HomeMy WebLinkAboutItem 06.n Date: November 5, 2018 Item No.
JOINT POWERS AGREEMENT WITH DAKOTA COUNTY
FOR 179TH STREET CONSTRUCTION
Proposed Action
Staff recommends adoption of the following motion: Move to approve Joint Powers Agreement
with Dakota County for the construction of 179th Street through the Knob Hill of Lakeville
development, City Project 18-09.
Overview
The Knob Hill of Lakeville development includes the construction of 179th Street, a future
County State Aid Highway (9), from Fieldcrest Avenue to Pilot Knob Road. The County will
share in the costs of constructing 179th Street to County standards in accordance with the County
policies included in the current adopted Dakota County Transportation Plan. The roadway
construction is scheduled to be completed in 2020. The Joint Powers Agreement (JPA)
establishes City and County project responsibilities and costs.
Primary Issues to Consider
• What is the project financing? Dakota County will reimburse Lakeville the County’s share
of the costs associated with constructing 179th Street to County standards. Lakeville will
subsequently reimburse the Knob Hill of Lakeville Developer Dakota County’s share of
the costs, not to exceed $690,000. The project is included in Dakota County’s adopted
2018-2022 Capital Improvement Program.
Supporting Information
• Joint Powers Agreement (Dakota County Contract No. C0030855)
Financial Impact: $0 Budgeted: Y☐ N☐ Source: N/A
Related Documents: Knob Hill of Lakeville Development Contract
Envision Lakeville Community Values: Design that Connects the Community
Report Completed by: Alex Jordan, Assistant City Engineer
Dakota County Contract C0030855
JOINT POWERS AGREEMENT FOR
ENGINEERING AND HIGHWAY CONSTRUCTION
BETWEEN
THE COUNTY OF DAKOTA
AND
THE CITY OF LAKEVILLE
FOR
COUNTY PROJECT NO. 97-191
CITY PROJECT NO.18-09
SYNOPSIS: Dakota County and the City of Lakeville agree to construct a portion of alignment B of adopted
Dakota County East-West Corridor Preservation Study (dated November 2003), a future County Road (179th
Street), from the intersection at County State Aid Highway (CSAH) 31 (Pilot Knob Road) to 3,200 feet west in
Lakeville, Dakota County.
C.P. 97-191 C0030855
October 16, 2018
2
THIS AGREEMENT, made and entered into by and between the County of Dakota, referred to in this
Agreement as "the County"; and the City of Lakeville, referred to in this Agreement as "the City"; and
witnesses the following:
WHEREAS, under Minnesota Statutes Sections 162.17, subdivision 1 and 471.59, subdivision 1, two or
more governmental units may enter into an Agreement to cooperatively exercise any power common to the
contracting parties, and one of the participating governmental units may exercise one of its powers on behalf
of the other governmental units; and
WHEREAS, it is considered mutually desirable to: a) construct a 3,200-foot segment of Alignment B of
adopted Dakota County East-West Corridor Preservation Study (dated June 2003), a future County Road
(179th Street), as a two-lane divided roadway that will operate safely and efficiently in the future as a County
Road; b) acquire right-of-way (120-foot wide corridor) through dedication; c) construct a full intersection at
179th Street and CSAH 31 (Pilot Knob Road); and d) construct trails along both sides of 179th Street,
hereafter referred to as “the Project”; and
WHEREAS, the adopted preservation corridor Alignment B between Highview Avenue to Trunk Highway 3
follows the proposed transition between 179th Street alignment and 175th Street alignment; and
WHEREAS, County Project (CP) 97-191 includes design, right of way dedication and construction of
approximately one-half mile of a future County road (179th Street) to meet County standards in conjunction
with the Knob Hill of Lakeville development; and
WHEREAS, the City desires to construct the improvements in 2018 and 2019 in conjunction with Knob Hill of
Lakeville’s developer-installed public improvements in anticipation of County reimbursement per polices
included in with the current adopted Dakota County 2030 Transportation Plan; and
WHEREAS, the current adopted Dakota County 2030 Transportation Plan includes Policy F.15 Cost Share
Participation – Future County Road Segments: At County discretion, participate in the construction and
engineering costs for constructing future County roadway segments to County standards, over and above
the costs that would have been incurred to construct the segment to city collector street standards.; and
WHEREAS, the City is the lead agency for CP 97-191; and
WHEREAS, entering into a joint powers agreement (JPA) with the City is necessary to define project costs
and responsibilities and to proceed with the project; and
WHEREAS, the approved 2018 Transportation Capital Improvement Program (CIP) budget includes $
$690,000 for the County share of CP 97-191; and
C.P. 97-191 C0030855
October 16, 2018
3
WHEREAS, the County will reimburse the City for the County’s share of the project costs, per polices
included in the current adopted Dakota County 2030 Transportation Plan, to the extent funds are budgeted
by the County Board; and
WHEREAS, the County will assume jurisdiction and maintenance of future County Road (179th Street) by
separate agreement at such time as the County determines it is appropriate to incorporate this segment of
road into the County highway system.
NOW, THEREFORE, it is agreed that the County and the City will share project responsibilities and jointly
participate in the project costs associated with engineering, highway construction, and related activities as
described in the following sections:
1. Engineering. Design engineering including all aspects of the Project (public involvement, agency
involvement, preliminary/final design etc.), surveying, mapping, construction engineering, construction
management, construction inspection, as-builts, wetland related approvals, and all related materials tes ting,
including the cost of County and City staff time for these purposes .
2. Future County Road Reimbursement. The construction costs for the Project 2-lane divided highway
expansion shall be shared in the amount of forty-eight (48%) by the County and fifty-two (52%) by the City.
The County shall reimburse the City the County’s share of the Project in the amount not to exceed $690,000
for the County share of CP 97-191 construction, design and construction engineering and administration.
This amount is the estimated additional cost of engineering and constructing 179th Street to County
standards.
3. Miscellaneous Elements. General maintenance will be handled in accordance with County policies
included in the current adopted Dakota County Transportation Plan.
4. City Utilities. Except as stated in the above sections of this Agreement, the City shall pay all other
costs for new sanitary sewer, water mains and appurtenances constructed as part of this Project. Further,
the City shall be responsible for the maintenance of all such facilities upon final acceptance of the Project.
5. Design and Construction. The City is the lead agency for the design and construction administration
of this Project, effective upon execution of this Agreement by both Parties. The City and the County shall
approve plans and specifications prior to construction.
6. Construction Standards. All construction, including traffic control, shall be accomplished in
accordance with applicable State Aid and County standards, specifications, and policies to the satisfaction of
the County. The County reserves the right to inspect construction materials and methods as needed. The
County will issue permits for construction within County right-of-way and will waive permit fees. Work on
C.P. 97-191 C0030855
October 16, 2018
4
County right-of-way is not authorized until County permits are approved. Construction shall be performed to
minimize the duration of traffic delays on CSAH 31 and provide for safe and convenient near the project
area.
7. Right-of-Way. The City in partnership with the developer and in a manner consistent with applicable
state laws and rules will acquire all perm anent and temporary highway right-of-way, and right-of-way for
sidewalk and trail construction, wetland damage mitigation and banking, drainage and ponding, water
pollution control best management practices for the Project, sanitary sewer, water mains and appurtenances,
and aesthetic elements. Upon final acceptance of the Project, the ownership of the permanent highway right-
of-way needed for the operation and maintenance of the future County Road shall remain with the City until
such time as the County shall take over jurisdiction and maintenance responsibility. Upon final acceptance
of the Project, the ownership of the drainage and utility easements shall remain with the City.
8. Payment. The City shall request payment for the County’s share of the Project costs under
Paragraph 2, up to a maximum amount of $690,000. The City will provide updated cost estimates to the
County showing the County and City shares of Project costs annually at the time of Capital Improvement
Program development. Updated cost estimates will also be provided by the City to the County at the
following times:
• prior to start of construction,
• quarterly during construction as substantial work is completed,
• once per year following the construction season until the Project is complete.
Project cost estimate updates include actual and estimated costs for engineering and construction.
The Parties acknowledge that Project cost estimates are subject to numerous variables causing the
estimates to be subject to change and the updates are provided for informational purposes in good faith.
Each agency is responsible for informing their respective councils or boards regarding Project cost
estimates.
The City will administer the contract and act as the paying agent for all payments to the contractor.
Payments to the contractor will be made as the project work progresses and when certified by the City
Engineer. The City will request first payment of the Counties share of the Project within the third quarter of
2018. Upon presentation of an itemized claim by the City, the County will reimburse the City for the County’s
share of Project costs within 35 days from the presentation of the claim. If any portion of an itemized claim is
questioned by the receiving agency, the remainder of the claim shall be promptly paid, and accompanied by
a written explanation of the amounts in question. Payment of any amounts in dispute will be made following
good faith negotiation and documentation of actual costs incurred in carrying out the work.
C.P. 97-191 C0030855
October 16, 2018
5
9. Amendments. Any amendments to this Agreement will be effective only after approval by both
governing bodies and execution of a written amendment document by duly authorized officials of each body.
10. Effective Dates. This Agreement will be effective upon execution by duly authorized officials of each
governing body and shall continue in effect until all work to be carried out in accordance with this Agreement
has been completed. Except for on-going maintenance activities including storm water management
systems, sidewalk/trails, landscape and lighting maintenance, in no event will this Agreement continue in
effect after December 31, 2022, unless the parties mutually agree to an extension of the project term.
11. Change Orders and Supplemental Agreements. Any change orders or supplemental agreements
that affect the Project cost participation must be approved by appointed representatives of both Parties prior
to execution of work. For the purposes of this section, the City’s appointed representative is Zach Johnson,
City Engineer, and the County’s appointed representative is Jeannine Briol Construction Engineer, or their
successors. Both Parties shall endeavor to provide timely approval of change orders and supplemental
agreements so as not to delay construction operations.
12. Final acceptance. Final acceptance of the Project must be approved by both the County and the
City.
13. Storm Sewer Maintenance. Upon final acceptance of the Project, maintenance of storm water
management systems shall be provided in accordance with the current County and City Maintenance
Agreement. The County will participate in replacement or repair of storm water management systems
constructed with the Project in accordance with County policies included in the current adopted
Transportation Plan.
14. Sidewalks and Trails. Upon final acceptance of the Project, maintenance of sidewalks and trails
shall be provided in accordance with the current County and City Maintenance Agreement . The County and
the City shall be responsible for the costs of trail resurfacing or reconstruction in accordance with County
policies included in the current adopted Transportation Plan.
15. Pavement Maintenance. Upon final acceptance of the Project, the County shall be responsible for all
pavement maintenance within CSAH 31 right of way unless necessitated by a failure of a municipal utility
system or installation of new facilities. Upon final acceptance of the Project, the City shall be responsible for
all pavement maintenance within 179th Street right of way until such time as the County determines it is
appropriate to incorporate this segment of road into the County highway system. At the time the County
assumes jurisdiction, the County shall be responsible for all pavement maintenance within County right of
way.
C.P. 97-191 C0030855
October 16, 2018
6
16. Rules and Regulations. The County and the City shall abide by Minnesota Department of
Transportation standard specifications, rules and contract administration procedures.
17. Indemnification. The County agrees to defend, indemnify, and hold harmless the City against any
and all claims, liability, loss, damage, or expense arising under the provisions of this Agreement and caused
by or resulting from negligent acts or omissions of the Count y and/or those of County employees or agents.
The City agrees to defend, indemnify, and hold harmless the County against any and all claims, liability, loss,
damage, or expense arising under the provisions of this Agreement for which the City is responsib le,
including future operation and maintenance of facilities owned by the City and caused by or resulting from
negligent acts or omissions of the City and/or those of City employees or agents. All Parties to this
Agreement recognize that liability for any claims arising under this Agreement are subject to the provisions of
the Minnesota Municipal Tort Claims Law; Minnesota Statutes, Chapter 466. In the event of any claims or
actions filed against either party, nothing in this Agreement shall be construed to allow a claimant to obtain
separate judgments or separate liability caps from the individual Parties.
18. Waiver. Any and all persons engaged in the work to be performed by the County shall not be
considered employees of the City for any purpose, including Worker’s Compensation, or any and all claims
that may or might arise out of said employment context on behalf of said employees while so engaged. Any
and all claims made by any third party as a consequence of any act or omission on the part of said Coun ty
employees while so engaged on any of the work contemplated herein shall not be the obligation or
responsibility of the City. The opposite situation shall also apply: the County shall not be responsible under
the Worker’s Compensation Act for any employees of the City.
19. Audits. Pursuant to Minnesota Statutes Sec 16 C. 05, Subd. 5, any books, records, documents, and
accounting procedures and practices of the County and the City relevant to this Agreement are subject to
examination by the County or the City and either the Legislative Auditor or the State Auditor as appropriate.
The County and the City agree to maintain these records for a period of six years from the date of
performance of all services covered under this Agreement.
20. Integration and Continuing Effect. The entire and integrated agreement of the Parties contained in
this Agreement shall supersede all prior negotiations, representations or agreements between the Cit y and
the County regarding the Project; whether written or oral. All agreements for future maintenance or cost
responsibilities shall survive and continue in full force and effect after completion of the highway construction
provided for in this Agreement.
21. Project Timing. It is understood that if the City’s funding partners for the City’s portion of the project
costs withdraw their commitment to fund their portion of the project costs, that neither party will be compelled
to complete the project until such time that the funding issues are resolved.
C.P. 97-191 C0030855
October 16, 2018
7
22. Authorized Representatives. The authorized representatives for the purpose of the administration of
this Agreement are:
Mark Krebsbach (or successor)
Dakota County Transportation Director/County Engineer
14955 Galaxie Avenue
Apple Valley, MN 55124
(952) 891-7102
Zach Johnson (or successor)
City Engineer
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044-8339
(952)-985-4501
All notices or communications required or permitted by this Agreement shall be either hand delivered or
mailed by certified mail, return receipt requested, to the above addresses. Either party may change its
address by written notice to the other party. Mailed notice shall be deemed complete two business days
after the date of mailing.
[SIGNATURE PAGE TO FOLLOW]
N:\Highway\Agreements\2018\97-191 Lakeville C0030855.docx
IN WITNESS THEREOF, the Parties have caused this Agreement to be executed by their duly authorized
officials.
CITY OF LAKEVILLE
RECOMMENDED FOR APPROVAL:
By
City Engineer Douglas P. Anderson, Mayor
(SEAL)
By
Charlene Friedges, City Clerk
Date
------------------------------------------------------------------------------------------------------------------------------------------
DAKOTA COUNTY
RECOMMENDED FOR APPROVAL: APPROVED AS TO FORM:
County Engineer Assistant County Attorney Date
By:
Physical Development Division Director
COUNTY BOARD RESOLUTIONS
No. 18-243 Date: April 24, 2018 Date:
KS18-455
10/22/18