HomeMy WebLinkAboutItem 06.d•
•
•
•
☒☐
April 24, 2020
Mark Kruse, Parks Superintendent
City of Lakeville
20195 Holyoke Avenue
Lakeville, Minnesota 55044
Re City of Lakeville
Orchard Lake Beach Restroom Improvements
Commission No. 202012
Dear Mark:
On Tuesday, April 21, 2020 at 3:00 P.M., quotes were received from six (6) contractors for the
Restroom Improvements project at Orchard Lake Beach. The apparent low bidder is Langer
Construction Company. We have contacted Langer Construction Company and have confirmed
that they have included all work required in their contract cost and can complete the work in the
specified time.
We are recommending that the City award a contract to Langer Construction Company of St. Paul,
Minnesota in the amount of $59,990.00 for this project. Langer Construction Company has
performed similar projects in the past and is qualified for the work of this project.
Sincerely,
Wold Architects and Engineers
Andrew Dahlquist | AIA, LEED AP
Associate
cc: Andrea Phillips, City of Lakeville
Nathan Cruz Rak, Wold
MF/CI_Lakeville/202012/crsp/apr20
Project Name:QUOTE TABULATION
Commission No.: 202012 Wold Architects and Engineers
Date: 21-Apr-20 332 Minnesota Street, Suite W2000
Time: 3:00pm Saint Paul, Minnesota 55101
651.227.7773 Fax: 651.223.5646
Bidders Name Base Quote
Langer Construction
54 Moreland Avenue E
St. Paul, MN 55118 $59,990
Office: (651) 457-5993
E-mail: josh@langerconstruction.com
Greystone Construction Company
500 S Marschall Road, Suite 300
Shakopee, MN 55379 $61,315
Office:
E-mail: THartman@greystoneconstruction.com
K.A. Witt Construction
1530 West 280th Street
New Prague, MN 56071 $68,600
Office: 952-758-2108
E-mail: jason@kawitt.com
RAK Construction
21435 Johnson St NE
East Bethel, MN 55011 $82,543
Office: 763-434-4210
E-mail: randy.pederson@rakconstruction.com
Green Construction Services
553 Como Avenue
St. Paul, MN 55103 $82,700
Office: 651-888-7000
E-mail: bradg@green-construct.com
Loeffler Construction
20520 Keokuk Avenue, Suite 100
Lakeville, MN 55044 $108,500
Office: 952-955-9006
E-mail: eprettyman@loefflerconstruction.com
ORCHARD LAKE BEACH RESTROOM
IMPROVEMENTS
Remarks
1
184651v1
FORM OF AGREEMENT
BETWEEN CITY OF LAKEVILLE AND CONTRACTOR
FOR NON-BID CONSTRUCTION CONTRACT
THIS AGREEMENT made this _____ day of _____________, 2020, by and between the
CITY OF LAKEVILLE, a Minnesota municipal corporation (“Owner” or “City”) and
_________________, a ____________________ (“Contractor”). Owner and Contractor, in
consideration of the mutual covenants set forth herein, agree as follows:
1. CONTRACT DOCUMENTS. The following documents shall be referred to as the
“Contract Documents”, all of which shall be taken together as a whole as the contract between the
parties as if they were set verbatim and in full herein:
A. This Agreement.
B. The City’s Request for Quotes for Orchard Lake Beach Restroom
Improvements, dated March 20, 2020.
C. Drawings and Specifications dated March 20, 2020 prepared by Wold
Architects and Engineers.
D. The Contractor’s Quote.
In the event of a conflict among the provisions of the Contract Documents, the order in which they
are listed above shall control in resolving any such conflicts. Contract Document “A” has the first
priority and Contract Document “D” has the last priority.
2. OBLIGATIONS OF THE CONTRACTOR. The Contractor shall provide the
goods, services, and perform the work in accordance with the Contract Documents. Contractor shall
not begin any work until the City has received the signed contract and has reviewed and approved
the insurance certificates and has given the Contractor a written notice to proceed. Contractor shall
exercise the same degree of care, skill, and diligence in the performance of the services as is
ordinarily possessed and exercised by a contractor under similar circumstances. City shall not be
responsible for discovering deficiencies in the accuracy of Contractor’s services.
3. CONTRACT PRICE. Owner shall pay Contractor for completion of the Work, in
accordance with the Contractor’s Proposal. Additional work performed without the City’s written
approval will not entitle Contractor to an increase in the Contract Price or an extension of the
Contract Time.
4. PAYMENT PROCEDURES.
A. Contractor shall submit Applications for Payment. Applications for Payment
will be processed by the Parks Superintendent.
B. Progress Payments; Retainage. Owner shall make 95% progress payments
on account of the Contract Price on the basis of Contractor’s Applications for
Payment during performance of the Work.
24th April
Langer Construction Company General Contractor
27th
2
184651v1
C. Payments to Subcontractors.
(1) Prompt Payment to Subcontractors. Pursuant to Minn. Stat. § 471.25,
Subd. 4a, the Contractor must pay any subcontractor within ten (10)
days of the Contractor’s receipt of payment from the City for
undisputed services provided by the subcontractor. The Contractor
must pay interest of 1 ½ percent per month or any part of a month to
the subcontractor on any undisputed amount not paid on time to the
subcontractor. The minimum monthly interest penalty payment for
an unpaid balance of $100.00 or more is $10.00. For an unpaid
balance of less than $100.00, the Contractor shall pay the actual
penalty due to the subcontractor.
(2) Form IC-134 (attached) required from general contractor. Minn. Stat.
§ 290.92 requires that the City of Lakeville obtain a Withholding
Affidavit for Contractors, Form IC-134, before making final
payments to Contractors. This form needs to be submitted by the
Contractor to the Minnesota Department of Revenue for approval.
The form is used to receive certification from the state that the vendor
has complied with the requirement to withhold and remit state
withholding taxes for employee salaries paid.
D. Final Payment. Upon final completion of the Work, Owner shall pay the
remainder of the Contract Price as recommended by the Parks
Superintendent. Final completion shall be when all of the work is completed.
5. COMPLETION DATE. The Work must be completed by October 23, 2020.
6. CONTRACTOR’S REPRESENTATIONS.
A. Contractor has examined and carefully studied the Contract Documents and
other related data identified in the Contract Documents.
B. Contractor has visited the Site and become familiar with and is satisfied as to
the general, local, and Site conditions that may affect cost, progress, and
performance of the Work.
C. Contractor is familiar with and is satisfied as to all federal, state, and local
laws and regulations that may affect cost, progress, and performance of the
Work.
D. Contractor has carefully studied all: Bidding Documents (drawings and
specifications) and is generally familiar with the project site which relates to
any aspect of the means, methods, techniques, sequences, and procedures of
construction to be employed by Contractor, including any specific means,
methods, techniques, sequences, and procedures of construction expressly
3
184651v1
required by the Bidding Documents, and safety precautions and programs
incident thereto.
F. Contractor does not consider that any further examinations, investigations,
explorations, tests, studies, or data are necessary for the performance of the
Work at the Contract Price, within the Contract Times, and in accordance
with the other terms and conditions of the Contract Documents.
G. Contractor is aware of the general nature of work to be performed by Owner
and others at the Site that relates to the Work as indicated in the Contract
Documents.
H. Contractor has correlated the information known to Contractor, information
and observations obtained from visits to the Site, reports and drawings
identified in the Contract Documents, and all additional examinations,
investigations, explorations, tests, studies, and data with the Contract
Documents.
I. The Contract Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for performance and furnishing of
the Work.
J. Subcontracts:
(1) Unless otherwise specified in the Contract Documents, the Contractor
shall, upon receipt of the executed Contract Documents, submit in
writing to the Owner the names of the Subcontractors proposed for
the work. Subcontractors may not be changed except at the request
or with the consent of the Owner.
(2) The Contractor is responsible to the Owner for the acts and omissions
of the Contractor's subcontractors, and of their direct and indirect
employees, to the same extent as the Contractor is responsible for the
acts and omissions of the Contractor's employees.
(3) The Contract Documents shall not be construed as creating any
contractual relation between the Owner and any subcontractor.
(4) The Contractor shall bind every subcontractor by the terms of the
Contract Documents.
7. WORKER’S COMPENSATION. The Contractor shall obtain and maintain for
the duration of this Contract, statutory Worker’s Compensation Insurance and Employer’s Liability
Insurance as required under the laws of the State of Minnesota.
8. INSURANCE. Prior to the start of the project, Contractor shall furnish to the City
a certificate of insurance showing proof of the required insurance required under this
4
184651v1
Paragraph. Contractor shall take out and maintain or cause to be taken out and maintained until six
(6) months after the City has accepted the public improvements, such insurance as shall protect
Contractor and the City for work covered by the Contract including workers’ compensation claims
and property damage, bodily and personal injury which may arise from operations under this
Contract, whether such operations are by Contractor or anyone directly or indirectly employed by
either of them. The minimum amounts of insurance shall be as follows:
Commercial General Liability (or in combination with an umbrella policy)
$2,000,000 Each Occurrence
$2,000,000 Products/Completed Operations Aggregate
$2,000,000 Annual Aggregate
The following coverages shall be included:
Premises and Operations Bodily Injury and Property Damage
Personal and Advertising Injury
Blanket Contractual Liability
Products and Completed Operations Liability
Automobile Liability
$2,000,000 Combined Single Limit – Bodily Injury & Property Damage
Including Owned, Hired & Non-Owned Automobiles
Workers Compensation
Workers’ Compensation insurance in accordance with the statutory requirements of
the State of Minnesota, including Employer’s Liability with minimum limits are as
follows:
$500,000 – Bodily Injury by Disease per employee
$500,000 – Bodily Injury by Disease aggregate
$500,000 – Bodily Injury by Accident
The Contractor shall carry Builders All Risk Insurance for the entire value of their proposal.
The Contractor’s insurance must be “Primary and Non-Contributory”.
Contractor shall also place and maintain an all risk or “Special Form” policy of property
insurance in the amount of the quoted sum for the entire work under this contract on a
replacement cost basis.
All insurance policies (or riders) required by this Contract shall be (i) taken out by and
maintained with responsible insurance companies organized under the laws of one of the states
of the United States and qualified to do business in the State of Minnesota, (ii) shall name the
City, its employees and agents as additional insureds (CGL and umbrella only) by endorsement
which shall be filed with the City. A copy of the endorsement must be submitted with the
certificate of insurance.
Contractor’s policies and Certificate of Insurance shall contain a provision that coverage
afforded under the policies shall not be cancelled without at least thirty (30) days’ advanced
written notice to the City, or ten (10) days’ notice for non-payment of premium.
5
184651v1
An Umbrella or Excess Liability insurance policy may be used to supplement Contractor’s
policy limits on a follow-form basis to satisfy the full policy limits required by this Contract.
9. WARRANTY. The Contractor shall be held responsible for any and all defects in
workmanship and materials which may develop in any part of the contracted service, and upon
proper notification by the City shall immediately replace, without cost to the City, any such faulty
work.
10. INDEMNIFICATION. To the fullest extent permitted by law, Contractor agrees
to defend, indemnify and hold harmless the City, and its employees, officials, and agents from and
against all claims, actions, damages, losses and expenses, including reasonable attorney fees, arising
out of Contractor’s negligence or its performance or failure to perform its obligations under this
Contract. Contractor’s indemnification obligation shall apply to subcontractor(s), or anyone
directly or indirectly employed or hired by Contractor, or anyone for whose acts Contractor may be
liable. Contractor agrees this indemnity obligation shall survive the completion or termination of
this Contract.
11. PERFORMANCE AND PAYMENT BONDS. Performance and Payment Bonds
are not required.
12. MISCELLANEOUS.
A. Terms used in this Agreement have the meanings stated in the General
Conditions.
B. Owner and Contractor each binds itself, its partners, successors, assigns and
legal representatives to the other party hereto, its partners, successors, assigns
and legal representatives in respect to all covenants, agreements, and
obligations contained in the Contract Documents.
C. Any provision or part of the Contract Documents held to be void or
unenforceable under any law or regulation shall be deemed stricken, and all
remaining provisions shall continue to be valid and binding upon Owner and
Contractor, who agree that the Contract Documents shall be reformed to
replace such stricken provision or part thereof with a valid and enforceable
provision that comes as close as possible to expressing the intention of the
stricken provisions.
D. Data Practices/Records.
(1) All data created, collected, received, maintained or disseminated for
any purpose in the course of this Contract is governed by the
Minnesota Government Data Practices Act, Minn. Stat. Ch. 13, any
other applicable state statute, or any state rules adopted to implement
the act, as well as federal regulations on data privacy.
6
184651v1
(2) All books, records, documents and accounting procedures and
practices to the Contractor and its subcontractors, if any, relative to
this Contract are subject to examination by the City.
E. All reports, plans, models, software, diagrams, analyses, and information
generated in connection with performance of this Agreement shall be the
property of the City. The City may use the information for its purposes.
F. Patented devices, materials and processes. If the Contract requires, or the
Contractor desires, the use of any design, devise, material or process covered
by letters, patent or copyright, trademark or trade name, the Contractor shall
provide for such use by suitable legal agreement with the patentee or owner
and a copy of said agreement shall be filed with the Owner. If no such
agreement is made or filed as noted, the Contractor shall indemnify and hold
harmless the Owner from any and all claims for infringement by reason of
the use of any such patented designed, device, material or process, or any
trademark or trade name or copyright in connection with the Project agreed
to be performed under the Contract, and shall indemnify and defend the
Owner for any costs, liability, expenses and attorney's fees that result from
any such infringement.
G. In providing services hereunder, Contractor shall abide by all statutes,
ordinances, rules and regulations pertaining to the provisions of services to
be provided.
H. Assignment. Neither party may assign, sublet, or transfer any interest or
obligation in this Contract without the prior written consent of the other party,
and then only upon such terms and conditions as both parties may agree to
and set forth in writing.
I. Waiver. In the particular event that either party shall at any time or times
waive any breach of this Contract by the other, such waiver shall not
constitute a waiver of any other or any succeeding breach of this Contract by
either party, whether of the same or any other covenant, condition or
obligation.
J. Governing Law/Venue. The laws of the State of Minnesota govern the
interpretation of this Contract. In the event of litigation, the exclusive venue
shall be in the District Court of the State of Minnesota for Dakota County.
K. Severability. If any provision, term or condition of this Contract is found to
be or become unenforceable or invalid, it shall not affect the remaining
provisions, terms and conditions of this Contract, unless such invalid or
unenforceable provision, term or condition renders this Contract impossible
to perform. Such remaining terms and conditions of the Contract shall
7
184651v1
continue in full force and effect and shall continue to operate as the parties’
entire contract.
L. Entire Agreement. This Contract represents the entire agreement of the
parties and is a final, complete and all-inclusive statement of the terms
thereof, and supersedes and terminates any prior agreement(s),
understandings or written or verbal representations made between the parties
with respect thereto.
M. Permits and Licenses; Rights-of-Way and Easements. The Contractor shall
give all notices necessary and incidental to the construction and completion
of the Project. The City will obtain all necessary rights-of-way and
easements. The Contractor shall not be entitled to any additional
compensation for any construction delay resulting from the City’s not timely
obtaining rights-of-way or easements.
N. If the work is delayed or the sequencing of work is altered because of the
action or inaction of the Owner, the Contractor shall be allowed a time
extension to complete the work but shall not be entitled to any other
compensation.
OWNER: CONTRACTOR:
CITY OF LAKEVILLE
BY: ____________________________ BY: ____________________________
Douglas P. Anderson, Mayor Its: _______________________
AND ___________________________
Charlene Friedges, City Clerk