HomeMy WebLinkAbout1021ORDINANCE NO. 1021
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
AN ORDINANCE ADOPTING FEES
THE CITY COUNCIL OF THE CITY OF LAKEVILLE, MINNESOTA ORDAINS THE FOLLOWING FEES:
I. LICENSES
a. Dynamic Display Sign:
i. Application fee $100.00
ii. Annual renewal fee $50.00
II. PERMITS
a. Building Permits
Total Valuation
Fee
$1.00 to $500.00
$30.00
$501.00 to $2,000.00
$30.00 for the $500.00 plus $3.25 for each additional
$100.00, or fraction thereof, to and including $2,000.00
$2,001.00 to $25,000.00
$73.75 for the first $2,000.00 plus $14.75 for each
additional $1,000.00, or fraction thereof, to and including
$25,000.00
$25,001.00 to $50,000.00
$413.00 for the first $25,000.00 plus $10.75 for each
additional $1,000.00, or fraction thereof, to and including
$50,000.00
$50,001.00 to $100,000.00
$681.75 for the first $50,000.00 plus $7.50 for each
additional $1,000.00, or fraction thereof, to and including
$100,000.00
$100,001.00 to $500,000.00
$1,056.75 for the first $100,000.00 plus $6.00 for each
additional $1,000.00, or fraction thereof, to and including
$500,000.00
$500,001.00 to
$3,456.75 for the first $500,000.00 plus $5.00 for each
$1,000,000.00
additional $1,000.00, or fraction thereof, to and including
$1,000,000.00
$1,000,001.00 and up $5,956.75 for the first $1,000,000.00 plus $4.00 for each
additional $1,000.00, or fraction thereof
b. Plan Check Fees
i. 65% of building permit fee for permits with valuations greater than $10,000.00.
ii. 25% of building permit fee for permits issued for similar buildings as required by
State Building Code.
c. Building Permits, Landscaping
i. $1000.00 escrow for landscaping to be collected with the building permit.
d. Building Permits, Erosion Control
i. $1000.00 escrow for erosion control/grading certification to be collected with the
building permit.
e. Plumbing Permits
i. Requirement: Master License Number or pipe layers certificate, $25,000.00 license
bond and current Certificate of Liability Insurance to be filed with City. Note: State
Department of Health Bond and Insurance Certificate will satisfy this requirement.
ii. Residential- Minimum (repairs and alterations, lawn sprinkler systems) $40.00
iii. Complete installation $90.00
iv. Commercial- 1.5% of contract/valuation price up to $10,000.00 and 1.0% of
contract/valuation price above $10,000.00
v. Commercial- Minimum $40.00
vi. RPZ Valve (new, replacement or rebuild) $40.00
vii. Water Softener/Water Heater $40.00
f. Heating Permits
i. Residential- Minimum repairs and alterations $40.00
ii. Residential- Complete installation $90.00
iii. Commercial- 1.5% of contract/valuation price up to $10,000.00 and 1.0% of
contract/valuation price above $10,000.00.
iv. Commercial minimum $40.00
g. Sewer and Water Permits
i. Requirement: Master License Number, $25,000.00 License Bond and current
Certificate of Liability Insurance to be filed with the City. Note: State Department of
Health Bond and Insurance Certificate will satisfy this requirement.
ii. Residential- Minimum repairs and alterations $40.00
iii. Residential- City water and sewer including conversion $90.00
iv. Commercial- One percent (1%) of contract/valuation price
v. Commercial- minimum $40.00
vi. Private sewer systems: New installation $250.00
vii. Private sewer systems: Repair $250.00
h. Electrical Permits
i. Requirement: State License from Board of Electricity. Note: An owner who actually
occupies or intends to occupy a single family residence is exempt from the licensing
requirement.
H. Residential- Minimum repairs and alterations $40.00
iii. Residential- Additions, remodels, lower levels (two trips) $70.00
iv. Residential- New installation (up to three trips) $135.00
v. Commercial- 1.5% of contract/valuation price up to $10,000.00 and 1.0% of
contract/valuation price above $10,000.00.
vi. Commercial minimum $40.00
vii. Additional trip charge $35.00
L Well Permits
i. Effective February 1, 1989, all well permits are issued by Dakota County.
j. Manufactured Home Inspections
L Installation permit (foundation, sewer, water, gas) $90.00
ii. Separate permit for electrical hookup $40.00
k. Swimming Pools
i. All in -ground pools, regardless of capacity, and above -ground pools that exceed
5,000 gallons $50.00
1. Zoning Permit
m. Signs
i. Permanent installation
ii. Temporary installation (10 days only)
n. Moving Structure (plus letter of credit or cash escrow)
o. Demolition
i. Residential Accessory structures
ii. All structures other than residential accessory
$30.00
$75.00
$50.00
$125.00
no charge
$50.00
p. Fire Systems
i. Fire Line- One percent of contract/valuation price
q. Sprinkler Fire Protection
i. Requirement: State Fire Protection Contractor License to be filed with the City.
ii. Commercial: 1.5% of contract/valuation price up to $10,000.00 and 1.0% of
contract/valuation price above $10,000.00 plus surcharge (.0005 times
contract/valuation)
Minimum $45.00
iv. Residential- New Construction $90.00
v. Residential- Remodel $45.00
r. Miscellaneous Commercial Mechanical
i. Refrigeration, piping, fuel tanks, etc.- 1.5% of contract/valuation price up to $10,000
and 1% of the contract/valuation price in excess of $10,000.00
ii. Minimum $40.00
s. Miscellaneous (re -inspections) Inspections
i. Minimum 1 hour
t. Re -Roof, Re -Side, Re -deck, and Retaining Walls over 4 feet high
i. Residential
ii. Commercial
u. Windows- Comprehensive or Egress
i. Residential
ii. Commercial
$55.00/hour
$50.00
$150.00
$50.00
$150.00
v. Inspections after hours (weekends, Holidays)
i. Only if an inspector is available for requested inspection (minimum 1 hour)
$110.00/hour
w. Investigation fee
i. Whenever any work for which a permit is required by Code has been commenced
without first obtaining said permit, the investigation fee shall be equal to the amount
of permit fee.
III. PLANNING AND ZONING
a. Platting
i. Also refer to Section IV
ii. Services performed by City personnel will be billed at 2.5 times actual payroll hourly
rate. Services provided by City consultant will be billed at current consultant rates.
Sketch Plan Review- $2,000.00 escrow for legal notices, planning, engineering and
legal services provided by staff and/or consultants
iv. Preliminary Plat- $500.00 per addition. In addition to the fee, a $2,000.00 escrow is to
be paid for legal notices, planning, engineering and legal services provided by staff
and/or consultant.
v. Final Plat- $200.00 per addition. In addition to the fee, a $2,000.00 escrow is to be
paid for planning, engineering and legal services provided by staff and/or
consultants.
b. Planned Unit Development
i. $500.00 plus $2,000.00 escrow for legal notices, planning, engineering and legal
services provided by staff and/or consultants.
c. PUD Amendment
$500.00 plus $2,000.00 escrow for legal notices, planning, engineering and legal
services provided by staff and/or consultants.
d. Variance
i. Single family (includes legal notice publications) $500.00
ii. All others, plus $1,000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants $500.00
e. Conditional Use Permit/CUP Amendment
i. Single family (includes legal notice publications) $500.00
ii. All others, plus $1,000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants $500.00
f. Conditional Use Permit, Interim Use Permit and Variance Extension
i. 111 extension $50.00
ii. Additional extensions $250.00
g. Home Occupation Permit $100.00
h. Interim Use Permit/IUP Amendment
i. Single family (includes legal notice publications) $500.00
ii. All others, plus $1,000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants $500.00
i. Rezoning
i. $500.00 plus $1000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants
j. Administrative Subdivision
i. $500.00 plus all applicable dedication requirements and $1,000.00 escrow for
planning, engineering and legal services provided by staff and/or consultants
k. Street and Easement Vacations
i. $200.00 plus $1,000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants.
1. Zoning Ordinance Text Amendment
i. $500.00 plus $2,000.00 escrow for legal notices, planning, engineering and legal
services provided by staff and/or consultants
m. Lot Release
i. $500.00 escrow for legal notices, planning, engineering and legal services provided by
staff and/or consultants
n. Parking Deferment
i. $100.00 plus $1,000.00 escrow for planning, engineering and legal services provided
by staff and/or consultants
o. Comprehensive Plan Amendment
i. $500.00 plus $2,000.00 escrow for legal notices, planning, engineering, and legal
services provided by staff and/or consultants
p. Site Plan
i. $100.00 plus $1,000.00 escrow for planning, engineering, and legal services provided
by staff and/or consultants
q. Administrative Permit (per City Ordinance 11-8-3) $100.00
r. Cost Recovery Fee (for code enforcement activities)
i. $100.00 per reinspection
s. Zoning Letter
t. Notice of Appeal
$100.00
$500.00 escrow
IV. ENGINEERING
a. Platting
Sketch plan review
i. Services performed by City personnel will be hourly and billed at 2.5 times actual
payroll hourly rate applied to the Planning and Zoning escrows.
ii. Preliminary Plat
1. $150.00/acre
2. $500.00 minimum
3. $3,200.00 maximum
iii. Final Plat
1. $150.00/acre
2. $500.00 maximum
b. Construction and Asbuilt Construction Plan Review
Site, grading, erosion control, drainage, utility and street plan and specifications review.
Services performed by City Personnel will be hourly. A cash escrow may be required (if not
collected through Planning and Zoning).
c. Wetland Conservation Act Administration (platting or non -platting action)
i. Services performed by City Personnel will be hourly, in addition to the minimum fee,
if a higher than average amount of time is spent on the services. In addition to the
below fees, an escrow will be required to fund special studies such as environmental
assessment worksheets, transportation, drainage, noise impacts, indirect source
permits, etc. The amount of escrow will be based on the site, complexity, diversity
and location of the project
1. Wetland Delineation
a. $325.00 minimum fee plus any incremental hourly staff fee
2. Wetland Application
a. $250.00 minimum fee plus any incremental hourly staff fee
3. Wetland Appeal of Notice of Decision
a. $300.00 minimum fee plus any incremental hourly staff fee
d. General Engineering
i. Developer Installed improvements
V.
i. Engineering administration- 3.0% of project construction cost (assuming
normal construction conditions and projection scheduling) or 3.25% if
security is in the form of a cash disbursement agreement.
2. Construction, grading/erosion control, final acceptance and warranty
inspection (hourly as charged by City's consultant). Services performed by
City personnel will be hourly and billed at 2.5 times actual payroll hourly rate.
Property Data and Asset/Infrastructure management fee (GIS fee) -
preparation of record construction drawings and city base map updating.
a. $90.00 parcel/lot
ii. City installed improvements (non -development)
1. Engineering contract administration- 2.0% to 3.0% of project construction
cost (depending on project).
2. Feasibility report- Services performed by consultants will be based on
consultant's hourly rate. Services performed by City personnel will be hourly
and billed at 2.5 times staff hourly rate.
3. Design- Services performed by consultants will be based on consultant's
hourly rate. Services performed by City personnel will be hourly and billed at
2.5 times staff hourly rate.
4. Construction observation and final inspection- Services performed by
consultants will be based on consultant's hourly rate. Services performed by
City personnel will be hourly and billed at 2.5 times staff hourly rate.
CONNECTION CHARGES AND OTHER DEVELOPMENT FEES
a. Storm Sewer Charge (storm water management infrastructure)
i. Single Family Residential $0.178/sq. ft.
ii. Multi -Family Residential $0.198/sq. ft.
iii. Commercial and Industrial $0.250/sq. ft.
b. Crystal Lake Surcharge (Crystal Lake Watershed only, storm water management
infrastructure)
i. Single Family Residential $0.0134/sq. ft.
ii. Multi -Family Residential $0.0153/sq. ft.
iii. Commercial and Industrial $0.0195/sq. ft.
c. Lateral Watermain Charge (adjacent non -assessed existing watermain)
i. Residential -$41.00 per Front Foot plus $408.00 per service
ii. Non -Residential -$48.00 per Front Foot plus $408.00 per service
d. Lateral Sanitary Sewer Charge (adjacent non -assessed existing sanitary sewer)
i. Residential and Non -Residential -$41.50 per Front Foot plus $418.00 per service
e. Sanitary Sewer Availability Charge
f. Sanitary Sewer Connection Charge
g. Watermain Unit Charge
i. Paid with building permit- funds water infrastructure
ii. Residential- $4,100.00 per unit
iii. High Density, Commercial, Industrial- $2,050.00 per unit
h. Park Dedication Fees
i. High Density Residential- $2,352.00 per dwelling unit
ii. Medium Density Residential- $3,068.00 per dwelling unit
iii. Low Density Residential- $4,509.00 per dwelling unit
iv. Commercial- $7,693.00 per acre
v. Industrial- $4,558.00 per acre
Ordinance shall be effective January 1, 2020.
Adopted by the Lakeville City Council this 2nd day of December 2019
By: Douglas P. Anderson, Mayor
Charlene Friedges, City Cler
$327.00 per unit
$825.00 per unit
SUMMARY OF ORDINANCE NO. 1021
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
AN ORDINANCE ADOPTING A FEE SCHEDULE
This ordinance prescribes fees sufficient to defray the costs incurred by the City of Lakeville in
reviewing, investigating and administering applications from the amendment to an official control
established pursuant to Minnesota Statutes Sections 462.351 to 462.364 and applications for permits
or approvals required under an official control established pursuant to those sections.
A printed copy of the ordinance is available for inspection by any person during regular office hours
at the office of the City Clerk.
APPROVED FOR PUBLICATION by the Lakeville City Council this 2nd day of December 2019
By: Douglas P. Anderson, Mayor