HomeMy WebLinkAboutItem 06.f
Date: April 1, 2019 Item No.
DODD BOULEVARD AND FLAGSTAFF AVENUE INTERSECTION IMPROVEMENTS
AWARD CONTRACT TO S.M. HENTGES & SONS, INC
AUTHORIZE FUNDING AND AMEND 2019 BUDGETS
Proposed Action
Staff recommends adoption of the following motion: Move to award contract to S.M. Hentges &
Sons, Inc. for Dodd Boulevard and Flagstaff Avenue Intersection Improvements, City Project 18-
05; authorize funding and amend 2019 budgets.
Overview
The City and Dakota County are partnering to construct intersection improvements at Dodd
Boulevard and Flagstaff Avenue to improve intersection operations and alleviate congestion, make
safety improvements and provide capacity for increasing traffic levels. Improvements include a
single-lane roundabout, trail and sidewalk, watermain replacement, storm sewer and storm water
management basins.
On Wednesday, February 27, 2019, at 10:00 a.m., the City received two bids for City Project 18-05
ranging from a low bid of $1,939,752.40 submitted by S.M. Hentges and Sons to a high bid of
$2,255,880.50. The engineer’s estimate of the construction cost was $1,758,596.50.
Primary Issues to Consider
• Construction of the improvements will begin June 10, 2019
• Project Financing (see attached)
Supporting Information
• Bid Tabulation, Agreement, Stonebrook Letter of Recommendation (March 27, 2019)
Financial Impact: $2,842,822 Budgeted: Y☒ N☐ Source: Multiple Sources
Related Documents: 2019-2023 City of Lakeville Capital Improvement Plan
Envision Lakeville Community Values: Design that Connects the Community
Report Completed by: Zach Johnson, City Engineer
Primary Issues to Consider
Project Financing
The City’s 2019 Capital Improvement Plan programs an estimated project cost of $1,850,000 in
2019, plus 2017 and 2018 encumbrances of $597,336, for a total estimated project cost of
$2,447,335. The increased estimated project cost is due to the addition of trunk water main
replacement within the project area, construction of new stormwater management basins adjacent
to the intersection, and existing unsuitable soils under the roadway requiring substantial
correction. The watermain replacement and stormwater management items are incorporated into
the CP 18-05 contract to minimize construction and schedule impacts, and to achieve cost and
construction efficiencies.
The City is the lead agency; therefore, the total estimated project cost (both City and County share)
is reflected in this memo. The County will reimburse the City 55% of the project costs, consistent
with the project’s Joint Powers Agreement (after consideration of grant funding and non-
participating utility costs).
The City applied for and was awarded $775,000 in Local Road Improvement Program (LRIP) funds
for construction of the improvements. The LRIP funding is shared between the City and County
and reduces overall project costs below those identified in the City’s Capital Improvement Plan.
Anticipated funding sources are shown below.
Funding Sources Amount
Municipal State Aid $699,334
Dakota County $1,075,475
Water Operating Fund $137,848
Sanitary Sewer Operating Fund $4,020
Storm Water Infrastructure Fund $151,145
LRIP Grant $775,000
Total $2,842,822
CITY OF LAKEVILLE
RESOLUTION NO. 19-__
RESOLUTION AWARDING CONTRACT FOR
DODD BOULEVARD AND FLAGSTAFF AVENUE INTERSECTION IMPROVEMENTS
CITY PROJECT 18-05
WHEREAS, the City of Lakeville received sealed bids on Wednesday, February 27, 2019, at 10:00
a.m. for Dodd Boulevard and Flagstaff Avenue Intersection Improvements, City Project 18-05; and
WHEREAS, the lowest responsible bid was from S.M. Hentges & Sons, Inc.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Lakeville,
Minnesota:
Hereby awards the contract to the lowest responsible bidder that meets all the bid requirements,
S.M. Hentges & Sons, Inc., with a bid in the amount of $1,939,752.40. The construction is proposed
to be completed as specified in the contract documents.
ADOPTED by the Lakeville City Council this 1st day of April 2019.
Douglas P. Anderson, Mayor
Charlene Friedges, City Clerk
CITY OF LAKEVILLE
RESOLUTION NO. 19-
RESOLUTION AUTHORIZING FUNDING FOR
DODD BOULEVARD AND FLAGSTAFF AVENUE INTERSECTION IMPROVEMENTS
CITY PROJECT 18-05
WHEREAS, the Dodd Boulevard and Flagstaff Avenue Intersection Improvements, City Project
18-05, is programmed in the adopted 2019-2023 Capital Improvement Plan.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Lakeville, Minnesota:
The estimated project cost is $2,842,822 and anticipated funding sources are listed below. City
staff is hereby authorized to amend the 2019 budgets and make the appropriate transfers between
funds with respect to the project funding sources up to 10% above the estimated costs. Funding
transfers may include loans between funds to cover engineering and other costs incurred on the
project in advance of receiving other funding.
Funding Sources Amount
Municipal State Aid $699,334
Dakota County $1,075,475
Water Operating Fund $137,848
Sanitary Sewer Operating Fund $4,020
Storm Water Infrastructure Fund $151,145
LRIP Grant $775,000
Total $2,842,822
ADOPTED by the Lakeville City Council this 1st day of April 2019.
______________________________
Douglas P. Anderson, Mayor
_________________________________
Charlene Friedges, City Clerk
I:\CC Drafts\CP18-05_Dodd Flagstaff Recommendation Letter.docx 1
March 28, 2019
Attn: Joe Powers
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044
Dear Mr. Powers :
The City of Lakeville has compiled the attached bid results for the CSAH 9 (Dodd Blvd) & Flagstaff
Avenue Reconstruction Project. The results of the bid were as follows:
Bidder Total Base Bid
SM Hentges & Sons, Inc. $1,939,752.40
McNamara Contracting, Inc. $2,255,880.50
This compares to the Engineer’s Estimate as follows:
Engineer’s Estimate $1,758,596.50
The low bid result was approximately 10% higher than the Engineer’s Estimate. Based on discussion
with City Staff and general observation of the construction industry, a few possible reasons for this
include:
• There are significant very sensitive underground and overhead private utilities on this project –
more so than a typical intersection in Lakeville. The contractor likely bid a factor of safety to
account for these challenges, but it is difficult to predict what that factor is going to be.
• The schedule is aggressive, with a mid-June start and a late-August finish. Given the challenges
with private utilities, along with necessary soil corrections, this may have also driven up project
costs.
• There is quite a bit of work available to road contractors. It is possible this is allowing
Contractors to be more selective with what projects they bid, as may have been representative
on this project (there were 17 prime plan holders with only 2 bidders).
If the City of Lakeville chooses to award this project to the low bidder based on total base bid, we
recommend awarding to SM Hentges & Sons, Inc. at a total bid amount of $1,939,752.40.
a 12279 Nicollet Avenue Burnsville, MN 55337
o 952.402.9202 f 952.403.6803
w stonebrookeengineering.com
I:\CC Drafts\CP18-05_Dodd Flagstaff Recommendation Letter.docx 2
If you have any questions, please feel free to give us a call to discuss.
Sincerely,
Tyler Newhall, PE
Project Manager
ABSTRACT OF BIDS* bid amount changed due to found calculation/addition errorDODD FLAGSTAFF ROUNDABOUTCITY OF LAKEVILLES.A.P. 188-117-004/019-609-024CITY PROJECT 18-05BID DATE: 2/27/2019TIME: 10:00AMITEM APPROX.NO. ITEM QUANT.UNITUNIT PRICEAMOUNTUNIT PRICEAMOUNTUNIT PRICEAMOUNT1 MOBILIZATION1.00LS$84,000.00$84,000.00 $156,500.00 $156,500.00 $145,000.00 $145,000.002 CLEARING0.40AC$4,000.00$1,600.00 $5,100.00 $2,040.00 $6,200.00 $2,480.003 GRUBBING0.40AC$4,000.00$1,600.00 $3,350.00 $1,340.00 $3,500.00 $1,400.004 CLEARING14.00TREE$300.00$4,200.00 $300.00 $4,200.00 $310.00 $4,340.005 GRUBBING14.00TREE$300.00$4,200.00 $200.00 $2,800.00 $205.00 $2,870.006 REMOVE GATE VALVE & BOX4.00EA$100.00$400.00 $150.00 $600.00 $275.00 $1,100.007 REMOVE HYDRANT1.00EA$500.00$500.00 $305.00 $305.00 $800.00 $800.008 REMOVE DRAINAGE STRUCTURE5.00EA$300.00$1,500.00 $410.00 $2,050.00 $550.00 $2,750.009 REMOVE SIGN TYPE C22.00EA$30.00$660.00 $30.00 $660.00 $32.00 $704.0010 REMOVE MAIL BOX SUPPORT1.00EA$50.00$50.00 $75.00 $75.00 $80.00 $80.0011 SALVAGE SIGN TYPE C2.00EA$40.00$80.00 $46.00 $92.00 $50.00 $100.0012 SAWING CONCRETE PAVEMENT (FULL DEPTH)23.00LF$4.00$92.00 $7.00 $161.00 $20.00 $460.0013 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)532.00LF$4.00$2,128.00 $3.00 $1,596.00 $3.00 $1,596.0014 REMOVE WATER MAIN1019.00LF$10.00$10,190.00 $11.25 $11,463.75 $7.00 $7,133.0015 REMOVE SEWER PIPE (STORM)89.00LF$12.00$1,068.00 $13.65 $1,214.85 $11.00 $979.0016 REMOVE CURB & GUTTER1818.00LF$4.00$7,272.00 $2.25 $4,090.50 $4.00 $7,272.0017 REMOVE WATER SERVICE PIPE34.00LF$6.00$204.00 $10.00 $340.00 $20.00 $680.0018 REMOVE CONCRETE DRIVEWAY PAVEMENT28.00SY$10.00$280.00 $13.25 $371.00 $35.00 $980.0019 REMOVE BITUMINOUS DRIVEWAY PAVEMENT939.00SY$7.00$6,573.00 $3.50 $3,286.50 $4.50 $4,225.5020 REMOVE BITUMINOUS PAVEMENT8179.00SY$2.50$20,447.50 $3.00 $24,537.00 $2.50 $20,447.5021 REMOVE BITUMINOUS WALK7821.00SF$1.00$7,821.00 $0.25 $1,955.25 $0.50 $3,910.5022 REMOVE CONCRETE WALK2174.00SF$1.00$2,174.00 $0.50 $1,087.00 $1.00 $2,174.0023 ABANDON WATER MAIN147.00LF$10.00$1,470.00 $18.50 $2,719.50 $12.00 $1,764.0024 EXCAVATION - COMMON11359.00CY$8.00$90,872.00 $15.00 $170,385.00 $20.00 $227,180.0025 EXCAVATION - SUBGRADE9021.00CY$9.00$81,189.00 $5.00 $45,105.00 $15.00 $135,315.0026 EXCAVATION - CHANNEL AND POND4390.00CY$7.00$30,730.00 $7.50 $32,925.00 $23.00 $100,970.0027 SELECT GRANULAR EMBANKMENT (CV)13018.00CY$15.00$195,270.00 $11.15 $145,150.70 $15.00 $195,270.0028 COMMON EMBANKMENT (CV)4824.00CY$3.00$14,472.00 $7.00 $33,768.00 $15.00 $72,360.0029 SUBGRADE PREPARATION22.00RS$100.00$2,200.00 $745.00 $16,390.00 $1,000.00 $22,000.0030 AGGREGATE SURFACING CLASS 1113.00TON$15.00$1,695.00 $28.00 $3,164.00 $50.00 $5,650.0031 STREET SWEEPER (WITH PICKUP BROOM)30.00HR$135.00$4,050.00 $165.00 $4,950.00 $150.00 $4,500.0032 WATER60.00MGAL$40.00$2,400.00 $50.00 $3,000.00 $80.00 $4,800.0033 AGGREGATE BASE CLASS 57469.00TON$16.00$119,504.00 $11.00 $82,159.00 $21.00 $156,849.0034 CONCRETE PAVEMENT 8.0"647.00SY$70.00$45,290.00 $71.00 $45,937.00 $70.00 $45,290.0035 DRILL & GROUT REINFORCEMENT BAR (EPOXY COATED)97.00EA$12.00$1,164.00 $25.00 $2,425.00 $10.00 $970.0036 TYPE SP 9.5 WEARING COURSE MIXTURE (2,B)373.00TON$80.00$29,840.00 $81.00 $30,213.00 $80.00 $29,840.0037 TYPE SP 12.5 WEARING COURSE MIXTURE (3,C)2030.00TON$60.00$121,800.00 $64.00 $129,920.00 $60.00 $121,800.0038 TYPE SP 12.5 NON WEARING COURSE MIXTURE (3,B)1016.00TON$57.00$57,912.00 $59.00 $59,944.00 $56.00 $56,896.00SM Hentges & Sons, Inc McNamara Contracting, IncEngineer's Estimate
ABSTRACT OF BIDS* bid amount changed due to found calculation/addition errorDODD FLAGSTAFF ROUNDABOUTCITY OF LAKEVILLES.A.P. 188-117-004/019-609-024CITY PROJECT 18-05BID DATE: 2/27/2019TIME: 10:00AMITEM APPROX.NO. ITEM QUANT.UNITUNIT PRICEAMOUNTUNIT PRICEAMOUNTUNIT PRICEAMOUNTSM Hentges & Sons, Inc McNamara Contracting, IncEngineer's Estimate39 FINE AGGREGATE BEDDING (CV)58.00CY$32.00$1,856.00 $35.00 $2,030.00 $21.00 $1,218.0040 15" RC PIPE APRON3.00EA$700.00$2,100.00 $895.00 $2,685.00 $1,000.00 $3,000.0041 18" RC PIPE APRON1.00EA$900.00$900.00 $950.00 $950.00 $1,100.00 $1,100.0042 21" RC PIPE APRON2.00EA$1,200.00$2,400.00 $1,000.00 $2,000.00 $6,000.00 $12,000.0043 24" RC PIPE APRON1.00EA$1,500.00$1,500.00 $3,550.00 $3,550.00 $6,150.00 $6,150.0044 21" RC PIPE CULVERT DES 3006 CL III72.00LF$60.00$4,320.00 $67.50 $4,860.00 $60.00 $4,320.0045 TRASH GUARD FOR 18" APRON1.00LF$400.00$400.00 $450.00 $450.00 $525.00 $525.0046 TRASH GUARD FOR 21" APRON2.00LF$500.00$1,000.00 $525.00 $1,050.00 $675.00 $1,350.0047 TRASH GUARD FOR 24" APRON1.00EA$600.00$600.00 $645.00 $645.00 $800.00 $800.0048 4" INSULATION8.00EA$40.00$320.00 $48.50 $388.00 $50.00 $400.0049 15" RC PIPE SEWER DES 3006 CL V1387.00LF$40.00$55,480.00 $91.25 $126,563.75 $60.00 $83,220.0050 18" RC PIPE SEWER DES 3006 CL V199.00LF$52.00$10,348.00 $57.00 $11,343.00 $63.00 $12,537.0051 24" RC PIPE SEWER DES 3006 CL III71.00LF$70.00$4,970.00 $110.00 $7,810.00 $74.00 $5,254.0052 CONSTRUCT BULKHEAD3.00EA$500.00$1,500.00 $405.00 $1,215.00 $375.00 $1,125.0053 CONNECT TO EXISTING STORM SEWER3.00EA$1,500.00$4,500.00 $890.00 $2,670.00 $2,800.00 $8,400.0054 CONNECT INTO EXISTING DRAINAGE STRUCTURE1.00EA$4,000.00$4,000.00 $1,320.00 $1,320.00 $3,200.00 $3,200.0055 CONNECT TO EXISTING SANITARY SEWER SERVICE1.00EA$1,800.00$1,800.00 $500.00 $500.00 $1,500.00 $1,500.0056 CONNECT TO EXISTING MANHOLES (SAN)1.00EA$2,000.00$2,000.00 $1,650.00 $1,650.00 $1,600.00 $1,600.0057 CAP SANITARY SEWER SERVICE1.00EA$200.00$200.00 $500.00 $500.00 $250.00 $250.0058 RECONSTRUCT SANITARY STRUCTURE8.00LF$400.00$3,200.00 $410.00 $3,280.00 $550.00 $4,400.0059 4" PVC SANITARY SERVICE PIPE5.00LF$50.00$250.00 $54.00 $270.00 $200.00 $1,000.0060 4" INSIDE DROP10.00LF$400.00$4,000.00 $160.00 $1,600.00 $90.00 $900.0061 18" HDPE PIPE SEWER-DIRECTIONAL DRILLED38.00LF$500.00$19,000.00 $540.00 $20,520.00 $600.00 $22,800.0062 IRRIGATION SYSTEM1.00LS$12,000.00$12,000.00 $17,500.00 $17,500.00 $16,000.00 $16,000.0063 TEMPORARY WATER SERVICE1.00LS$5,000.00$5,000.00 $3,725.00 $3,725.00 $7,000.00 $7,000.0064 CONNECT TO EXISTING WATER MAIN3.00EA$1,500.00$4,500.00 $1,400.00 $4,200.00 $1,400.00 $4,200.0065 CONNECT TO EXISTING WATER SERVICE1.00EA$800.00$800.00 $725.00 $725.00 $500.00 $500.0066 HYDRANT2.00EA$5,000.00$10,000.00 $4,300.00 $8,600.00 $5,000.00 $10,000.0067 ADJUST VALVE BOX1.00EA$300.00$300.00 $315.00 $315.00 $500.00 $500.0068 2" CORPERATION STOP1.00EA$500.00$500.00 $500.00 $500.00 $525.00 $525.0069 6" GATE VALVE & BOX3.00EA$2,500.00$7,500.00 $1,600.00 $4,800.00 $2,900.00 $8,700.0070 8" GATE VALVE & BOX1.00EA$3,000.00$3,000.00 $2,150.00 $2,150.00 $3,300.00 $3,300.0071 12" GATE VALVE & BOX1.00EA$3,500.00$3,500.00 $3,425.00 $3,425.00 $4,700.00 $4,700.0072 1" CURB STOP & BOX1.00EA$350.00$350.00 $410.00 $410.00 $800.00 $800.0073 2" CURB STOP & BOX1.00EA$500.00$500.00 $665.00 $665.00 $800.00 $800.0074 ANODE BAG2.00EA$250.00$500.00 $320.00 $640.00 $200.00 $400.0075 1" TYPE K COPPER PIPE70.00LF$30.00$2,100.00 $35.25 $2,467.50 $28.00 $1,960.0076 2" TYPE K COPPER PIPE10.00LF$50.00$500.00 $54.50 $545.00 $70.00 $700.00
ABSTRACT OF BIDS* bid amount changed due to found calculation/addition errorDODD FLAGSTAFF ROUNDABOUTCITY OF LAKEVILLES.A.P. 188-117-004/019-609-024CITY PROJECT 18-05BID DATE: 2/27/2019TIME: 10:00AMITEM APPROX.NO. ITEM QUANT.UNITUNIT PRICEAMOUNTUNIT PRICEAMOUNTUNIT PRICEAMOUNTSM Hentges & Sons, Inc McNamara Contracting, IncEngineer's Estimate77 6" WATERMAIN DUCTILE IRON CL 5224.00LF$50.00$1,200.00 $49.00 $1,176.00 $75.00 $1,800.0078 6" WATERMAIN HDPE (DIRECTIONAL DRILLED)71.00LF$100.00$7,100.00 $166.00 $11,786.00 $225.00 $15,975.0079 6" PVC WATERMAIN65.00LF$40.00$2,600.00 $83.00 $5,395.00 $44.00 $2,860.0080 8" PVC WATERMAIN396.00LF$45.00$17,820.00 $29.50 $11,682.00 $38.00 $15,048.0081 12" PVC WATERMAIN568.00LF$50.00$28,400.00 $85.00 $48,280.00 $48.00 $27,264.0082 DUCTILE IRON FITTINGS591.00LB$10.00$5,910.00 $18.50 $10,933.50 $12.00 $7,092.0083 ADJUST FRAME & RING CASTING4.00EA$400.00$1,600.00 $375.00 $1,500.00 $500.00 $2,000.0084 CASTING ASSEMBLY26.00EA$800.00$20,800.00 $680.00 $17,680.00 $700.00 $18,200.0085 CONSTRUCT DRAINAGE STRUCTURE DESIGN H3.40LF$300.00$1,020.00 $240.00 $816.00 $470.00 $1,598.0086 CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-402035.90LF$500.00$17,950.00 $360.00 $12,924.00 $475.00 $17,052.5087 CONSTRUCT DRAINAGE STRUCTURE DESIGN 96-402010.30LF$1,000.00$10,300.00 $1,235.00 $12,720.50 $1,425.00 $14,677.5088 CONSTRUCT DRAINAGE STRUCTURE DESIGN 2' X 3'19.80LF$350.00$6,930.00 $310.00 $6,138.00 $625.00 $12,375.0089 CONSTRUCT DRAINAGE STRUCTURE DESIGN 48-402253.30LF$500.00$26,650.00 $420.00 $22,386.00 $600.00 $31,980.0090 CONSTRUCT DRAINAGE STRUCTURE DESIGN 72-40224.60LF$850.00$3,910.00 $1,015.00 $4,669.00 $1,850.00 $8,510.0091 CONSTRUCT DRAINAGE STRUCTURE DESIGN SPECIAL 11.00EA$2,000.00$2,000.00 $4,100.00 $4,100.00 $4,600.00 $4,600.0092 RANDOM RIPRAP CLASS III55.00CY$100.00$5,500.00 $82.00 $4,510.00 $115.00 $6,325.0093 5" CONCRETE WALK839.00SF$5.00$4,195.00 $6.25 $5,243.75 $10.00 $8,390.0094 6" CONCRETE WALK2997.00SF$12.00$35,964.00 $13.00 $38,961.00 $11.00 $32,967.0095 CONCRETE CURB & GUTTER DESIGN SPECIAL150.00LF$25.00$3,750.00 $55.00 $8,250.00 $46.00 $6,900.0096 CONCRETE CURB & GUTTER DESIGN B612327.00LF$20.00$6,540.00 $20.00 $6,540.00 $15.00 $4,905.0097 CONCRETE CURB & GUTTER DESIGN B6184401.00LF$15.00$66,015.00 $23.50 $103,423.50 $14.00 $61,614.0098 CONCRETE CURB & GUTTER DESIGN D418553.00LF$20.00$11,060.00 $24.25 $13,410.25 $17.00 $9,401.0099 CONCRETE MEDIAN919.00SY$45.00$41,355.00 $45.00 $41,355.00 $34.00 $31,246.00100 7" CONCRETE DRIVEWAY PAVEMENT81.00SY$70.00$5,670.00 $81.00 $6,561.00 $97.00 $7,857.00101 TRUNCATED DOMES394.00SF$40.00$15,760.00 $47.00 $18,518.00 $45.00 $17,730.00102 RELOCATE FLAGPOLE1.00EA$1,000.00$1,000.00 $5,000.00 $5,000.00 $1,500.00 $1,500.00103 MAIL BOX SUPPORT1.00EA$200.00$200.00 $260.00 $260.00 $300.00 $300.00104 RELOCATE MAIL BOX SUPPORT1.00EA$100.00$100.00 $155.00 $155.00 $160.00 $160.00105 HANDOLE8.00EA$715.00$5,720.00 $715.00 $5,720.00 $1,800.00 $14,400.00106 INSTALL 1.5" NON METALLIC CONDUIT1100.00LF$4.10$4,510.00 $4.10 $4,510.00 $6.00 $6,600.00107 GUIDE POST TYPE B7.00EA$50.00$350.00 $75.00 $525.00 $80.00 $560.00108 TRAFFIC CONTROL SUPERVISOR1.00LS$5,000.00$5,000.00 $5,000.00 $5,000.00 $3,200.00 $3,200.00109 TRAFFIC CONTROL1.00LS$15,000.00$15,000.00 $30,600.00 $30,600.00 $32,000.00 $32,000.00110 INSTALL SIGN TYPE C2.00EA$150.00$300.00 $75.00 $150.00 $80.00 $160.00111 SIGN PANELS TYPE C455.00SF$50.00$22,750.00 $58.00 $26,390.00 $60.00 $27,300.00112 SIGN PANELS TYPE D15.00SF$50.00$750.00 $86.50 $1,297.50 $90.00 $1,350.00113 CONIFEROUS TREE 6' HT B & B3.00TREE$600.00$1,800.00 $505.00 $1,515.00 $525.00 $1,575.00114 DECIDUOUS TREE 1.5" CAL B & B5.00TREE$600.00$3,000.00 $570.00 $2,850.00 $525.00 $2,625.00
ABSTRACT OF BIDS* bid amount changed due to found calculation/addition errorDODD FLAGSTAFF ROUNDABOUTCITY OF LAKEVILLES.A.P. 188-117-004/019-609-024CITY PROJECT 18-05BID DATE: 2/27/2019TIME: 10:00AMITEM APPROX.NO. ITEM QUANT.UNITUNIT PRICEAMOUNTUNIT PRICEAMOUNTUNIT PRICEAMOUNTSM Hentges & Sons, Inc McNamara Contracting, IncEngineer's Estimate115 PERENNIAL 1 GAL CONT317.00SHRUB$35.00$11,095.00 $13.50 $4,279.50 $23.00 $7,291.00116 PERENNIAL 1 GAL CONT801.00PLANT$35.00$28,035.00 $13.50 $10,813.50 $19.00 $15,219.00117 PERENNIAL 1 GAL CONT317.00PLANT$35.00$11,095.00 $13.50 $4,279.50 $21.00 $6,657.00118 TEMPORARY FENCE879.00LF$5.00$4,395.00 $1.50 $1,318.50 $2.00 $1,758.00119 CLEAN ROOT CUTTING600.00LF$8.00$4,800.00 $6.00 $3,600.00 $4.00 $2,400.00120 STABILIZED CONSTRUCTION EXIT1.00LS$2,000.00$2,000.00 $4,200.00 $4,200.00 $1,500.00 $1,500.00121 EROSION CONTROL SUPERVISOR1.00LS$2,500.00$2,500.00 $13,500.00 $13,500.00 $1,000.00 $1,000.00122 WATER TREATMENT TYPE ROCK WEEPER1.00EA$1,000.00$1,000.00 $850.00 $850.00 $1,900.00 $1,900.00123 STORM DRAIN INLET PROTECTION27.00EA$300.00$8,100.00 $170.00 $4,590.00 $125.00 $3,375.00124 CULVERT END CONTROLS3.00EA$175.00$525.00 $75.00 $225.00 $500.00 $1,500.00125 SEDIMENT CONTROL LOG TYPE COMPOST130.00LF$3.00$390.00 $2.25 $292.50 $5.00 $650.00126 SILT FENCE, TYPE MS1365.00LF$2.00$2,730.00 $1.75 $2,388.75 $2.00 $2,730.00127 SUBSOILING3.70AC$350.00$1,295.00 $315.00 $1,165.50 $500.00 $1,850.00128 SOIL BED PREPARATION3.70AC$200.00$740.00 $87.00 $321.90 $200.00 $740.00129 COMMON TOPSOIL BORROW500.00CY$33.00$16,500.00 $26.00 $13,000.00 $31.00 $15,500.00130 COMPOST GRADE 274.00CY$50.00$3,700.00 $56.00 $4,144.00 $30.00 $2,220.00131 FILTER TOPSOIL BORROW490.00CY$75.00$36,750.00 $33.00 $16,170.00 $29.00 $14,210.00132 FERTILIZER TYPE 31062.00LB$0.60$637.20 $0.50 $531.00 $0.50 $531.00133 FERTILIZER TYPE 479.00LB$0.70$55.30 $0.50 $39.50 $2.00 $158.00134 EROSION CONTROL BLANKETS CATEGORY 3N7029.00SY$2.00$14,058.00 $1.20 $8,434.80 $1.00 $7,029.00135 RAPID STABILIZATION METHOD 47029.00SY$1.50$10,543.50 $1.30 $9,137.70 $1.00 $7,029.00136 SEEDING3.70AC$100.00$370.00 $77.00 $284.90 $125.00 $462.50137 SEED MIXTURE 25-131352.00LB$3.00$1,056.00 $2.60 $915.20 5 $1,760.00138 SEED MIXTURE 25-141167.00LB$3.00$501.00 $3.25 $542.75 5 $835.00139 SEED MIXTURE 25-15120.00LB$3.00$60.00 $3.00 $60.00 10 $200.00140 SEED MIXTURE 33-26128.00LB$22.00$616.00 $28.00 $784.00 35 $980.00141 HYDRAULIC REINFORCED FIBER MATRIX8184.00LB$1.00$8,184.00 $1.15 $9,411.60 1.25 $10,230.00142 RAPID STABILIZATION METHOD 326.00MGAL$400.00$10,400.00 $102.00 $2,652.00 700 $18,200.00143 LANDSCAPE ROCK34.00CY$75.00$2,550.00 $165.00 $5,610.00 125 $4,250.00144 LANDSCAPE ROCK56.00CY$75.00$4,200.00 $163.00 $9,128.00 125 $7,000.00145 4" SOLID LINE MULTI-COMPONENT (WR)2370.00LF$0.30$711.00 $0.60 $1,422.00 0.6 $1,422.00146 24" SOLID LINE MULTI-COMPONENT (WR)120.00LF$12.00$1,440.00 $9.25 $1,110.00 10 $1,200.00147 4" DOUBLE SOLID LINE MULTI-COMPONENT (WR)1690.00LF$0.60$1,014.00 $1.25 $2,112.50 1.25 $2,112.50148 4" SOLID LINE PREFORM TAPE (WR)3250.00LF$3.00$9,750.00 $3.45 $11,212.50 3.5 $11,375.00149 4" DOTTED LINE PREFORM TAPE (WR)60.00LF$3.00$180.00 $3.45 $207.00 3.5 $210.00150 18" DOTTED LINE PREFORM TAPE (WR)90.00LF$15.00$1,350.00 $20.00 $1,800.00 11 $990.00151 PAVEMENT MESSAGE PREFORM TAPE (WR)100.00SF$15.00$1,500.00 $16.00 $1,600.00 17 $1,700.00
ABSTRACT OF BIDS* bid amount changed due to found calculation/addition errorDODD FLAGSTAFF ROUNDABOUTCITY OF LAKEVILLES.A.P. 188-117-004/019-609-024CITY PROJECT 18-05BID DATE: 2/27/2019TIME: 10:00AMITEM APPROX.NO. ITEM QUANT.UNITUNIT PRICEAMOUNTUNIT PRICEAMOUNTUNIT PRICEAMOUNTSM Hentges & Sons, Inc McNamara Contracting, IncEngineer's Estimate152 CROSSWALK PREFORM TAPE (WR)580.00SF$15.00$8,700.00 $12.50 $7,250.00 13 $7,540.00TOTAL: $1,758,596.50 $1,939,752.40 $2,255,880.50