Date: Item No.
EMPIRE BUILDER INVESTMENTS (PROGRESSIVE RAIL) CONDITIONAL USE PERMIT
Proposed Action
Staff recommends adoption of the following motion: Move to: 1) approve the Empire Builder Investments
(Progressive Rail) conditional use permit and adopt the findings of fact and, 2) the Site Improvement
Performance Agreement and Stormwater Management Agreement.
Overview
Representatives of Empire Builder Investments, Inc. (Progressive Rail) request approval of a conditional use
permit to allow a liquid propane (LP) storage and dispensing facility to be located on property at 21778
Highview Avenue. The proposed LP storage tanks are an allowed use in the I-2, General Industrial District
subject to approval of a conditional use permit. The LP storage would be in conjunction with receiving rail
shipments of the LP, transferring to storage tanks, and final distribution of LP from the subject property to
customers via trucks.
The Planning Commission held a public hearing on January 4, 2018 to consider the conditional use
permit request. The Planning Commission recommended unanimous approval subject to the 15
stipulations listed in the December 29, 2017 planning report. There were no public comments at the
public hearing.
Primary Issues to Consider
Is the proposed outdoor storage and transfer of liquid propane storage tanks compatible with the industrial
use of the property and other nearby industrial properties? The proposed storage and handling of the liquid
propane will meet all setback and fire safety requirements subject to compliance with the stipulations of the
conditional use permit. In addition, Progressive Rail has agreed to address the non-conformities identified by
staff as part of the conditional use permit request.
Supporting Information
• Conditional use permit form
• Findings of fact
• Site Improvement Performance Agreement and Stormwater Management Agreement
• January 4, 2018 draft Planning Commission meeting minutes
• December 29, 2017 planning and engineering reports
Financial Impact: Budgeted: Y☐ N☐ Source:
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Diversified Economic Development
Report Completed by: Frank Dempsey, AICP, Associate Planner
January 16, 2018
None
Zoning Ordinance
1
(Reserved for Dakota County Recording Information)
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
CONDITIONAL USE PERMIT NO. 18-____
1. Permit. Subject to the terms and conditions set forth herein, the City of Lakeville
approves a conditional use permit for Empire Builder Investments, Inc. (Progressive
Rail) to allow liquid propane storage on property in the I-2, General Industrial District
located at 21778 Highview Avenue.
2. Property. The permit is for the following described property in the City of Lakeville,
Dakota County, Minnesota:
Lot 1, Block 1, Empire Builder Investments First Addition
3. Conditions. The conditional use permit is issued subject to the following conditions:
a. All areas of the outdoor storage yard that are driven on, parked on or used for
outdoor storage of products that can be wind-blown or carried by site drainage
into the storm sewer system shall be paved with asphalt bituminous.
b. All required State of Minnesota permits and certifications shall be obtained
and remain in good standing prior to the commencement of liquid propane
delivery to the subject property, transfer to the storage tanks, transloaded to
delivery trucks and transportation of the liquid propane fuel on public roads.
c. Waste products, as defined by the Zoning Ordinance, shall not be stored on
site.
2
d. Compliance with the requirements listed in the Engineering Division
memorandum dated December 29, 2017.
e. A minimum of 50 paved and striped parking spaces shall be available for
parking at all times. All vehicle parking shall occur on designated spaces
paved with bituminous asphalt in accordance with the approved site plan.
f. The outdoor storage area and parking area shall be paved with asphalt
bituminous surfacing no later than June 1, 2018 in accordance with the
approved site plan. A cash or letter of credit security in the amount of $66,000
shall be submitted to guarantee completion of the additional asphalt
bituminous paving.
g. All non-compostable materials such as litter, fine metals, plastics, glass, or
other materials that can be carried by into the storm sewer system shall be
swept and properly disposed of on a regular basis.
h. Permanent or temporary outdoor storage of material shall not occur between
Highview Avenue and the west side of the building.
i. The LP office/control building exterior building materials shall comply with
Zoning Ordinance requirements.
j. All landscaping on site shall be maintained and kept free of dead materials.
The gravel surface area north of the main building and adjacent to the Wausau
Supply property shall be restored with grass and landscaping in accordance
with the landscape plan approved with the 1998 preliminary and final plat.
Any dead landscape materials shall be replaced with like materials in
compliance with Zoning Ordinance requirements.
k. Installation of any lighting shall require an electrical permit and shall be
down-cast style fixtures.
l. A parking deferment agreement shall be approved prior to the issuance of a
building permit for the propane storage facility.
m. LP delivery trucks shall not be stored on site unless located on a bituminous
asphalt paved surface and not within the parking spaces required for the
Progressive Rail building.
3
n. A building permit is required prior to installation of the propane storage
tanks.
o. The Fire Marshal shall approve the liquid propane storage facility prior to
issuance of a building permit.
4. Termination of Permit. The City may revoke the permit following a public
hearing for violation of the terms of the permit.
5. Lapse. If within one year of the issuance of this conditional use permit,
construction of the project has not commenced, this permit shall lapse.
6. Criminal Penalty. Violation of the terms of this conditional use permit is a
criminal misdemeanor.
Date:_______________________
CITY OF LAKEVILLE
BY:________________________
Douglas P. Anderson, Mayor
BY:________________________
Charlene Friedges, City Clerk
The following instrument was acknowledged before me this 16th day of January, 2018 by
Douglas P. Anderson, Mayor and by Charlene Friedges, City Clerk of the City of
Lakeville, a Minnesota municipal corporation, on behalf of the corporation.
__________________________
Notary Public
DRAFTED BY:
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044
1
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
EMPIRE BUILDER INVESTMENTS, INC. CONDITIONAL USE PERMIT
FINDINGS OF FACT AND DECISION
On January 4, 2018 the Lakeville Planning Commission met at it’s regularly scheduled
meeting to consider a conditional use permit for Empire Builder Investments, Inc. to allow
liquid propane storage in the I-2, General Industrial District located at 21778 Highview Avenue.
The Planning Commission conducted a public hearing on the proposed conditional use permit
preceded by published and mailed notice. The applicant was present and the Planning
Commission heard testimony from all interested persons wishing to speak. The City Council
hereby adopts the following:
FINDINGS OF FACT
1. The property is located in Planning District No. 8 of the Comprehensive Plan, which guides the
property for industrial uses.
2. The property is zoned I-2, General Industrial District.
3. The legal description of the property is:
Lot 1, Block 1, Empire Builder Investments First Addition
4. Section 11-4-3E of the City of Lakeville Zoning Ordinance provides that a conditional use
permit may not be issued unless certain criteria are satisfied. The criteria and our findings
regarding them are:
a. The proposed action has been considered in relation to the specific policies and
provisions of and has been found to be consistent with the official City Comprehensive
Plan.
Finding: The proposed liquid propane storage tanks are an allowed use on the industrial
guided and zoned property.
b. The proposed use is or will be compatible with present and future land uses of the area.
Finding: Provided compliance with the conditional use permit, the proposed liquid propane
storage tanks will be compatible with existing and future land uses in the area.
2
c. The proposed use conforms with all performance standards contained in the Zoning
Ordinance.
Finding: Provided compliance with the conditional use permit, the proposed liquid propane
storage tanks will conform with all performance standards contained in the Zoning
Ordinance and the City Code.
d. The proposed use can be accommodated with existing public services and will not
overburden the City’s service capacity.
Finding: The subject property lies within in the current MUSA. The property is served
with City sanitary sewer and water. The use of the property for liquid propane storage
will have no impact on the City’s service capacity provided compliance with the
stipulations of the conditional use permit.
e. Traffic generation by the proposed use is within capabilities of streets serving the
property.
Finding: Traffic generated by the liquid propane storage facility is within the capabilities of
Highview Avenue which serves the property.
5. The planning report dated December 29, 2017 prepared by Associate Planner Frank Dempsey
is incorporated herein.
DECISION
The City Council approves the conditional use permit in the form attached thereto.
DATED: January 16, 2018
LAKEVILLE CITY COUNCIL
BY: _________________________
Douglas P. Anderson, Mayor
BY: _________________________
Charlene Friedges, City Clerk
1
City of Lakeville
Planning Department
Memorandum
To : Planning Commission
From: Frank Dempsey, AICP, Associate Planner
Date: December 29, 2017
Subject: Packet Material for the January 2, 2018 Planning Commission Meeting
Agenda Item: Empire Builder Investments (Progressive Rail) Conditional Use Permit
Action Deadline: January 21, 2018
INTRODUCTION
Representatives of Empire Builder Investments, Incorporated (a/k/a Progressive Rail) have
submitted an application and plans for a conditional use permit to allow liquid propane (LP)
storage tanks and dispensing facility to be located on property at 21778 Highview Avenue. The
proposed LP storage tanks are an allowed use in the I-2, General Industrial District subject to
approval of a conditional use permit. The LP storage would be in conju nction with receiving rail
shipments of the LP, transferring to storage tanks and final distribution of LP from the subject
property to customers via trucks.
EXHIBITS
A. Location and Zoning Map
B. Aerial Photo Map
C. Site Plans (2 Pages)
D. Site/Grading and Utility Plan
E. New Building Elevation and Floor Plans (2 Pages)
2
F. Storage Tank Sample Photo and Layout Sketch (2 Pages)
G. December 4, 2017 Site Inspection Photos (4 Pages)
H. Historical Aerial Photos of outdoor storage areas (3 Pages)
I. 1998 Landscape/Site Plan
STAFF ANALYSIS
Background. The subject property was developed in 1999 by Empire Builder Investments, Inc.
for use as an office, maintenance and storage building and also a transload facility for the rail
company. The property totals 15.9 acres in area. The building totals 115,000 square feet which
includes the 48,000 square foot addition constructed in 2000. The rail transload and outdoor
storage facility includes a variety of products including various raw materials and other products
which are transported to customers via truck for final distribution. Progressive Rail also operates
transload and shipping facilities in Bloomington, Cannon Falls and Randolph.
Zoning. The subject property is zoned I-2, General Industrial District. Section 11-87-7.D of the
Zoning Ordinance allows crude oil, gasoline or other liquid storage tanks by conditional use
permit. Section 11-4-7.E requires that the Planning Commission consider possible effects of the
proposed use with its judgement based upon, but not limited to, the following factors:
1. The proposed action has been considered in relation to the specific policies and provisions
of and has been found to be consistent with the official city comprehensive plan.
The existing property and proposed uses are consistent with the industrial land use
designation of the Comprehensive Plan. Specific land use policies directed by the Zoning
Ordinance are addressed in this planning report with specific conditions included as necessary
to assure compliance with the Zoning Ordinance.
2. The proposed use is or will be compatible with present and future land uses of the area.
The industrial use of the property, as well as the proposed use of LP storage tanks, are allowed
industrial uses are consistent with other industrial uses in the area.
3. The proposed use conforms with all performance standards contained in this code.
The proposed use will conform with all performance standards contained in the Zoning
Ordinance subject to the stipulations recommended in this report to be included in the
conditional use permit.
3
4. The proposed use can be accommodated with existing public services and will not
overburden the city's service capacity.
The proposed use including LP storage tanks on the property can be accommodated with
existing public services including sanitary sewer, water and stormwater facilities and will not
overburden the city’s service capacity.
5. Traffic generation by the proposed use is within capabilities of streets serving the property.
Traffic generated by the introduction of LP storage tanks on the property is within capabilities
of streets serving the property.
Non-Conforming Conditions. Any request for a conditional use permit necessitates the review
of the property for any zoning noncompliance issues so as not to increase the non-conforming
conditions on the property. Staff inspected the property on December 4, 2017 after receiving the
conditional use permit application. Non-conforming conditions that were identified include:
1. Unpaved outdoor storage area (allowed when the site was developed in 1998)
2. Outdoor storage area not swept or otherwise maintained to control materials from
discharging to stormwater basins
3. Unmaintained drainage catch-basins and stormwater basins
4. Vehicles driving and parking on unpaved surfaces outside of designated parking spaces
5. Deferred parking spaces used for the storage of products and materials.
6. Outdoor storage of materials in the front yard of the property (as viewed from previous
inspections and aerial photos)
Action Plan. The applicant proposes to pave a two-way entrance drive along the north side of the
building and pave the drive lanes for ingrees and egrees between the main north entrance and the
LP facility and back to the main access drive along the north side of the building. The applicant
has also committed to improving maintenance of loose materials on the site including general
site clean-up and maintenance of storm water basins.
Site Plan. Progressive Rail proposes to increase the pavement width along the north side of the
building to allow two-way vehicle traffic into and out of the outside storage yard. Asphalt
bituminous paving will also be installed over approximately one acre of the outdoor storage yard
to include the drive aisles for the liquid propane transload vehicles. Paving of the drive lanes in
the outdoor storage area will reduce the non-conforming outdoor storage surfacing requirement
and allow Progressive Rail to sweep and otherwise maintain the outdoor storage yard to help
prevent much of the release of fine materials into the storm basins as well as wind borne dust
from leaving the property.
4
Access and On-Site Circulation. Vehicles will continue to access the site from Highview Avenue.
215th Street (CSAH 70) is located approximately ¼ mile to the north and intersects with Highview
Avenue. The LP trucks will only use the north entrance which requires widening the pavement
surfacing on that side of the building. The site layout provides adequate space to accommodate
truck turning movements throughout the property.
Parking. The office, maintenance and warehouse space of the existing 115,000 square foot
building and proposed 360 square foot (30’x12’) control station building for theLP storage and
transfer station requires 102 parking spaces on site. The Progressive Rail site required 100
parking spaces when the 2000 addition was approved in 2000. A parking deferment was
approved at that time for 50 of the 100 required parking spaces. Staff determined that
approximately 37 of the minimum required 50 parking spaces were available to employees. The
remainder of the spaces on the east side of the site were converted to use for outdoor storage.
This created a shortage of available parking within designated parking spaces. Progressive Rail
proposes to construct and stripe additional spaces for a total of 50 parking spaces on site as part
of this conditional use permit. Approximately 37 spaces will be available in front of the building.
The remaining spaces will be in various locations within the outdoor storage area as shown on
the site plan.
In conjunction with the conditional use permit, a revised parking deferment agreement will be
required. City staff has the authority to administratively approve a parking deferment for up to
50% of the required parking spaces provided the applicant can adequately demonstrate that the
total required number of parking spaces are not necessary for their operations. The applicant
indicates that there will be an estimated 49 employees, of which 34 employees are on site during
the main shift. The proposed parking lot and drive aisles meet the size and dimension
requirements of the Zoning Ordinance.
Staff will draft the parking deferment agreement in conjunction with City Council consideration
of the conditional use permit.
Liquid Propane Storage and Building. The plans propose the installation of two 60,000 gallon
liquid propane storage tanks and the possibility of the installation of four additional tanks for a
total of six on the property. The storage, unloading and loading area will be located
approximately 230 feet east of the existing main building.
Building Exterior. The proposed office/control station building is proposed to be vinyl sided
with an asphalt shingled roof. Vinyl siding is considered a Grade F material. Section 11-17-9.E.
of the Zoning Ordinance requires that industrial buildings use only Grades A-E materials on wall
surfaces that abut a property with an adjacent industrial building with brick, wood, stone or
5
decorative concrete wall surfaces such as the Progressive Rail building and buildings to the north
(Wausau) and to the south. The building exterior material plan shall be amended to include
Grade A-E materials.
Landscaping. The gravel surfaced area located near the northwest corner of the property
adjacent to the Wausau Supply property that has been used for parking shall be surfaced with
grass and landscaping in compliance with the landscape plan approved with the 1998 Empire
Builder Investments, Inc. preliminary and final plat (see Exhibit I). The landscaping approved
with the 1998 project plans had been installed and had died or was removed. All landscaping on
site shall be maintained and kept free of dead materials. Any dead landscape materials shall be
replaced with like materials in compliance with Zoning Ordinance requirements.
Findings of Fact. Findings of Fact are attached for your review and consideration.
RECOMMENDATION
Planning Department staff recommends approval of the conditional use permit for Empire
Builder Investments, Inc. to store liquid propane on the subject property in the I-2 District
located at 21778 Highview Avenue subject to the following stipulations:
1. All areas of the outdoor storage yard that are driven on, parked on or used for outdoor
storage of products that can be wind-blown or carried by site drainage into the storm
sewer system shall be paved with asphalt bituminous.
2. All required State of Minnesota permits and certifications shall be obtained and remain in
good standing prior to the commencement of liquid propane delivery to the subject
property, transfer to the storage tanks, transloaded to delivery trucks and transportation
of the liquid propane fuel on public roads.
3. Waste products, as defined by the Zoning Ordinance, shall not be stored on site.
4. Compliance with the requirements listed in the Engineering Division memorandum
dated December 29, 2017.
5. A minimum of 50 paved and striped parking spaces shall be available for parking at all
times. All vehicle parking shall occur on designated spaces paved with bituminous
asphalt in accordance with the approved site plan.
6
6. The outdoor storage area and parking area shall be paved with asphalt bituminous
surfacing no later than June 1, 2018 in accordance with the approved site plan. A cash or
letter of credit security in the amount of $66,000 shall be submitted to guarantee
completion of the additional asphalt bituminous paving.
7. All non-compostable materials such as litter, fine metals, plastics, glass, or other materials
that can be carried by into the storm sewer system shall be swept and properly disposed of
on a regular basis.
8. Permanent or temporary outdoor storage of material shall not occur between Highview
Avenue and the west side of the building.
9. The LP office/control building exterior building materials shall comply with Zoning
Ordinance requirements.
10. All landscaping on site shall be maintained and kept free of dead materials. The gravel
surface area north of the main building and adjacent to the Wausau Supply property shall
be restored with grass and landscaping in accordance with the landscape plan approved
with the 1998 preliminary and final plat. Any dead landscape materials shall be replaced
with like materials in compliance with Zoning Ordinance requirements.
11. Installation of any lighting shall require an electrical permit and shall be down-cast style
fixtures.
12. A parking deferment agreement shall be approved prior to the issuance of a building
permit for the propane storage facility.
13. LP delivery trucks shall not be stored on site unless located on a bituminous asphalt paved
surface and not within the parking spaces required for the Progressive Rail building.
14. A building permit is required prior to installation of the propane storage tanks.
15. The Fire Marshal shall approve the liquid propane storage facility prior to issuance of a
building permit.
I-1O-R
RM-1
I-2
I-1 I-2 P/OSI-2 I-2
P/OS
PUD RH-1
I-1
21 5TH S T W
214TH ST W
220TH ST WHIGHVIEW AVEHAMBURG AVE213
T
H
S
T
W
215TH ST WHEYWOOD AVEHERON WAY
219T
H
S
T
WHOLYOKE AVEÜ
21778 HIGHVIEW AVENUE
EXHIBIT A
21778 Highview Avenue
Property Information
December 15, 2017
0 875 1,750437.5 ft
0 270 540135 m
1:9,600
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed. This is not a legal document and should not be substituted for a title search,appraisal, survey, or for zoning verification.
EXHIBIT B
NEW BITUMINOUS DRIVE
EXIST BITUMINOUS DRIVE
NEW CONTROL STATION 30' x 12' (BY OWNER)
25'-0" MIN. AWAY FROM CENTERLINE OF DRIVE
EXIST RAIL SPUR
EXIST
DRIVE
HIGH VIEW AVENUEEXIST
DRIVE
92' - 0"500' - 0"92' - 0"
EXIST STORAGE BINS PROPERTY LINE 1,751' +/-
EXIST RAIL SPUR
EXISTING BUILDING
PROPERTY LINE 1,620' +/-PROPERTY LINE 316' +/-P R O P E R T Y L IN E 1 5 6 ' +/-PROPERTY LINE 400' +/-EXIST RAIL SPUR
UPGRADE RAIL TO A DRIVE
OVER TRACK- SHOWN GREY (BY
OWNER)
ARROWS INDICATE DIRECTION
OF TRAFFIC
ARROWS INDICATE
DIRECTION OF TRAFFIC
EXIST SEDIMENT BASIN
SEE CIVIL24' - 0"20' - 0"HYD.
HYD.
HYD.
EXIST RETAINING WALL
EXIST PAVING
FUTURE EXPANSION
TANKS
SECTION OF TRACK TO REMAIN
CLEAR AT ALL TIMES
EXISTING
BUILDING
NEW DUAL LANE - SINGLE TRUCK
LOADING STATION
NEW GUARD RAIL AROUND
SEDIMENT BASIN (BY OWNER)
LOADING PLATFORM &
COMPRESSOR PAD
(BY LP COMPANY)
GUARD RAILS (BY OWNER)
NEW TRUCK SKID (BY
LP COMPANY)
(2) NEW 60,000 GAL.
PROPANE TANKS (BY
LP COMPANY)
170' - 0"
MIN.
20' - 0"
GUARD RAILS
(BY OWNER)
NEW ELECTRICAL SERVICE
TRANSFORMER (BY OWNER)MIN.25' - 0"24' - 0"℄NEW BITUMINOUS DRIVE
STRIPE NEW PARKING
SPACES
EXIST RAIL SPUR
7
16 14
13
25 DEFERRED
PARKING SPACES
6
NEW BITUMINOUS DRIVE (BY OWNER)
19
15 12 NEW SEDIMENT
BASIN - SEE CIVIL
NEW TEMP STORAGE
AREA24' - 0"NEW AUTO PARKING
SB-1 SB-2
SB-3
SB-4
SITE INFORMATION:
TOTAL LOT AREA:
15.95 ACRES
ZONING:
I-2 INDUSTRIAL DISTRICT
BUILDING SETBACKS:
FRONT: 40 FEET MINIMUM AT HIGHVIEW AVE.
SIDE/INTERIOR: 10 FEET MINIMUM
REAR:30 FEET MINIMUM
PARKING SETBACKS:
15 FROM ANY PUBLIC OR PRIVATE ROAD. 5' FROM REAR OR SIDE INTERIOR
PROPERTY LINE
SITE CONSTRAINTS:
MAXIMUM IMPERVIOUS SURFACE LOT COVERAGE = N/A
PROPOSED BUILDING SIZE:
PROPOSED ACCESSORY BUILDING: 339 SF
PARKING REQUIREMENTS:
REQUIRED PARKING STALL SIZE: 90 DEGREES, 9'-0" x 20'-0"
(WITH 2' CURB
OVERHANG ALLOWED, 24'-0" AISLE
PARKING SUMMARY:
EXISTING BUILDING
PARKING REQUIRED = 100
PARKING ON SITE = 50
DEFERRED PARKING = 50
PROPOSED ACCESSORY BUILDING
OFFICE: 339 SF - 10% = 305 SF/200 = 2
TOTAL AMOUNT OF PARKING REQUIRED = 102
AMOUNT OF PARKING SHOWN ON SITE = 77
AMOUNT OF PARKING DEFFERED = 25
NUMBER OF EMPLOYEES = 49
70% OF EMPLOYEES ON SITE DURING FIRST SHIFT = 34
ZONING ORDINANCE USED:
CITY OF LAKEVILLE
CODE OF ORDINANCES -
ON-LINE
DATE: 07-05-2017
Scale
Project number
Date
Drawn by
Checked by
21476 GRENADA AVENUE
LAKEVILLE, MN 55044
PH: 952-469-2171
FAX: 952-469-2173
EMAIL:
office@approdevelopment.com
CONDITIONAL USE
PERMIT SUBMITTAL
11/22/17
As indicated
12/20/2017 2:48:22 PMA1-1
SITE PLAN
17-01-0127
21778 HIGHVIEW AVENUE
LAKEVILLE, MN 55044
CLIENT NO.
17-01-0127
12/12/17
MR
JJC
1" = 60'-0"A1-1
1 SITE PLAN
60'30'0'60'
NORTH
1
1
2
No. Description Date
1 REVISION #1 12/12/17
2 REVISINO #2 12/20/17
2
EXHIBIT C
24' - 0"20' - 0"HYD.
LOADING
PLATFORM
TRUCKER WAITING AREA AND
CONTROL ROOM
30' - 0"
MIN.
20' - 0"
GUARD RAIL 20' - 0"24' - 0"NEW BITUMINOUS DRIVE6' - 0"10' - 0"6' - 0"11' - 0"4' - 0"11' - 0"5' - 0"8' - 0"16' - 0"15' - 0"33' - 0"170' - 0"14' - 6"12' - 0"5' - 0"14' - 0"MIN.25' - 0"12' - 0"12' - 0"6' - 0"12' - 0"
GUARD RAIL
60' - 0 1/4"
13' - 0"
COMPRESSOR
PAD
60K PROPANE
TANK
60K PROPANE
TANK
ENTRANCE
SECTION OF RAIL
ALONG LP TANKS
& GUARD RAIL
TO BE LEVEL
LIGHT POLE LIGHT POLE
TRUCK SKID
LIGHT POLE
ENTRANCE
GUARD RAIL24' - 0"10' - 0"7' - 0"
PRECAST PIER
TRANSFORMER
6' - 0"12' - 0"
DUAL PUMP
PAD℄℄℄℄℄℄NEW BITUMINOUS DRIVE
NEW BITUMINOUS DRIVE
GUARD RAIL
NEW TEMP STORAGE AREA
70' - 0"36' - 0"24' - 0"RADIUS50' - 0"NEW BITUMINOUS PAD
EXIST RAIL SPUR
NOTE:
1. LP LIGHTING SPEC - RAB FXLED125SF HIGH EFFICIENCY LED FLOOD
LIGHT, RAB PS4-11-20WT SQUARE STEEL POLE FOR FLOOD LIGHTS, RAB
BC4 COVERS (BY LP COMPANY)
2. ALL GUARD RAILS IN ACCORDANCE WITH NFPA 58
Scale
Project number
Date
Drawn by
Checked by
21476 GRENADA AVENUE
LAKEVILLE, MN 55044
PH: 952-469-2171
FAX: 952-469-2173
EMAIL:
office@approdevelopment.com
CONDITIONAL USE
PERMIT SUBMITTAL
11/22/17
As indicated
12/20/2017 2:48:22 PMA1-2
SITE PLAN
17-01-0127
21778 HIGHVIEW AVENUE
LAKEVILLE, MN 55044
CLIENT NO.
17-01-0127
12/12/17
MR
JJC
1" = 20'-0"A1-2
1
SITE PLAN - LP TRANSLOAD
AREA
20'10'0'20'
NORTH
1
No. Description Date
1 REVISION #1 12/12/17
SB-1 SB-2
SB-4
SB-3
ARROWS INDICATE
DIRECTION OF TRAFFIC
961.8
959.6
959.6
961.
2
959.9959.1
958.5
958.
9 959.8958.0958.4
959.
0
961.
1
962.4
961.1961.6962.3961.6
962.
9962.0
963.0962.632.0963.0 961.6
960.3
960.
6
960.
1
NE
W
B
I
T
.
NE
W
B
I
T
.20.024.0NEW SEDIMENTATION BASIN COMBINED WITH
EXISTING BASIN. USE 12" CLAY LINER.
DEAD VOLUME SHOWN = 14,375 CU. FT.
NEW BIT.
NEW BIT.
INSTALL MUD RAIL ALONG
ALL RAILS AT NEW PAVEMENT
959.
5
959.8
962.
2
959.6
960.
6
960.3
NEW DUAL PUMP PAD
NEW LIGHT
POLE
NEW GUARD RAIL AT
PERIMETER OF POND
NEW LOADING PLATFORM
NEW COMPRESSOR PAD
NEW CONTROL STATION 30' x 12'
PROPOSED TRANSFORMER LOCATION
(2) NEW 60,000
GAL. PROPANE
TANKS
NEW TRUCK SKID
FUTURE EXPANSION TANKS
GUARD RAILS
(BY OWNER)
NEW GUARD RAIL 961.0
961.
0
13
25 DEFERRED
PARKING SPACES
12
959.8957.
5
957.8BOTTOM=951.0
FE=953.0
FE=952.0 FE=953.0
NWL=950.0
HWL=955.0
INSTALL FLARED END
SECTION AND RIP-RAP AT
EXISTING CULVERT
5 C.Y.
RIP-RAP
INSTALL PERMANENT FILTER
TRAP AT CATCH BASIN
SKIMMER STRUCTURE AND 14 L.F. OF 12" RCP
STORM PIPE AT 0.0% SLOPE.
OVERFLOW=955.0
INV=953.0
SUMP INV=951.0
955.
5
30 C.Y.
RIP-RAP
NWL=953.0
HWL=955.5
NEW BIT. DRIVE
NEW BITUMINOUS
NEW AUTO PARKING
956.
7
24.0NEW BIT.
PROPOSED LEGEND
WATER MAIN
SANITARY SEWER
STORM SEWER
WATER SERVICE
SANITARY SERVICE
CHAIN LINK FENCE
VINYL/WOOD FENCE
LIGHT POLE
HYDRANT
WATER VALVE
SANITARY MANHOLE
STORM MANHOLE
CATCH BASIN
SILT FENCE
GRADING LIMITS
999 CONTOUR LINE
SPOT ELEVATION
DRAINAGE ARROW
DETAIL
NOTE
S S S S
W W W W
S S S S
EXHIBIT D
First Floor
100' - 0"
Top of Wall
108' - 1 1/8"
T.O. Footing
96' - 0"
2
A3-2
12
5
12
12
Approx. Height
115' - 4"
ASPHALT SHINGLE
5" HORIZONTAL VINYL
SIDING
SKIRT BOARD
First Floor
100' - 0"
Top of Wall
108' - 1 1/8"
T.O. Footing
96' - 0"
1
A3-2
12
5
Approx. Height
115' - 4"
ASPHALT SHINGLE
5" HORIZONTAL VINYL
SIDING
ALUM GUTTERS
SKIRT BOARD
First Floor
100' - 0"
Top of Wall
108' - 1 1/8"
T.O. Footing
96' - 0"
1
A3-2
12
5
Approx. Height
115' - 4"
First Floor
100' - 0"
Top of Wall
108' - 1 1/8"
T.O. Footing
96' - 0"
12
5
12
12
Approx. Height
115' - 4"
ASPHALT SHINGLE
5" HORIZONTAL VINYL
SIDING
SKIRT BOARD
ALUM GUTTERS
Scale
Project number
Date
Drawn by
Checked by
21476 GRENADA AVENUE
LAKEVILLE, MN 55044
PH: 952-469-2171
FAX: 952-469-2173
EMAIL:
office@approdevelopment.com
CONDITIONAL USE
PERMIT SUBMITTAL
11/22/17
1/4" = 1'-0"12/20/2017 2:48:23 PMA3-1
EXTERIOR
ELEVATIONS
17-01-0127
21778 HIGHVIEW AVENUE
LAKEVILLE, MN 55044
CLIENT NO.
17-01-0127
12/12/17
MR
JJC
1/4" = 1'-0"A3-1
1 WEST ELEVATION 1/4" = 1'-0"A3-1
2 NORTH ELEVATION
1/4" = 1'-0"A3-1
4 SOUTH ELEVATION
1/4" = 1'-0"A3-1
3 EAST ELEVATION
ASPHALT SHINGLE
5" HORIZONTAL VINYL
SIDING
SKIRT BOARD
HALF LIGHT EXTERIOR
DOORS
1
1
1
1
No. Description Date
1 REVISION #1 12/12/17
EXHIBIT E
1
A3-2
2
A3-2
30' - 0"
5 1/2"14' - 6 1/2"5 1/2"14' - 1"5 1/2"12' - 0"5 1/2"11' - 1"5 1/2"4' - 0 3/4"2' - 11 1/2"4' - 0 3/4"30' - 0"
9' - 5"5 1/2"4' - 8"5 1/2"14' - 1"5 1/2"
7' - 0 1/2"2' - 4 1/2"7' - 0 1/2"7' - 0 1/2"6' - 7"5 1/2"4' - 0 1/2"12' - 0"5 1/2"11' - 1"5 1/2"101 102
W1
TRUCKER LOUNGE
101
CONTROL ROOM
102
SATELLITE
RESTROOM
LACATION
5'-0"W x 4'-0"D POURED
CONC STOOP AND
FOUN. WALL
5'-0"W x 4'-0"D POURED
CONC STOOP AND
FOUN. WALL
VINYL
FLOORING
CONC. SLAB
EXT. FRAMED WALL
2x6 @ 16" O.C.
INT. FRAMED WALL
2x6 @ 16" O.C.
FLUSH BEAM
SEE STRUCTURAL
W1
2
1
1
3
1
1
11
1
1
1
A3-2
2
A3-2GYP BD. CLG.GYP BD. CLG.
VENTED SOFFIT
ALUM. GUTTERALUM. LEADER VENTED SOFFIT
1
1
A3-2
2
A3-2
ALUM. GUTTERALUM. LEADER
EXTERIOR WALL BELOW
RIDGE VENT
12:12SLOPE12:5SLOPE12:12SLOPE12:5SLOPE12:5
SLOPE
12:5
SLOPE
1
LIGHTED EXIT SIGN W/ EMERGENCY LIGHTS, DARK PORTION INDICATES
SIGN FACE DIRECTION
REFLECTED CEILING PLAN LEGEND
RECESSED CAN TYPE LIGHT FIXTURE
4' STRIP FLUORESCENT FIXTURE SURFACE MOUNTED
1 2
EXT. SHEAR WALL TYPE
FULL HEIGHT LOAD BEARING WALL FULL HEIGHT LOAD BEARING WALL
SEE STRUCTURAL DRAWINGS
GYP. BD. WALL
FULL HEIGHT WALL
3
2X6 WOOD STUDS @ 16" O.C.
6 1/2"
SOUND ATTEN. BATT INSULATION
1/2" GYP. BD. ONE LAYER
EACH SIDE - PT FULL
HEIGHT
EXT. WALL TYPE
7 1/2"
1/2" GYP. BD. OVER
VAPOR BARRIER
2X6 WOOD STUDS @ 16" O.C.
WITH R-20 BATT INSUL.
ZIP R-SHEATHING 7/16" PANEL
W/ 1" RIGID INSUL. R-6
VINYL SIDING W/ 5" REVEAL
8"
1/2" GYP. BD. OVER
VAPOR BARRIER
2X6 WOOD STUDS @ 16" O.C.
WITH R-20 BATT INSUL.
ZIP R-SHEATHING 7/16" PANEL
W/ 1" RIGID INSUL. R-6 OVER
1/2" PLYWOOD
VINYL SIDING W/ 5" REVEAL
1
Scale
Project number
Date
Drawn by
Checked by
21476 GRENADA AVENUE
LAKEVILLE, MN 55044
PH: 952-469-2171
FAX: 952-469-2173
EMAIL:
office@approdevelopment.com
CONDITIONAL USE
PERMIT SUBMITTAL
11/22/17
As indicated
12/20/2017 2:48:22 PMA2-1
FLOOR PLAN
17-01-0127
21778 HIGHVIEW AVENUE
LAKEVILLE, MN 55044
CLIENT NO.
17-01-0127
12/12/17
MR
JJC
1/4" = 1'-0"A2-1
1 FLOOR PLAN
1/4" = 1'-0"A2-1
2 REFLECTED CEILING PLAN
1/4" = 1'-0"A2-1
3 ROOF PLAN
4'2'0'4'
NORTH
4'2'0'4'
NORTH
4'2'0'4'
3/4" = 1'-0"A2-1
4 WALL TYPES
No. Description Date
1 REVISION #1 12/12/17
EXHIBIT F
EXHIBIT F
EXHIBIT G
EXHIBIT H
EXHIBIT I
1
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
EMPIRE BUILDER INVESTMENTS, INC. CONDITIONAL USE PERMIT
FINDINGS OF FACT AND RECOMMENDATION
On January 4, 2018 the Lakeville Planning Commission met at it’s regularly scheduled
meeting to consider a conditional use permit for Empire Builder Investments, Inc. to allow
liquid propane storage in the I-2, General Industrial District located at 21778 Highview Avenue.
The Planning Commission conducted a public hearing on the proposed conditional use permit
preceded by published and mailed notice. The applicant was present and the Planning
Commission heard testimony from all interested persons wishing to speak.
FINDINGS OF FACT
1. The property is located in Planning District No. 8 of the Comprehensive Plan, which guides the
property for industrial uses.
2. The property is zoned I-2, General Industrial District.
3. The legal description of the property is:
Lot 1, Block 1, Empire Builder Investments First Addition
4. Section 11-4-3E of the City of Lakeville Zoning Ordinance provides that a conditional use
permit may not be issued unless certain criteria are satisfied. The criteria and our findings
regarding them are:
a. The proposed action has been considered in relation to the specific policies and
provisions of and has been found to be consistent with the official City Comprehensive
Plan.
Finding: The proposed liquid propane storage tanks are an allowed use on the industrial
guided and zoned property.
b. The proposed use is or will be compatible with present and future land uses of the area.
Finding: Provided compliance with the conditional use permit, the proposed liquid propane
storage tanks will be compatible with existing and future land uses in the area.
2
c. The proposed use conforms with all performance standards contained in the Zoning
Ordinance.
Finding: Provided compliance with the conditional use permit, the proposed liquid propane
storage tanks will conform with all performance standards contained in the Zoning
Ordinance and the City Code.
d. The proposed use can be accommodated with existing public services and will not
overburden the City’s service capacity.
Finding: The subject property lies within in the current MUSA. The property is served
with City sanitary sewer and water. The use of the property for liquid propane storage
will have no impact on the City’s service capacity provided compliance with the
stipulations of the conditional use permit.
e. Traffic generation by the proposed use is within capabilities of streets serving the
property.
Finding: Traffic generated by the liquid propane storage facility is within the capabilities of
Highview Avenue which serves the property.
5. The planning report dated December 29, 2017 prepared by Associate Planner Frank Dempsey
is incorporated herein.
RECOMMENDATION
The Planning Commission recommends that the City Council approve the conditional use
permit in the form attached thereto.
DATED: January 4, 2018
LAKEVILLE PLANNING COMMISSION
BY: _________________________
Pat Kaluza, Vice Chair
City of Lakeville
Public Works – Engineering Division
Memorandum
To: Frank Dempsey, Associate Planner
From: Alex Jordan, Senior Project Engineer
McKenzie L. Cafferty, Environmental Resources Manager
Copy: Zach Johnson, City Engineer
Dave Olson, Community and Economic Development Director
Daryl Morey, Planning Director
Gene Abbott, Building Official
Date: December 29, 2017
Subject: Progressive Rail
• Site Plan Review
• Grading Plan Review
• Conditional Use Permit
BACKGROUND
Appro Development, Inc, on behalf of Empire Builder Investment, Inc. (a/k/a Progressive Rail)
has submitted a Conditional Use Permit application to install liquid propane storage tanks
and dispensing facility on Lot 1, Block 1, Empire Builder Investments First Addition. The
property is located east of and adjacent to Highview Avenue; south of 215th Street (CSAH 70);
and north of 220th Street. The parent parcel is zoned I-2, General Industrial District.
The proposed Conditional Use Permit application will be completed by:
Applicant: Appro Development, Inc.
Engineer: Jacobson Engineers & Surveyors.
SSIITTEE CCOONNDDIITTIIOONNSS
The parent parcel was developed in 1999 for use as an office, maintenance and storage
building and transload facility for the rail company. The property currently operates as a rail
transload and outdoor storage facility for a variety of products. Several existing private
stormwater management basins and storm sewer utilities exist within the rear outdoor
storage area.
PPRROOGGRREESSSSIIVVEE RRAAIILL –– LLOOTT 11,, BBLLOOCCKK 11,, EEMMPPIIRREE BBUUIILLDDEERR IINNVVEESSTTMMEENNTTSS FFIIRRSSTT AADDDDIITTIIOONN
CCOONNDDIITTIIOONNAALL UUSSEE PPEERRMMIITT
DDEECCEEMMBBEERR 2299,, 22001177
PPAAGGEE 22 OOFF 44
SSIITTEE PPLLAANN RREEVVIIEEWW
Appro Development, Inc. proposes to construct two 60,000-gallon liquid propane (LP) storage
tanks, including unloading and loading areas, to be located approximately 230 feet east of
the existing main building. In conjunction with the proposed storage tank improvements, the
Applicant proposes to construct a paved surface over the rear yard storage areas, parking
areas, and drive aisles. In addition, the Applicant proposes to expand the drive aisle north of
the existing building to allow for two-way semi-truck circulation between the front and rear
of the buildings.
PPUUBBLLIICC SSTTRREEEETTSS AANNDD AACCCCEESSSS
Highview Avenue
The parent parcel is located east of and adjacent to Highview Avenue, a minor collector
industrial roadway, as identified in the City’s Transportation Plan. 40-feet of ½ right-of-way
way was dedicated for Highview Avenue with the Empire Builder Investments First Addition
plat. No additional right-of-way will need to be dedicated with the Conditional Use Permit
application.
Highview Avenue is currently constructed as a 24-foot undivided rural roadway adjacent to
the parent parcel and was rehabilitated in 2016 with City Project No. 16-04. The parent parcel
has two existing driveways that access Highview Avenue. No modifications or improvements
to the driveway accesses are proposed with the Conditional Use Permit application.
CCOONNSSTTRRUUCCTTIIOONN AACCCCEESSSS
Construction traffic access and egress for site grading, utility, and pavement construction
shall be restricted to one entrance off of Highview Avenue.
DDRRAAIINNAAGGEE AANNDD GGRRAADDIINNGG
The parent parcel is located within subdistrict SC-3A of the South Creek Stormwater District,
as identified in the City’s Water Resources Management Plan.
A stormwater management system was constructed in 1999 in conjunction with the site
development. Various improvements have been added since development of the site to
reduce rate control and provide water quality treatment of the stormwater generated from
the site. The site ultimately discharges to a City-owned sedimentation basin located directly
east of the site on Outlot A, Empire Builder Investments First Addition. The majority of the site
is either hardscaped or an impervious aggregate surface.
The proposed site adds under an acre of impervious surface which is under the threshold of
the permitting requirements of the MPCA Construction General Permit with respect to the
water quality volume. The City’s Water Resources Management Plan requires that any project
which adds impervious surface within the South Creek Stormwater District shall provide for
PPRROOGGRREESSSSIIVVEE RRAAIILL –– LLOOTT 11,, BBLLOOCCKK 11,, EEMMPPIIRREE BBUUIILLDDEERR IINNVVEESSTTMMEENNTTSS FFIIRRSSTT AADDDDIITTIIOONN
CCOONNDDIITTIIOONNAALL UUSSEE PPEERRMMIITT
DDEECCEEMMBBEERR 2299,, 22001177
PPAAGGEE 33 OOFF 44
infiltration of 1.5 inches over the newly created impervious area. Due to the nature of the site
activity and existing gravel soils within the site, staff recommends eliminating the infiltration
of the runoff generated from the site. The Applicant shall remove all sediment collected in the
existing basins and provide a clay liner at the bottom of the basins. Additionally, the
Applicant shall construct a structural outlet on the east basin to reduce the discharge rate and
provide for additional water quality treatment from the site. A $10,000 security for the
stormwater management improvements on the site shall be required with the Conditional
Use Permit and shall be submitted prior to the issuance of a building permit for the
installation of the LP tanks. The Applicant shall enter into a private stormwater and site
maintenance agreement with the City for the privately owned and maintained stormwater
management basins, prior to the issuance of a building permit for the installation of the fuel
tanks.
The Applicant shall submit as-built record grading and utility plans following completion of
the project.
The proposed site plan and improvements contain more than one acre of site disturbance. A
National Pollution Discharge Elimination System General Stormwater Permit for construction
activity is required from the Minnesota Pollution Control Agency for areas exceeding one acre
being disturbed by grading. A copy of the Notice of Stormwater Permit Coverage must be
submitted to the City upon receipt from the MPCA.
SSTTOORRMM SSEEWWEERR
No public storm sewer is proposed to be constructed in conjunction with the site plan
improvements. A private storm sewer system will be installed to convey the discharge from
the site improvements to the City-owned stormwater basin east of the site.
The Trunk Storm Sewer Area Charge has been collected on the parent parcel and will not be
required with the Conditional Use Permit.
EERROOSSIIOONN CCOONNTTRROOLL
The Developer shall prepare a SWPPP and erosion control plan prior to any grading or land
disturbance.
Additional erosion control measures may be required during construction as deemed
necessary by City staff. Any additional measures required shall be installed and maintained
by the Applicant.
PPRROOGGRREESSSSIIVVEE RRAAIILL –– LLOOTT 11,, BBLLOOCCKK 11,, EEMMPPIIRREE BBUUIILLDDEERR IINNVVEESSTTMMEENNTTSS FFIIRRSSTT AADDDDIITTIIOONN
CCOONNDDIITTIIOONNAALL UUSSEE PPEERRMMIITT
DDEECCEEMMBBEERR 2299,, 22001177
PPAAGGEE 44 OOFF 44
SSEECCUURRIITTIIEESS
The Applicant shall provide a Letter of Credit as security for the Applicant-installed
improvements with the Conditional Use Permit. The security will be required prior to issuance
of a building permit for the LP storage tanks.
CONSTRUCTION COSTS
Site Grading, Erosion Control, Restoration, Stormwater Basins
and Grading Certification
10,000.00
SUBTOTAL - CONSTRUCTION COSTS $ 10,000.00
OTHER COSTS
City Construction Observation 1,000.00
Developer’s Record Drawing 1,000.00
SUBTOTAL - OTHER COSTS $ 2,000.00
TOTAL PROJECT SECURITIES $ 12,000.00
RREECCOOMMMMEENNDDAATTIIOONN
Engineering recommends approval of the Conditional Use Permit, site plan and grading plan
for Progressive Rail, subject to the requirements and stipulations within this report.