HomeMy WebLinkAboutItem 06.n Date: Item No.
ACCEPT PROPOSAL FROM BRAUN INTERTEC FOR PROFESSIONAL SERVICES FOR
DODD BOULEVARD AND FLAGSTAFF AVENUE INTERSECTION IMPROVEMENTS
Proposed Action
Staff recommends adoption of the following motion: Move to accept Braun Intertec’s proposal for
professional services on the Dodd Boulevard and Flagstaff Avenue Intersection Improvements,
City Project 18-05.
Overview
The City and Dakota County are partnering to construct intersection improvements at Dodd
Boulevard and Flagstaff Avenue to improve intersection operations and alleviate congestion, make
safety improvements and provide capacity for increasing traffic levels. Improvements include a
single-lane roundabout, trail and sidewalk, watermain replacement and storm water management
improvements. The City Council awarded the construction contract to S.M. Hentges & Sons on
April 1, 2019. The project begins on June 10, 2019 and should be substantially complete by August
30, 2019.
Braun Intertec submitted a proposal to provide materials testing and laboratory inspection
consistent with the Minnesota Department of Transportation’s Schedule of Materials Control.
Primary Issues to Consider
• The City is the lead agency; therefore, the total estimated cost of $31,585 for the
professional services (both City and County share) is reflected in this memo. The County
will reimburse the City 55% of the costs, consistent with the project’s Joint Powers
Agreement.
Supporting Information
• Braun Intertec proposal dated March 18, 2019
Financial Impact: $31,585 Budgeted: Y☒ N☐ Source: Multiple Funds
Related Documents: Lakeville 5-year Capital Improvement Plan
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer
June 3, 2019
AA/EOE
Braun Intertec Corporation
11001 Hampshire Avenue S
Minneapolis, MN 55438
Phone: 952.995.2000
Fax: 952.995.2020
Web: braunintertec.com
March 18, 2019 Proposal QTB095616
Joseph Powers, PE
City of Lakeville
20195 Holyoke Avenue
Lakeville, MN 55044
Re: Proposal for Construction Materials Testing Services
County State Aid Highway 9 (Dodd Boulevard) & Flagstaff Avenue Reconstruction
S.A.P. 019-609-024, S.A.P. 188-117-004, City Project No. 9-54
Dodd Boulevard at Flagstaff Avenue
Lakeville, Minnesota
Dear Mr. Powers:
Braun Intertec Corporation is pleased to submit this proposal to provide construction materials testing
services for the County State Aid Highway (CSAH) 9 (Dodd Boulevard) and Flagstaff Avenue
Reconstruction Project in Lakeville, Minnesota.
We have completed the geotechnical evaluation for the Dodd Boulevard and Flagstaff Avenue
Reconstruction Project, so we have a unique understanding of the site and construction challenges. We
can aid the construction team by applying this experience and transferring our knowledge developed
during the design phase which will provide professional continuity to the construction. Our work on the
project to date gives us familiarity with the project team and design development which allows us to
understand some of the considerations used when developing the project’s design.
Since our inception in 1957, we have grown into one of the largest employee owned engineering firms in
the nation. With around 1,000 employee owners, retaining our firm gives you access to a diverse range of
services and professionals you can consult with if the unforeseen occurs. The size of our company also
allows us to respond quickly when schedule constraints occur.
Our Understanding of Project
We understand this project will include the construction of a roundabout at the intersection of Dodd
Boulevard and Flagstaff Avenue. The construction will include pavement subgrade preparation,
aggregate base and select granular borrow placement, new concrete curb and gutter, sidewalk, medians,
driveways, and new bituminous pavement. This project will also include improvements to the watermain
and storm sewer utilities.
This project is a City of Lakeville project with state-aid funding. Projects that are constructed with state-
aid funding are required to perform Quality Control and Quality Assurance (QC/QA) testing in accordance
with the Minnesota Department of Transportation’s (MnDOT’s) 2018 Standard Specifications for
Construction along with MnDOT’s Schedule of Materials Control. This project is using MnDOT’s 2018
State Aid for Local Transportation (SALT) Schedule of Materials Control. Personnel with MnDOT
City of Lakeville
Proposal QTB095616
March 18, 2019
Page 2
certifications must complete the monitoring and testing. Braun Intertec will perform the QA field testing
on the project as listed in our scope of services and as shown on our attached cost estimate table. The
contractor will be responsible for performing all of the required QC testing and submitting all the
documentation upon completion of the project. An audit of the project could be conducted upon
completion. The audit may include reviewing tests and paperwork provided by your QC/QA
representative.
Available Project Information
This proposal was prepared using the following documents and information.
Project plans and specifications prepared by Stonebrooke Engineering, Inc. dated January 16,
2019 and January 30, 2019 respectively.
Project Addendum numbered 1, dated February 20, 2019.
A Geotechnical Evaluation Report (B1711465) prepared by Braun Intertec Corporation.,
dated December 17, 2018.
Braun Intertec Project Personnel
For this project, we will provide technicians that are MnDOT certified in each specialized field. For the
proposed scope of services, our staff will have the following certifications:
Aggregate Production
Grading & Base I
Concrete Field I
Bituminous Street
Bituminous Plant I
MnDOT or ACI Strength Testing
Accredited Laboratory
In the 2018 SALT Schedule of Material Control, which is part of this project’s testing requirements,
MnDOT requires laboratories performing acceptance tests for payment to be accredited by the AASHTO
Resource (formerly AASHTO Materials Reference Laboratory [AMRL]) for all test procedures performed.
Braun Intertec is one of the few independent testing companies that is accredited in the metro area.
With Braun Intertec’s Metro Material Laboratory typically operating 24 hours a day, laboratory test
results are delivered in a timely manner.
Scope of Services
Testing services will be performed on an on-call, as-needed basis as requested and scheduled by you or
your on-site project personnel. Based on our understanding of the project, we propose the following
services.
City of Lakeville
Proposal QTB095616
March 18, 2019
Page 3
Soil Related Services
Perform nuclear gauge density tests on sub-grade, embankment, and utility backfill
materials.
Perform Dynamic Cone Penetrometer (DCP) tests on select granular borrow and aggregate
base materials.
Perform moisture content tests at time of compaction on backfill, fill and aggregate base
materials.
Perform gradation tests on select granular borrow, aggregate base and fine aggregate
bedding materials.
Perform laboratory standard Proctor tests on backfill and fill materials.
Prepare the preliminary and final grading and base report along with assembling the random
sampling locations report for the aggregate base according to MnDOT Specifications.
Observe and evaluate the soils exposed in the bottoms of excavations to determine if the
soils are similar to those encountered with the geotechnical evaluation and suitable for
support of fill, foundations or pavements. Our engineer can provide consultation for
conditions that appear to differ from the geotechnical evaluation.
Concrete Field Testing Related Services
Sample and test the plastic concrete for slump, air content, temperature prior to placement.
Prepare 4-inch by 8-inch cylinders for compressive strength testing.
Supply beam molds, curing and testing of flexural strength beams for the truck apron of the
roundabout.
Laboratory compressive strength testing of cylinders.
Develop the Weekly Concrete Reports for the Project Engineer’s review and their submittal
to MnDOT’s Concrete Office.
Bituminous Related Services
Collect one verification sample per mix per day of production. Perform quality assurance
tests on these samples which include Rice specific gravity, asphalt content, extracted
aggregate gradation, gyratory density, coarse aggregate angularity, and fine aggregate
angularity.
Randomly determine and mark pavement core locations.
Observe the contractor coring and core testing in accordance with MnDOT’s specifications,
which include watching quality control personnel weigh the cores at their laboratory.
City of Lakeville
Proposal QTB095616
March 18, 2019
Page 4
Collect companion cores and test for thickness and density of pavement cores.
Reporting and Project Management
Test results will be issued weekly for the project as the various tasks are performed. If, at any time, there
are failing tests which do not appear to be in accordance with the plans and specifications or MnDOT’s
Schedule of Materials Control, we will notify the engineer’s representative and any others that we are
directed to notify.
Before the final project closeout, we will issue a final report. The report will include the following:
Braun Intertec technician roster for technicians that conducted testing on the project.
Completed MnDOT Materials Certification Exceptions Summary for items tested by
Braun Intertec.
Completed Preliminary and Final Grading and Base Report.
Moisture, Density, DCP, Proctor and Gradation tests.
Concrete mix designs.
Weekly concrete reports.
Concrete compressive strength results.
Completed test reports for samples sent to the MnDOT Materials Lab.
Bituminous mix designs.
Bituminous verification test results.
Bituminous contractor’s summary sheets.
Random core log location worksheets.
Completed density incentive/disincentive worksheets.
Copies of concrete and bituminous plant certifications.
Basis of Scope of Work
The costs associated with the proposed scope of services were estimated using the following
assumptions. If the construction schedule is modified or the contractor completes the various phases of
the project at different frequencies or durations than shown in this proposal, we may need to adjust the
City of Lakeville
Proposal QTB095616
March 18, 2019
Page 5
overall cost accordingly. The scope of work and number of trips required to perform these services are as
shown in the attached table. Notable assumptions in developing our estimate include:
Compaction testing will be performed using the nuclear density method on subgrade
preparation material; a minimum of one test will be conducted each trip with one trip
assumed.
Compaction testing will be performed using the nuclear density method on embankment and
utility backfill and fill material; a minimum of three tests will be conducted each trip with
twenty-five trips assumed.
We understand compaction testing on granular materials will be performed using the
Dynamic Cone Penetration (DCP) method; a minimum of two tests will be conducted each
trip with four trips assumed.
We understand compaction testing on aggregate base will be performed using the Dynamic
Cone Penetration (DCP) method; a minimum of five tests will be conducted each trip with
two trips assumed.
We assume thirty sets of concrete tests will be required to complete the project.
We assume the rebar observations before concrete placements will be completed by the
project representative’s construction oversight manager.
Bituminous paving will be completed in four days for this project.
We assume MnDOT Metro Inspections will perform concrete batch plant monitoring and
testing for this project.
We assume MnDOT Metro Inspections will perform bituminous plant monitoring and testing
for this project.
We assume the project engineer of record will review and approve the contractor’s quality
control submittals and test results.
We assume City of Lakeville Staff will perform the test rolling on the subgrade, select
granular borrow and aggregate base for this project.
You, or others you may designate, will provide us with current and approved plans and
specifications for the project. Modification to these plans must also be sent to us so we can
review their incorporation into the work.
We will require a minimum of 24 hours’ notice for scheduling inspections for a specific time.
Shorter than 24 hours’ notice may impact our ability to perform the requested services, and
the associated impacts will be the responsibility of others.
City of Lakeville
Proposal QTB095616
March 18, 2019
Page 6
If the work is completed at different rates than described above, this proposal should be revised.
Cost and Invoicing
We will furnish the services described herein for an estimated fee of $31,585. Our estimated costs are
based on industry averages for construction production. Depending on the contractor’s performance,
our costs may be significantly reduced or slightly higher than estimated. A tabulation showing our
estimated hourly and/or unit rates associated with our proposed scope of services is also attached.
Additional Services and Overtime
It is difficult to estimate all of the services, and the quantity of each service, that will be required for any
project. Our services are also directly controlled by the schedule and performance of others. For these
reasons, our actual hourly or unit quantities and associated fees may vary from those reported herein.
If the number of hours or units ultimately required exceed those assumed for purposes of this proposal,
they will be invoiced at the hourly or unit rates shown in the attached tabulation. If services are
ultimately required that have not been identified or described herein, they will be invoiced in accordance
with our current Schedule of Charges. Prior to exceeding our estimated fees, we will update you
regarding the progress of our work.
This cost estimate was developed with the understanding that the scope of services defined herein will
be required and requested during our normal work hours of 7:00 a.m. to 4:00 p.m., Monday through
Friday. Services that we are asked to provide to meet the project requirements or the contractor’s
construction schedule outside our normal work hours will be invoiced using an overtime rate factor. The
factor for services provided outside our normal work hours or on Saturday will be 1.25 times the normal
hourly rate for the service provided. The factor for services provided on Sunday or legal holidays will be
1.5 times the normal hourly rate for the service provided. We have not included premiums for overtime;
however, we recommend that allowances and contingencies be made for overtime charges. You will be
billed only for services provided on a time and material basis.
General Remarks
We will be happy to meet with you to discuss our proposed scope of services further and clarify the
various scope components.
We appreciate the opportunity to present this proposal to you. After reviewing this proposal, please sign
and return one copy to our office as notification of acceptance and authorization to proceed. If
anything in this proposal is not consistent with your requirements, please let us know immediately.
Braun Intertec will not release any written reports until we have received a signed agreement. Also,
ordering services from Braun Intertec constitutes acceptance of the terms of this proposal.
The proposed fee is based on the scope of services described and the assumption that our services will
be authorized within 30 days and that others will not delay us beyond our proposed schedule.
Client:Service Description:Work Site Address:
Dodd Boulevard at Flagstaff Avenue
Lakeville, MN 55024
City of Lakeville
Joseph Powers
20195 Holyoke Ave
Lakeville, MN 55044
(952) 985-4400
Construction Materials Testing
SAP 188-117-004
City Project No. 9-54
Description Quantity Units Unit Price Extension
Phase 1 Construction Materials Testing
Activity 1.1 Soil Testing $11,419.00
207 Compaction Testing - Nuclear 65.00 Hour 71.00 $4,615.00
Work Activity Detail Qty Units Hrs/Unit Extension
Embankment & Utilities 25.00 Trips 2.50 62.50
Subgrade Preparation 1.00 Trip 2.50 2.50
1308 Nuclear moisture-density meter charge, per hour 65.00 Each 18.00 $1,170.00
217 Compaction Testing - DCP 18.00 Hour 71.00 $1,278.00
Work Activity Detail Qty Units Hrs/Unit Extension
Aggregate Base 2.00 Trips 3.00 6.00
Select Granular Borrow 4.00 Trips 3.00 12.00
1530 Asphalt Content (ASTM D 2172/6307), per sample 1.00 Each 134.00 $134.00
209 Sample pick-up 6.00 Hour 71.00 $426.00
1318 Standard Proctor Test(ASTM D 698)8.00 Each 160.00 $1,280.00
1162 Sieve analysis with 200 wash (ASTM C 136 and C 117), per sample 8.00 Each 115.00 $920.00
1861 CMT Trip Charge 32.00 Each 28.00 $896.00
126 Project Engineer 5.00 Hour 140.00 $700.00
Work Activity Detail Qty Units Hrs/Unit Extension
Grading 2.00 Each 2.50 5.00
Activity 1.2 Concrete Testing $9,940.00
261 Concrete Testing 75.00 Hour 71.00 $5,325.00
Work Activity Detail Qty Units Hrs/Unit Extension
Sidewalks / Medians / Driveway Aprons /
Pavement
20.00 Trips 2.50 50.00
Curb & Gutter 10.00 Trips 2.50 25.00
1364 Compressive strength of concrete cylinders (ASTM C 39), per
specimen
87.00 Each 25.00 $2,175.00
Work Activity Detail Qty Units Hrs/Unit Extension
Sidewalks / Medians / Driveway Aprons /
Pavement
19.00 Sets 3.00 57.00
Curb & Gutter 10.00 Sets 3.00 30.00
278 Concrete Cylinder Pick up 15.00 Hour 71.00 $1,065.00
Work Activity Detail Qty Units Hrs/Unit Extension
Cylinder Pickup 15.00 Trips 1.00 15.00
1861 CMT Trip Charge 45.00 Each 28.00 $1,260.00
1367 Flexural strength of beams (ASTM C 78 and ASTM C 293), per
specimen
1.00 Each 115.00 $115.00
Activity 1.3 Pavement Testing $4,846.00
1530 Asphalt Content (ASTM D 2172/6307), per sample 4.00 Each 134.00 $536.00
209 Sample pick-up 6.00 Hour 71.00 $426.00
Work Activity Detail Qty Units Hrs/Unit Extension
Sample Pick-Up 4.00 Trips 1.50 6.00
Page 1 of 203/15/2019 04:03 PM
Project Proposal
QTB095616
City of Lakeville CSAH 9 & Flagstaff Avenue SAP 019-609-024
Proposal Total:$31,585.00
1532 Extracted aggregate gradation (ASTM D 5444), per sample 4.00 Each 94.00 $376.00
1528 Rice specific gravity (ASTM D 2041), per sample Each 72.00 $.00
1568 Gyratory gravity (AASHTO T312), per sample Each 160.00 $.00
1542 Thickness and density of pavement core (ASTM D 2726)28.00 Each 45.00 $1,260.00
1705 Fine Aggregate Angularity (ASTM C1252), per sample 4.00 Each 70.00 $280.00
1688 Percent crushed (ASTM D5821), per sample 4.00 Each 72.00 $288.00
221 Bituminous Coring 16.00 Hour 91.00 $1,456.00
Work Activity Detail Qty Units Hrs/Unit Extension
Mark & Observe Contractor Coring & Testing 4.00 Trips 4.00 16.00
1861 CMT Trip Charge 8.00 Each 28.00 $224.00
Activity 1.4 Project Management, Engineering Review & Oversight $5,380.00
226 Project Manager 24.00 Hour 140.00 $3,360.00
228 Senior Project Manager 2.00 Hour 155.00 $310.00
238 Project Assistant 10.00 Hour 71.00 $710.00
1230 MnDOT Final Report 1.00 Each 1,000.00 $1,000.00
Phase 1 Total:$31,585.00
Page 2 of 203/15/2019 04:03 PM
Project Proposal
QTB095616
City of Lakeville CSAH 9 & Flagstaff Avenue SAP 019-609-024