Date: January 16, 2018 Item No.
ACCEPTANCE OF IMPROVEMENTS, FINAL PAYMENT TO RYAN CONTRACTING
COMPANY, AND RESOLUTION AUTHORIZING FUNDING FOR CITY
IMPROVEMENT PROJECT 15-02
Proposed Action
Staff recommends adoption of the following motion: Move to accept improvements, approve
final payment to Ryan Contracting Company, and authorize funding for City Improvement
Project 15-02.
Overview
Ryan Contracting Company is requesting final acceptance and final payment of Final Pay
Voucher No. 17 in the amount of $178,360.01 for the 2015 Street Reconstruction Project
Contract 2, City Improvement Project 15-02. Attached is a summary of costs and change orders
associated with the project. The original contract amount was $8,771,384.25. Two change orders
and additional costs, based on exceedances to unit priced quantities for commodities used during
construction, bring the final amount to $8,918,000.61.
While this is the final acceptance and payment, Ryan Contracting Company is disputing Class 5
aggregate quantities and may bring a claim forward in the future. However, the City is
contractually obligated to closeout this project since the work is complete and work through a
dispute resolution based on the terms of the contact. Overall, costs remain within the project
contingency amount.
All necessary paperwork, including lien waivers, the IC-134’s and Consent of Surety to Final
Payment have been submitted. Staff recommends acceptance and approval of the final pay
estimate.
Primary Issues to Consider
• Was all work satisfactorily completed? All work was satisfactorily completed and the
contractor has met the administrative requirements for final payment.
Supporting Information
• A copy of the final pay voucher, cost summary, and funding information is attached.
Financial Impact: $178,360.01 Budgeted: Yes Source: 429 Bonds & Spec. Assess.
Related Documents (CIP, ERP, etc.): CIP
Community Values: Good Value for Public Services
Completed By: Chris Petree, Public Works Director
Funding Information
The acceptance of improvements and final payment to S.M. Hentges & Sons, Inc., City
Improvement Project 15-02 Contract 1, was approved by Council on September 18, 2017.
Both phases one and two of the 15-02 improvement project are under budget, including the
estimated contingency amounts. The phase one project funding included a transfer from the
General Fund for $300,000 that was intended to offset the costs of the project. As bond proceeds
were sufficient to cover project costs, this $300,000 remains unspent at the end of the project and,
per bond counsel, can be reauthorized by City Council for another purpose. Staff recommends
that this $300,000 remain in the Construction Improvement Fund to pay for the claim noted
above or help offset the costs of other improvement construction projects (i.e. 2018 street
reconstruction projection). Per bond requirements, any excess bond proceeds (after the
reduction for the $300,000 General Fund transfer) must be transferred to the Debt Service Fund
for payments on the related bonds.
CITY OF LAKEVILLE
RESOLUTION NO:
RESOLUTION AUTHORIZING FUNDING FOR CITY IMPROVEMENT PROJECT
15-02 (2015 STREET RECONSTRUCTION)
WHEREAS, the City of Lakeville has recommended the final acceptance of City
Improvement project 15-02; and
WHEREAS, the actual costs for the project were less than anticipated; and
WHEREAS, the City Council had authorized a transfer of $500,000 from the General
Fund for the purposes of funding the 2015 street reconstruction project phase I ($300,000) and
phase 2 ($200,000) per resolution #15-63.
NOW, THEREFORE, BE IT RESOLVED, the final estimated costs of the 15-02 project
(including phases one and two) are $21,729,225. Anticipated funding sources are listed below.
Staff is hereby authorized to amend the 2017 budgets and make the appropriate transfers
between funds, effective December 31, 2017, with respect to the funding sources up to 10% above
the estimated costs.
ADOPTED by the Lakeville City Council this 16th day of January 2018
______________________________
Douglas P. Anderson, Mayor
_________________________________
Charlene Friedges, City Clerk
Anticipated Funding Source Amount
Bond proceeds (2015 and 2016)18,676,161$
Tax levy 49,986
Special Assessments (prepayments)389,040
Transfers (General Fund)500,000
Other (interest)34,785
Water Operating Fund 2,589,621
Sewer Operating Fund 160,024
Transfer of unspent bond proceeds to related Debt Service
Fund (370,392)
Transfer to Construction Improvement Fund (300,000)
21,729,225$
Contract Amounts
Original Contract $8,771,384.25
Contract Changes $19,284.88
Revised Contract $8,790,669.13
Funds Encumbered
Original $8,771,384.25
Additional N/A
Total $8,771,384.25
Work Certified To Date
Base Bid Items $8,898,715.73
Backsheet $0.00
Change Order $19,284.88
Supplemental Agreement $0.00
Work Order $0.00
Material On Hand $0.00
Total $8,918,000.61
Amount Paid This Final Pay Voucher $178,360.01
02109-82 $0.00 $8,918,000.61 $0.00 $8,739,640.60 $178,360.01 $8,918,000.61
Percent Retained: 0%
Work Certified
This Pay Voucher
Work Certified
To Date
Less Amount
Retained
Less Previous
Payments
Amount Paid
This Pay Voucher
Total Amount
Paid To Date
I hereby certify that a Final Examination has been made of the noted Contract, that the Contract has been completed,
that the entire amount of Work Shown in this Final Voucher has been performed and the Total Value of the Work Performed
in accordance with, and pursuant to, the terms of the Contract is as shown in this Final Voucher.
Approved By
County/City/Project Engineer
Finance Director
Approved By Ryan Contracting Company
Contractor
Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project 02109-82 - LKVL - 2015 Street Reconstruction Contract 2
Final Pay Voucher No. 17
Contractor: Ryan Contracting Company
26480 France Avenue
Elko New Market, MN 55020
Contract No.
Vendor No. .
For Period: 3/1/2017 - 11/28/2017
Warrant # __________ Date ___________
Page 1
Date
1 04/23/2015 04/30/2015 $304,513.17 $15,225.66 $289,287.51
2 05/01/2015 05/31/2015 $1,108,807.12 $55,440.35 $1,053,366.77
3 06/01/2015 06/30/2015 $983,355.01 $49,167.76 $934,187.25
4 07/01/2015 08/01/2015 $960,094.68 $48,004.73 $912,089.95
5 08/02/2015 08/31/2015 $444,246.34 $22,212.32 $422,034.02
6 09/01/2015 09/30/2015 $243,570.00 $12,178.50 $231,391.50
7 10/01/2015 10/31/2015 $89,347.38 $4,467.37 $84,880.01
8 11/01/2015 03/31/2016 $70,480.00 $3,524.00 $66,956.00
9 04/01/2016 04/30/2016 $494,907.71 $24,745.38 $470,162.33
10 05/01/2016 05/31/2016 $971,163.08 $48,558.15 $922,604.93
11 06/01/2016 06/30/2016 $1,123,717.90 $56,185.90 $1,067,532.00
12 07/01/2016 07/31/2016 $1,032,626.95 $51,631.35 $980,995.60
13 08/01/2016 08/31/2016 $440,513.61 $22,025.68 $418,487.93
14 09/01/2016 09/30/2016 $369,789.00 $18,489.45 $351,299.55
15 10/01/2016 10/31/2016 $238,003.53 ($254,353.89) $492,357.42
16 11/01/2016 02/28/2017 $42,865.13 $857.30 $42,007.83
17 03/01/2017 11/28/2017 $0.00 ($178,360.01) $178,360.01
Totals: $8,918,000.61 $0.00 $8,918,000.61
02109-82 Payment Summary
No. From Date To Date
Work Certified
Per Pay Voucher
Amount Retained
Per Pay Voucher
Amount Paid
Per Pay Voucher
UNF 8,918,000.60 0.00 8,739,640.59 178,360.01 8,918,000.60
Totals: $8,918,000.60 $0.00 $8,739,640.59 $178,360.01 $8,918,000.60
02109-82 Funding Category Report
Funding
Category
No.
Work
Certified
To Date
Less
Amount
Retained
Less
Previous
Payments
Amount Paid
This
Pay Voucher
Total
Amount Paid
To Date
UNF Unfunded 178,360.01 8,790,669.13 8,771,384.25 8,918,000.60
Totals: $178,360.01 $8,790,669.13 $8,771,384.25 $8,918,000.60
02109-82 Funding Source Report
Accounting
No.
Funding
Source
Amount Paid
This
Pay Voucher
Revised
Contract
Amount
Funds
Encumbered
To Date
Paid To
Contractor
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 2
SCHEDULE A - SURFACE IMPROVEMENTS
1 2021.501 MOBILIZATION LS $440,000.00 1 0 $0.00 1 $440,000.00
2 2101.502 CLEARING TREE $300.00 62 0 $0.00 119 $35,700.00
3 2101.507 GRUBBING TREE $200.00 62 0 $0.00 118 $23,600.00
4 2101.511
CLEARING AND
GRUBBING SHRUB EACH $100.00 38 0 $0.00 7 $700.00
5 2101.603 ROOT CUTTING L F $10.00 170 0 $0.00 80 $800.00
6 2104.501
REMOVE
CONCRETE CURB
AND GUTTER
L F $3.00 40690 0 $0.00 40755.32 $122,265.96
7 2104.503
REMOVE
BITUMINOUS
WALK
S F $2.00 14375 0 $0.00 13272 $26,544.00
8 2104.503
REMOVE
CONCRETE WALK S F $2.00 38480 0 $0.00 33060 $66,120.00
9 2104.505
REMOVE
CONCRETE
DRIVEWAY
PAVEMENT
S Y $6.00 2395 0 $0.00 2554.3 $15,325.80
10 2104.505
REMOVE
BITUMINOUS
DRIVEWAY
PAVEMENT
S Y $4.00 8335 0 $0.00 9265.3 $37,061.20
11 2104.505
REMOVE
BITUMINOUS
PAVEMENT
S Y $10.00 200 0 $0.00 0 $0.00
12 2104.509 REMOVE SIGN EACH $100.00 56 0 $0.00 56 $5,600.00
13 2104.509
REMOVE MAIL
BOX SUPPORT EACH $25.00 20 0 $0.00 45 $1,125.00
14 2104.509
REMOVE MAIL
BOX EACH $50.00 10 0 $0.00 4 $200.00
15 2104.511
SAWING
CONCRETE
PAVEMENT (FULL
DEPTH)
L F $5.00 1670 0 $0.00 1594.4 $7,972.00
16 2104.513
SAWING
BITUMINOUS
PAVEMENT (FULL
DEPTH)
L F $3.00 6470 0 $0.00 6238.3 $18,714.90
17 2104.601
SALVAGE AND
REINSTALL
LANDSCAPE
STRUCTURE
LS $10,000.00 1 0 $0.00 1 $10,000.00
18 2104.602
SALVAGE AND
REINSTALL MAIL
BOX
EACH $150.00 191 0 $0.00 181 $27,150.00
19 2104.618
SALVAGE &
REINSTALL STONE
PAVER DRIVEWAY
S F $10.00 350 0 $0.00 339.5 $3,395.00
20 2105.501
COMMON
EXCAVATION (P)C Y $19.00 26030 0 $0.00 26030 $494,570.00
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 3
21 2105.507
SUBGRADE
EXCAVATION (EV)C Y $3.00 8470 0 $0.00 92.5 $277.50
22 2105.515
EXPLORATORY
EXCAVATION HOUR $100.00 20 0 $0.00 20.5 $2,050.00
23 2105.522
SELECT
GRANULAR
BORROW (LV)
CU
YD $19.00 31025 0 $0.00 42572.18 $808,871.42
24 2105.533
SALVAGE
GRANULAR
BORROW (EV)
C Y $0.01 23450 0 $0.00 25906.58 $259.07
25 2105.533
SALVAGED
GRANULAR
BORROW PLACED
(LV)
C Y $4.00 25750 0 $0.00 20771.58 $83,086.32
26 2105.604
GEOTEXTILE
FABRIC TYPE V S Y $1.20 95990 0 $0.00 95990 $115,188.00
27 2105.607
1 1/2" CLEAR
ROCK C Y $40.00 160 0 $0.00 196.4 $7,856.00
28 2105.607 3" CLEAR ROCK C Y $40.00 650 0 $0.00 1362.76 $54,510.40
29 2112.501
SUBGRADE
PREPARATION RDST $300.00 210 0 $0.00 210 $63,000.00
30 2123.610
STREET
SWEEPER (WITH
PICKUP BROOM)
HOUR $130.00 60 0 $0.00 96.25 $12,512.50
31 2130.501 WATER MGAL $35.00 550 0 $0.00 115.284 $4,034.94
32 2131.502
CALCIUM
CHLORIDE
SOLUTION
GAL $1.00 1500 0 $0.00 0 $0.00
33 2211.501
AGGREGATE
BASE CLASS 5
(LV)
C Y $20.00 1950 0 $0.00 0 $0.00
34 2232.501
MILL BITUMINOUS
STEP JOINT (1.5")L F $2.00 1010 0 $0.00 1034 $2,068.00
35 2331.604
BITUMINOUS
PAVEMENT
RECLAMATION
S Y $5.50 75560 0 $0.00 75560 $415,580.00
36 2357.502
(2015)
BITUMINOUS
MATERIAL FOR
TACK COAT
GAL $2.00 2095 0 $0.00 2485 $4,970.00
37 2360.501
(2015) TYPE SP
12.5 WEARING
COURSE MIX (2,C)
TON $40.00 3890 0 $0.00 3294.52 $131,780.80
38 2360.502
(2015) TYPE SP
12.5 NON WEAR
COURSE MIX (2,C)
TON $40.00 4820 0 $0.00 4448.77 $177,950.80
39 2360.503
(2015) TYPE SP 9.5
WEARING
COURSE MIX (2,B)
3.0" THICK
S Y $22.00 5725 0 $0.00 5351.82 $117,740.04
(2016)
BITUMINOUS
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 4
40 2357.502
MATERIAL FOR
TACK COAT GAL $2.00 1880 0 $0.00 2665 $5,330.00
41 2360.501
(2016) TYPE SP
12.5 WEARING
COURSE MIX (2,C)
TON $40.00 3410 0 $0.00 4388.56 $175,542.40
42 2360.502
(2016) TYPE SP
12.5 NON WEAR
COURSE MIX (2,C)
TON $40.00 4325 0 $0.00 4604.38 $184,175.20
43 2360.503
(2016) TYPE SP 9.5
WEARING
COURSE MIX (2,B)
3.0" THICK
S Y $22.00 4210 0 $0.00 4998.7546 $109,972.60
44 2360.601
CONCRETE CURB
PROTECTION L F $1.40 18400 0 $0.00 7910.1 $11,074.14
45 2360.601
TEMPORARY
BITUMINOUS
PATCH
S Y $35.00 560 0 $0.00 40.8 $1,428.00
46 2505.601
UTILITY
COORDINATION LS $1.00 1 0 $0.00 1 $1.00
47 2506.522
ADJUST FRAME &
RING CASTING
(SANITARY)
EACH $500.00 95 0 $0.00 95 $47,500.00
48 2506.522
ADJUST FRAME &
RING CASTING
(STORM)
EACH $300.00 49 0 $0.00 57 $17,100.00
49 2506.522
ADJUST FRAME &
RING CASTING
(MANHOLE)
EACH $300.00 19 0 $0.00 16 $4,800.00
50 2521.501
5" CONCRETE
WALK S F $5.00 50770 0 $0.00 41400 $207,000.00
51 2521.501
6" CONCRETE
WALK S F $6.00 4200 0 $0.00 2540.6 $15,243.60
52 2531.501
CONCRETE CURB
& GUTTER DESIGN
D412
L F $12.00 40750 0 $0.00 36835.1 $442,021.20
53 2531.501
CONCRETE CURB
& GUTTER DESIGN
B618
L F $14.00 815 0 $0.00 4437.7 $62,127.80
54 2531.507
7" CONCRETE
DRIVEWAY
PAVEMENT
S Y $70.00 1420 0 $0.00 5486.8 $384,076.00
55 2531.507
7" CONCRETE
DRIVEWAY
PAVEMENT
(SPECIAL)
S Y $18.00 1110 0 $0.00 116.6111 $2,099.00
56 2531.601
CONCRETE CURB
& GUTTER REPAIR L F $18.00 4165 0 $0.00 126 $2,268.00
57 2531.618
TRUNCATED
DOMES S F $40.00 372 0 $0.00 444 $17,760.00
58 2531.618
ADA COMPLIANCE
SUPERVISOR LS $1.00 1 0 $0.00 1 $1.00
59 2540.602 MAIL BOX EACH $200.00 10 0 $0.00 7 $1,400.00
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 5
60 2540.602
MAIL BOX
SUPPORT EACH $50.00 20 0 $0.00 45 $2,250.00
61 2540.602
MAIL BOX
(TEMPORARY)EACH $50.00 371 0 $0.00 371 $18,550.00
62 2557.602
REPAIR DOG
FENCE EACH $300.00 30 0 $0.00 2 $600.00
63 2563.601
TRAFFIC
CONTROL LS $30,000.00 1 0 $0.00 1.0000004333 $30,000.01
64 2565.602
NMC LOOP
DETECTOR EACH $3,000.00 2 0 $0.00 2 $6,000.00
65 2571.501
CONIFEROUS
TREE 8' HT B&B TREE $550.00 24 0 $0.00 13 $7,150.00
66 2571.502
DECIDUOUS TREE
2.5" CAL B&B TREE $550.00 24 0 $0.00 51.5 $28,325.00
67 2573.540
FILTER LOG TYPE
WOOD FIBER
BIOROLL
L F $5.00 720 0 $0.00 720 $3,600.00
68 2573.550
EROSION
CONTROL
SUPERVISOR
LS $1.00 1 0 $0.00 1 $1.00
69 2573.602
TEMPORARY
ROCK
CONSTRUCTION
ENTRANCE
EACH $300.00 12 0 $0.00 0 $0.00
70 2574.525
BOULEVARD
TOPSOIL
BORROW
C Y $35.00 170 0 $0.00 0 $0.00
71 2575.501 SEEDING ACRE $4,000.00 0.4 0 $0.00 0 $0.00
72 2575.505
SODDING, TYPE
LAWN (INCL.
TOPSOIL & FERT.)
S Y $5.00 69450 0 $0.00 57800 $289,000.00
73 2575.535
WATER (TURF
ESTABLISHMENT)MGAL $20.00 3850 0 $0.00 0 $0.00
74 2582.501
PAVEMENT
MESSAGE (RIGHT-
THRU ARROW)
PAINT
EACH $75.00 4 0 $0.00 2 $150.00
75 2582.501
PAVEMENT
MESSAGE (RIGHT
ARROW) PAINT
EACH $50.00 4 0 $0.00 2 $100.00
76 2582.501
PAVEMENT
MESSAGE (LEFT-
THRU ARROW)
PAINT
EACH $75.00 2 0 $0.00 1 $75.00
77 2582.501
PAVEMENT
MESSAGE (LEFT
ARROW) PAINT
EACH $50.00 4 0 $0.00 2 $100.00
78 2582.501
PAVEMENT
MESSAGE (THRU
ARROW) PAINT
EACH $50.00 4 0 $0.00 7.0312 $351.56
79 2582.502
4" SOLID LINE
WHITE-PAINT L F $0.25 5080 0 $0.00 3732.1 $933.03
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 6
80 2582.502
4" DOUBLE SOLID
LINE YELLOW-
PAINT
L F $0.30 2910 0 $0.00 1418 $425.40
81 2582.502
12" SOLID LINE
YELLOW-PAINT L F $3.00 100 0 $0.00 29.5 $88.50
Totals For Section SCHEDULE A - SURFACE IMPROVEMENTS: $0.00 $5,417,199.09
SCHEDULE B - WATER MAIN IMPROVEMENTS
82 2021.501 MOBILIZATION LS $1.00 1 0 $0.00 1 $1.00
83 2104.501
REMOVE WATER
SERVICE PIPE L F $1.00 11820 0 $0.00 13725 $13,725.00
84 2104.501
REMOVE WATER
MAIN L F $1.00 21460 0 $0.00 20898.49 $20,898.49
85 2104.509
REMOVE GATE
VALVE AND BOX EACH $300.00 55 0 $0.00 51 $15,300.00
86 2104.509
REMOVE CURB
STOP & BOX EACH $100.00 371 0 $0.00 368 $36,800.00
87 2104.509
REMOVE
HYDRANT EACH $300.00 56 0 $0.00 54 $16,200.00
88 2104.603
ABANDON WATER
MAIN L F $8.00 70 0 $0.00 0 $0.00
89 2105.601 DEWATERING LS $1.00 1 0 $0.00 1 $1.00
90 2451.601
GRANULAR
FOUNDATION
AND/OR BEDDING
(LV)
C Y $0.01 1175 0 $0.00 0 $0.00
91 2504.601
TEMPORARY
WATER SERVICE LS $140,000.00 1 0 $0.00 1 $140,000.00
92 2504.602
CONNECT TO
EXISTING WATER
MAIN
EACH $1,500.00 16 0 $0.00 16 $24,000.00
93 2504.602
CONNECT TO
EXISTING WATER
SERVICE
EACH $500.00 371 0 $0.00 367 $183,500.00
94 2504.602 HYDRANT EACH $4,000.00 56 0 $0.00 56 $224,000.00
95 2504.602
1" CORPORATION
STOP EACH $250.00 371 0 $0.00 367 $91,750.00
96 2504.602
2" CORPORATION
STOP EACH $1,000.00 1 0 $0.00 1 $1,000.00
97 2504.602
6" GATE VALVE
AND BOX EACH $1,600.00 56 0 $0.00 56 $89,600.00
98 2504.602
8" GATE VALVE
AND BOX EACH $1,900.00 56 0 $0.00 45 $85,500.00
99 2504.602
12" GATE VALVE
AND BOX EACH $3,000.00 5 0 $0.00 5 $15,000.00
100 2504.602
1" CURB STOP
AND BOX EACH $350.00 371 0 $0.00 367 $128,450.00
101 2504.602
2" CURB STOP &
BOX EACH $850.00 1 0 $0.00 1 $850.00
102 2504.602
IRRIGATION
SYSTEM REPAIR EACH $400.00 50 0 $0.00 102 $40,800.00
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 7
103 2504.603
1" TYPE K
COPPER PIPE L F $18.00 12870 0 $0.00 13728 $247,104.00
104 2504.603
2" TYPE K
COPPER PIPE L F $50.00 50 0 $0.00 25 $1,250.00
105 2504.603
6" WATERMAIN
DUCTILE IRON CL
52 W/POLYWRAP
L F $42.00 850 0 $0.00 767.3338 $32,228.02
106 2504.603
8" WATER MAIN -
PVC C900 L F $32.00 20170 0 $0.00 20134.94 $644,318.08
107 2504.603
12" WATER MAIN -
PVC C900 L F $50.00 880 0 $0.00 922.72 $46,136.00
108 2504.604
4" POLYSTYRENE
INSULATION S Y $25.00 250 0 $0.00 19 $475.00
109 2504.608
DUCTILE IRON
FITTINGS LB $6.00 11770 0 $0.00 9197 $55,182.00
Totals For Section SCHEDULE B - WATER MAIN IMPROVEMENTS: $0.00 $2,154,068.59
SCHEDULE C - SANITARY SEWER IMPROVEMENTS
110 2021.501 MOBILIZATION LS $1.00 1 0 $0.00 1 $1.00
111 2104.501
REMOVE
SANITARY SEWER
SERVICE PIPE
L F $20.00 140 0 $0.00 110 $2,200.00
112 2105.602
EXCAVATE TO
LOCATE SERVICE EACH $500.00 4 0 $0.00 2 $1,000.00
113 2503.511
4" PVC PIPE
SEWER L F $35.00 140 0 $0.00 0 $0.00
114 2503.602
CONNECT TO
EXISTING
SANITARY SEWER
SERVICE
EACH $550.00 4 0 $0.00 0 $0.00
115 2503.602 8"X4" PVC WYE EACH $750.00 4 0 $0.00 0 $0.00
116 2503.603
TELEVISE
SANITARY SEWER
SERVICE
EACH $160.00 392 0 $0.00 372 $59,520.00
117 2506.602 CHIMNEY SEAL EACH $300.00 95 0 $0.00 95 $28,500.00
Totals For Section SCHEDULE C - SANITARY SEWER
IMPROVEMENTS:$0.00 $91,221.00
SCHEDULE D - STORM SEWER IMPROVEMENTS
118 2021.501 MOBILIZATION LS $1.00 1 0 $0.00 1 $1.00
119 2104.501
REMOVE PVC
DRAIN TILE L F $1.00 11260 0 $0.00 6125 $6,125.00
120 2104.501
REMOVE SEWER
PIPE (STORM)L F $10.00 3070 0 $0.00 2796.4 $27,964.00
121 2104.509
REMOVE
DRAINAGE
STRUCTURE
EACH $300.00 65 0 $0.00 54 $16,200.00
122 2104.509
REMOVE CASTING
ASSEMBLY EACH $100.00 43 0 $0.00 50 $5,000.00
123 2104.523
SALVAGE
CASTING EACH $100.00 30 0 $0.00 35 $3,500.00
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 8
124 2502.521 4" TP PIPE DRAIN L F $13.00 4670 0 $0.00 8705.1 $113,166.30
125 2502.541
6" PERF TP PIPE
DRAIN L F $14.00 42300 0 $0.00 41500.75 $581,010.50
126 2502.541
8" PERF TP PIPE
DRAIN L F $19.00 90 0 $0.00 0 $0.00
127 2502.602
4" TP PIPE DRAIN
CLEAN OUT EACH $200.00 369 0 $0.00 372 $74,400.00
128 2502.602
6" TP PIPE DRAIN
CLEAN OUT EACH $250.00 86 0 $0.00 197 $49,250.00
129 2503.541
12" RC PIPE
SEWER DES 3006
CL V
L F $40.00 575 0 $0.00 441.2 $17,648.00
130 2503.541
15" RC PIPE
SEWER DES 3006
CL V
L F $41.00 1250 0 $0.00 1045.25 $42,855.25
131 2503.541
18" RC PIPE
SEWER DES 3006
CL III
L F $43.00 330 0 $0.00 270 $11,610.00
132 2503.541
21" RC PIPE
SEWER DES 3006
CL III
L F $50.00 595 0 $0.00 566 $28,300.00
133 2503.541
24" RC PIPE
SEWER DES 3006
CL III
L F $52.00 243 0 $0.00 225 $11,700.00
134 2503.541
27" RC PIPE
SEWER DES 3006
CL III
L F $59.00 260 0 $0.00 231 $13,629.00
135 2503.541
30" RC PIPE
SEWER DES 3006
CL III
L F $68.00 10 0 $0.00 0 $0.00
136 2503.541
36" RC PIPE
SEWER DES 3006
CL III
L F $80.00 220 0 $0.00 194 $15,520.00
137 2503.541
42" RC PIPE
SEWER DES 3006
CL III
L F $120.00 40 0 $0.00 36 $4,320.00
138 2503.603
CLEAN PIPE
SEWER L F $4.00 3530 0 $0.00 2716 $10,864.00
139 2503.603
CONNECT TO
EXISTING SUMP
DRAIN
EACH $300.00 20 0 $0.00 66 $19,800.00
140 2506.501
CONST DRAINAGE
STRUCTURE DES
48-4020
L F $250.00 150 0 $0.00 163.626 $40,906.50
141 2506.501
CONST DRAINAGE
STRUCTURE DES
60-4020
L F $350.00 20 0 $0.00 25.99 $9,096.50
142 2506.501
CONST DRAINAGE
STRUCTURE DES
72-4020
L F $400.00 7 0 $0.00 10.06 $4,024.00
143 2506.501
CONST DRAINAGE
STRUCTURE DES L F $500.00 14 0 $0.00 13.93 $6,965.00
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 9
84-4020
144 2506.502
CONSTRUCT
DRAINAGE
STRUCTURE
DESIGN SPECIAL
(2'X3')
EACH $2,000.00 31 0 $0.00 30.83 $61,660.00
145 2506.602
CONNECT TO
EXISTING
STRUCTURE
EACH $1,000.00 10 0 $0.00 9 $9,000.00
146 2506.602
CONNECT TO
EXISTING STORM
SEWER SPECIAL
EACH $2,500.00 1 0 $0.00 1 $2,500.00
147 2506.602
RECONSTRUCT
DRAINAGE
STRUCTURE
EACH $1,000.00 15 0 $0.00 1 $1,000.00
148 2506.602
CASTING
ASSEMBLY
(CATCHBASIN)
EACH $600.00 36 0 $0.00 54 $32,400.00
149 2506.602
CASTING
ASSEMBLY
(STORM
MANHOLE)
EACH $500.00 3 0 $0.00 1 $500.00
150 2506.602
SALVAGE AND
REINSTALL
STORM PIPE
L F $30.00 1480 0 $0.00 47.1 $1,413.00
151 2573.530
STORM DRAIN
INLET
PROTECTION
EACH $100.00 139 0 $0.00 139 $13,900.00
Totals For Section SCHEDULE D - STORM SEWER
IMPROVEMENTS:$0.00 $1,236,228.05
SCHEDULE E - CONTRACT MANAGEMENT
152 2016.601 DEDUCTION LS ($1.00) 1 0 $0.00 1 ($1.00)
Totals For Section SCHEDULE E - CONTRACT MANAGEMENT: $0.00 ($1.00)
Change Order 1
153 98254
WORK REQUEST
1: PRIVATE
DRAINTILE
INSTALL
LS $9,812.00 1 0 $0.00 1 $9,812.00
154 98255
WORK REQUEST
2: REPAIR WATER
LEAK
LS $1,707.34 1 0 $0.00 1 $1,707.34
155 98256
WORK REQUEST
3: ADDITIONAL
DRAINTILE
SERVICE
LS $1,350.00 1 0 $0.00 1 $1,350.00
156 98260
WORK REQUEST
4: 16440 GRIFFON
TRAIL
LS $500.00 1 0 $0.00 1 $500.00
157 98258
WORK REQUEST
5: GRINNELL
AVENUE CBMH
5903
LS $1,177.50 1 0 $0.00 1 $1,177.50
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 10
158 98259
WORK REQUEST
6: GREENBRIAR
PAVING RE-
MOBILIZATION
LS $1,750.00 1 0 $0.00 1 $1,750.00
Totals For Change Order 1: $0.00 $16,296.84
Change Order 2
159 98376
WORK REQUEST
7: ADDL
DRAINTILE
INSTALL FOR
LEAKING VALVE
LS $2,988.04 1 0 $0.00 1 $2,988.04
Totals For Change Order 2: $0.00 $2,988.04
Project Totals: $0.00 $8,918,000.61
02109-82 Project Material Status
Line Item Description Units Unit Price
Contract
Quantity
Quantity
This
Pay
Voucher
Amount
This
Pay
Voucher
Quantity
To Date
Amount
To Date
CO1 Change
Order 8/1/2015 Change Order No. 1 (see change order document for detailed
description)$16,296.84 $16,296.84
CO2 Change
Order 8/31/2015 Change Order No. 2 (see change order document for detailed
description)$2,988.04 $2,988.04
Contract Change Totals: $19,284.88 $19,284.88
02109-82 Contract Changes
No. Type Date Explanation
Estimated
Amount
Amount
Paid
To Date
CITY OF LAKEVILLE
20195 Holyoke Avenue
Lakeville, MN 55044-8339
Project No. 02109-82
Final Pay Voucher No. 17
Page 11