Lakeville North HS Overflow Parking Lot
& Ames Arena Parking Lot Improvements
City Project 19-13
City Council Work Session
February 24, 2020
Lakeville, Minnesota—Positioned to Thrive
Project Update (2020 vs 2019)
•City staff, Lakeville North HS Athletics Director and Lakeville Area Schools staff completed design changes over the winter
•Revisions include:
•Football practice field relocation
•Storm water management consolidation
•Trail realignment
•Accessibility changes
Lakeville, Minnesota—Positioned to Thrive
Project Update (2020 vs 2019)
•Outcome
•Parking improvements at Ames Arena
•Increased football practice field sideline and spectator area
•Grading changes that support the future relocation of the discuss throwing field
•Enhanced Lake Marion ES green space
•Improved pedestrian accessibility
Lakeville, Minnesota—Positioned to Thrive
Site Plan
Lakeville, Minnesota—Positioned to Thrive
Parking Lot Improvements
•Lakeville North HS Overflow Parking Lot
•185 Parking Spaces (including 6 ADA)
•Additional 63 Parking Spaces
•Ames Arena Parking Lot
•158 Parking Spaces (including 6 ADA)
•Additional 81 Parking Spaces
Lakeville, Minnesota—Positioned to Thrive
Project Schedule
Open Bids February 28
Lakeville Area Schools Board Meeting March 10/March 31
•(JPA with City)
Lakeville Arenas Board Meeting March 18
•(JPA with City)
City Council Meeting April 6
•(JPA with ISD 194 & Lakeville Arenas)
•(Award Contract)
Construction July 6 –August 15
Lakeville, Minnesota—Positioned to Thrive
Next Steps
•Open Bids and Determine Project Costs
•Agreements
•Lakeville Area Schools
•Lakeville Arenas
•Award Contract
•Construction