FINAL ACCEPTANCE OF PUBLIC STREETS AND UTILITIES
WILD WINGS
Proposed Action
Staff recommends adoption of the following motion: Move to approve final acceptance of public
streets and utilities installed with Wild Wings.
Overview
Ryan Contracting Company requests final acceptance of the public street and utility improvements
installed with the development of Wild Wings. The prime contractor responsible for the public
improvement work was Ryan Contracting Company.
The public utilities for the entire development, the curb and gutter and bituminous base-course
pavement for Eastwood Avenue were constructed in 2018. The curb and gutter and bituminous
base-course pavement for Eagleview Drive were constructed in 2019. The bituminous wear-course
pavements were constructed in 2019. The public street and utility improvements were tested and
inspected by WSB and the City’s Public Works Department.
Primary Issues to Consider
• The public street and utility improvements were completed consistent with the City’s
construction standard specifications and the administrative requirements for final
acceptance.
Supporting Information
• None.
Financial Impact: $0 Budgeted: Y☐ N☐ Source: N/A
Related Documents:
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Zach Johnson, City Engineer