Date: April 15, 2019 Item No.
FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
BERRES RIDGE 3RD ADDITION
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
streets and utilities installed with Berres Ridge 3r d Addition.
Overview
Berres Ridge Development Co, LLC requests final acceptance of the public street and utility
improvements installed with the development of Berres Ridge 3rd Addition. The prime
contractor responsible for the public improvement work was Friedges Contracting Company.
The public utilities, curb and gutter, and bituminous base-course pavement were constructed in
2017. The bituminous wear-course pavement was constructed in 2018. The public street and
utility improvements for the development were tested and inspected by WSB and the City’s
Public Works Department.
Primary Issues to Consider
• The public street and utility improvements installed with the development were
completed consistent with the City’s construction standard specifications and the
administrative requirements for final acceptance.
Supporting Information
• None.
Financial Impact: $0 Budgeted: Y☐ N☐ Source: N/A
Related Documents:
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer