HomeMy WebLinkAboutItem 06.m
Date: October 15, 2018 Item No.
FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
streets and utilities installed with Avonlea Village Green.
Overview
KJPL Development, Inc., requests final acceptance of the public street and utility improvements
installed with the development of Avonlea Village Green. The prime contractor responsible for
the public improvement work was Nova-Frost, Inc.
The public utilities, curb and gutter, and bituminous base-course pavements were constructed in
2017. The bituminous wear-course pavement was constructed in 2018. The public street and
utility improvements for the above-referenced development were tested and inspected by WSB &
Associates and the City’s Public Works Department.
Primary Issues to Consider
• The public street and utility improvements installed with the above-referenced
development were completed consistent with the City’s construction standard
specifications and the administrative requirements for final acceptance.
Supporting Information
• None.
Financial Impact: $0 Budgeted: Y☐ N☐ Source: N/A
Related Documents: (CIP, ERP, etc.):
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer