Loading...
HomeMy WebLinkAboutItem 06.i Date: Item No. AWARD CONTRACT TO McNAMARA CONTRACTING FOR 2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYS Proposed Action Staff recommends adoption of the following motion: Move to award contract to McNamara Contracting, Inc. for 2018 Miscellaneous Roadway Repairs and Overlays, City Project 18-01. Overview On February 20th, 2018, the Lakeville City Council approved plans and specifications for City Project 18-01. On Tuesday, March 20th, 2018, at 10:00 a.m. the City received four bids for City Project 18-01. The bids ranged from a low bid of $756,500.03 submitted by McNamara Contracting to a high bid of $978,000.81. The engineer’s estimate of the construction cost was $969,039. Primary Issues to Consider • Anticipated funding sources are the Pavement Management Fund, Park Dedication Fund and Trail Improvement Fund. • Construction is anticipated to begin in May 2018. Final restoration/completion is expected by October 2018. Supporting Information • Bid Tabulation • Agreement Financial Impact: $756,500.03 Budgeted: Y☒ N☐ Source: Multiple Sources Related Documents: Adopted 2018-2022 Capital Improvement Plan Envision Lakeville Community Values: Safety Throughout the Community Report Completed by: Zach Johnson, City Engineer April 2, 2018 CITY OF LAKEVILLE RESOLUTION NO. 18-__ RESOLUTION AWARDING CONTRACT FOR 2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYS WHEREAS, the City of Lakeville received sealed bids on Tuesday, March 20, 2018, at 10:00 a.m. for 2018 miscellaneous roadway repairs and overlays, City Project 18-01; and WHEREAS, the lowest responsible bid was from McNamara Contracting, Inc. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Lakeville, Minnesota, hereby awards the contract to the lowest responsible bidder that meets all the bid requirements, McNamara Contracting, Inc., with a bid in the amount of $756,500.03. The construction is proposed to be completed as specified in the contract documents. ADOPTED by the Lakeville City Council this 2nd day of April 2018 Douglas P. Anderson, Mayor Charlene Friedges, City Clerk 2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYS CONTRACT FOR CONSTRUCTION CITY IMPROVEMENT PROJECT NO. 18-01 CONTRACT FOR CONSTRUCTION THIS AGREEMENT, made and entered into as of the 2nd day of April, 2018, by and between the City of Lakeville, a municipal corporation under the laws of the State of Minnesota, hereinafter called the “Owner,” and McNamara Contracting, Inc., hereinafter called the “Contractor.” WITNESSETH: That in consideration of their mutual covenants and agreements as hereinafter set forth, the Owner for itself and the Contractor for itself, its successors, and assigns, covenants and agrees as follows, to wit: 1.The Contractor agrees to furnish all the necessary materials, labor, use of tools, equipment, plant and every other thing necessary to perform the work designated and referred to in this Contract, including all Contractor’s superintendence, and to furnish everything necessary for the completion of the improvement which is the subject of this Contract (except such things as the Owner has specifically agreed to provide, according to the Contract Documents); and agrees under penalty of a public contractor’s corporate surety bond in the amount of seven hundred fifty-six thousand five hundred and 03/100 Dollars ($756,500.03) to perform and complete the work shown in the plans and drawings, entitled “2018 Miscellaneous Roadway Repair and Overlays,” prepared by the City of Lakeville and dated March 1, 2018, and to conform in all respects with the provisions and requirements of the General Conditions, Supplementary General Conditions and Specifications for said improvement, which is entitled “2018 Miscellaneous Roadway Repairs and Overlays”. 2.The Contractor agrees that performance shall be in accordance with the terms, requirements and conditions of this instrument, and laws of the State of Minnesota, and the following documents. ADVERTISEMENT FOR BIDS for said 2018 Miscellaneous Roadway Repairs and Overlays for the Owner. PROPOSAL by the Contractor, presented to the Council of the Owner on March 20, 2018, and accepted by the Owner on April 2, 2018. CONTRACT DOCUMENTS for said 2018 Miscellaneous Roadway Repairs and Overlays dated March 1, 2018, referred to in the preceding paragraph of this Agreement and made a part of the aforementioned proposal. PLANS AND DRAWINGS for said 2018 Miscellaneous Roadway Repairs and Overlays as identified in a preceding paragraph of this Contract and which are dated March 1, 2018. ANY ADDENDA to the plans, drawings, general conditions and specifications for said 2018 Miscellaneous Roadway Repairs and Overlays which addenda were prepared by the City of Lakeville. PUBLIC CONTRACTOR’S SURETY BOND in the principal sum of the amount bid. Each and all of the aforementioned Contract Documents are hereby incorporated into this Contract by specific reference and the terms and provisions thereof are and constitute a part of this Contract as though attached hereto or fully set forth herein. 3.The Owner agrees to pay the Contractor for the performance of this Contract and the Contractor agrees to accept in full compensation therefor, the sums set forth within the aforementioned proposal of the Contractor for each unit and each type of unit of work to be performed. It is understood and agreed that the said proposal is for the construction of 2018 Miscellaneous Roadway Repairs and Overlays on a unit price basis in accordance with the said proposal, and that sum of $756,500.03 as set out in said proposal, is the sum of the unit prices, multiplied by the estimated quantities of the respective units of work listed therein. 2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYS CONTRACT FOR CONSTRUCTION CITY IMPROVEMENT PROJECT NO. 18-01 4.This contract may be terminated by the City at any time upon discovery by the City that the prime contractor or subcontractor has submitted a false statement under oath verifying compliance with any of the minimum criteria set forth in Minn. Stat. § 16C.285, subd. 3. IN WITNESS WHEREOF, the parties hereto have hereunto set their hands and seals as of the day and year first above written. CONTRACTOR CITY OF LAKEVILLE, MN By Douglas P. Anderson, Mayor By Charlene Friedges, City Clerk (Corporate Seal) (City Seal) By Authorized Official BID OPENING DATE 3/20/201810:00AMITEM UNITTOTAL ESTIMATED QUANTITYBID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICESCHEDULE A: REPAIRS CITY WIDEMOBILIZATION LS 1 65,000.00$ 65,000.00$ 24,400.00$ 24,400.00$ 31,690.00$ 31,690.00$ 96,325.00$ 96,325.00$ 25,572.46$ 25,572.46$ TRAFFIC CONTROL LS 1 10,000.00$ 10,000.00$ 19,000.00$ 19,000.00$ 23,633.00$ 23,633.00$ 11,700.00$ 11,700.00$ 12,671.51$ 12,671.51$ 12" RCP CL V LF 75 45.00$ 3,375.00$ 65.00$ 4,875.00$ 43.25$ 3,243.75$ 42.50$ 3,187.50$ 69.31$ 5,198.25$ 12" RC PIPE APRON EA 4 1,000.00$ 4,000.00$ 1,050.00$ 4,200.00$ 950.00$ 3,800.00$ 1,045.00$ 4,180.00$ 1,580.15$ 6,320.60$ 15" FLARED END SECTION EA 1 1,056.00$ 1,056.00$ 1,400.00$ 1,400.00$ 1,345.00$ 1,345.00$ 1,150.00$ 1,150.00$ 1,185.92$ 1,185.92$ 18" RC PIPE SEWER DES 3006 CL III LF 32 100.00$ 3,200.00$ 58.00$ 1,856.00$ 48.53$ 1,552.96$ 48.00$ 1,536.00$ 71.48$ 2,287.36$ 24" RC PIPE SEWER DES 3006 CL III LF 131 55.00$ 7,205.00$ 70.00$ 9,170.00$ 53.80$ 7,047.80$ 50.00$ 6,550.00$ 87.73$ 11,492.63$ 24" RC PIPE APRON EA 4 2,250.00$ 9,000.00$ 2,500.00$ 10,000.00$ 2,005.00$ 8,020.00$ 1,960.00$ 7,840.00$ 2,401.09$ 9,604.36$ 4" PERF TP PIPE DRAIN LF 25 20.00$ 500.00$ 40.00$ 1,000.00$ 20.00$ 500.00$ 20.00$ 500.00$ 27.08$ 677.00$ 4" TP PIPE CLEAN OUT EA 2 150.00$ 300.00$ 250.00$ 500.00$ 396.00$ 792.00$ 200.00$ 400.00$ 292.42$ 584.84$ SALVAGE AND RECONSTRUCT 4" PERF DRAIN TILE LF 28 20.00$ 560.00$ 40.00$ 1,120.00$ 20.00$ 560.00$ 10.00$ 280.00$ 27.08$ 758.24$ 5" CONCRETE WALK SF 1585 7.00$ 11,095.00$ 6.75$ 10,698.75$ 7.12$ 11,285.20$ 7.13$ 11,301.05$ 7.04$ 11,158.40$ 6" PERF TP PIPE DRAIN LF 190 25.00$ 4,750.00$ 25.00$ 4,750.00$ 21.10$ 4,009.00$ 20.00$ 3,800.00$ 30.32$ 5,760.80$ 6" TP PIPE DRAIN CLEAN OUT EA 2 225.00$ 450.00$ 290.00$ 580.00$ 448.00$ 896.00$ 250.00$ 500.00$ 351.99$ 703.98$ 7" CONCRETE DRIVEWAY SY 146 70.00$ 10,220.00$ 65.50$ 9,563.00$ 69.10$ 10,088.60$ 79.00$ 11,534.00$ 75.05$ 10,957.30$ ADJUST FRAME & RING CASTING EA 76 525.00$ 39,900.00$ 518.00$ 39,368.00$ 525.00$ 39,900.00$ 600.00$ 45,600.00$ 804.94$ 61,175.44$ ADJUST VALVE BOX TOP EA 15 325.00$ 4,875.00$ 528.00$ 7,920.00$ 245.00$ 3,675.00$ 375.00$ 5,625.00$ 268.64$ 4,029.60$ ADJUST VALVE BOX TOP & MIDS EA 7 525.00$ 3,675.00$ 585.00$ 4,095.00$ 345.00$ 2,415.00$ 500.00$ 3,500.00$ 306.20$ 2,143.40$ AGGREGATE BASE CLASS 5 - (PATCHING) TON 10 25.00$ 250.00$ 25.00$ 250.00$ 50.00$ 500.00$ 30.00$ 300.00$ 175.41$ 1,754.10$ BITUMINOUS TACK COAT GAL 1032 2.15$ 2,218.80$ 3.05$ 3,147.60$ 3.00$ 3,096.00$ 2.50$ 2,580.00$ 1.50$ 1,548.00$ CASTING ASSEMBLY EA 1 950.00$ 950.00$ 500.00$ 500.00$ 750.00$ 750.00$ 1,000.00$ 1,000.00$ 696.40$ 696.40$ COMMON EXCAVATION (CV) CY 40 40.00$ 1,600.00$ 36.00$ 1,440.00$ 40.00$ 1,600.00$ 25.00$ 1,000.00$ 72.12$ 2,884.80$ CONCRETE CURB & GUTTER (ALL TYPES) LF 7867 23.00$ 180,941.00$ 13.65$ 107,384.55$ 16.74$ 131,693.58$ 15.55$ 122,331.85$ 16.84$ 132,480.28$ CONNECT TO EXISTING STORM SEWER EA 3 875.00$ 2,625.00$ 1,200.00$ 3,600.00$ 633.00$ 1,899.00$ 800.00$ 2,400.00$ 1,597.48$ 4,792.44$ CONSTRUCT DRAINAGE STRUCTURE (27"; LV-STM-17) EA 1 1,700.00$ 1,700.00$ 1,250.00$ 1,250.00$ 4,267.50$ 4,267.50$ 1,100.00$ 1,100.00$ 2,669.68$ 2,669.68$ CROSSWALK PAINT SF 594 2.45$ 1,455.30$ 2.73$ 1,621.62$ 4.87$ 2,892.78$ 2.00$ 1,188.00$ 2.82$ 1,675.08$ DITCH GRADING SY 180 15.00$ 2,700.00$ 10.00$ 1,800.00$ 3.50$ 630.00$ 10.00$ 1,800.00$ 21.66$ 3,898.80$ DITCH GRADING LS 1 5,000.00$ 5,000.00$ 700.00$ 700.00$ 500.00$ 500.00$ 1,000.00$ 1,000.00$ 1,142.18$ 1,142.18$ EDGE MILL 6' WIDE SY 4971 1.30$ 6,441.00$ 2.97$ 14,763.87$ 2.58$ 12,825.18$ 2.17$ 10,787.07$ 3.58$ 17,796.18$ FOUNDATION MATERIAL (3" MINUS) TON 15 35.00$ 525.00$ 33.00$ 495.00$ 68.00$ 1,020.00$ 39.00$ 585.00$ 125.22$ 1,878.30$ PEDESTRIAN CURB RAMP EA 12 1,000.00$ 12,000.00$ 420.00$ 5,040.00$ 443.10$ 5,317.20$ 675.00$ 8,100.00$ 731.05$ 8,772.60$ HARDRIVES, INC.OFFICIAL BID TABULATIONCITY OF LAKEVILLE2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYSCITY OF LAKEVILLE IMPROVEMENT PROJECT NO. 18-01DENOTES CORRECTED FIGUREENGINEER'S ESTIMATE MCNAMARA CONTRACTINGGMH ASPHALT CORPORATION NORTHWEST ASPHALT, INC. BID OPENING DATE 3/20/201810:00AMITEM UNITTOTAL ESTIMATED QUANTITYBID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICEHARDRIVES, INC.OFFICIAL BID TABULATIONCITY OF LAKEVILLE2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYSCITY OF LAKEVILLE IMPROVEMENT PROJECT NO. 18-01DENOTES CORRECTED FIGUREENGINEER'S ESTIMATE MCNAMARA CONTRACTINGGMH ASPHALT CORPORATION NORTHWEST ASPHALT, INC.REMOVE PEDESTRIAN CURB RAMP EA 12 500.00$ 6,000.00$ 150.00$ 1,800.00$ 250.00$ 3,000.00$ 150.00$ 1,800.00$ 716.96$ 8,603.52$ REMOVE AND REPLACE BITUMINOUS PAVEMENT SY 1159 50.00$ 57,950.00$ 42.00$ 48,678.00$ 30.50$ 35,349.50$ 39.60$ 45,896.40$ 52.92$ 61,334.28$ REMOVE AND REPLACE CONCRETE APRON SF 360 18.00$ 6,480.00$ 10.00$ 3,600.00$ 7.70$ 2,772.00$ 8.30$ 2,988.00$ 14.14$ 5,090.40$ REMOVE BITUMINOUS DRIVEWAY PAVEMENT SY 887 8.00$ 7,096.00$ 10.00$ 8,870.00$ 6.00$ 5,322.00$ 5.00$ 4,435.00$ 16.18$ 14,351.66$ REMOVE BITUMINOUS TRAIL SF 25 8.00$ 200.00$ 74.00$ 1,850.00$ 2.00$ 50.00$ 1.00$ 25.00$ 26.33$ 658.25$ REMOVE CASTING EA 1 75.00$ 75.00$ 74.00$ 74.00$ 250.00$ 250.00$ 150.00$ 150.00$ 489.22$ 489.22$ REMOVE CONCRETE WALK SF 1585 1.50$ 2,377.50$ 3.00$ 4,755.00$ 1.30$ 2,060.50$ 1.00$ 1,585.00$ 4.58$ 7,259.30$ REMOVE CONCRETE DRIVEWAY SY 110 14.00$ 1,540.00$ 17.80$ 1,958.00$ 9.00$ 990.00$ 5.00$ 550.00$ 10.24$ 1,126.40$ REMOVE CURB AND GUTTER (ALL TYPES) LF 7867 7.50$ 59,002.50$ 4.75$ 37,368.25$ 4.40$ 34,614.80$ 3.82$ 30,051.94$ 9.22$ 72,533.74$ REMOVE SEWER PIPE STORM (ALL SIZES) LF 199 15.00$ 2,985.00$ 12.00$ 2,388.00$ 7.40$ 1,472.60$ 10.00$ 1,990.00$ 21.66$ 4,310.34$ REPAIR INVISIBLE FENCE EA 67 150.00$ 10,050.00$ 50.00$ 3,350.00$ 32.00$ 2,144.00$ 100.00$ 6,700.00$ 205.77$ 13,786.59$ REPAIR IRRIGATION SYSTEM EA 67 450.00$ 30,150.00$ 150.00$ 10,050.00$ 137.00$ 9,179.00$ 250.00$ 16,750.00$ 449.80$ 30,136.60$ RANDOM RIPRAP CLASS III CY 55 110.00$ 6,050.00$ 115.00$ 6,325.00$ 88.62$ 4,874.10$ 86.50$ 4,757.50$ 129.96$ 7,147.80$ SILT FENCE TYPE MACHINE SLICED LF 70 2.75$ 192.50$ 6.43$ 450.10$ 7.54$ 527.80$ 5.00$ 350.00$ 10.83$ 758.10$ TRUNCATED DOMES SF 112 47.00$ 5,264.00$ 40.00$ 4,480.00$ 42.20$ 4,726.40$ 52.50$ 5,880.00$ 56.86$ 6,368.32$ TURF ESTABLISHMENT AC 0.95 50,000.00$ 47,500.00$ 22,049.04$ 20,946.59$ 7,925.00$ 7,528.75$ 53,648.00$ 50,965.60$ 36,011.98$ 34,211.38$ WEARING COURSE MIXTURE SP 9.5 SPWEA240B (3.0" THICK DRIVEWAY) SY 887 20.00$ 17,740.00$ 30.50$ 27,053.50$ 19.00$ 16,853.00$ 33.09$ 29,350.83$ 28.07$ 24,898.09$ WEARING COURSE MIXTURE SP 12.5 SPWEB240B (PATCHING) SF 25 10.00$ 250.00$ 42.00$ 1,050.00$ 8.00$ 200.00$ 5.00$ 125.00$ 41.95$ 1,048.75$ WEARING COURSE MIXTURE SP 9.5 SPWEA240B (OVERLAY) TON 1276 45.00$ 57,420.00$ 50.00$ 63,800.00$ 54.65$ 69,733.40$ 54.16$ 69,108.16$ 69.50$ 88,682.00$ SUBTOTAL SCHEDULE A: 715,889.60$ SUBTOTAL SCHEDULE A: 545,334.83$ SUBTOTAL SCHEDULE A: 523,092.40$ SUBTOTAL SCHEDULE A: 643,138.90$ SUBTOTAL SCHEDULE A: 737,065.67$ SCHEDULE B: KING PARK TRAIL RECLAIM AND EXTENSIONMOBILIZATION LS 1 1,800.00$ 1,800.00$ 1,500.00$ 1,500.00$ 1,735.00$ 1,735.00$ 1,350.00$ 1,350.00$ 7,291.54$ 7,291.54$ TRAFFIC CONTROL LS 1 1,500.00$ 1,500.00$ 370.00$ 370.00$ 370.00$ 370.00$ 350.00$ 350.00$ 379.06$ 379.06$ 3" BITUMINOUS TRAIL SP 9.5 SPWEA240B SF 10225 1.50$ 15,337.50$ 1.30$ 13,292.50$ 2.00$ 20,450.00$ 1.24$ 12,679.00$ 1.37$ 14,008.25$ FOUNDATION MATERIAL (3" MINUS) TON 20 35.00$ 700.00$ 29.00$ 580.00$ 67.00$ 1,340.00$ 35.00$ 700.00$ 125.23$ 2,504.60$ COMMON EXCAVATION (CV) CY 130 25.00$ 3,250.00$ 38.00$ 4,940.00$ 50.00$ 6,500.00$ 25.00$ 3,250.00$ 60.67$ 7,887.10$ AGGREGATE BASE (CV) CLASS 5 TON 160 25.00$ 4,000.00$ 23.50$ 3,760.00$ 44.25$ 7,080.00$ 20.00$ 3,200.00$ 45.26$ 7,241.60$ RECLAIM BITUMINOUS TRAIL SY 748 2.50$ 1,870.00$ 5.80$ 4,338.40$ 7.92$ 5,924.16$ 2.00$ 1,496.00$ 3.56$ 2,662.88$ REMOVE BITUMINOUS PAVEMENT SY 120 5.50$ 660.00$ 2.60$ 312.00$ 6.00$ 720.00$ 5.00$ 600.00$ 6.02$ 722.40$ TURF ESTABLISHMENT AC 0.15 50,000.00$ 7,500.00$ 10,500.00$ 1,575.00$ 7,700.00$ 1,155.00$ 38,352.00$ 5,752.80$ 56,569.27$ 8,485.39$ BID OPENING DATE 3/20/201810:00AMITEM UNITTOTAL ESTIMATED QUANTITYBID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICEHARDRIVES, INC.OFFICIAL BID TABULATIONCITY OF LAKEVILLE2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYSCITY OF LAKEVILLE IMPROVEMENT PROJECT NO. 18-01DENOTES CORRECTED FIGUREENGINEER'S ESTIMATE MCNAMARA CONTRACTINGGMH ASPHALT CORPORATION NORTHWEST ASPHALT, INC.REMOVE CURB AND GUTTER (ALL TYPES) LF 220 5.75$ 1,265.00$ 3.60$ 792.00$ 6.50$ 1,430.00$ 5.00$ 1,100.00$ 5.73$ 1,260.60$ BITUMINOUS CURB LF 220 15.00$ 3,300.00$ 12.20$ 2,684.00$ 10.00$ 2,200.00$ 9.58$ 2,107.60$ 11.15$ 2,453.00$ SILT FENCE TYPE MACHINE SLICED LF 430 2.75$ 1,182.50$ 2.90$ 1,247.00$ 2.72$ 1,169.60$ 2.75$ 1,182.50$ 3.79$ 1,629.70$ SUBGRADE EXCAVATION (CV) CY 25 30.00$ 750.00$ 41.00$ 1,025.00$ 50.00$ 1,250.00$ 25.00$ 625.00$ 60.66$ 1,516.50$ SUBTOTAL SCHEDULE B: $ 43,115.00 SUBTOTAL SCHEDULE B: $ 36,415.90 SUBTOTAL SCHEDULE B: $ 51,323.76 SUBTOTAL SCHEDULE B: $ 34,392.90 SUBTOTAL SCHEDULE B: $ 58,042.62 SCHEDULE C: DODD PARK TRAIL CULVERT CROSSINGMOBILIZATION LS 1 5,000.00$ 5,000.00$ 1,400.00$ 1,400.00$ 171.00$ 171.00$ 2,427.00$ 2,427.00$ 1,911.85$ 1,911.85$ TRAFFIC CONTROL LS 1 2,000.00$ 2,000.00$ 315.00$ 315.00$ 317.00$ 317.00$ 300.00$ 300.00$ 324.91$ 324.91$ REMOVE BITUMINOUS PAVEMENT SY 35 5.00$ 175.00$ 11.50$ 402.50$ 15.00$ 525.00$ 10.00$ 350.00$ 25.78$ 902.30$ BITUMINOUS TRAIL SP 9.5 SPWEA240B SF 850 20.00$ 17,000.00$ 5.50$ 4,675.00$ 3.60$ 3,060.00$ 3.68$ 3,128.00$ 3.62$ 3,077.00$ BITUMINOUS TACK COAT GAL 8 2.15$ 17.20$ 3.50$ 28.00$ 15.00$ 120.00$ 10.00$ 80.00$ 1.50$ 12.00$ TURF ESTABLISHMENT AC 0.11 50,000.00$ 5,500.00$ 14,400.00$ 1,584.00$ 7,923.00$ 871.53$ 383.52$ 42.19$ 46,444.27$ 5,108.87$ SUBTOTAL SCHEDULE C: $ 29,692.20 SUBTOTAL SCHEDULE C: $ 8,404.50 SUBTOTAL SCHEDULE C: $ 5,064.53 SUBTOTAL SCHEDULE C: $ 6,327.19 SUBTOTAL SCHEDULE C: $ 11,336.93 SCHEDULE D: JUNO TRAILMOBILIZATION LS 1 8,000.00$ 8,000.00$ 2,600.00$ 2,600.00$ 7,365.00$ 7,365.00$ 1,350.00$ 1,350.00$ 8,106.38$ 8,106.38$ TRAFFIC CONTROL LS 1 6,000.00$ 6,000.00$ 525.00$ 525.00$ 3,137.50$ 3,137.50$ 500.00$ 500.00$ 541.52$ 541.52$ RECLAIM BITUMINOUS TRAIL SY 4460 2.50$ 11,150.00$ 3.00$ 13,380.00$ 7.72$ 34,431.20$ 2.17$ 9,678.20$ 2.71$ 12,086.60$ BIOBARRIER LF 6173 6.00$ 37,038.00$ 5.90$ 36,420.70$ 7.41$ 45,741.93$ 6.50$ 40,124.50$ 4.77$ 29,445.21$ 3" BITUMINOUS TRAIL SP 9.5 SPWEA240B SF 40900 1.50$ 61,350.00$ 1.40$ 57,260.00$ 2.00$ 81,800.00$ 1.19$ 48,671.00$ 1.28$ 52,352.00$ CONCRETE BOLLARD EA 2 750.00$ 1,500.00$ 350.00$ 700.00$ 300.00$ 600.00$ 250.00$ 500.00$ 812.28$ 1,624.56$ REMOVE BITUMINOUS PAVEMENT SY 256 5.50$ 1,408.00$ 3.60$ 921.60$ 6.00$ 1,536.00$ 5.00$ 1,280.00$ 10.43$ 2,670.08$ PEDESTRIAN CURB RAMP EA 1 1,000.00$ 1,000.00$ 585.00$ 585.00$ 617.18$ 617.18$ 675.00$ 675.00$ 731.05$ 731.05$ REMOVE PEDESTRIAN CURB RAMP EA 1 200.00$ 200.00$ 175.00$ 175.00$ 500.00$ 500.00$ 150.00$ 150.00$ 715.61$ 715.61$ TRUNCATED DOMES SF 16 47.00$ 752.00$ 40.00$ 640.00$ 42.20$ 675.20$ 52.50$ 840.00$ 56.86$ 909.76$ TURF ESTABLISHMENT AC 0.4 50,000.00$ 20,000.00$ 41,000.00$ 16,400.00$ 7,660.00$ 3,064.00$ 38,352.00$ 15,340.80$ 51,462.33$ 20,584.93$ REPAIR IRRIGATION SYSTEM EA 5 450.00$ 2,250.00$ 300.00$ 1,500.00$ 137.00$ 685.00$ 250.00$ 1,250.00$ 585.18$ 2,925.90$ REPAIR INVISIBLE FENCE EA 5 150.00$ 750.00$ 80.00$ 400.00$ 32.00$ 160.00$ 100.00$ 500.00$ 81.23$ 406.15$ FOUNDATION MATERIAL (3" MINUS) TON 100 35.00$ 3,500.00$ 30.00$ 3,000.00$ 64.00$ 6,400.00$ 35.00$ 3,500.00$ 42.62$ 4,262.00$ ADJUST FRAME & RING CASTING EA 2 525.00$ 1,050.00$ 775.00$ 1,550.00$ 525.00$ 1,050.00$ 650.00$ 1,300.00$ 805.18$ 1,610.36$ BID OPENING DATE 3/20/201810:00AMITEM UNITTOTAL ESTIMATED QUANTITYBID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICE BID UNIT PRICE BID PRICEHARDRIVES, INC.OFFICIAL BID TABULATIONCITY OF LAKEVILLE2018 MISCELLANEOUS ROADWAY REPAIRS AND OVERLAYSCITY OF LAKEVILLE IMPROVEMENT PROJECT NO. 18-01DENOTES CORRECTED FIGUREENGINEER'S ESTIMATE MCNAMARA CONTRACTINGGMH ASPHALT CORPORATION NORTHWEST ASPHALT, INC.SUBGRADE EXCAVATION (CV) CY 150 30.00$ 4,500.00$ 27.00$ 4,050.00$ 60.00$ 9,000.00$ 20.00$ 3,000.00$ 45.23$ 6,784.50$ 5" CONCRETE WALK SF 775 7.00$ 5,425.00$ 8.00$ 6,200.00$ 8.04$ 6,231.00$ 6.50$ 5,037.50$ 7.04$ 5,456.00$ SUBTOTAL SCHEDULE D: $ 165,873.00 SUBTOTAL SCHEDULE D: $ 146,307.30 SUBTOTAL SCHEDULE D: $ 202,994.01 SUBTOTAL SCHEDULE D: $ 133,697.00 SUBTOTAL SCHEDULE D: $ 151,212.61 SCHEDULE E: CITY HALL TRASH ENCLOSUREMOBILIZATION LS 1 1,000.00$ 1,000.00$ 2,300.00$ 2,300.00$ 550.00$ 550.00$ 650.00$ 650.00$ 3,902.13$ 3,902.13$ TRAFFIC CONTROL LS 1 1,000.00$ 1,000.00$ 105.00$ 105.00$ 106.00$ 106.00$ 100.00$ 100.00$ 108.30$ 108.30$ 7" CONCRETE DRIVEWAY SY 36 70.00$ 2,520.00$ 117.00$ 4,212.00$ 90.31$ 3,251.16$ 79.00$ 2,844.00$ 75.05$ 2,701.80$ CONCRETE CURB & GUTTER (ALL TYPES) LF 75 23.00$ 1,725.00$ 50.00$ 3,750.00$ 66.55$ 4,991.25$ 30.00$ 2,250.00$ 32.49$ 2,436.75$ RAIN GUARDIAN TURRET EA 2 2,700.00$ 5,400.00$ 2,775.00$ 5,550.00$ 1,800.00$ 3,600.00$ 2,500.00$ 5,000.00$ 2,748.49$ 5,496.98$ REMOVE BITUMINOUS PAVEMENT SY 44 8.00$ 352.00$ 6.65$ 292.60$ 10.00$ 440.00$ 5.00$ 220.00$ 17.56$ 772.64$ REMOVE AND REPLACE BITUMINOUS PAVEMENT SY 10 50.00$ 500.00$ 135.00$ 1,350.00$ 75.00$ 750.00$ 75.00$ 750.00$ 183.50$ 1,835.00$ REMOVE CURB AND GUTTER (ALL TYPES) LF 75 7.50$ 562.50$ 13.30$ 997.50$ 25.00$ 1,875.00$ 10.00$ 750.00$ 9.22$ 691.50$ REMOVE FENCE LF 41 10.00$ 410.00$ 24.40$ 1,000.40$ 15.00$ 615.00$ 5.00$ 205.00$ 22.66$ 929.06$ TURF ESTABLISHMENT AC 0.02 50,000.00$ 1,000.00$ 24,000.00$ 480.00$ 13,450.00$ 269.00$ 38,352.00$ 767.04$ 73,441.00$ 1,468.82$ SUBTOTAL SCHEDULE E: $ 14,469.50 SUBTOTAL SCHEDULE E: $ 20,037.50 SUBTOTAL SCHEDULE E: $ 16,447.41 SUBTOTAL SCHEDULE E: $ 13,536.04 SUBTOTAL SCHEDULE E: $ 20,342.98 $ 715,889.60 $ 545,334.83 $ 523,092.40 $ 643,138.90 $ 737,065.67 $ 43,115.00 $ 36,415.90 $ 51,323.76 $ 34,392.90 $ 58,042.62 $ 29,692.20 $ 8,404.50 $ 5,064.53 $ 6,327.19 $ 11,336.93 $ 165,873.00 $ 146,307.30 $ 202,994.01 $ 133,697.00 $ 151,212.61 $ 14,469.50 $ 20,037.50 $ 16,447.41 $ 13,536.04 $ 20,342.98 TOTAL: $ 969,039.30 TOTAL: $ 756,500.03 TOTAL: $ 798,922.11 TOTAL: $ 831,092.03 TOTAL: $ 978,000.81 SCHEDULE A: REPAIRS CITY WIDESCHEDULE B: KING PARK TRAIL RECLAIM AND EXTENSIONSCHEDULE C: DODD PARK TRAIL CULVERT CROSSINGSCHEDULE D: JUNO TRAILSCHEDULE E: CITY HALL TRASH ENCLOSURE