HomeMy WebLinkAboutLA184563 9171 187th St W Permit PackRESIDENTIAL BUILDING PERMIT APPLICATION
PAGE 2
OFFICE USE ONLY
BUILDING PERMIT TYPE REQUIRED INSPECTIONS
SINGLE FAMILY DWELLING BUILDING
DUPLEX AS BUILT
TOWNHOUSE UNITS BUILDING FINAL
DETACHED TOWN HOUSE UNIT DECK FOOTING
CONDO FIREPLACE
ACESSORY BUILDING FOOTING
REROOF FOUNDATION
RESIDE FRAMING
PORCH FRAMING
GARAGES
INSULATION
RES ADDN/REPAIR/RMDL
DECK
PORCH
GARAGES LATH
LOWER LEVEL FINISH LOWER LEVEL FINAL
ADDITION OTHER
FOUNDATION ONLY PORCH FOOTING
MISCELLANEOUS POURED WALL
DEMO SEPTIC TANK REMOVAL
MOVED SITE
MECHANICAL
CITY BUILDING VALUATION: $AIR TEST
FINAL
BUILDING PERMIT FEES ROUGH-IN
$PERMIT FEE PLUMBING
$PLAN CHECK FINAL
$SURCHARGE ROUGH-IN
$METRO SAC METER SIZE
$CITY WATER HOOKUP UNIT PRESSURE REDUCING VALVE
$CITY SEWER HOOKUP UNIT SEWER/WATER
$LANDSCAPE ESCROW SEWER/WATER
$TREE ESCROW FINAL
$MISC ESCROW STREET DRAINTILE
$PLUMBING BUILDING INFORMATION
$MECHANICAL TYPE OF CONSTRUCTION
$SEWER WATER ZONING
$OTHER CODE EDITION
$TOTAL FIRE SUPPRESSION SYSTEM
OCCUPANCY GROUP
APPROVED BY:
BUILDING INSPECTOR: Date:
PLUMBING/MECHANICAL
INSPECTOR: Date:
COMMENTS:
20195 Holyoke Avenue, Lakeville, MN 55044
952-985-4400 952-985-4499 fax
www.lakevillemn.gov
Sewer & Water Tie Card
Address:________________________________________
Contractor:______________________________________
Permit Number:__________________________________
Final Date:________________
Street Drain-Tile:______
Size of Water Service: 1”
Comments: AIRTEST SANITARY OVER 20’/2 FITTINGS
THIS CARD MUST BE COMPLETED AND ON-SITE AT TIME
OF SEWER & WATER INSPECTION
Concept Approval ONLYSubject to Field InspectionInspectorDate2020MN BldgCode10/01/2020dmathews
Secure door closed until deck isconstructed with a separate permit.
Interior BWP AboveUFER Ground-Provide 20' Rebar in footing and stubup near electrical service panel.3ply 9-1/2" or 2ply
11-7/8" lvl
(3)14" LVL
4' WSP4' WSP4' WSP4' WSP4' WSP2'CS-PF2'CS-PFCS-PFCS-PFCS-PF2'CS-PF2'CS-PF2'CS-PF2'CS-PF2'CS-PF2'CS-PF(2)9-1/2 LVL(3)14" LVL
CS-PFCS-PFCS-PFCS-PFCS-PFCS-PF-Min. 15" clearance to anyobstruction from center ofW.C., 24" in front(typ).
B.W.
LINE B1
4'-0"
WSP
4'-0"
WSP
4'-0"
WSP
4'-0"
WSP
BRACED PANEL TYPE
WSP = 7/16 OSB
GWB = 1/2" GYP BOTH SIDES
CS-PF = CONTINUOSLY SHEATHED PORTAL FRAME -
IRC FIGURE R602.10.4.6 (SEE SHT. 3 & 4)
BASEMENT
BRACED WALL
LINES
1
Scale: 1/16" = 1'-0"
BASEMENT1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
1'-6"1'-6"
CS-PF
1'-6"
CS-PF
2'-0"
CS-PF
2'-0"
B.W.
LINE 1A
B.W.
LINE 1B 40'-0"2'-0"
CS-PF
2'-0"
4'-0"
WSP
4'-0"
WSP
2'-0"2'-0"
CS-PF
B.W.
LINE GA 18'-0"B.W.LINE G1B.W.LINE G2B.W.LINE 12B.W.LINE 13B.W.LINE 11WSP4'-0"WSP4'-0"WSP4'-0"WSP4'-0"4'-0"WSP4'-0"WSP4'-0"WSP4'-0"GWB2'-0"CS-PF2'-0"4'-0"GWBWSP4'-0"4'-0"GWB4'-0"WSP4'-0"WSP30'-0"
1ST FLOOR
BRACED WALL
LINES
2
Scale: 1/16" = 1'-0"
FIRST FLOOR1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
B.W.LINE 211'-6"1'-6"
CS-PF
1'-6"
CS-PF
WSP4'-0"WSP4'-0"WSP4'-0"4'-0"WSP4'-0"WSP4'-0"WSP4'-0"
WSP
1'-6"
1'-6"
CS-PF
1'-6"B.W.LINE 22B.W.
LINE 2A
B.W.
LINE 2B 40'-0"30'-0"
2ND FLOOR
BRACED WALL
LINES
3
Scale: 1/16" = 1'-0"
SECOND FLOOR1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
EXTENT OF HEADER WITH DOUBLE PORTAL FRAMES (TWO BRACED WALL PANELS)
EXTENT OF HEADER WITH SINGLE PORTAL FRAME
(ONE BRACED WALL PANEL)
2′-18′ FINISHED WIDTH OF OPENINGFOR SINGLE OR DOUBLE PORTAL
PONY WALL
HEIGHT
MIN. 3″x11¼″ NET HEADER STEEL HEADER PROHIBITED
IF ½″ SPACER IS USED, PLACE ON BACK-SIDE OF HEADER
FASTEN SHEATHING TO HEADER WITH 8D
COMMON OR GALVANIZED BOX NAILS IN 3″ GRID
PATTERN AS SHOWN
HEADER TO JACK-STUD STRAP PER TABLE
R602.10.6.4 ON BOTH SIDES OF OPENINGOPPOSITE SIDE OF SHEATHING
MIN. DOUBLE 2″x4″ FRAMING COVERED WITH MIN.7/16″ THICK WOOD STRUCTURAL PANEL SHEATHINGWITH 8D COMMON OR GALVANIZED BOX NAILS AT
3″ O.C. IN ALL FRAMING (STUDS,
BLOCKING, AND SILLS) TYP.
MIN. LENGTH OF PANEL PER TABLE R602.10.5
MIN. (2) ½″ DIAMETER ANCHOR BOLTSINSTALLED PER SECTION R403.1.6 WITH
2″x2″x3/16″ PLATE WASHER
TENSION STRAP PERTABLE 602.10.6.4
(ON OPPOSITE SIDE
OF SHEATHING)
BRACED WALL LINECONTINUOUSLY SHEATHEDWITH WOOD STRUCTURALPANELS
IF NEEDED, PANELSPLICE EDGES SHALL
OCCUR OVER AND BE
NAILED TO COMMON
BLOCKING WITHIN THEMIDDLE 24″ OF THEPORTAL- LEG HEIGHT.ONE ROW OF 3″ O.C.
NAILING IS REQUIRED
IN EACH PANEL EDGE.
TYPICAL PORTAL
FRAME CONSTRUCTION
MIN. DOUBLE 2x4 POST(KING AND JACK STUD)
NUMBER OF JACK
STUDS PER TABLES
R602.7(1) & (2)
FASTEN TOP
PLATE TOHEADER WITHTWO
ROWS OF 16D
SINKER NAILS AT
3″ O.C. TYP.
MIN. 7 /16″ WOOD
STRUCTURAL
PANELSHEATHING
FASTEN KING STUDTO HEADER WITH 6
16D SINKERS
OVER CONCRETE OR MASONRY BLOCK FOUNDATION ANCHOR BOLTS PER
SECTION R403.1.612″ MAX. TOTAL WALL HEIGHT10″ MAX. HEIGHTFIGURE R602.10.6.4
ALTERNATE
BRACED WALL
PANEL
4
Scale: Not to Scale
CONTINUOUSLY SHEATHED PORTAL FRAME1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
WOOD STRUCTURAL PANELSHEATHING TO TOP OF BAND
OR RIM JOIST
NAIL SOLE PLATE
TO JOIST PERTABLE R602.3(1)
(2) FRAMING ANCHORS
APPLIED ACROSS
SHEATHING JOINT WITH A
CAPACITY OF 670 LBS INTHE HORIZONTAL ANDVERTICAL DIRECTIONS
NAIL SOLE
PLATE TO JOISTPER TABLER602.3(1)
WOOD STRUCTURAL PANEL SHEATHING OVER APPROVED BAND OR RIM JOIST
OVER RAISED WOOD FLOOR - FRAMING ANCHOR OPTION
(WHERE PORTAL SHEATHING DOES NOT LAP OVER BAND OR RIM JOIST)
APPROVED BANDOR RIM JOIST
WOOD STRUCTURAL PANEL
SHEATHING TO TOP OF BAND
OR RIM JOIST
NAIL SOLE PLATETO JOIST PERTABLE R602.3(1)
ATTACH SHEATHING TO
BAND OR RIM JOIST WITH
8D COMMON NAILS AT 3″
O.C. TOP AND BOTTOM
WOOD STRUCTURAL PANEL SHEATHING OVER APPROVED BAND OR RIM JOIST
OVER RAISED WOOD FLOOR - OVERLAP OPTION
(WHERE PORTAL SHEATHING LAPS OVER BAND OR RIM BOARD)
FRONT ELEVATION
FIGURE R602.10.6.4
SECTION
NAIL SOLEPLATE TO JOISTPER TABLER602.3(1)
APPROVED BANDOR RIM JOISTMIN.OVERLAP9¼″ALTERNATE
BRACED WALL
PANEL
5
Scale: Not to Scale
CONTINUOUSLY SHEATHED PORTAL FRAME1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
SOLID BLOCKING BETWEEN
RAFTERS ATTACHED TO TOP
PLATES WITH 8d @ 6″ O.C. ALONG
LENGTH OF BRACED WALL PANEL
FIGURE R602.10.8.2(1)
BRACED WALL PANEL CONNECTION
TO PERPENDICULAR RAFTERS15.25″ MAX2″ MAXOPENBRACED WALL
PANEL
CONNECTION TO
RAFTERS
6
Scale: Not to Scale
BRACED WALL PANEL CONNECTION TO RAFTERS1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
CONTINUOUS RIM
OR BAND JOIST
FULL-HEIGHT BLOCKING
CONTINUOUS ALONG LENGTH
OF BRACED WALL PANEL
PERPENDICULAR FRAMING
8d @ 6″ O.C. ALONG
BRACED WALL PANEL
8d @ 6″ O.C. ALONG
BRACED WALL PANEL
BRACED WALL PANEL
BRACED WALL PANEL
3-16d @ 16″ O.C. ALONG
BRACED WALL PANEL
3-16d @ 16″ O.C. ALONG
BRACED WALL PANEL
PERPENDICULAR FRAMING
CONTINUOUS RIM
OR BAND JOIST
FIGURE R602.10.8(1)
BRACED WALL PANEL CONNECTION WHEN PERPENDICULAR TO FLOOR/CEILING FRAMING
FULL-HEIGHT BLOCKING
CONTINUOUS ALONG LENGTH
OF BRACED WALL PANEL
BRACED WALL
PANEL
CONNECTIONS
TO FLOOR /CLG
7
Scale: Not to Scale
BRACED PANEL CONNECTIONS1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
CONTINUOUS RIM
OR END JOIST
ADDITIONAL FRAMING
MEMBER DIRECTLY ABOVE
BRACED WALL PANEL
FULL-HEIGHT BLOCKING
@ 16″ O.C. ALONG
BRACED WALL PANEL
8d @ 6″ O.C. ALONG
BRACED WALL PANEL
8d @ 6″ O.C. ALONG
BRACED WALL PANEL TOE NAIL 3-8d
NAILS AT EACH
BLOCKING
MEMBER
BRACED WALL PANEL
BRACED WALL PANEL
3-16d @ 16″ O.C. ALONG
BRACED WALL PANEL 3-16d @ 16″ O.C. ALONG
BRACED WALL PANEL
BRACED WALL PANEL
3-16d AT EACH
BLOCKING MEMBER
2-16d NAILS
EACH SIDE
CONTINUOUS RIM
OR END JOIST
FIGURE R602.10.8(2)
BRACED WALL PANEL CONNECTION WHEN PARALLEL TO FLOOR/CEILING FRAMING
ADDITIONAL FRAMING
MEMBER DIRECTLY BELOW
BRACED WALL PANEL
FULL-HEIGHT BLOCKING
@ 16″ O.C. ALONG
BRACED WALL PANEL
BRACED WALL
PANEL
CONNECTIONS
TO FLOOR /CLG
8
Scale: Not to Scale
BRACED PANEL CONNECTIONS1
_____________________________________
9171 187TH ST
LAKEVILLE, MN
BLANCHARD
ENGINEERING
6936 WASHBURN AVE. S.
RICHFIELD, MN 55423
612-861-6361CCOPYRIGHT BLANCHARD ENGINEERING
BRACED WALLS
9171 187th St Lakeville
FIG. R602.10.1.3 LAKEVILLE, MN
WIND BRACING
115 MPH
DETACHED
MAX. SPA. = 60 FEET
REQUIRED BRACING LENGTH TABLE R602.10.3(1)
ADJUSTMENT FACTORS TABLE R602.10.3(2)
EXPOSURE
2 STORY
CONDITION B
ADJ FACTOR 1.00
ROOF EAVE TO RIDGE HT
HT = 10.5'
ADJ FACTOR 1.03
WALL HEIGHT ADJUSTMENT
HT. 1ST = 9.25'
ADJ FACTOR = 0.96
NUMBER OF BRACED WALL LINES
2 1.00
3 1.30
4 1.45
B. W.
LINE
SPA. MIN.
LENGTH
EXPOSURE EAVE TO
RIDGE HT.
WALL HT. NO. OF
BWL
TOTAL
ADJ.
MIN.
REQ'D
PROVIDED
21 30.0 4.5 1.00 1.03 0.96 1.00 0.99 4.4 12.0
22 30.0 4.5 1.00 1.03 0.96 1.00 0.99 4.4 12.0
2A 40.0 6.0 1.00 1.03 0.96 1.00 0.99 5.9 16.0
2B 40.0 6.0 1.00 1.03 0.96 1.00 0.99 5.9 12.0
G1 30.0 4.5 1.00 1.03 0.96 1.00 0.99 4.4 8.0
G2 30.0 4.5 1.00 1.03 0.96 1.00 0.99 4.4 8.0
GA 18.0 3.2 1.00 1.03 0.96 1.00 0.99 3.2 12.0
11 9.0 3.2 1.00 1.03 0.96 1.30 1.29 4.1 12.0
12 30.0 9.0 1.00 1.03 0.96 1.30 1.29 11.6 16.0
13 30.0 9.0 1.00 1.03 0.96 1.30 1.29 11.6 16.0
1A 40.0 11.5 1.00 1.03 0.96 1.00 0.99 11.4 16.0
1B 40.0 11.5 1.00 1.03 0.96 1.00 0.99 11.4 16.0
B1 LINE 1A X 1.15 =13.1 16.0
ADJUSTMENT FACTORS
Hebert
HVAC Load Calculations
for
Hebert
9171 187th St W
Lakeville,mn
Prepared By:
Randy Andrews
Lofgren Heating
5708 Upper 147th Street West
Apple Vallley, MN 55124
Wednesday, September 02, 2020
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 2
Project Report
General Project Information
Project Title:Hebert
Project Date:Wednesday, September 02, 2020
Client Name:Hebert
Client Address:9171 187th St W
Client City:Lakeville,mn
Company Name:Lofgren Heating
Company Representative:Randy Andrews
Company Address:5708 Upper 147th Street West
Company City:Apple Vallley, MN 55124
Company E-Mail Address:rrandrews@lofgrenheating-ac.com
Design Data
Reference City:Minneapolis, Minnesota
Building Orientation:Front door faces Southeast
Daily Temperature Range:Medium
Latitude:44 Degrees
Elevation:834 ft.
Altitude Factor:0.970
Elevation Sensible Adj. Factor:1.000
Elevation Total Adj. Factor:1.000
Elevation Heating Adj. Factor:1.000
Elevation Heating Adj. Factor:1.000
Outdoor Outdoor Outdoor Indoor Indoor Grains
Dry Bulb Wet Bulb Rel.Hum Rel.Hum Dry Bulb Difference
Winter:-15 -15.33 80%n/a 72 n/a
Summer:88 72 47%50%75 29
Check Figures
Total Building Supply CFM:1,188 CFM Per Square ft.:0.298
Square ft. of Room Area:3,984 Square ft. Per Ton:1,385
Volume (ft³) of Cond. Space:34,636
Building Loads
Total Heating Required Including Ventilation Air:57,647 Btuh 57.647 MBH
Total Sensible Gain:25,892 Btuh 79 %
Total Latent Gain:6,702 Btuh 21 %
Total Cooling Required Including Ventilation Air:32,593 Btuh 2.72 Tons (Based On Sensible + Latent)
2.88 Tons (Based On 75% Sensible
Capacity)
Notes
Calculations are based on 8th edition of ACCA Manual J.
All computed results are estimates as building use and weather may vary.
Be sure to select a unit that meets both sensible and latent loads.
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 3
Load Preview Report
Scope
Has
AED
Net
Ton
ft.²
/Ton Area
Sen
Gain
Lat
Gain
Net
Gain
Sen
Loss
Sys
Htg
CFM
Sys
Clg
CFM
Sys
Act
CFM
Duct
Size
Building 2.72 1,467 3,984 25,892 6,702 32,593 57,647 1,051 1,188 1,188
System 1 No 2.72 1,467 3,984 25,892 6,702 32,593 57,647 1,051 1,188 1,188 21x10
Ventilation 534 1,352 1,886 7,150
Zone 1 3,984 25,358 5,350 30,708 50,497 1,051 1,188 1,188 21x10
1-Main Level 1,382 11,599 1,914 13,513 19,444 405 543 543 6--6
2-Upper Level 1,220 10,494 2,422 12,916 15,874 331 492 492 6--6
3-Lower Level 1,382 3,264 1,014 4,278 15,179 316 153 153 2--6
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 4
Total Building Summary Loads
Component
Description
Area
Quan
Sen
Loss
Lat
Gain
Sen
Gain
Total
Gain
4A-1a-o: Glazing-Double pane low-e (e = 0.20 or less),
operable window, e=0.20 on surface 2, wood with
metal clad frame, u-value 0.32, SHGC 0.33
403 11,220 0 10,780 10,780
11N: Door-Metal - Polystyrene Core 63 1,918 0 529 529
12F-0sw: Wall-Frame, R-21 insulation in 2 x 6 stud
cavity, no board insulation, siding finish, wood studs
2509 14,188 0 2,169 2,169
15BO-10sf-10: Wall-1089 4,642 0 709 709
16B-50: Roof/Ceiling-Under Attic with Insulation on Attic
Floor (also use for Knee Walls and Partition
Ceilings), Vented Attic, No Radiant Barrier, Dark
Asphalt Shingles or Dark Metal, Tar and Gravel or
Membrane, R-50 insulation
1220 2,123 0 1,171 1,171
21A-24: Floor-Basement, Concrete slab, any thickness, 2
or more feet below grade, no insulation below floor,
any floor cover, shortest side of floor slab is 24' wide
1382 3,006 0 0 0
Subtotals for structure:37,097 0 15,358 15,358
People:7 1,400 1,610 3,010
Equipment:2,500 7,000 9,500
Lighting:0 0 0
Ductwork:0 0 0 0
Infiltration: Winter CFM: 144, Summer CFM: 75 13,400 1,450 1,041 2,491
Ventilation: Winter CFM: 140, Summer CFM: 70 7,150 1,352 534 1,886
AED Excursion:0 0 349 349
Total Building Load Totals:57,647 6,702 25,892 32,593
Check Figures
Total Building Supply CFM:1,188 CFM Per Square ft.:0.298
Square ft. of Room Area:3,984 Square ft. Per Ton:1,385
Volume (ft³) of Cond. Space:34,636
Building Loads
Total Heating Required Including Ventilation Air:57,647 Btuh 57.647 MBH
Total Sensible Gain:25,892 Btuh 79 %
Total Latent Gain:6,702 Btuh 21 %
Total Cooling Required Including Ventilation Air:32,593 Btuh 2.72 Tons (Based On Sensible + Latent)
2.88 Tons (Based On 75% Sensible
Capacity)
Notes
Calculations are based on 8th edition of ACCA Manual J.
All computed results are estimates as building use and weather may vary.
Be sure to select a unit that meets both sensible and latent loads.
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 5
Building Pie Chart
Building
Loss
57,647
Btuh
Floor 5%Roof 4%
Wall 33%
Glass 19%
Door 3%
Infiltration 23%
Ventilation 12%
Building
Gain
32,593
Btuh
Roof 4%
Wall 9%
Glass 33%
Door 2%People 9%
Equipment 29%
Infiltration 8%
Ventilation 6%AED Excursion 1%
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 6
System 1 Whole House Summary Loads
Component
Description
Area
Quan
Sen
Loss
Lat
Gain
Sen
Gain
Total
Gain
4A-1a-o: Glazing-Double pane low-e (e = 0.20 or less),
operable window, e=0.20 on surface 2, wood with
metal clad frame, u-value 0.32, SHGC 0.33
403 11,220 0 10,780 10,780
11N: Door-Metal - Polystyrene Core 63 1,918 0 529 529
12F-0sw: Wall-Frame, R-21 insulation in 2 x 6 stud
cavity, no board insulation, siding finish, wood studs
2509 14,188 0 2,169 2,169
15BO-10sf-10: Wall-1089 4,642 0 709 709
16B-50: Roof/Ceiling-Under Attic with Insulation on Attic
Floor (also use for Knee Walls and Partition
Ceilings), Vented Attic, No Radiant Barrier, Dark
Asphalt Shingles or Dark Metal, Tar and Gravel or
Membrane, R-50 insulation
1220 2,123 0 1,171 1,171
21A-24: Floor-Basement, Concrete slab, any thickness, 2
or more feet below grade, no insulation below floor,
any floor cover, shortest side of floor slab is 24' wide
1382 3,006 0 0 0
Subtotals for structure:37,097 0 15,358 15,358
People:7 1,400 1,610 3,010
Equipment:2,500 7,000 9,500
Lighting:0 0 0
Ductwork:0 0 0 0
Infiltration: Winter CFM: 144, Summer CFM: 75 13,400 1,450 1,041 2,491
Ventilation: Winter CFM: 140, Summer CFM: 70 7,150 1,352 534 1,886
AED Excursion:0 0 349 349
System 1 Whole House Load Totals:57,647 6,702 25,892 32,593
Check Figures
Supply CFM:1,188 CFM Per Square ft.:0.298
Square ft. of Room Area:3,984 Square ft. Per Ton:1,385
Volume (ft³) of Cond. Space:34,636
System Loads
Total Heating Required Including Ventilation Air:57,647 Btuh 57.647 MBH
Total Sensible Gain:25,892 Btuh 79 %
Total Latent Gain:6,702 Btuh 21 %
Total Cooling Required Including Ventilation Air:32,593 Btuh 2.72 Tons (Based On Sensible + Latent)
2.88 Tons (Based On 75% Sensible
Capacity)
Notes
Calculations are based on 8th edition of ACCA Manual J.
All computed results are estimates as building use and weather may vary.
Be sure to select a unit that meets both sensible and latent loads.
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 7
Detailed Room Loads - Room 1 - Main Level (Average Load Procedure)
General
Calculation Mode:Htg. & clg.Occurrences:1
Room Length:1,382.0 ft.System Number:1
Room Width:1.0 ft.Zone Number:1
Area:1,382.0 sq.ft.Supply Air:543 CFM
Ceiling Height:9.0 ft.Supply Air Changes:2.6 AC/hr
Volume:12,438.0 cu.ft.Req. Vent. Clg:0 CFM
Number of Registers:6 Actual Winter Vent.:54 CFM
Runout Air:91 CFM Percent of Supply.:10 %
Runout Duct Size:6 in.Actual Summer Vent.:32 CFM
Runout Air Velocity:461 ft./min.Percent of Supply:6 %
Runout Air Velocity:461 ft./min.Actual Winter Infil.:51 CFM
Actual Loss:0.133 in.wg./100 ft.Actual Summer Infil.:27 CFM
Item
Description
Area
Quantity
-U-
Value
Htg
HTM
Sen
Loss
Clg
HTM
Lat
Gain
Sen
Gain
NW-Wall-12F-0sw 39 X 9 255 0.065 5.7 1,442 0.9 0 220
SE-Wall-12F-0sw 39 X 9 258 0.065 5.7 1,459 0.9 0 223
NE-Wall-12F-0sw 41 X 9 336 0.065 5.7 1,900 0.9 0 290
SW-Wall-12F-0sw 41 X 9 303 0.065 5.7 1,713 0.9 0 262
SE-Door-11N 6 X 7 42 0.350 30.5 1,279 8.4 0 353
SE-Door-11N 3 X 7 21 0.350 30.5 639 8.4 0 176
NW-Gls-4A-1a-o shgc-0.33 0%S 96 0.320 27.8 2,673 24.1 0 2,317
SE-Gls-4A-1a-o shgc-0.33 0%S 30 0.320 27.8 835 31.0 0 929
NE-Gls-4A-1a-o shgc-0.33 0%S 33 0.320 27.8 919 24.2 0 797
SW-Gls-4A-1a-o shgc-0.33 0%S 66 0.320 27.8 1,837 31.0 0 2,044
Subtotals for Structure:14,696 0 7,611
Infil.: Win.: 51.1, Sum.: 26.6 1,440 3.297 4,748 0.256 514 369
AED Excursion:159
People: 200 lat/per, 230 sen/per:2 400 460
Equipment:1,000 3,000
Room Totals:19,444 1,914 11,599
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 8
Detailed Room Loads - Room 2 - Upper Level (Average Load Procedure)
General
Calculation Mode:Htg. & clg.Occurrences:1
Room Length:1,220.0 ft.System Number:1
Room Width:1.0 ft.Zone Number:1
Area:1,220.0 sq.ft.Supply Air:492 CFM
Ceiling Height:8.0 ft.Supply Air Changes:3.0 AC/hr
Volume:9,760.0 cu.ft.Req. Vent. Clg:0 CFM
Number of Registers:6 Actual Winter Vent.:44 CFM
Runout Air:82 CFM Percent of Supply.:9 %
Runout Duct Size:6 in.Actual Summer Vent.:29 CFM
Runout Air Velocity:417 ft./min.Percent of Supply:6 %
Runout Air Velocity:417 ft./min.Actual Winter Infil.:42 CFM
Actual Loss:0.109 in.wg./100 ft.Actual Summer Infil.:22 CFM
Item
Description
Area
Quantity
-U-
Value
Htg
HTM
Sen
Loss
Clg
HTM
Lat
Gain
Sen
Gain
NW-Wall-12F-0sw 30 X 8 195 0.065 5.7 1,103 0.9 0 169
SE-Wall-12F-0sw 30 X 8 188 0.065 5.7 1,063 0.9 0 163
NE-Wall-12F-0sw 44 X 8 313 0.065 5.7 1,770 0.9 0 271
SW-Wall-12F-0sw 44 X 8 346 0.065 5.7 1,957 0.9 0 299
NW-Gls-4A-1a-o shgc-0.33 0%S 45 0.320 27.8 1,253 24.1 0 1,086
SE-Gls-4A-1a-o shgc-0.33 0%S 52 0.320 27.8 1,448 31.0 0 1,611
NE-Gls-4A-1a-o shgc-0.33 0%S 39 0.320 27.8 1,086 24.1 0 941
SW-Gls-4A-1a-o shgc-0.33 0%S 6 0.320 27.8 167 31.0 0 186
UP-Ceil-16B-50 1220 X 1 1220 0.020 1.7 2,123 1.0 0 1,171
Subtotals for Structure:11,970 0 5,897
Infil.: Win.: 42.0, Sum.: 21.9 1,184 3.297 3,904 0.256 422 303
AED Excursion:144
People: 200 lat/per, 230 sen/per:5 1,000 1,150
Equipment:1,000 3,000
Room Totals:15,874 2,422 10,494
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 9
Detailed Room Loads - Room 3 - Lower Level (Average Load Procedure)
General
Calculation Mode:Htg. & clg.Occurrences:1
Room Length:1,382.0 ft.System Number:1
Room Width:1.0 ft.Zone Number:1
Area:1,382.0 sq.ft.Supply Air:153 CFM
Ceiling Height:9.0 ft.Supply Air Changes:0.7 AC/hr
Volume:12,438.0 cu.ft.Req. Vent. Clg:0 CFM
Number of Registers:2 Actual Winter Vent.:42 CFM
Runout Air:76 CFM Percent of Supply.:28 %
Runout Duct Size:6 in.Actual Summer Vent.:9 CFM
Runout Air Velocity:389 ft./min.Percent of Supply:6 %
Runout Air Velocity:389 ft./min.Actual Winter Infil.:51 CFM
Actual Loss:0.095 in.wg./100 ft.Actual Summer Infil.:27 CFM
Item
Description
Area
Quantity
-U-
Value
Htg
HTM
Sen
Loss
Clg
HTM
Lat
Gain
Sen
Gain
NW-Wall-12F-0sw 39 X 9 315 0.065 5.7 1,781 0.9 0 272
SE-Wall-15BO-10sf-10 39 X 9 351 0.049 4.3 1,496 0.7 0 229
NE-Wall-15BO-10sf-10 41 X 9 369 0.049 4.3 1,573 0.7 0 240
SW-Wall-15BO-10sf-10 41 X 9 369 0.049 4.3 1,573 0.7 0 240
NW-Gls-4A-1a-o shgc-0.33 0%S 36 0.320 27.8 1,002 24.1 0 869
Floor-21A-24 1 X 1382 1382 0.025 2.2 3,006 0.0 0 0
Subtotals for Structure:10,431 0 1,850
Infil.: Win.: 51.1, Sum.: 26.6 1,440 3.297 4,748 0.256 514 369
AED Excursion:45
Equipment:500 1,000
Room Totals:15,179 1,014 3,264
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
Rhvac - Residential & Light Commercial HVAC Loads Elite Software Development, Inc.
Lofgren Htg. & A/C Hebert
Farmington, MN 55024 Page 10
System 1 Room Load Summary
No
Room
Name
Area
SF
Htg
Sens
Btuh
Min
Htg
CFM
Run
Duct
Size
Run
Duct
Vel
Clg
Sens
Btuh
Clg
Lat
Btuh
Min
Clg
CFM
Act
Sys
CFM
---Zone 1---
1 Main Level 1,382 19,444 405 6-6 461 11,599 1,914 543 543
2 Upper Level 1,220 15,874 331 6-6 417 10,494 2,422 492 492
3 Lower Level 1,382 15,179 316 2-6 389 3,264 1,014 153 153
Ventilation 7,150 534 1,352
System 1 total 3,984 57,647 1,051 25,892 6,702 1,188 1,188
System 1 Main Trunk Size:21x10 in.
Velocity:815 ft./min
Loss per 100 ft.:0.098 in.wg
Cooling System Summary
Cooling
Tons
Sensible/Latent
Split
Sensible
Btuh
Latent
Btuh
Total
Btuh
Net Required:2.72 79% / 21%25,892 6,702 32,593
Recommended:2.88 75% / 25%25,892 8,631 34,522
Actual:1.00 77% / 23%9,240 2,760 12,000
Equipment Data
Heating System Cooling System
Type:Natural Gas Furnace Standard Air Conditioner
Model:QC-F38-E78-G QC-C12
Indoor Model:S12
Brand:Quikcool FE Series Quikcool AS Series
Description:Hi Efficiency Furnace Standard Efficiency Air Condit
Efficiency:78.3 AFUE 12.4 SEER
Sound:8.1 bels
Capacity:38,000 Btuh 12,000 Btuh
Sensible Capacity:n/a 9,240 Btuh
Latent Capacity:n/a 2,760 Btuh
C:\ ...\9171 187TH LAKEVILLE 09022020.rhv Wednesday, September 02, 2020, 10:34 AM
9/21/20 X
DJM