FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
streets and utilities installed with Berres Ridge 2nd Addition and Enclave at St. Frances Woods.
Overview
Berres Ridge Development Co, LLC requests final acceptance of the public street and utility
improvements installed with the development of Berres Ridge 2nd Addition. The prime
contractor responsible for the public improvement work was Friedges Contracting Company.
Enclave at St. Francis Woods, LLC requests final acceptance of the public street and utility
improvements installed with the development of Enclave at St. Frances Woods. The prime
contractor responsible for the public improvement work was Swenke Ims Contracting, LLC.
The public utilities, curb and gutter, and bituminous base-course pavements for these
developments were constructed in 2015 and 2016. The bituminous wear-course pavements for
these developments were constructed in 2017. The public street and utility improvements for the
above-referenced developments were tested and inspected by WSB & Associates and the City’s
Public Works Department.
Primary Issues to Consider
• The public street and utility improvements installed with the above-referenced
developments were completed consistent with the City’s construction standard
specifications and the administrative requirements for final acceptance.
Supporting Information
• None.
Financial Impact: $0 Budgeted: Y☐ N☐ Source: N/A
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer