HomeMy WebLinkAboutItem 06.n Date: January 19, 2021 Item No.
PROPOSAL FROM STANTEC FOR PROFESSIONAL SERVICES
FOR 165th STREET WATERSHED DRAINAGE SYSTEM IMPROVEMENTS
Proposed Action
Staff recommends adoption of the following motion: Move to accept Stantec proposal for
professional services for the 165th Street Watershed Drainage System Improvements, City Project
20-45.
Overview
The Lakeville 5-year Capital Improvement Plan (2021-2025) programs drainage system
improvements to the 165th Street watershed. The project is intended to address localized flooding
and stormwater infrastructure capacity issues. Proposed improvements include expansion of an
existing stormwater management basin, installation of a new outlet control structure, and
enhancements to facilitate infiltration and improve water quality. The proposed project schedule is
a) design in Winter/Spring 2021; and b) construction in Summer/Fall 2021.
Stantec’s proposal identifies the scope of services and estimated cost to complete the final design,
construction staking and assistance in field construction oversight.
Primary Issues to Consider
• Proposal is subject to the Master Agreement for Professional Engineering Services between
the City and Stantec approved by the City Council on July 18, 2016
• Additional project funding for engineering and construction is provided in the form of a
$250,000 grant from the Lower Minnesota River Watershed District and the Minnesota
Board of Soil and Water Resources.
Supporting Information
• Stantec proposal dated January 14, 2021
Financial Impact: $48,900 Budgeted: Y☒ N☐ Source: Stormwater Infra. Fund and Grant
Related Documents: Lakeville 5-year Capital Improvement Plan (2021-2025)
Envision Lakeville Community Values: Good Value for Public Services
Report Completed by: McKenzie Cafferty, Environmental Resources Manager
Stantec Consulting Services Inc.
1800 Pioneer Creek Center, Maple Plain, MN 55359
January 14th, 2021
File: B005895-19-020
Attention: Mac Cafferty, Natural Resource Manger
City Hall
201995 Holyoke Avenue
Lakeville, MN 55044
Dear Mr. Cafferty,
Reference: Proposal to Complete Design, Bidding, and Construction Oversight for the 165th Street
Water Quality Improvement Project
We are pleased to present to you this proposal to assist the City of Lakeville with the next stage of the 165th
Street Drainage Improvement Project. We have partnered with the City to complete the initial design
evaluation for the project. This proposal describes efforts to complete the design and construction of a
portion of the project.
Project Understanding
In 2020 the City of Lakeville (City) completed an evaluation for several drainage and water quality
improvement options for the 165th Street Office Park. Wenck (now part of Stantec) assisted the City with
this evaluation. In Fall of 2020, the City submitted an application for grant funding to the Lower Minnesota
Watershed District. The City was awarded grant funds to complete one aspect of the project which includes
modifications to the stormwater pond adjacent to the Harley Davidson dealership, located south of 165th
Street between Kenrick Avenue and Kentucky Avenue. The project will include the multiple components:
increase the live storage of the pond through excavation; installation of a new outlet control structure; and
adding a sand filter bench for water quality treatment. This project will have the following benefits: adding
flood storage volume to the Lee Lake/Crystal Lake watersheds (which generally lack storage volume),
improving water quality within the watershed, and reducing nuisance drainage conditions (during larger rain
events the public 165th Street sewer backs onto private property at the office park located east of the pond).
This proposal provides a scope and budget to complete several tasks including: development of a grant
work plan; complete the final design plan set; public bidding process; construction staking and oversight;
as-built surveys; and assisting with grant administration.
Task 1 – Develop Grant Workplan
As part of the process to secure the grant funds, a work plan describing the tasks to be completed needs to
be submitted to the Lower Minnesota River Watershed and the Minnesota Board of Soil and Water
Resources (BWSR). We will work with the City to develop the work plan which will include a description of
the activities to be completed and an estimated project schedule. We will develop the work plan based on
examples from other grant projects. We will provide a draft of the plan to the City for review, address one
round of comments, and then provide the final submittal to the Watershed and BWSR. Task Estimate:
$1,500
January 14, 2021
Mr. Mac Cafferty
Page 2 of 5
Reference: 165th Street Water Quality Project Proposal
Task 2 – Complete Final Design and Engineering Plan Set
The current plans for this project are at the 60% design level. We will prepare a 90% design plan set
and provide these plans to the City for review and comment. We will also provide an updated cost
estimate. We will coordinate a web-based design review meeting with the City to discuss comments.
Based on the design review meeting and comments provided by the City, we will prepare the final
engineering plan set for bidding and construction. We estimate that the final plan set will contain
multiple sheets including: existing conditions; removals; notes & erosion control; plan view of the pond
improvements; plan view of the outlet structure replacement; profile views of the pond improvements
and outlet structure, and three detail sheets. Task Estimate: $14,600
Task 3 – Bid Package and Public Bidding Process
We will prepare the full Bid Package including the engineering plans for construction, project details,
project specifications, and notice to bidders. We will post the Bid Package to Quest to initiate the public
bidding process. Our experience with recent City projects indicates that conducting a pre-bid meeting
with potential contractors at the project site is beneficial to the overall bidding process. The onsite pre-
bid meeting allows contractors to see important components of project access for construction and
allows for time to directly answer contractor questions which results in competitive bid prices. We will
attend the mandatory pre-bid field meeting with the potential bidders and attend the bid opening with
the City. For this task we will plan to complete the bid opening following the online option through Quest
to continue to follow COVID safety protocols. Our assumption is this task will be completed in the same
manner as the Middle Creek online bid opening in September 2020. We will answer questions from the
contractors during the bid period as needed. After the bid opening, we will compile the bid tabulation
and will be provide it to the City along with a recommendation for moving forward with contractor
selection. Task Estimate: $7,200
Task 4 – Contractor Management
We will partner with the City to coordinate the field schedule with the project contractor. We will
complete review of material submittals for specific project components in preparation for construction.
We will also review the contract items submitted for payment and provide confirmation to the City on the
completed items to authorize payment. Task Estimate: $4,500
Task 5 – Construction Staking and Field Construction Oversight
We will provide field staking, including known utilities to facilitate the construction of the project. We will
stake the access and staging areas along City property and clearly mark “No Access” areas identified by
the City to the contractor. We will also provide stakes showing the locations of specific design features
and elevations that need to be called out for the project. After the initial staking of work limits and design
practices the contractor will be responsible for maintaining/replacing damaged or lost stakes.
We have worked directly with City staff to conduct construction inspections site visits for similar
stormwater projects. Based on the scale of the 165th Street project, we anticipate construction will take
three to four weeks. We will lead an initial pre-construction kickoff meeting with the City and selected
contractor. We will complete up to ten site visits in coordination with City staff during construction to
ensure key design components are properly installed and connected to existing City infrastructure. We will
January 14, 2021
Mr. Mac Cafferty
Page 3 of 5
Reference: 165th Street Water Quality Project Proposal
coordinate directly with City staff during construction and provide verbal field updates to City each day our
field staff are onsite at the project. During the last week of project construction, we will develop a punch
list of final project items that need to be addressed before construction can be certified as complete. We
will review the punch list with the City and the construction contractor to ensure the project design and
specifications have been met. Task Estimate: $16,000
Task 6 – Final Project Review and As-Built Surveys
We will review the final contract submittals for the project from the construction contractor and provide a
recommendation to the City on the final project status. The final payment application will be reviewed and
provided to the City for their records and processing. Additionally, we will collect survey information on
the installed elevation of various project features during construction of the project. We will use the
survey data collected during construction to create a final as-built plan sheet that will be provided to the
City in PDF and GIS format (shapefiles or geodatabases) for inclusion within their GIS database. Task
Estimate: $2,500.
Task 7 – Public Outreach
There will be interest in the drainage improvement projects associated with the 165th Street office park,
including this pond improvement project. The City will want to provide some information to residents and
businesses in the area. Under this task we will assist the City with preparation of a one-page project
summary to distribute and participate in one public informational meeting. Task Estimate: $1,400.
Task 8 – Grant Assistance
During the project there will be requirements to provide updates to the Lower Minnesota River
Watershed and BWSR on the progress of the project under the grant. Additionally, some progress
submittals are required. Our team has experience with grant reporting requirements. We will provide
data and assistance to the City to submit interim project progress updates as part of the grant, which are
usually required two times per year. Task Estimate: $1,200.
Project Schedule and Cost
We will begin working on the project immediately upon receipt of authorization from the City. Assuming that
this proposal is approved at the Lakeville City Council meeting on Tuesday January 19th, we will begin
completing Task 1 with a goal to have the work plan complete by the end of January. The bulk of the work
for the project cannot begin until the grant funds are released to the City. It is estimated that the grant funds
will be available to begin Tasks 2 through 7 sometime in late March to early April. Our goal will be to begin
Task 2 design in April and have it completed by June 1st. This would allow bidding of the project in early
summer, which should in turn allow for a wide construction window from late summer through the fall. We
will work with the City to adjust the project schedule as needed to ensure the City goals for completion of
this project are met.
January 14, 2021
Mr. Mac Cafferty
Page 4 of 5
Reference: 165th Street Water Quality Project Proposal
We will complete the tasks described in this proposal for a total not to exceed cost of $48,900. Efforts will
be billed following our time and materials rates. This project will be completed following the terms and
conditions of the agreement between Stantec and the City of Lakeville. If out of scope tasks are identified or
requested, we will provide an estimate to the City for completing additional tasks before proceeding.
As your trusted and experienced partner, we understand the City of Lakeville's needs and will work closely
with your staff from start to finish, maintaining open communication, and consistent responsiveness. To
streamline the process and maintain consistency, we have assigned staff to this project that have
experience working on City of Lakeville projects. Thank you for this opportunity to provide this proposal –
we look forward to working with you.
Regards,
Stantec Consulting Services Inc.
Jeff Madejczyk
Project Manager
763-479-4263
jmadejczyk@wenck.com
Daniel Elemes, PE
Project Engineer
651-395-5225
delemes@wenck.com
January 14, 2021
Mr. Mac Cafferty
Page 5 of 5
Reference: 165th Street Water Quality Project Proposal
By signing this proposal, the City of Lakeville authorizes Stantec to proceed with the services herein
described and the Client acknowledges that it has read and agrees to be bound by the attached
Professional Services Terms and Conditions.
This proposal is accepted and agreed on the ____ day of January 2021
Per: City of Lakeville
Print Name & Title Signature