HomeMy WebLinkAboutItem 07 (DEA)City of Lakeville
Planning Department
Memorandum
To: Planning Commission
From: Frank Dempsey, AICP, Associate Planner
Date: June 11, 2021
Subject: Packet Material for the June 17, 2021 Planning Commission Meeting
Agenda Item: Dakota Electric Association Conditional Use Permit
Application Action Deadline: July 20, 2021
INTRODUCTION
Representatives of Dakota Electric Association (DEA) have submitted an application and plans
for a conditional use permit to construct an electric transformer and switching substation to be
located at 21075 Glade Avenue. The proposed facility would be constructed on the last
remaining commercial lot within Superamerica 2nd Addition platted in 1996. Section 11-73-7.J
of the Zoning Ordinance allows electric substations as essential services requiring approval of a
conditional use permit in the C-2, Highway Commercial District subject to the requirements of
Chapter 26 of the Zoning Ordinance.
The following exhibits are attached for your information:
EXHIBITS
A. Location and Zoning Map
B. Aerial Photo
C. Site Plan
D. Grading Plan
E. Landscaping Plan
F. Cross Section Views (4 pages)
G. Example Street View of Juniper Hedge Screening at 165th Street
2
Surrounding Land Uses and Zoning
North – Spirit of Joy Church (RM-2 District)
South –Lakeville Boulevard and Belzer Auto Dealership (C-2 District)
East – Glade Avenue and Speedway Motor Fuel/Convenience Store (C-2 District)
West – Single Family Home fronting 210th St., 3.8 acres (RM-2 District)
STAFF ANALYSIS
Dakota Electric Association is an electric power cooperative that supplies areas of Dakota, Rice,
Goodhue, and Scott Counties for residential, agricultural, commercial, industrial, and other public
and private customers. There are seven electric substations in Lakeville, most of which were
constructed between the early 1990’s and 2014 as electric demand increased as Lakeville grew in
population and development. DEA has determined that additional electrical transmission/switching
station capacity is needed to serve the growing power needs within the city requiring the
construction of a new facility at the proposed location. It is anticipated that site preparation would
begin in 2021 and installation of the substation equipment would occur in 2022 or 2023. Due to this
anticipated timeline, DEA is requesting a two-year timeframe before the conditional use permit
would expire. The Zoning Ordinance states that a conditional use permit shall expire unless the
project commences within one year of approval.
Existing Conditions
The 1.48 acre property was platted as Lot 2, Block 1, Superamerica 2nd Addition, one of four lots
platted by the Superamerica motor fuel and convenience store group in 1996 for the construction of
the existing motor fuel and convenience store located east of Glade Avenue. The Spirit of Joy
Church north of the subject property was constructed in 1975 but was included as part of the
Superamerica 2nd Addition plat in 1996 for the purpose of road right-of-way dedication and
construction. A 25-foot wide Northern States Power (aka Xcel Energy) electric power utility
easement and a 20-foot wide Northern Natural Gas Company easement run east and west across the
south portion of the property. An Xcel Energy electric transformer and switching stat ion is located
approximately 4/10ths mile to the west that was constructed in 1970 and expanded in the late 1990’s
as part of the installation of the transmission line along Lakeville Boulevard toward Farmington and
south along Hamburg Avenue to CSAH 70 and west toward Interstate 35. That transformer,
switching station, and power lines are unrelated to the proposed DEA substation.
Site Development Plans
Dakota Electric Association has submitted site, grading, landscape, and sectional view plans that
detail the proposed substation layout. Two paved driveway accesses are proposed onto Glade
3
Avenue. The compound area will be gravel surface consistent with other DEA substations in the
city.
Parking. The Zoning Ordinance does not have specific parking requirements for
electric substations. There is adequate area on site for the parking of periodic maintenance
vehicles. Employees will be able to access the substation and park vehicles inside the gated area.
Setbacks. The C-2 District requires that structures be set back a minimum of 30 feet from the
front property (Glade Avenue right-of-way) line, and 30 feet from the north, west, and south
property lines. The additional setback requirements from the north and west property lines are
due to the residential zoning of the adjacent properties. The electrical equipment will meet the
C-2 District setback requirements. A six-foot tall chain link barbed wire security fence will
enclose the property.
Landscaping / Screening / Fencing. The Zoning Ordinance requires commercially zoned
property developments to provide a landscaping buffer adjacent to residentially zoned properties.
A continuous row of tall growing juniper shrubs will be installed along the north, west, and east
boundaries. Flowering crab apple trees will be planted along the south boundary of the site south
of the proposed stormwater basin. The site will be between four and eight feet lower than the
property to the west and one to five feet lower than the property to the north. The juniper shrubs
shall be a minimum of six feet tall at the time of planting. A sample photo of Street View
adjacent to the town-office buildings on 165th Street east of Kenrick Avenue is included as Exhibit
H as an example of screening with tall growing juniper shrubs similar to the ones proposed for
the DEA site’s north and west elevations. A $34,000 financial security shall be submitted to
guarantee installation of the site landscaping. This figure is based on the landscape installer’s
estimate provided by DEA.
Site Lighting. No security lighting is proposed. A city streetlight is located at the north driveway
entrance. Any future security lighting shall be downcast and subject to approval of an electrical
permit.
Construction Schedule. DEA is requesting a two-year timeframe to commence construction on
the site. Due to materials production and delivery schedules, it is possible that construction may
extend beyond the conditional use permit one-year deadline. Staff recommends a two-year
timeframe to commence construction from the date of City Council approval.
Engineering Memorandum. A memorandum has been prepared by Christina Orlowsky, Civil
Engineer, dated June 10, 2021. The memorandum describes site development, grading, and
utilities as well as stormwater management.
4
RECOMMENDATION
Planning Department staff recommends approval of the Dakota Electric Association amendment
to Conditional Use Permit No. 94-05 subject to the following stipulations:
1. The site improvements shall be completed as identified on the site plan approved with the
conditional use permit application.
2. All landscape materials shall comply with the minimum size requirements of the Zoning
Ordinance. The landscape plan shall be revised to include plant sizes meeting Zoning
Ordinance requirements prior to City Council consideration of the conditional use
permit. A $34,000 financial security shall be submitted to guarantee installation of the site
landscaping.
3. Any future security lightin g shall be downcast and subject to approval of an electrical
permit.
4. The conditional use permit expiration date shall be two years from the date of City
Council approval.
5. Site development shall require a stormwater maintenance agreement between Dakota
Electric Association and the City.
Findings of fact are attached
C-2
I-2
P/OS
RM-2
RSMH
P/OS
RST-2P/OS
I-2
P/OS
RS-4
RST-2
C-2SHAKESPEARE BLVD
BRUTUS DR
GREE
NWOO
DAVE GLADEAVEGOODHUE WAYGREENWOODCT CAESAR ST
210TH ST WGROMMETAVE
LAKEVILLE BLVD
PRIVATE RD
LAKEVILLE BLVDCLEOPATRADR
A NTHONY DR
CEDARAVEDAKOTA ELECTRIC - 21075 GLADE AVENUE
CONDITIONAL USE PERMIT
¹
EXHIBIT A
5/27/2021 Dakota County GIS
gis.co.dakota.mn.us/dcgis/1/1
Dakota Electric Conditional Use Permit 20175 Glade Avenue
Disclaimer: Map and parcel data are believed to be accurate, but accuracy is not guaranteed.
This is not a legal document and should not be substituted for a title search,appraisal, survey, or
for zoning verification.
Map Scale
1 inch = 430 feet
5/27/2021
EXHIBIT B
EXHIBIT C
EXHIBIT D
PROPOSED
EXHIBIT E
PROPOSED
EXHIBIT F
PROPOSED
PROPOSED
PROPOSED
EXHIBIT G
1
CITY OF LAKEVILLE
DAKOTA COUNTY, MINNESOTA
DAKOTA ELECTRIC ASSOCIATION
CONDITIONAL USE PERMIT
FINDINGS OF FACT AND RECOMMENDATION
On June 17, 2021 the Lakeville Planning Commission met at its regularly scheduled
meeting to consider the application of Dakota Electric Association for a conditional use permit to
allow the construction of an electric power transformer and switching station located at 21075
Glade Avenue. The Planning Commission conducted a public hearing on the proposed
conditional use permit preceded by published and mailed notice. The applicant was present and
the Planning Commission heard testimony from all interested persons wishing to speak.
FINDINGS OF FACT
1. The property is located in Planning District No. 6 of the 2040 Comprehensive
Land Use Plan, which guides the property for Commercial land use.
2. The subject property is zoned C-2, Highway Commercial District .
3. The legal description of the property is:
LOT 2, BLOCK 1, SUPERAMERICA 2ND ADDITION
4. Chapter 4 of the City of Lakeville Zoning Ordinance provides that a conditional
use permit may not be issued unless certain criteria are satisfied. The criteria and
our findings regarding them are:
a) The proposed action has been considered in relation to the specific policies and
provisions of and has been found to be consistent with the Official City
Comprehensive Plan.
Finding: The proposed electric power substation facility will be consistent with the
policies and provisions of Planning District 6 of the 2040 Comprehensive Land Use
Plan.
b) The proposed use is or will be compatible with future land uses of the area.
2
The proposed electric power substation facility will be compatible with existing and
future land uses in the area given conformance with the stipulations outlined in the
conditional use permit.
c) The proposed use conforms with all performance standards contained in this Code.
The proposed electric power substation facility meets all performance standards set forth
in the Zoning Ordinance given conformance with the stipulations outlined in the
conditional use permit.
d) The proposed use can be accommodated with existing public services and will not
overburden the City’s service capacity.
The proposed electric power substation facility and related equipment and buildings
will not impact existing public services.
e) Traffic generation by the proposed use is within capabilities of streets serving the
property.
The proposed electric power substation facility will not negatively impact the capacity
of the streets serving the property.
5. The planning report dated June 11, 2021 prepared by Associate Planner Frank
Dempsey is incorporated herein.
RECOMMENDATION
The Planning Commission recommends that the City Council approve the conditional
use permit conditioned upon compliance with the planning report prepared by Frank
Dempsey, Associate Planner, dated June 11, 2021.
DATED: June 17, 2021
LAKEVILLE PLANNING COMMISSION
BY:____________________________
Jeff Witte, Vice Chair
City of Lakeville
Public Works – Engineering Division
Memorandum
To: Frank Dempsey, Associate Planner
From: Christina Orlowsky, Project Engineer
McKenzie L. Cafferty, Environmental Resources Manager
Copy: Zach Johnson, City Engineer
John Hennen, Parks and Recreation Director
Jerilyn Erickson, Finance Director
Gene Abbott, Building Official
Date: June 10, 2021
Subject: Dakota Electric Cedar Substation – Lot 2, Block 1, SuperAmerica 2nd Addition
• Site Plan Review
• Grading and Erosion Control Plan Review
• Utility Plan Review
BBAACCKKGGRROOUUNNDD
Dakota Electric Association has submitted a site plan application for Dakota Electric Cedar
Substation on Lot 2, Block 1, SuperAmerica 2nd Addition. The property is located north of and
adjacent to Lakeville Boulevard, and west of and adjacent to Glade Avenue. The parent parcel
is zoned C-2, Highway Commercial District.
The proposed site plan application will be completed by:
Applicant: Dakota Electric Association
Engineer: Johnson & Scofield, Inc.
SSIITTEE CCOONNDDIITTIIOONNSS
The parent parcel is currently undeveloped land with trees along the southern and western
portion of the lot which generally slopes from west to east. There are existing overhead
electric lines along the southern portion of the lot.
DDAAKKOOTTAA EELLEECCTTRRII CC CCEEDDAARR SSUUBBSSTTAATTII OONN –– LLOOTT 22,, BBLLOOCCKK 11,, SSUUPPEERRAAMMEERRIICCAA 22NNDD AADDDDIITTIIOONN
SSIITTEE PPLLAANN
JJUUNNEE 1100,, 22002211
PPAAGGEE 22 OOFF 44
SSIITTEE PPLLAANN
The development of Lot 2, Block 1, SuperAmerica 2nd Addition includes the construction of
substation structures on a crushed limestone pad, stormwater improvements, and two
driveway accesses to Glade Avenue east of the site.
EEAASSEEMMEENNTTSS
Lot 2, Block 1, SuperAmerica 2nd Addition contains the following easements to remain with
the plat.
• NSP Transmission Line easement per Doc. No. 365732
• Northern Natural Gas Co. pipeline easement per Doc. No. 413881
• Perimeter drainage and utility easements
SSTTRREEEETT AANNDD SSUUBBDDIIVVIISSIIOONN LLAAYYOOUUTT
Lakeville Boulevard
Lot 2, Block 1, SuperAmerica 2nd Addition is located north of and adjacent to Lakeville
Boulevard, a major collector roadway as identified in the City’s Transportation Plan. The right-
of-way for Lakeville Boulevard was dedicated with the SuperAmerica 2nd Addition.
Glade Avenue
Lot 2, Block 1, SuperAmerica 2nd Addition is located west of Glade Avenue, a local roadway as
identified in the City’s Transportation Plan. The right-of-way for Glade Avenue was dedicated
with the SuperAmerica 2nd Addition plat. The development of Lot 2, Block 1, SuperAmerica
2nd Addition includes the construction of two driveway access from Glade Ave. The Applicant
shall provide a security for the construction of the driveway aprons and the replacement of
the existing sidewalk at the location of the accesses prior to City Council approval.
CCOONNSSTTRRUUCCTTIIOONN AACCCCEESSSS
Construction traffic access and egress shall be restricted to a single entrance from Glade
Avenue.
PPAARRKKSS,, TTRRAAIILLSS AANNDD SSIIDDEEWWAALLKKSS
The Park Dedication fee was collected with the parent parcel and will not be required with the
site plan improvements.
UUTTIILLIITTIIEESS
SSAANNIITTAARRYY SSEEWWEERR
The proposed site improvements do not require sanitary sewer to be extended to serve the
property.
DDAAKKOOTTAA EELLEECCTTRRII CC CCEEDDAARR SSUUBBSSTTAATTII OONN –– LLOOTT 22,, BBLLOOCCKK 11,, SSUUPPEERRAAMMEERRIICCAA 22NNDD AADDDDIITTIIOONN
SSIITTEE PPLLAANN
JJUUNNEE 1100,, 22002211
PPAAGGEE 33 OOFF 44
The Sanitary Sewer Availability Charge has been collected on the parent parcels and will not
be required with the building permit.
WWAATTEERRMMAAIINN
The proposed site improvements do not require water service to be extended to serve the
property.
DDRRAAIINNAAGGEE AANNDD GGRRAADDIINNGG
Lot 2, Block 1, SuperAmerica 2nd Addition is located within subdistrict SC-12 and SC-69 of the
South Creek drainage district as identified in the City’s Water Resources Management Plan.
Development of the site will include the construction of one privately owned and maintained
stormwater management basin. The private stormwater basin will be located on the southern
end of the parcel and will treat runoff generated from the proposed improvements.
Prior to the issuance of a building permit the Applicant shall sign a private maintenance
agreement for the stormwater management basin and utility easement over the basin. The
basin will provide water quality treatment, volume reduction and rate control of the
stormwater runoff generated from the proposed site improvements. Stormwater basin
designs must be reviewed by the City and be consistent with City requirements prior to the
issuance of a building permit. The Applicant shall provide a security for the proposed grading,
erosion control, and restoration of the site prior to City Council approval.
Lot 2, Block 1, SuperAmerica 2nd Addition contains more than one acre of site disturbance. A
National Pollution Discharge Elimination System General Stormwater Permit for construction
activity is required from the Minnesota Pollution Control Agency for areas exceeding one acre
being disturbed by grading. A copy of the Notice of Stormwater Permit Coverage must be
submitted to the City upon receipt from the MPCA.
SSTTOORRMM SSEEWWEERR
The proposed site is designed for stormwater to sheet drain south to the proposed privately
owned and maintained stormwater management basin. The outlet control structure in the
basin is proposed to connect the to an existing City storm sewer catch basin along Lakeville
Boulevard, south of and adjacent to the site. The Applicant shall provide a security prior to
City Council approval to ensure a proper connection is made to the existing storm sewer
catch basin.
The Trunk Storm Sewer Area Charge has been collected on the parent parcels and will not be
required with the site plan improvements.
DDAAKKOOTTAA EELLEECCTTRRII CC CCEEDDAARR SSUUBBSSTTAATTII OONN –– LLOOTT 22,, BBLLOOCCKK 11,, SSUUPPEERRAAMMEERRIICCAA 22NNDD AADDDDIITTIIOONN
SSIITTEE PPLLAANN
JJUUNNEE 1100,, 22002211
PPAAGGEE 44 OOFF 44
FEMA FLOODPLAIN ANALYSIS
Lot 2, Block 1, SuperAmerica 2nd Addition is shown on the Flood Insurance Rate Map (FIRM)
as Zone X by the Federal Emergency Management Agency (FEMA. Based on this designation,
there are no areas in the plat located within a Special Flood Hazard Area (SFHA), as
determined by FEMA.
WWEETTLLAANNDDSS
There are no wetlands on the site.
TTRREEEE PPRREESSEERRVVAATTIIOONN
There are no significant trees on the site.
EERROOSSIIOONN CCOONNTTRROOLL
The Applicant is responsible for obtaining an MPCA Construction Permit for the site as well as
developing a SWPPP for the site prior to issuance of a building permit. The permit requires
that all erosion and sediment BMPs be clearly outlined in a SWPPP. Changes made
throughout construction must be documented in the SWPPP. All basin slopes and slopes
adjacent to wetlands must have erosion control blanket installed.
Additional erosion control measures may be required during construction as deemed
necessary by City staff. Any additional measures required shall be installed and maintained
by the Applicant.
RREECCOOMMMMEENNDDAATTIIOONN
Engineering recommends approval of the site plan, grading plan, erosion control plan and
utility plan for Dakota Electric Cedar Substation, subject to the requirements within this report
including:
1. The Applicant shall submit a security based on their Engineer’s estimate of the
items listed in this report prior to City Council Approval.
2. The Applicant shall submit as-built record drawings following the completion
of this project.