REJECTION OF BIDS FOR THE REHABILITATION OF WELLS 8, 11, AND 12
Proposed Action
Staff recommends adoption of the following motion: Move to reject bids for the rehabilitation of
Wells 8, 11, and 12.
Overview
As part of ongoing preventive maintenance activities, the Utilities Division schedules its water
production wells for rehabilitation on a recurring basis. The division schedules submersible wells
on a 10-year rotation and vertical turbine wells on an 8-year rotation. The long drive shaft and
potential for bending and wear of the shaft and supports are the reason behind the more frequent
scheduling of vertical turbine wells. Well rehabilitations involve pulling the pump, motor, and
drive shaft, removing several hundred feet of down hole piping, evaluating the motor and pump
for efficient operation, and removing any sand from the bottom of the well.
The City opened bids for the project on September 20. Four contractors responded to the
request for bids with bid totals ranging from $236,463.00 to $284,365.00. Each of the contractors
complied with the specifications, however bid totals exceeded the budgeted amount by a
minimum of $56,000. Based on historical costs, the approved budget for this project was
$180,000.
Maintaining efficiently operating production wells is important to the overall efficiency of the
water distribution system. Staff is exploring alternatives to complete the most needed well
rehabilitation work within the available funding.
Primary Issues to Consider
• Why did costs exceed budget? In reviewing the bid responses and comparing them with past
work, several areas stood out, cost for piping, cost for pump and motor repairs, and
mobilization costs for removing sand were all higher than expected. Staff will review the
scope of work prior to rebidding the project.
Supporting Information
• A copy of the bid tabulation is attached.
Financial Impact: $0 Budgeted: Yes Source: 7610.6295
Related Documents (CIP, ERP, etc.): 2019 Approved Budget
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: Neil Normandin, Public Works and Facilities Coordinator
Mineral Service Plus, LLC Yes 270,515.00$
E.H.Renner & Sons Yes 236,463.00$
Keys Well Drilling Yes 284,365.00$
Bergerson-Caswell, Inc Yes 249,805.00$
BID TABULATION
REHABILITATION OF WELLS NO. 8, 11, AND 12
11:00 a.m., Friday, September 20, 2019
Contractor Bid Bond Total Bid