment in the amount of $182,245.00 for City Project 16-15.
The original contract amount was $197,860.00. No change orders were processed for this
project. The final construction cost is $182,245.00.
Primary Issues to Consider
• The public improvements were tested and inspected by the City’s Public Works
Department and Wenck Associates, Inc. All work was completed consistent with the
Contract and the administrative requirements for final payment.
Supporting Information
• Letter of Recommendation Dated November 22, 2017, from Wenck Associates, Inc.
Financial Impact: $182,245 Budgeted: Y☒ N☐ Source: Utility Fund – Env. Resources
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Notes: Additional funding provided by Vermillion River Watershed Joint Powers Organization
Report Completed by: McKenzie Cafferty, Environmental Resources Manager