WHEREAS, the Kingsley Lake Outlet Control Structure, City Project 20-59, is
programmed in the adopted Lakeville 2020 Budget.
NOW, THEREFORE, BE IT RESOLVED, by the City Council of the City of Lakeville,
Minnesota:
The estimated project cost is $39,685 and anticipated funding sources are listed below. City staff is
hereby authorized to amend the 2020 budget (if needed as the project is completed) and make the
appropriate transfers between funds with respect to the project funding sources up to 10% above
the estimated costs. Funding transfers may include loans between funds to cover engineering and
other costs incurred on the project in advance of receiving other funding.
Funding Sources
Amount
Utility Fund - Environmental Resources
$39,685
Total
$39,685
ADOPTED by the Lakeville City Council this 8th day of September 2020.
Douglas P. Anderson, Mayor
Charlene Friedges, City Cle