HomeMy WebLinkAbout19-064CITY OF LAKEVILLE
RESOLUTION NO. 19-64
RESOLUTION AUTHORIZING FUNDING FOR
SOUTH CREEK AT HAMBURG AVENUE STREAM RESTORATION.
CITY PROJECT 19-06
WHEREAS, the South Creek at Hamburg Avenue Stream Restoration, City Project 19-06,
is programmed in the adopted Lakeville 5 -year Capital Improvement Plan (2019-2023).
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Lakeville,
Minnesota:
The estimated project cost is $272,910 and anticipated funding sources are listed below. City staff
is hereby authorized to amend the 2019 budgets and make the appropriate transfers between funds
with respect to the project funding sources up to 10% above the estimated costs. Funding transfers
may include loans between funds to cover engineering and other costs incurred on the project in
advance of receiving other funding.
Funding Sources
Amount
Utility Fund - Environmental Resources
$18,900
MnDNR Conservation Partners Legacy Grant
$254,010
Total
$272,910
ADOPTED by the Lakeville City Council this 17`h day of June 2019
Douglas P. Anderson, Mayor
Charlene Friedges, City Cler