City of Lakeville
Memorandum
To: Planning Commission
Justin Miller, City Administrator
Julie Stahl, Finance Director
Paul Oehme, Public Works Director
Zach Johnson, City Engineer
Joe Masiarchin, Parks & Recreation Director
September 19, 2024
2025-2029 Capital Improvement Plan (CIP)
Attached is a draft of the proposed 2025-2029 Capital Improvement Plan (CIP). The CIP is comprised of
the following components: Transportation, Utility, Environmental Resources, Parks and Recreation,
Facilities, Equipment and Technology. Included with this plan are the project descriptions, locations,
revenues and expenditures.
The 2025-2029 CIP includes public improvement projects due in large part to increased growth,
economic conditions, and the resulting increase in revenue from City permits and connection charges
to finance infrastructure improvements. The following are the more significant improvement projects
included in the 2025-2029 CIP:
Transportation
• CP XX-02: Annual Street Rehabilitation/Reconstruction construction
• CP XX-03: Annual Collector Roadway Rehabilitation/Reconstruction construction
• CP 22-03: 210th St Reconstruction ( construction, payment to Dakota County)
• CP 22-16: Freight Rail Car Storage Facility ( construction)
• CP 23-04: 179th St/CSAH 9 Realignment (Highview Ave - Cedar Ave), Dodd Boulevard Modernization
(Gerdine Path - Dodd Lane) (construction,payment to Dakota County)
• CP 24-04: 185th St/CSAH 60 Extension (Dodd Blvd - Highview Ave) (construction,and
payments to Dakota County)
• CP 24-05: 179th St/Future CSAH 9 Bridge ( construction)
• CP 25-04: 185th St/CSAH 60 Expansion (Kenwood Tr - Ipava Ave) (construction;
payment to Dakota County)
• CP 25-05: Holyoke Ave/Highview Ave Reconstruction ( construction)
• CP 26-04: Dodd Blvd/CSAH 9 Modernization (210th St – 202nd St/Kenwood Tr) (construction)
• CP 26-05: Interstate 35/CSAH 50 Interchange (construction)
• CP 26-06: 202nd St/CSAH 50 and Hamburg Ave Roundabout ( construction)
• CP 26-15: Lake Marion Greenway (construction)
• CP 28-04: Dodd Blvd/CSAH 9 Modernization (215th St - 210th St) ( construction)
Utilities
2
• Watermain maintenance/replacement and sanitary sewer rehabilitation - in conjunction with
annual street rehabilitation/reconstruction projects construction
• Lift Station 26 construction
• Dakota Heights Water Tower Repainting construction
• Wells 24 and 25 (construction)
Parks
• Grand Prairie Park (construction)
• Voyageur Park construction
• East Community Park construction
• Spyglass Park - Phase II construction
• Ritter Meadows Park construction
• Klamath Trail Retaining Wall construction
• Grand Prairie Skatepark construction
• Various trail and trail lighting projects construction
Facilities
• Public Safety Training Facility (FiRST Center) (construction)
• Central Maintenance Facility (CMF) Expansion construction
• Water Treatment Facility (WTF) Expansion construction
• Fire Station Renovations (construction)
The CIP was presented to the City Council at their August 26 workshop. The final 2025-2029 CIP will be
considered for approval at the October 7, 2024 City Council meeting.
Minnesota State Statute 462.356 provides that capital improvements are reviewed by the Planning
Commission for consistency with the Comprehensive Plan and the Planning Commission report their
findings in writing to the City Council. The Planning Commission is not responsible for reviewing the
fiscal implications of the CIP. Staff reviewed the CIP and finds it consistent with the Comprehensive Plan.
Therefore, staff recommends a motion finding that the capital improvements identified in the 2025-
2029 CIP are in compliance with the Comprehensive Plan.
DRAFT
City of Lakeville 2025-2029 Capital Improvement Plan- Page 2
Table of Contents
2025-2029 Capital Improvement Plan
Page
Introduction 3-7
Debt Analysis & Tax Impact
Narrative
7-14
14-29
Projects & Funding Sources by Category 30-37
Projects by Funding Source 38-43
Street Reconstruction Plan (2025-2029) 44
Facility Plan (2025-2034) 45
Equipment Plan (2025-2034) 46
Technology Plan (2025-2034) 47
City Planning/Studies/Project chart 48
Map of Major Projects
49
City of Lakeville 2025-2029 Capital Improvement Plan- Page 3
Introduction
The Capital Improvement Plan provides a long-range framework to meet the infrastructure needs
and development objectives of our community. It provides policy makers and the community with
a strategic (documented) approach to implementation and administration of improvement
projects and equipment acquisitions.
The Plan identifies the allocation of the City’s financial resources and maximizes the use of non-
tax revenues to finance the improvements. Municipal State Aid Street Funds (MSA), connection
charges, special assessments and other revenue sources are vital elements to financing City
improvements. The use of these revenue sources reduces the reliance on property taxes to finance
these improvements.
The City should pursue the financing strategy as presented, but future events may require changes
in both costs and revenues. The Capital Improvement Plan represents a significant financial,
engineering and development undertaking for the City in the years ahead. The Capital
Improvement Plan is consistent with the City’s Comprehensive Plan and takes into consideration
projects identified in the Dakota County Capital Improvement Plan.
Categories
Transportation includes all roads, streets, street lights, bridges and traffic signals within the City
with the exception of Interstate I-35 and routine maintenance of County roads. Major funding
sources include Municipal State Aid Street funds, special assessments and property taxes.
Utility infrastructure includes the construction and major maintenance of all water systems such
as wells, towers and the water treatment facility. Utilities also include sanitary sewer and storm
sewer systems. The primary source of financing for developing new systems is connection charges
when property develops or with the issuance of a building permit. Maintenance projects are
financed with user fees. The Water Treatment Plant expansion in 2027 is planned to include a
combination of bond funding (principal and interest payments to be repaid with user fees), and
fund balance/net assets in the Water Trunk Fund and Water Operating Fund, respectively.
Environmental Resources system includes lakes, wetlands, streams, prairies and woodlands.
Maintenance project are financed with user fees.
Parks system includes regional, community and neighborhood parks as well as trails and
recreation facilities such as the Arts Center and Heritage Center. Major resources include park
dedication fees collected when property develops, and grants. Maintenance projects are financed
with property taxes and other revenue sources. A parks bond referendum was approved in the fall
of 2021 and related projects are being constructed between 2022-2026.
Facilities include the city hall, police station, fire stations, central maintenance facility and other
municipal buildings including the FiRST Center. Primary revenue sources include, but not limited
City of Lakeville 2025-2029 Capital Improvement Plan- Page 4
to, property taxes, General Fund, Water Fund, and planned bond proceeds in several years (for the
FiRST Center, Fire station renovations, CMF expansion, and Water Treatment plant expansion).
Equipment includes all major equipment acquisitions and replacement. Primary revenue sources
include, but not limited to, Liquor Fund contributions, General Fund, Utility Funds, sale of assets
and property taxes.
Technology includes all major technology-related equipment acquisitions and replacement.
Primary revenue sources include, but not limited to, Liquor Fund, General Fund, Utility Funds,
and property taxes.
Program Summary
The majority of capital investments are in Facilities and Transportation for the next five years.
The total budgeted capital expenditures by category are shown below. The projects are financed
from diverse revenues sources. A summary is shown below. Details are shown on subsequent
pages.
Total
Cost Type: 2023 2024 2025 2026 2027 2028 2029 2025-2029
* *
Transportation 25,098,000 20,367,324 17,185,300 32,573,864 28,359,413 13,975,825 8,909,719 101,004,121
Utility/Environmental Resources 12,498,000 5,785,000 8,114,000 8,328,325 6,009,500 5,970,000 4,300,000 32,721,825
Parks 27,346,743 21,286,096 6,899,020 8,148,563 6,074,000 3,247,000 2,382,000 26,750,583
Facilities 2,103,940 15,509,650 30,504,000 21,999,200 60,475,800 21,554,940 1,351,818 135,885,758
Equipment 2,283,229 3,592,958 3,454,342 3,792,210 4,561,752 3,050,729 2,944,054 17,803,087
Technology 754,250 705,798 611,908 288,314 692,574 689,088 424,603 2,706,487
70,084,162$ 67,246,826$ 66,768,570$ 75,130,476$ 106,173,039$ 48,487,582$ 20,312,194$ 316,871,861$
*2023 and 2024 are based on the adopted CIP for those years. Budget and actual costs differ. Only 2025-2029 are shown in the
chart below.
Project Cost Summary
City of Lakeville 2025-2029 Capital Improvement Plan- Page 5
City of Lakeville 2025-2029 Capital Improvement Plan- Page 6
*Park bond referendum timing shows planned use of bonds, not bond issuance year. Bond funds
will be spent first, and any overage on the project will be paid by the Park Dedication Fund.
Total
Funding Source 2025 2026 2027 2028 2029 2025-2029
General Fund 255,472$ 232,825 278,100 130,000 219,674 1,116,071
Communications Fund 37,260 50,822 54,547 51,078 53,047 246,754
Escrow 806,065 800,000 949,629 196,000 - 2,751,694
Property Taxes & Fund Balance 2,310,500 2,628,750 2,440,000 2,485,000 2,555,000 12,419,250
G.O. Bonds -Property Tax Lev 4,183,245 3,915,707 6,280,000 6,378,425 4,634,719 25,392,096
G.O. Bonds - Special Assessments 645,000 - 350,000 875,000 - 1,870,000
Municipal State Aid/ MSA bonds 4,411,930 7,522,288 6,071,158 3,381,610 2,980,000 24,366,986
MSA/ MSA bonds-Special Assessments - - 350,000 - - 350,000
Dakota County 7,382,000 11,248,175 9,996,126 3,534,790 380,000 32,541,091
Dakota County-Advance of City share (2,642,940) (976,763) 1,957,500 (2,840,000) (1,605,000) (6,107,203)
Water Trunk Fund/revenue bonds 3,750,000 1,380,000 11,875,000 2,215,000 265,000 19,485,000
Stormwater Infrastructure Fund 1,804,000 2,513,825 1,625,000 205,000 205,000 6,352,825
Sanitary Sewer Trunk Fund 2,090,000 165,000 135,000 75,000 75,000 2,540,000
Park Dedication Fund 2,547,945 3,530,313 2,882,500 1,760,000 1,105,000 11,825,758
Park Bond Referendum* 2,452,625 2,025,000 - - - 4,477,625
Park Improvement Fund 618,450 1,053,250 961,500 875,000 667,000 4,175,200
Trail Improvement Fund 560,000 970,000 2,230,000 612,000 610,000 4,982,000
Utility- Water 2,720,354 2,841,699 11,248,748 1,288,840 1,747,237 19,846,877
Utility- Sanitary Sewer 1,290,354 1,266,699 1,824,248 1,403,840 1,477,237 7,262,377
Utility- Environmental Resources 1,037,885 989,176 1,029,066 995,130 986,354 5,037,611
Utility- Street Light 10,000 97,500 60,000 - - 167,500
Franchise Fees - 4,238,250 4,671,184 3,356,387 - 12,265,821
Facilities Fund- Bond Proceeds 17,792,608 15,761,750 32,328,816 16,643,613 - 82,526,787
Facilities Fund- Other/Partnership 7,170,000 - - - - 7,170,000
Tax Levy- Equipment, Facilities & Technology 900,000 2,500,000 4,150,000 2,550,000 2,400,000 12,500,000
Fund Balance use- Equipment, Facility & Tech. 2,429,757 744,938 964,123 554,807 (103,747) 4,589,878
Arenas 1,843 1,337 3,402 1,497 1,500 9,579
Liquor Fund 577,605 591,981 644,520 928,330 787,817 3,530,253
Antenna Rental 482,113 497,247 512,873 531,236 571,356 2,594,825
Equipment sale proceeds 300,000 300,000 300,000 300,000 300,000 1,500,000
Other/Grants/Donations/Partnerships 844,500 8,240,707 - - - 9,085,207
66,768,570$ 75,130,476$ 106,173,039$ 48,487,582$ 20,312,194$ 316,871,861$
Funding Source Summary
City of Lakeville 2025-2029 Capital Improvement Plan- Page 7
Debt Analysis and Tax Impact
In reviewing the 2025-2029 Capital Improvement Plan, the City Council should consider the level
of debt, the commitment of funds to repay that debt, as well as the annual tax impact associated
with the scheduled projects.
As of 12/31/2024, the City of Lakeville will have $155,450,000 in debt. The following chart reflects
the type of debt that comprises the $155.45M.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 8
The 2025-2029 CIP includes projects that are funded by bond proceeds. Bonds are issued for the
project costs that the City is funding through tax levies as well as the costs that are specially assessed
to property owners. The City anticipates $114,788,883 in bonding for projects in the CIP plan for
2025-2029, including the following-
$27,262,096 for street reconstruction/collector road rehabilitation projects in 2025-
2029
$17,792,608 for the FiRST Center in 2025
$17,000,000 for the CMF facility expansion in 2027
$5,000,000 for the bonded portion of a Water Treatment Facility expansion project
in 2027
$15,761,750 in 2026, $15,328,816 in 2027 and $16,643,613 in 2028 for fire station
remodel projects.
The anticipated bonding amount for 2025 is $22,620,853, which assumes no bonding is needed in
2025 for planned equipment expenditures. The current CIP projections assume no bond funding
will be needed for the Municipal State Aid (MSA) projects, which will be dependent on project
costs and timing, as well as the ability of Dakota County to provide advance funding on certain
MSA projects.
Major projects scheduled for 2025, which are planned to be funded with bonds are listed below (note
that these amounts also include any bonds which will be repaid by special assessments):
Amount
50,375,000$
14,200,000
57,800,000
3,260,000
5,125,000
815,000
16,290,000
7,415,000
70,000
100,000
Total remaining principal: 155,450,000
Bond Type Purpose
Various capital projects (Central Maintenance
Facility, Police Station)
Street reconstruction projects
GO Capital Improvement
GO Street Reconstruction
Various capital improvement projects; Includes
special assessment-supported debt.
Various street improvement projects
Holyoke Water Tower, Water Treatment Facility
Improvements, Wells 21 and 22
Construction of liquor store (2007)
Watermain replacement (in conjunction with street
reconstruction projects)
Lift station #6 replacement
Holyoke Ave Street Lights
Arenas projects 2021-2022, Keokuk Liquor Store
construction
GO Improvement
GO State-aid Street Revenue
GO Water Revenue
HRA Lease Revenue-Liquor
Water revenue
Sewer revenue
Street light revenue
Tax Abatement
City of Lakeville 2025-2029 Capital Improvement Plan- Page 9
Major projects which involve a property tax levy component in 2025 are listed below:
Project costs in the CIP may be higher than the tax levy amounts above, due to additional funding
sources beyond tax levy, such as fund balance, or other sources (as reflected in the CIP). There are
sometimes transfers from General Fund balance reserve into Capital Project Funds to reduce the
impact on the tax levy, and such transfers are not reflected in the table above.
Project Description
Total estimated
bonds in 2025
25-02: 2025 Street Reconstruction 4,145,000$
25-03: Collector Roadway Rehabilitiation 683,245
25-12 FiRST Center 17,792,608
TOTAL 22,620,853$
Project Description Tax Levy
Pavement maintenance project 25-01 (Pavement
Management Fund) 1,800,000$
Park improvements (Park Improvement Fund) 450,000
Equipment purchases (Equipment Fund) 200,000
Facilities maintenance/improvements (Building Fund) 100,000
Technology needs (Technology Fund) 300,000
Trail maintenance/rehabilitation (Trail Improvement Fund) 550,000
TOTAL 3,400,000$
City of Lakeville 2025-2029 Capital Improvement Plan- Page 10
The following chart reflects the cumulative effect of new debt issued as indicated in the CIP and the retirement of existing debt. The top line is
the resulting debt balance at the end of each year.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 11
The following charts reflect the cumulative effect of new debt issued as indicated in the proposed CIP and the retirement of existing debt on a per
capita basis, and on a per household basis, respectively.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 12
City of Lakeville 2025-2029 Capital Improvement Plan- Page 13
The impact of the 2025-2029 CIP and other anticipated bond payment adjustments on the debt
service property tax levy are reflected in the following table:
Each year, certain bond issues mature and the corresponding debt service payments are
eliminated. As noted in the CIP, the City initiated a Pavement Management Program starting in
2009, which increased the scope of the annual street reconstruction projects, which in turn has
increased the amount of debt related to such street reconstruction projects. The amount of debt
service dropping off each year as payments are made is less than the amount that we are adding
for new CIP projects. This results in an increase in the debt service property tax levy.
The proposed CIP projects will impact the debt service beginning in 2026. The anticipated bond
payments on debt issued in conjunction with these new projects will result in an increased debt
service levy of approximately $722,000 for 2026, $1,666,000 for 2027, $3,424,000 for 2028, and
$4,290,000 for 2029.
The $114.8M of bonding for projects in the 2025-2029 CIP will require significant bond payments
beginning in 2026 from the following sources: tax levy, special assessments, and Water Operating
Fund. The estimated annual payments by source are shown in the table and chart below.
Projected Change in Debt Levy
2025 2026 2027 2028 2029
Total 2025-
2029
Annual Debt Levy 12,973,074 12,156,415 12,524,937 11,936,712 10,869,762 60,460,900
Change from:
Existing Debt - (816,660) 368,522 (588,225) (1,066,950) (2,103,312)
One-time Adjustments - - - - - -
New CIP:
Street projects 93,529 722,121 1,270,169 2,124,950 2,988,111 7,198,879
Equipment - - - - - -
Facilities - - 396,326 1,298,916 1,301,934 2,997,176
Parks - - - - - -
Change from New CIP: 93,529 722,121 1,666,495 3,423,866 4,290,045 10,196,055
Total Change 93,529 (94,539) 2,035,017 2,835,641 3,223,095 8,092,743
Revised Debt Levy 13,066,603 12,878,536 14,191,432 15,360,578 15,159,807 68,553,644
% Change in Debt Levy -1% 10% 8% -1%
City of Lakeville 2025-2029 Capital Improvement Plan- Page 14
*Each year reflects a cumulative total of the funding that would be needed from each of the sources
for that year (for example, the obligations shown in 2027 include the change from new CIP debt
in 2025 as well as 2026).
Impact of the Capital Improvement Plan on the Operating Budget
The City’s Operating Budget is affected by the Capital Improvement Plan. Capital improvements
typically result in ongoing expenses for routine operation, repair and maintenance upon
completion or acquisition. Existing City facilities and equipment will eventually require
rehabilitation, renovation or upgrades to accommodate new uses or address needed
improvements. Older facilities usually involve higher maintenance and repair costs as well.
Capital improvements make a positive contribution to the economic vitality, quality of life and
fiscal well-being of our community in spite of potential recurring operating costs. Capital projects
such as the redevelopment of under-performing or under-used areas of the City, and the
infrastructure expansion needed to support new development, help promote the economic
development and growth that generates additional operating revenues. These new revenue sources
provide the funding needed to maintain, improve and expand the City’s infrastructure.
Additional considerations
Dakota County staff continue to prepare the Dakota County’s draft 2025-2029 Transportation,
Transportation Sales & Use Tax, and Regional Rail Authority Capital Improvement Program. City
and County staff continue to coordinate efforts to create CIPs that align with both local and
regional transportation needs.
TRANSPORTATION PROJECTS
Implements the following Envision Lakeville Community Values:
Diversified Economic Development
Good Value for Public Services
Funding of New Debt from CIP (Cumulative Payments by Year)
2026 2027 2028 2029 2030
Tax Levy 722,121 1,666,495 3,423,866 4,290,045 4,898,799
Special Assessments 78,536 78,536 121,153 227,694 227,694
Franchise Fees 414,816 1,729,613 2,923,594 4,129,076 5,013,816
Water Fund - - 608,807 608,807 608,807
1,215,473 $3,474,644 $7,077,419 $9,255,621 $10,749,116*
City of Lakeville 2025-2029 Capital Improvement Plan- Page 15
Safety Throughout the Community
Design That Connects the Community
PAVEMENT MANAGEMENT
The City’s current Pavement Management Program started in 2009. Local public streets and
collector/arterial roads are inspected on a regular basis. Each segment of improved street/road is
assigned an Overall Condition Index (OCI) rating. OCI ratings assist in scheduling preventive
maintenance and prioritizing local street and collector/arterial road rehabilitation and
reconstruction projects. Project costs for local street and collector/arterial road reconstruction
projects are based on adopted policy in which benefited properties are assessed 40% of project costs
and the remaining 60% of project costs are financed through property taxes. Routine pavement
maintenance is not assessed.
Oversight of associated public infrastructure such as pedestrian/bicyclist facilities (sidewalks,
Americans with Disability Act (ADA) ramps), bridges (inspections/repairs), and small safety
improvements are included in the City’s Pavement Management Program.
PAVEMENT MAINTENANCE (XX-01)
Annual preventive maintenance program designed to protect the City’s investment in public
street/road infrastructure assets. Best management practices include crack sealing, seal coating,
surface sealing, mill and overlay and roadway patching. Associated maintenance activities such as
curb and gutter repair, drain tile repair, pavement marking painting, and stormwater
infrastructure repair are included. Maintenance is financed primarily through property taxes. A
portion of the City’s annual Municipal State Aid (MSA) allotment is applied toward street/road
maintenance, with the remaining MSA balance applied toward MSA-designated projects and debt
payments on previously issued bonds supporting these projects. The remaining principal and
interest balances due on MSA-supported bonds at the end of 2024 will be $3,260,000. The final
principal payment will be made in 2036.
LOCAL STREET REHABILITATION/RECONSTRUCTION (XX-02)
Annual program designed to extend street life, minimize total life cycle costs, and improve local
streets when routine maintenance costs exceed the cost-benefit of the investment or streets
approach the end of their life cycle. Citywide OCI goal for local streets is 75. Both rehabilitation
(surface sealing/mill and overlay) and reconstruction (reclamation) practices are utilized.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 16
COLLECTOR/ARTERIAL ROAD REHABILITATION AND RECONSTRUCTION (XX-03)
Annual program designed to extend roadway life, minimize total life cycle costs, or improve
collector/arterial roads when routine maintenance costs exceed the cost-benefit of the investment
or roads approach the end of their life cycle. Citywide OCI goal for collector/arterial roads is 75.
Both rehabilitation (mill and overlay) and reconstruction (reclamation) practices are utilized.
DRAINAGE IMPROVEMENTS/UTILITY REPAIRS ON COUNTY HIGHWAYS (XX-10)
Annual maintenance program designed to improve the overall performance and effectiveness of
the shared County and City stormwater management system and extend the service life of City
sanitary sewer and water infrastructure located along County highways. The program is designed
to improve public utility infrastructure and minimize total life cycle costs through routine
maintenance that coincides with County pavement preservation projects.
CITY AND COUNTY COLLECTOR/ARTERIAL ROAD IMPROVEMENTS
Partnership projects aligning with local development objectives, and local and regional (County
State Aid Highway/CSAH) transportation needs. Designed to create and maintain a safe, efficient,
multi-modal transportation system. City-led projects list all costs, including the County’s
estimated cost-share. County-led projects list only the City’s estimated cost-share.
CP 23-04:
o Phase I: 179th Street/Future CSAH 9 Realignment (Highview Ave – Cedar Ave)
o Phase II: Dodd Boulevard Modernization (Gerdine Path - Dodd Lane)
Phase I constructed in 2023. City share of costs paid in 2025 per Joint Powers Agreement.
Phase II programmed for 2024 construction as 2-lane undivided City collector roadway
with trails along both sides. City share of costs paid in 2025 per Joint Powers Agreement.
Roadways identified as jurisdictional transfers in 2024, following the completion of Phase
II construction.
CP 24-04: 185th Street/CSAH 60 Extension (Dodd Blvd - Highview Ave)
Constructed in 2023. City share of costs paid in 2025/2026 per Joint Powers Agreement.
CP 24-05: 179th Street/Future CSAH 9 Extension (Pilot Knob Rd – E City Limits)
Programmed for 2026 construction with Developer-installed improvements as a 2-lane
divided County highway with trails along both sides. Project includes a highway bridge
City of Lakeville 2025-2029 Capital Improvement Plan- Page 17
spanning North Creek with trails along both sides. City and County share of costs paid per
Joint Powers Agreement, subject to planned land development. Identified as future (long-
term) jurisdictional transfer.
CP 25-04: 185th Street/CSAH 60 Expansion (Kenwood Tr - Ipava Ave)
Programmed for 2025 construction as a 4-lane divided County highway with trails along
both sides. City share of costs paid in 2026-2028 per Joint Powers Agreement.
CP 26-04: Dodd Boulevard/CSAH 9 Modernization (210th St – 202nd St/Kenwood Tr)
Programmed for 2027 construction as a 2-lane divided County highway with trails along
both sides. City share of costs paid per future Joint Powers Agreement.
CP 26-07: CSAH 60 Alignment Study (Cedar Avenue/CSAH 23 – Flagstaff Avenue)
Programmed for 2026 study to determine the future alignment/corridor of CSAH 60 as it
extends east into Farmington. City share of costs (22.5%) paid in 2026 per future Joint
Powers Agreement.
CP 28-04: Dodd Boulevard/CSAH 9 Modernization (215th St/CSAH 7- 210th St)
Programmed for 2028 construction as a 2-lane divided County highway with trails along
both sides. City share of costs paid in 2028 per future Joint Powers Agreement.
CITY AND COUNTY INTERSECTION IMPROVEMENTS
Partnership projects aligning with local and regional (County State Aid Highway/CSAH)
transportation needs. Designed to alleviate congestion, improve intersection operations, provide
for increasing traffic levels and improve safety. City-led projects list all costs, including the
County’s estimated cost-share. County-led projects list only the City’s estimated cost-share. Traffic
signals along County highways are owned by the County. Maintenance on City-owned traffic
signals is done by County through a maintenance agreement.
CP 22-03: 210th Street and Dodd Boulevard/CSAH 9 Roundabout
Constructed in 2022. City share of costs paid in 2025 per Joint Powers Agreement.
CP 26-05: Interstate 35 and Kenwood Trail/CSAH 50 Interchange Reconstruction
Minnesota Department of Transportation (MnDOT) completed a State-funded corridor
study of Interstate 35 (I-35) between CSAH 70 and the Interstate 35E/35W split in 2024.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 18
The study provides local agencies with information on future scoping of MnDOT-led
pavement preservation projects along the corridor, and reasonable assumptions on the
future footprint of I-35 at the CSAH 50 interchange.
County-led preliminary engineering and design of the I-35 and CSAH 50 Interchange
Reconstruction is programmed for 2024/2025. The City and County were awarded
$5,040,000 in Federal Funding (Fiscal Year 2023) to complete engineering and design.
Construction will be funded through a combination of local, county, state and potentially
federal funds. State and federal funding for construction have not been secured, therefore,
construction year (currently planned for 2028/2029) is still to be determined. The City
acquired parcels in 2017 (Burger King) and 2021 (BP) for right-of-way purposes, both of
which were funded by the Metropolitan Council’s Right-of-Way Acquisition Loan Fund
(RALF). The loans are to be repaid in the year of construction. The City and County will
share in the repayment costs per future Joint Powers Agreement.
CP 26-06: 202nd Street/CSAH 50 and Hamburg Avenue Roundabout
Programmed for 2026 construction as a single-lane roundabout. Dakota County
responsible for 100% of project cost per future Joint Powers Agreement. City is only
anticipating contributing costs toward streetlights at this time.
OTHER PROJECTS
CP 22-08: CenterPoint Energy Tree Replacement
Reforestation program designed to replace trees along Ipava Avenue (202nd Street – 165th
Street) removed with CenterPoint Energy’s 2022 gas pipeline project. Tree planting
completed in 2023 with scheduled maintenance/management in 2024/2025. CenterPoint
Energy to reimburse the City 100% of costs in 2023-2025 per agreement.
CP 22-16: Freight Rail Car Storage and Transload Facility
Programmed for 2026 construction. The City was awarded $750,000 in Federal Funding
(Fiscal Year 2023) for engineering design and $7,000,000 in State Funding for construction.
Project includes construction of a 90-car storage yard, and a 30-car transload facility within
the City’s industrial parks, south of CSAH 70.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 19
CP 25-05: Holyoke/Highview Avenue (202nd St/CSAH 50 – Dodd Blvd/CSAH 9)
o Phase I: Heritage Drive to South of 190th Street
o Phase II: South of 190th Street to Dodd Boulevard/CSAH 9
Phase I programmed for 2027 construction. Project includes road rehabilitation and
modernization, intersection improvements and a pedestrian underpass. Phase II
programmed for 2030 construction. Project includes road rehabilitation and
modernization and intersection improvements and a pedestrian underpass.
ENVIRONMENTAL RESOURCES PROJECTS
Implements the following Envision Lakeville Community Values:
A Sense of Community and Belonging
Access to a Multitude of Natural Amenities and Recreational Opportunities
ER-1: WATER QUALITY/CONSERVATION PROJECTS
Water Quality Best Management Practices
Partnership projects aligning with Black Dog Watershed Water Management Organization,
Dakota County Soil and Water Conservation District and Vermillion River Watershed Joint
Powers Organization restoration and protection strategies. Funding intended as City’s cost-share
to meet partnership or grant matching requirements. Emphasis on Federal Clean Water Act,
Minnesota Pollution Control Agency MS4 permit and Total Maximum Daily Load compliance.
Urban Restoration - Public System Initiatives and Improvements
Program designed to restore and manage landscaping at public facilities and public open spaces
by replacing hardscape and lawns with native plants/low-maintenance vegetation. Best
management practices include native grasses/plants, prairies, rain gardens and woodlands to
provide storm water rate control/volume reduction or water quality improvements.
Water Conservation
Program designed to implement water conservation strategies at public facilities/open spaces to
reduce water use. Best management practices include water reuse and smart irrigation systems.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 20
Irrigation Efficiencies (HOA)
Program designed to reduce groundwater usage by Homeowner Associations. Irrigation system
audits improve private irrigation system efficiency through recommended improvements that a)
preserve groundwater aquifers, b) reduce potential for pollutants to enter area waters through
runoff, and c) reduce City infrastructure costs. Best management practices include field studies of
irrigation systems, and cost-share for smart controllers/irrigation system efficiency improvements.
ER-2: LAKE MANAGEMENT
Water Quality Assessments and Water Quality Treatments
Annual management program designed to promote and protect public water resources. Annual
assessment results are used to identify best management practices and strategies and prioritize and
schedule treatments. Assessment techniques include aquatic plant surveys, aquatic invasive species
monitoring, fish surveys and water monitoring/sampling. Best management practices and
strategies include chemical treatments, education and outreach, and fish management.
ER-3: STORMWATER INFRASTRUCTURE MAINTENANCE
Storm Water Basin Rehabilitation
Annual maintenance program designed to extend service life/minimize life-cycle costs of public
storm water basin collection systems. Storm water management basins improve water quality of
stormwater runoff and reduce peak stormwater discharge rates. Public storm water basins are
inspected regularly. Inspections assist in scheduling maintenance and prioritizing rehabilitation
projects. Best management practices include maintenance at emergency overflow/easement areas,
sediment/vegetation removal and slope restoration. Emphasis on Minnesota Pollution Control
Agency Municipal Separate Storm Sewer System (MS4) permit compliance.
Storm Water Infrastructure Maintenance/Rehabilitation
Annual preventive maintenance program designed to protect the City’s investment in public
stormwater infrastructure. Best management practices include flared-end section repairs,
sediment removal, storm sewer pipe and manhole repairs, and stormwater conveyance systems
improvements. Emphasis on Minnesota Pollution Control Agency Municipal Separate Storm
Sewer System (MS4) permit compliance.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 21
FLARED-END SECTION (FES) Maintenance
Annual maintenance program designed to improve the overall performance and effectiveness of
the City’s stormwater management system. Best management practices include removal of
accumulated sediment that is restricting stormwater flow through flared-end sections (FES),
stormwater infrastructure designed to convey water to/from stormwater management basins.
ER-4: STORMWATER INFRASTRUCTURE SYSTEM EXPANSION
The Water Resources Management Plan anticipates the extension/expansion of new stormwater
infrastructure to serve areas of planned land development and with local street and
collector/arterial road rehabilitation/reconstruction projects. New infrastructure includes storm
sewer pipes and structures, mechanical storm water/sediment separators, storm water basins and
wetlands, and storm water filtration/infiltration systems and rain gardens. These best management
practices provide storm water rate control, volume reduction and water quality improvements.
Timing of new stormwater infrastructure is subject to planned land development.
CP 20-45: 165th St Drainage System Improvements
Programmed for construction in 2026. Project includes addition of stormwater
infrastructure improvements to assist in the safe and efficient collection and conveyance of
stormwater runoff from significant rainfall events within the 165th Street watershed.
CP 24-44: Greenridge Park Stormwater Facility
Programmed for 2025 construction. The City and Vermillion River Watershed Joint
Powers Organization propose to partner on a stormwater best management practice to
improve stormwater quality.
ER-5: FORESTRY
Annual maintenance program designed to manage, preserve, and protect public woodland assets.
Best management practices include Emerald Ash Borer program (tree injections, tree
removal/stump grinding of infected trees and reforestation of public parks/open spaces).
ER-6: VEGETATION MAINTENANCE - CITY OUTLOT/PUBLIC LAND
Annual maintenance program designed to help establish deep-rooted native vegetation that will
help prevent erosion and filter out chemicals, and nutrients, like phosphorous, that degrades water
City of Lakeville 2025-2029 Capital Improvement Plan- Page 22
quality. Managing invasive and noxious weeds also helps to establish the native vegetation,
increase biodiversity, and improve habitat for local wildlife.
UTILITY PROJECTS
Implements the following Envision Lakeville Community Values:
Good Value for Public Services
U-1: SANITARY SEWER TRUNK SYSTEM IMPROVEMENTS
The Sanitary Sewer Plan anticipates the extension of sanitary sewer trunk facilities to serve areas
of anticipated/planned growth. Lift Station 26 is programmed for construction in 2025. Timing of
sanitary sewer trunk system improvements subject to growth rate and location of planned land
development.
U-2: SANITARY SEWER LIFT STATION REHABILITATION
Lift station service life is 12-15 years. Pumps, motors and equipment are inspected, repaired and
replaced to ensure uninterrupted service. Lift stations are inspected/cleaned annually and
scheduled for rehabilitation every 12-15 years. Lift Stations 3, 4, 5, 6, 7, 8, 11, 18, 19, 20, and 22 are
scheduled for rehabilitation in 2025-2029.
XX-01/XX-02: SANITARY SEWER REHABILITATION
Sanitary sewer infrastructure is subject to breaks, cracks and root intrusion. Rehabilitating
damaged sanitary sewer infrastructure is required to maintain the integrity and function of the
sanitary sewer system. Sanitary sewer within planned transportation project limits is inspected and
required maintenance is programmed with the road improvements to minimize life-cycle costs.
U-3: SANITARY SEWER SYSTEM INFLOW AND INFILTRATION MAINTENANCE
Annual program designed to manage peak discharge rates and maintain/extend the overall service
life of the sanitary sewer collection system through rehabilitating infrastructure susceptible to
inflow and infiltration (groundwater). Public sanitary sewer infrastructure is inspected (televising
250,000 pipe-feet/year) and cleaned (jetting 75 pipe-miles/year) to maintain the integrity and
function of the sanitary sewer collection system.
XX-01/XX-02: WATERMAIN REPLACEMENT
City of Lakeville 2025-2029 Capital Improvement Plan- Page 23
Watermain infrastructure is subject to breaks, cracks, and corrosion. Replacing damaged
watermain infrastructure is required to maintain the integrity and function of the water system.
Watermain within planned transportation project limits is evaluated based on age, break history
and soil conditions. Required maintenance or preventive measures (hydrant/valve bolt
replacement, corrosion protection) are programmed with the road improvements to minimize life-
cycle costs.
U-4: WELL CONSTRUCTION
The Water Plan provides guidance in identifying future water system facilities required to serve
areas of planned land development. Well #23 is under construction and will be brought online in
2025, and Wells 24 and 25 are programmed for 2028 construction. Construction timing and well
location subject to population demand/water needs. The Wellhead and Source Water Protection
Plan must be amended prior to receiving a Minnesota Department of Health permit.
U-5: WATERMAIN TRUNK SYSTEM IMPROVEMENTS
The Water Plan anticipates the extension of watermain trunk facilities to serve areas of planned
land development. Timing of watermain trunk system improvements subject to growth rate and
location of planned land development.
U-6: WATER SYSTEM DISTRIBUTION FEATURES
The Water Plan provides guidance in identifying future water system features required to serve
areas of planned land development, including features to either reduce or boost the water pressure
due to the elevation of new development. New pressure reducing valves are programmed for 2025,
2026 and 2028 construction. Construction timing and location subject to growth rate and location
of planned land development.
U-7: WELL AND PUMP REHABILITATION
Pumps, motors and equipment are inspected, repaired and replaced to ensure uninterrupted,
efficient service and a water system operating at maximum pumping capacity. City wells provide
water for on-demand distribution system (24 hours/day, 7 days/week). Multiple starts/stops place
tremendous stress on the motors and pump components and constant water exposure can lead to
corrosion. Well and pumps are scheduled for rehabilitation every 8-10 years, based on pump type.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 24
U-8: WATER TOWER AND RE SERVOIR MAINTENANCE
Maintenance program designed to manage, preserve and protect investment in water storage tanks
(interior and exterior). Maintenance removes buildup, dirt/dust, and extends the life of the coating
system, minimizing total lifecycle costs.
U-9: WATER METER REPLACEMENT
Annual program designed to replace residential and commercial water meters approaching the
end of their life cycle, to ensure accurate water monitoring use data for Minnesota Department of
Natural Resources reporting. Program goal is 1,200 water meter replacements per year (based on
meter age) with the intent of meeting/maintaining a 20-year service life. Routine water meter
replacement is completed by City Utilities staff. 2022 costs included one-time costs to convert the
current water meter system to a fixed-base system and reduced meter replacement costs for 2023-
2025.
U-10: FIBER OPTIC CABLE CONNECTIONS
Extension of fiber optic cable to remote utility sites (lift stations, wells) for better and more
reliable communication.
PARKS AND RECREATION PROJECTS
Implements the following Envision Lakeville Community Values:
Good Value for Public Services
Safety Throughout the Community
Design That Connects the Community
A Sense of Community and Belonging
Access to a Multitude of Natural Amenities and Recreational Opportunities
P-1: PARKS MAJOR MAINTENANCE PROJECTS
Includes general maintenance projects, maintenance of buildings, park shelters and grounds, fields
and open spaces (examples- re-shingle park shelters, replace signs, replace rubber floors, seal park
parking lots, resurface basketball and tennis courts, etc.).
P-2: PARK DEVELOPMENT - ADMINISTRATIVE PROJECTS-
The Park Dedication Fund budget provides appropriations for many activities including planning,
design and feasibility reports for park projects such as Voyageur Park and Spyglass Park Phase II.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 25
P-3: PARK DEVELOPMENT DEVELOPER CREDITS
Represents credits associated with new development when the park dedication requirement is
fulfilled through a land dedication.
P-4: FUTURE PARK LAND ACQUISITION
Represents potential costs of land acquisition where needed to fulfill future plans for parks in the
City.
P-5: TRAIL IMPROVEMENTS
The City retained a third party in 2022 to evaluate the condition of all trail segments in our
community and plans are to do this again in 2026. Based on the evaluations, staff will develop a
plan for either overlaying or reclaiming City trail segments, along with crack filling and fog sealing
of trails.
Maintenance of sidewalks and trails along Dakota County roadways is provided in accordance with
the current County and City Maintenance Agreement for County Bikeway Trails. In 2021, the
Dakota County Board of Commissioners approved the following regarding trails and sidewalks
along Dakota County roadways:
Multi-Use Trails and Sidewalk Maintenance
Dakota County will participate in pavement preservation, overlay, or reconstruction of
trails and sidewalks along the County highway system up to 100 percent. The City is
responsible for snow and ice removal. To be eligible for County participation in trails and
sidewalks, a system-wide maintenance agreement between the County and local agency
will be required to identify system-wide trail and sidewalk roles and cost responsibilities.
P-6: PARK IMPROVEMENTS
The Park Improvement Fund provides funding for replacement and upgrades to playgrounds,
shelters and buildings, parking lots used to access City parks, and other park amenities (ballfields
and rinks).
City of Lakeville 2025-2029 Capital Improvement Plan- Page 26
P-7: PEDESTRIAN CROSSING PROJECTS
The Park Dedication Fund provides funding for pedestrian crossing upgrades to include
implementation of pedestrian/bicycle safety strategies. Crossing locations will be evaluated based
on the City’s Pedestrian Crossing Policy and programmed/prioritized accordingly.
P-8: RITTER MEADOWS PARK
The Parks, Trails and Open Space Plan calls for a neighborhood park in the area which is proposed
to be constructed in 2027.
P-9: VOYAGEUR PARK
The Parks, Trails, and Open Space Plan calls for a neighborhood park East of Cedar Avenue and
south of 181st Street serving the future development in this area. The park will be approximately 2
acres in size and is proposed to be constructed in 2025.
P-10: SPYGLASS PARK PHASE II
Spyglass Park currently consists of a playground, shelter, and green space on a parcel 4.2 acres in
size. Once the area north of the park develops, plans are to expand the park with additional green
space and amenities to serve all the neighborhoods in the area. Construction is proposed to be
completed in 2026.
P-11: KEOKUK AVENUE/172ND STREET PARK
The Parks, Trails and Open Space Plan calls for a neighborhood park in the area which is proposed
to be constructed in 2030. Planning/design costs are included in 2029.
P-12: GRAND PRAIRIE SKATEPARK
Planning/design costs are included in 2027 with construction planned for 2028.
P-13: OTHER PROJECTS
This category is intended to include smaller park projects such as adding artwork in the parks, tree
planting, security cameras at park facilities, Pickleball courts in the south side of the City (Wild
Meadows/Hasse), and the completion of an ADA Transition Plan.
23-13: KLAMATH TRAIL RETAINING WALL
There are two existing modular block retaining walls (totaling over 1,200 feet in length) along the
south side of Klamath Trail, west of County State Aid Highway 5, which were constructed in 1999.
City of Lakeville 2025-2029 Capital Improvement Plan- Page 27
A Condition Assessment Report was completed by a third party after it was noticed that the modular
block walls are showing signs of deterioration. Based on the anticipated life span of these walls and
the condition assessment that indicates visible staining, cracking along the face of individual blocks
along with other types of deterioration, the replacement of these walls is scheduled to be completed
in 2027 with prefabricated modular block walls (PMBW). This is currently planned to be funded by
the Trail Improvement fund.
CP 24-20 GRAND PRAIRIE PARK (FORMERLY KNOWN AS AVONLEA COMMUNITY PARK)
Construction of this park is underway in 2024, with completion anticipated in 2025. This project
was approved as part of the 2021 Park Bond Referendum. Lakeville Lions has committed $500,000
toward the Avonlea splash pad over five years ($100,000/year). Lakeville Baseball Association has
committed $1 Million toward the project over 10 years ($100,000/year).
CP 25-15: NORTH CREEK GREENWAY
o Phase I: 173rd Street to East Community Park Trailhead
o Phase II: East Community Park Trailhead to 160th Street (CSAH 46)
Multi-phased County greenway project designed to provide connectivity City and County trail
system. Phase I is programmed for 2025 construction. Phase II is programmed for 2026
construction and includes trailhead in East Community Park.
CP 25-20: EAST COMMUNITY PARK PHASE II
The 2018 Master Plan for the park identified specific amenities. The park is proposed to be
constructed in 2026, which was approved as part of the 2021 Park Bond Referendum.
CP 26-15: LAKE MARION GREENWAY
o Phase IA: Ritter Farm Park to West of Dodd Boulevard/CSAH 9
o Phase IB: East of Dodd Boulevard/CSAH 9 to Holyoke Avenue
o Phase II: Holyoke Avenue to Cedar Avenue/CSAH 23
o Phase III: Murphy-Hanrehan Park to Ritter Farm Park
Multi-phased County greenway project designed to provide connectivity City and County trail
system. Phase IA and IB programmed for 2026 construction and includes Kenrick Avenue
crossing, mini trailhead in Ritter Farm Park, mini trailhead in Downtown and Parking Lot A
reconstruction.
FACILITIES PROJECTS
City of Lakeville 2025-2029 Capital Improvement Plan- Page 28
City of Lakeville – FiRST Center: First Responders Skills Training Center
A regional public safety training facility does not currently exist for use by public safety personnel
in the south metro area and adjacent cities and counties. A regional training facility would help
ensure our safety personnel have the highest degree of training possible to serve the public. The
Minnesota Legislature has clearly stated that public safety personnel need to be better trained and
equipped to respond to the growing demands placed on them. The biggest challenge for mid-sized
departments is the funding for and ongoing maintenance required of a permanent training
facility. Public safety personnel often use local businesses, schools, and vacant facilities as
temporary training sites since there is not a permanent site that fits all the training and classroom
needs. A permanent, dedicated site within Dakota County, available to all jurisdictions within the
south metro and Greater Minnesota area, would improve the ability to consistently and routinely
train public safety employees, as well as maintain certifications.
The project proposes to redevelop the city’s old public works property located at 7777 214th Street
into a regional public safety training facility that would include the following features:
Physical training area for fire, police and EMS
Virtual training area
Firing range training area with vehicle access
Equipment cleaning and armory area
Tactical training room with movable partitions for fire, police and EMS
Classroom/meeting space for fire, police and EMS
Office space
Restrooms/lockers
$7 Million of funding was awarded for this public safety training center through the 2023
Minnesota Legislature capital investment (cash funding) bill and an additional $800,000 was
awarded in 2024 through Federal Congressionally Directed Funding. The design of the facility will
be complete and bid in 2024, with construction of the facility in 2025 and operational by mid-2026.
City of Lakeville – Fire Department Facility Assessment/Transition to FT
Firefighters
City of Lakeville 2025-2029 Capital Improvement Plan- Page 29
In anticipation of transitioning to a full-time firefighting staff, a fire station facility study was
completed in 2023. The study indicated there are significant improvements that need to be
completed to each station to modernize them to meet best practices for station designs and to add
dorm/sleeping quarters and related kitchen and laundry areas to accommodate full-time staff.
The city completed a temporary renovation of FS4 in 2024 to accommodate the hiring of the first
six new full-time firefighters in April. The city plans to add an additional six new full-time
firefighters in 2025 and another six full-time firefighters in 2026.
City Council is considering implementing one of two scenarios over the next six years:
1. Complete renovations and additions at all four existing fire stations to modernize them to
accommodate the needs of full-time staff. This scenario could cost up to $52 million.
2. Complete renovations of Stations 1 and 3, but instead of renovating Stations 2 and 4 the
city would consider purchasing land within the Dodd Boulevard/Cedar Avenue area to
construct a new fire station that would replace Stations 4 and 2, eliminating the need for
them to be fully renovated. The old fire station sites could then be used for other municipal
needs or sold for private development. This scenario could cost up to $68 million.
The CIP currently includes $60 million of costs related to Fire Stations between 2026-2028, and is
planned to be funded by bonds and franchise fees.
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
STREET PROJECTS
XX‐01 Pavement Management ‐ Maintenance Maintenance R
Taxes 2,130,500 2,195,000 2,260,000 2,330,000 2,400,000 11,315,500
Municipal State Aid 120,000 120,000 120,000 120,000 120,000 600,000
Water Operating Fund 100,000 100,000 100,000 100,000 100,000 500,000
Sanitary Sewer Operating Fund 100,000 100,000 100,000 100,000 100,000 500,000
2,450,500 2,515,000 2,580,000 2,650,000 2,720,000 12,915,500
XX‐02 Street Reconstruction ‐ Note 1 Reconstruction/Maintenance R
Property Tax Levy‐ next year project costs (ex‐ 2026 project costs in 2025)‐ 155,000 155,000 155,000 155,000 620,000
G.O. Improvement Bonds ‐ Taxes 3,500,000 3,425,000 3,530,000 3,635,000 3,745,000 17,835,000
G.O. Improvement Bonds ‐ Sp. Assess.645,000 ‐ ‐ 875,000 ‐ 1,520,000
Water Operating Fund 900,000 470,000 470,000 470,000 470,000 2,780,000
Sanitary Sewer Operating Fund 250,000 250,000 250,000 250,000 250,000 1,250,000
Stormwater Infrastructure Fund 105,000 105,000 105,000 105,000 105,000 525,000
5,400,000 4,405,000 4,510,000 5,490,000 4,725,000 24,530,000
XX‐03 Collector Roadway Rehabilitation‐ Note 1 Rehabilitation R
G.O. Improvement Bonds ‐ Taxes 683,245 490,707 2,750,000 2,743,425 889,719 7,557,096
G.O. Improvement Bonds ‐ Sp. Assess.‐ ‐ 350,000 ‐ ‐ 350,000
Water Operating Fund 35,000 50,000 100,000 100,000 50,000 335,000
Sanitary Sewer Operating Fund 5,000 15,000 25,000 25,000 15,000 85,000
Sanitary Sewer Trunk Fund (fiber conduit)‐ ‐ 50,000 ‐ ‐ 50,000
Park Dedication Fund (fiber conduit)‐ ‐ 100,000 ‐ ‐ 100,000
Other cost share arrangement‐ Credit River (Judicial Rd)‐ 490,707 ‐ ‐ ‐ 490,707
723,245 1,046,414 3,375,000 2,868,425 954,719 8,967,803
XX‐10 Dakota County Pavement Preservation Rehabilitation R
Taxes (Pavement Management Fund)30,000 ‐ 25,000 ‐ ‐ 55,000
Water Operating Fund 10,000 5,000 5,000 ‐ ‐ 20,000
Sanitary Sewer Operating Fund 10,000 5,000 5,000 ‐ ‐ 20,000
50,000 10,000 35,000 ‐ ‐ 95,000
22‐03 210th Street Reconstruction Collector Rehabilitation IP
Municipal State Aid (repay County advance from 2022) Roundabout 524,000 ‐ ‐ ‐ ‐ 524,000
Dakota County‐ Advance funding of city share (524,000) ‐ ‐ ‐ ‐ (524,000)
‐ ‐ ‐ ‐ ‐ ‐
22‐08 Centerpoint Energy Tree Replacement Project Other IP
Other funding‐ Centerpoint (tree planting and watering/replacement) 140,000 ‐ ‐ ‐ ‐ 140,000
140,000 ‐ ‐ ‐ ‐ 140,000
22‐16 Freight Rail Car Storage and Transload Facility Other IP
Improvement Construction Fund (fund balance)150,000 ‐ ‐ ‐ ‐ 150,000
Other state funding (project subject to grant funding)‐ 7,000,000 ‐ ‐ ‐ 7,000,000
Other federal funding (project subject grant funding)‐ 750,000 ‐ ‐ ‐ 750,000
150,000 7,750,000 ‐ ‐ ‐ 7,900,000
City of Lakeville, Minnesota
Capital Improvements Plan
Projects & Funding Sources by Category
2025‐2029
Page 30
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
23‐04 179th St/Future CSAH 9 (Highview Ave ‐ Cedar Ave)‐Phase I Rehabilitation IP
Dodd Boulevard (Gerdine Path‐ Dodd Lane) ‐ Phase II
Municipal State Aid (repay County advances in 2025)3,067,930 ‐ ‐ ‐ ‐ 3,067,930
Dakota County‐ Advance funding of city share (4,527,875) ‐ ‐ ‐ ‐ (4,527,875)
Escrow 690,000 ‐ ‐ ‐ ‐ 690,000
Park Dedication Fund 769,945 ‐ ‐ ‐ ‐ 769,945
‐ ‐ ‐ ‐ ‐ ‐
24‐04 185th St/Future CSAH 60 (Dodd Blvd ‐ Highview Ave) Extension with roundabout IP
Municipal State Aid (repay County advances from 2022 and 2023) 430,000 2,300,000 ‐ ‐ ‐ 2,730,000
Dakota County‐ Advance funding of city share (430,000) (2,300,000) ‐ ‐ ‐ (2,730,000)
‐ ‐ ‐ ‐ ‐ ‐
24‐05 179th St Bridge and Future CSAH 9 Bridge/Traffic Signal IP
Municipal State Aid ‐ 2,440,200 ‐ ‐ ‐ 2,440,200
Dakota County ‐ 6,850,000 ‐ ‐ ‐ 6,850,000
Park Dedication Fund ‐ 67,313 ‐ ‐ ‐ 67,313
Escrow ‐ 800,000 ‐ ‐ ‐ 800,000
Stormwater Infrastructure Fund ‐ 2,232,825 ‐ ‐ ‐ 2,232,825
Water Trunk Fund ‐ 590,000 ‐ ‐ ‐ 590,000
Streetlight Operating Fund ‐ 67,500 ‐ ‐ ‐ 67,500
‐ 13,047,838 ‐ ‐ ‐ 13,047,838
25‐04 185th St/CSAH 60 (Kenwood Tr‐Ipava Ave)Modernization IP
Municipal State Aid 135,000 281,763 1,417,500 2,840,000 ‐ 4,674,263
Dakota County 5,700,000 ‐ ‐ ‐ ‐ 5,700,000
Dakota County‐ Advance funding of city share 2,838,935 (281,763) (1,417,500) (2,840,000) ‐ (1,700,328)
Escrow 116,065 ‐ ‐ ‐ ‐ 116,065
Park Dedication Fund 200,000 ‐ ‐ ‐ ‐ 200,000
Stormwater Infrastructure Fund 1,300,000 ‐ ‐ ‐ ‐ 1,300,000
Sanitary Sewer Trunk Fund 15,000 ‐ ‐ ‐ ‐ 15,000
Water Operating Fund 150,000 ‐ ‐ ‐ ‐ 150,000
Sanitary Sewer Operating Fund 15,000 ‐ ‐ ‐ ‐ 15,000
Other funding‐ State 704,500 ‐ ‐ ‐ ‐ 704,500
Water Trunk Fund (fiber conduit‐ connectivity for wells)50,000 50,000
Street Light Operating Fund 10,000 ‐ ‐ ‐ ‐ 10,000
11,234,500 ‐ ‐ ‐ ‐ 11,234,500
25‐05 Holyoke/Highview Avenue Reconstruction Rehabilitation IP
Municipal State Aid ‐ 1,955,000 3,192,400 ‐ 1,255,000 6,402,400
MSA/MSA Bonds ‐ Sp. Assess.‐ ‐ 350,000 ‐ ‐ 350,000
Escrow ‐ ‐ 657,600 ‐ ‐ 657,600
Park Dedication Fund ‐ ‐ 1,200,000 ‐ ‐ 1,200,000
Stormwater Infrastructure Fund ‐ ‐ 1,035,000 ‐ ‐ 1,035,000
Water Operating Fund ‐ ‐ 75,000 ‐ ‐ 75,000
Sanitary Sewer Operating Fund ‐ ‐ 145,000 ‐ ‐ 145,000
Trail Improvement Fund ‐ ‐ 200,000 ‐ ‐ 200,000
Street Light Operating Fund ‐ ‐ 50,000 ‐ ‐ 50,000
‐ 1,955,000 6,905,000 ‐ 1,255,000 10,115,000
Page 31
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
26‐04 CSAH9 Modernization (210th St‐ CSAH 50)Modernization IP
Municipal State Aid 135,000 270,000 917,971 ‐ ‐ 1,322,971
Dakota County 765,000 1,530,000 7,397,500 ‐ ‐ 9,692,500
Escrow 292,029 292,029
Stormwater Infrastructure ‐ ‐ 250,000 ‐ ‐ 250,000
Water Operating ‐ ‐ 2,500 ‐ ‐ 2,500
Sanitary Sewer Operating ‐ ‐ 5,000 ‐ ‐ 5,000
Street Light Operating ‐ ‐ 10,000 ‐ ‐ 10,000
General Fund (Weather siren‐ Fiber conduit)‐ ‐ 40,000 ‐ ‐ 40,000
Park Dedication ‐ ‐ 97,500 ‐ ‐ 97,500
900,000 1,800,000 9,012,500 ‐ ‐ 11,712,500
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction Interchange Reconstruction IP
Municipal State Aid (City share of repayment of 2017 and 2021/2022 RALF
loans)
‐ ‐ 260,852 ‐ ‐ 260,852
Municipal State Aid (City share of project costs) ‐ 75,000 ‐ 1,605,000 1,680,000
Dakota County (County share of repayment of 2017 and 2021/2022 RALF
loans)
‐ ‐ 1,478,161 ‐ ‐ 1,478,161
Dakota County (share of CSAH 50 Watershed Improvements at Jurel Way) 165,000 165,000
Dakota County‐ Advance funding of city share ‐ 1,605,000 3,375,000 ‐ (1,605,000) 3,375,000
Stormwater Infrastructure 135,000 135,000
General Fund (Weather siren‐ Fiber conduit)10,000 10,000
Sanitary Sewer Trunk (Lift Station‐ Fiber conduit)10,000 10,000
Water Trunk Fund (wells/towers‐ Fiber conduit)10,000 10,000
Park Dedication Fund Fiber conduit)‐ ‐ 10,000 ‐ ‐ 10,000
‐ 1,680,000 5,454,013 ‐ ‐ 7,134,013
26‐06 CSAH 50 Roundabout at Hamburg Ave Roundabout N
Streetlight Operating Fund ‐ 30,000 ‐ ‐ ‐ 30,000
‐ 30,000 ‐ ‐ ‐ 30,000
26‐07 CSAH 60 Alignment Study (CSAH 23‐ Flagstaff Ave)Rehabilitation N
Pavement Management Fund ‐ 78,750 ‐ ‐ ‐ 78,750
‐ 78,750 ‐ ‐ ‐ 78,750
26‐15 Lake Marion Greenway Greenway IP
Park Dedication Fund 28,000 2,050,000 ‐ ‐ 60,000 2,138,000
Pavement Management Fund ‐ 200,000 ‐ ‐ ‐ 200,000
Dakota County (new trails)162,000 967,500 ‐ ‐ 345,000 1,474,500
Dakota County (trail improvements)‐ 640,500 ‐ ‐ ‐ 640,500
Park Improvement Fund (Ritter Farm parking lot/roadway improvements)‐ 225,000 ‐ ‐ ‐ 225,000
Trail Improvement Fund ‐ 110,000 ‐ ‐ ‐ 110,000
Sanitary Sewer Fund (Fiber conduit)‐ 90,000 ‐ ‐ ‐ 90,000
Park Dedication Fund (Fiber conduit)‐ 90,000 ‐ ‐ ‐ 90,000
190,000 4,373,000 ‐ ‐ 405,000 4,968,000
28‐04 Dodd Blvd/CSAH 9 Modernization (215th St‐ 210th St.)Rehabilitation N
Municipal State Aid ‐ 80,325 162,435 421,610 ‐ 664,370
Dakota County ‐ 455,175 920,465 3,499,790 ‐ 4,875,430
Escrow 196,000 196,000
Park Dedication 30,000 30,000
Escrow ‐
‐ 535,500 1,082,900 4,147,400 ‐ 5,765,800
Total Transportation Projects* 21,238,245 39,226,502 32,954,413 15,155,825 10,059,719 118,634,704
*(Includes utility and trail improvements completed with street reconstruction projects)
Page 32
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
UTILITY PROJECTS
U‐1 Sanitary Sewer Trunk Improvements
Sanitary Sewer Trunk Fund ‐ Fees R 75,000 75,000 75,000 75,000 75,000 375,000
U‐2 Sanitary Sewer Lift Station Rehabilitation
Sanitary Sewer Operating Fund ‐ User Fees R 205,000 105,000 235,000 275,000 275,000 1,095,000
XX‐02/XX‐01 Sanitary Sewer Rehabilitation
Sanitary Sewer Operating Fund ‐ User Fees (included above with
transportation projects) R ‐ ‐ ‐ ‐ ‐ ‐
U‐3 Sanitary Sewer Inflow/Infiltration Maintenance
Sanitary Sewer Operating Fund ‐ User Fees R 575,000 575,000 575,000 575,000 575,000 2,875,000
24‐09 Lift Station #26/Crystal Lake Lift Station
Sanitary Sewer Trunk Fund ‐ Fees N 2,000,000 ‐ ‐ ‐ ‐ 2,000,000
XX‐02/XX‐01 Watermain Replacement
Water Operating Fund ‐ User Fees (included above with street reconstruction projects) R ‐ ‐ ‐ ‐ ‐ ‐
Water Operating Fund ‐ User Fees (included above with pavement management projects)‐ ‐ ‐ ‐ ‐ ‐
U‐4 Well Construction
Water Trunk Fund ‐ Fees IP ‐ ‐ 100,000 1,800,000 ‐ 1,900,000
U‐5 Watermain Trunk Extensions
Water Trunk Fund ‐ Fees R 265,000 265,000 265,000 265,000 265,000 1,325,000
U‐6 Water Distribution Features
Water Trunk Fund ‐ Fees R 60,000 150,000 ‐ 150,000 ‐ 360,000
U‐7 Well and Pump Rehabilitation
Water Operating Fund ‐ User Fees R 100,000 200,000 200,000 100,000 300,000 900,000
U‐8 Tower and Reservoir Maintenance
Water Operating Fund ‐ User Fees R ‐ 1,000,000 ‐ ‐ 150,000 1,150,000
U‐9 Water meter replacement
Water Operating Fund ‐ User Fees R 150,000 300,000 300,000 300,000 300,000 1,350,000
U‐10 Fiber Optic Cable Connection
Water Operating Fund ‐ User Fees IP 45,000 37,000 37,000 40,000 30,000 189,000
Sanitary Sewer Operating Fund ‐ User Fees 25,000 25,000 25,000 30,000 30,000 135,000
Water Trunk Fund ‐ Fees (conduit costs included above with street projects)‐ ‐ ‐ ‐ ‐ ‐
Sanitary Sewer Trunk Fund ‐ Fees (conduit costs included above with street projects)‐ ‐ ‐ ‐ ‐ ‐
Total Utility Projects* 3,500,000$ 2,732,000$ 1,812,000 3,610,000 2,000,000$ 13,654,000
*(Excludes utility replacements done with street reconstruction projects)
Page 33
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
ENVIRONMENTAL RESOURCES PROJECTS
ER‐1 Water Quality/Conservation Projects
Environmental Resources User Fees R
Water Quality BMPs 75,000 75,000 75,000 75,000 75,000 375,000
Urban Restoration‐ Public System Initiatives 10,000 10,000 10,000 10,000 10,000 50,000
Water Conservation‐ Public System Improvements 20,000 20,000 20,000 20,000 20,000 100,000
105,000 105,000 105,000 105,000 105,000 525,000
ER‐2 Lake Management R
Environmental Resources ‐ User Fees (water quality assessment) 60,000 60,000 60,000 60,000 60,000 300,000
Environmental Resources ‐ User Fees (water quality treatment) 15,000 15,000 15,000 15,000 15,000 75,000
Dakota County 35,000 35,000 35,000 35,000 35,000 175,000
110,000 110,000 110,000 110,000 110,000 550,000
ER‐3 Stormwater Infrastructure Maintenance
Environmental Resources ‐ User Fees R ‐
Stormwater Basin Rehabilitation 350,000 350,000 350,000 350,000 350,000 1,750,000
Stormwater Infrastructure Maintenance/Rehabilitation 190,000 190,000 190,000 190,000 190,000 950,000
FES Maintenance‐(MS4 Pond/Outfall Insp)85,000 85,000 85,000 85,000 85,000 425,000
625,000 625,000 625,000 625,000 625,000 3,125,000
ER‐4 Storm Water Conveyance System Expansion
Stormwater Infrastructure Fund ‐ Fees R 100,000 100,000 100,000 100,000 100,000 500,000
100,000 100,000 100,000 100,000 100,000 500,000
ER‐5 Forestry (Ash tree injection/removal, reforestation parks/public spaces)R
General Fund (Ash tree injection)62,000 62,000 62,000 62,000 62,000 310,000
General Fund (Ash tree removal)43,000 43,000 43,000 43,000 43,000 215,000
General Fund (Reforestation)25,000 25,000 25,000 25,000 25,000 125,000
130,000 130,000 130,000 130,000 130,000 650,000
ER‐6 Vegetation Maintenance‐ City Outlots/Public land
Environmental Resources ‐ User Fees R 140,000 140,000 140,000 140,000 140,000 700,000
140,000 140,000 140,000 140,000 140,000 700,000
20‐45 165th St Drainage System Improvements IP
Stormwater Infrastructure Fund ‐ Fees 275,000 ‐ ‐ ‐ ‐ 275,000
275,000 ‐ ‐ ‐ ‐ 275,000
23‐58 East Lake Rough Fish Barrier N
Environmental Resources ‐ User Fees 50,000 ‐ ‐ 50,000
50,000 ‐ ‐ ‐ ‐ 50,000
24‐44 Stormwater Management Improvements at Greenridge Park N
Stormwater Infrastructure Fund ‐ Fees 24,000 76,000 ‐ ‐ ‐ 100,000
VRWJPO ‐ 200,000 ‐ 200,000
24,000 276,000 ‐ ‐ ‐ 300,000
Total Environmental Resources Projects 1,559,000$ 1,486,000$ 1,210,000$ 1,210,000$ 1,210,000$ 6,675,000$
Page 34
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
PARKS PROJECTS
P‐1 Parks Major Maintenance
Park Improvement Fund R
General Maintenance 18,250 18,250 18,500 19,500 19,500 94,000
Buildings/Shelters/Grounds 55,000 40,000 40,000 54,500 48,500 238,000
Court Reconstruction/Resurfacing 13,200 7,000 30,000 22,000 12,000 84,200
Field Improvements/Maintenance 91,000 44,000 44,000 46,000 46,000 271,000
Open space improvement and maintenance 40,000 27,000 27,000 27,000 27,000 148,000
217,450 136,250 159,500 169,000 153,000 835,200
P‐2 Park Development ‐ Adminstrative Projects R
Park Dedication Fund ‐ Fees (future park projects)20,000 20,000 20,000 20,000 20,000 100,000
Park Dedication Fund ‐ Fees (comm./industrial park fee analysis)‐ 15,000 ‐ ‐ ‐ 15,000
Park Dedication Fund ‐ Fees (parks, trails, and open spaces plan)‐ ‐ ‐ 150,000 ‐ 150,000
20,000 35,000 20,000 170,000 20,000 265,000
P‐3 Park Development ‐ Developer Credits R
Park Dedication Fund 435,000 435,000 435,000 435,000 435,000 2,175,000
435,000 435,000 435,000 435,000 435,000 2,175,000
P‐4 Future Park Land Acquisition R
Park Dedication Fund ‐ Fees ‐ ‐ ‐ 100,000 100,000 200,000
‐ ‐ ‐ 100,000 100,000 200,000
P‐5 Trail Improvements (Various Trails)R
Trail Improvement Fund 530,000 830,000 530,000 612,000 610,000 3,112,000
Park Dedication Fund (trail connectivity‐ general)‐ ‐ ‐ 100,000 100,000 200,000
Park Dedication Fund‐ CP25‐01 Eclipse Ave Trail (Outlot A to Greenway) 40,000 ‐ ‐ ‐ ‐ 40,000
Dakota County (contribution toward Eclipse Ave Trail CP25‐01) 40,000 ‐ ‐ ‐ ‐ 40,000
610,000 830,000 530,000 712,000 710,000 3,392,000
P‐6 Park Improvements (Various Parks)R
Park Improvement Fund‐ playground replacement 226,000 346,000 236,000 489,000 372,000 1,669,000
Park Improvement Fund‐ park parking lot improvements 90,000 75,000 210,000 113,000 55,000 543,000
Park Improvement Fund‐ other 85,000 271,000 356,000 104,000 87,000 903,000
401,000 692,000 802,000 706,000 514,000 3,115,000
P‐7 Pedestrian Crossing Projects IP
Park Dedication Fund‐Pedestrian Crossing: Ipava Ave. & 183rd St. (CP 23‐xx6) 55,000 ‐ ‐ ‐ ‐ 55,000
55,000 ‐ ‐ ‐ ‐ 55,000
P‐8 Ritter Meadows Park IP
Park Dedication Fund ‐ Fees (planning/design)‐ 58,000 20,000 ‐ ‐ 78,000
Park Dedication Fund ‐ Fees (construction)‐ ‐ 750,000 ‐ ‐ 750,000
‐ 58,000 770,000 ‐ ‐ 828,000
P‐9 Voyager Park IP
Park Dedication Fund ‐ Fees (planning/design/master plan)20,000 ‐ ‐ ‐ ‐ 20,000
Park Dedication Fund ‐ Fees (construction)700,000 ‐ ‐ ‐ ‐ 700,000
720,000 ‐ ‐ ‐ ‐ 720,000
P‐10 Spyglass Park‐ Phase II IP
Park Dedication Fund ‐ Fees (planning/design/master plan)45,000 20,000 ‐ ‐ ‐ 65,000
Park Dedication Fund ‐ Fees (construction)‐ 400,000 ‐ ‐ ‐ 400,000
45,000 420,000 ‐ ‐ ‐ 465,000
P‐11 Keokuk Avenue/172nd St. Park IP
Park Dedication Fund ‐ Fees (planning/design/master plan)‐ ‐ ‐ ‐ 65,000 65,000
‐ ‐ ‐ ‐ 65,000 65,000
P‐12 Grand Prairie Skatepark N
Park Dedication Fund ‐ Fees (design)‐ ‐ 50,000 ‐ ‐ 50,000
Park Dedication Fund ‐ Fees (construction)‐ ‐ ‐ 600,000 ‐ 600,000
‐ ‐ 50,000 600,000 ‐ 650,000
Page 35
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
P‐13 Other Projects IP/N
Park Dedication Fund ‐Art in the Park/Heritage Center 10,000 10,000 10,000 10,000 10,000 50,000
Park Dedication Fund ‐ Fees‐King Park Spectator protection and safety fencing 100,000 ‐ ‐ ‐ ‐ 100,000
Park Dedication Fund ‐ Fees‐ADA Transition Plan ‐ 200,000 ‐ ‐ ‐ 200,000
Park Dedication Fund ‐ Fees‐ Pickleball courts‐ S side of city (Wild Meadows/Hasse)‐ ‐ 175,000 ‐ ‐ 175,000
Park Dedication Fund ‐ Fees‐ Tree Planting 15,000 15,000 15,000 15,000 15,000 75,000
Park Dedication Fund ‐ Fees‐ Security cameras‐ TBD/Antlers Shelters 20,000 ‐ ‐ ‐ ‐ 20,000
Park Dedication Fund ‐ Fees‐ Other amenities to be determined ‐ ‐ ‐ 300,000 300,000 600,000
145,000 225,000 200,000 325,000 325,000 1,220,000
23‐13 Klamath Trail Retaining Wall IP
Trail Improvement Fund ‐ ‐ 1,500,000 ‐ ‐ 1,500,000
‐ ‐ 1,500,000 ‐ ‐ 1,500,000
24‐20 Grand Prairie Park‐formerly known as Avonlea Community Park ‐ Note 1 (referendum bonds)IP
Park Bonds Fund (construction)2,102,625 ‐ ‐ ‐ ‐ 2,102,625
2,102,625 ‐ ‐ ‐ ‐ 2,102,625
25‐15 North Creek Greenway Trail/Trailhead IP
Park Dedication Fund ‐ Fees (construction)90,000 90,000
Dakota County (contribution to North Creek Greenway Trailhead) 510,000 510,000
Trail Improvement Fund (CP25‐15A / North Creek Trail, 173rd to East Park) 30,000 ‐ 30,000
Trail Improvement Fund (CP26‐15B‐North Creek Trl East Park to 160th ‐ 30,000 30,000
Dakota County (contribution to North Creek Greenway Trails) 170,000 170,000 340,000
800,000 200,000 ‐ ‐ ‐ 1,000,000
25‐20 East Community Park Phase II ‐ Note 1 (referendum bonds)IP
Park Bonds Fund (planning/design)350,000 200,000 ‐ ‐ ‐ 550,000
Park Bonds Fund (construction)‐ 1,825,000 ‐ ‐ ‐ 1,825,000
Park Dedication Fund ‐ Fees (construction)‐ 150,000 ‐ ‐ ‐ 150,000
Dakota County (contribution to East Community Park Trailhead)‐ 400,000 ‐ ‐ ‐ 400,000
350,000 2,575,000 ‐ ‐ ‐ 2,925,000
Total Parks Projects 5,901,075$ 5,606,250$ 4,466,500$ 3,217,000$ 2,322,000$ 21,512,825$
Equipment Plan‐ Totals by department included below, various funding sources
Facilities 59,977 33,401 ‐ ‐ ‐ 93,378
City Clerk ‐ 318,000 ‐ ‐ ‐ 318,000
Inspections ‐ ‐ 43,600 ‐ ‐ 43,600
Police 965,458 758,972 1,526,583 724,890 1,264,623 5,240,526
Fire 193,963 433,300 409,880 157,920 172,500 1,367,563
Engineering ‐ ‐ ‐ ‐ 57,500 57,500
Construction Services 65,495 69,425 54,500 ‐ 32,174 221,594
Streets 1,364,179 1,098,925 1,578,395 1,282,726 635,618 5,959,843
Forestry 54,044 57,287 ‐ ‐ ‐ 111,331
Parks 593,647 611,157 742,333 716,699 339,965 3,003,801
Environmental Resources ‐ ‐ 33,756 ‐ ‐ 33,756
Communications 33,000 45,000 45,000 40,000 52,000 215,000
Utilities‐ Water/Sewer 124,579 366,743 127,705 128,494 389,674 1,137,195
Total Planned Equipment Purchases 3,454,342$ 3,792,210$ 4,561,752$ 3,050,729$ 2,944,054$ 17,803,087$
Page 36
Total
CIP # Project Funding Source Project Type Status* 2025 2026 2027 2028 2029 2025‐2029
Facilities Plan‐ Totals by facility included below, various funding sources
Art Center‐Performing Arts (LAAC building)210,000 90,000 135,000 ‐ 2,368 437,368
Art Center‐Fine Arts (ALC building)20,000 ‐ 570,000 ‐ ‐ 590,000
Heritage Center 748,000 ‐ ‐ 108,000 96,160 952,160
Central Maintenance Facility 458,000 356,000 17,660,000 300,000 797,704 19,571,704
City Hall 105,000 100,000 ‐ 135,000 17,051 357,051
Fire Station #1 275,000 ‐ ‐ 20,791,940 ‐ 21,066,940
Fire Station #2 ‐ 20,268,200 ‐ ‐ ‐ 20,268,200
Fire Station #3 ‐ ‐ 20,330,800 ‐ ‐ 20,330,800
Fire Station #4 48,000 7,000 30,000 ‐ 124,700 209,700
Police Station 80,000 275,000 ‐ 15,000 133,875 503,875
Heritage Liquor Store ‐ ‐ ‐ 65,000 ‐ 65,000
Kenrick Liquor Store ‐ 40,000 ‐ ‐ ‐ 40,000
Keokuk Liquor Store 60,000 ‐ ‐ ‐ ‐ 60,000
Public Safety Training Facility 24,000,000 ‐ ‐ ‐ ‐ 24,000,000
Water Treatment Facility 4,500,000 863,000 21,750,000 140,000 179,960 27,432,960
Total Planned Facility Expenditures 30,504,000$ 21,999,200$ 60,475,800$ 21,554,940$ 1,351,818$ 135,885,758$
Technology Plan‐ Total use of Funds
See Technology Plan attachment for breakout by department/cost type 611,908 288,314 692,574 689,088 424,603 2,706,487
Total Planned Technology Equipment Expenditures 611,908$ 288,314$ 692,574$ 689,088$ 424,603$ 2,706,487$
TOTAL‐ ALL PROJECTS 66,768,570$ 75,130,476$ 106,173,039$ 48,487,582$ 20,312,194$ 316,871,861
*Status Key
R These are recurring annual projects. The costs may have changed slightly from the prior year CIP due to revised estimates, and a subsequent year added to the CIP.
IP These projects were included in a prior year CIP. The costs and funding sources may have been revised due to more accurate estimates since the prior CIP.
N These projects are new to the CIP this year.
Note 1‐ The majority of this project is anticipated to be funded with bonds. Park projects funded primarily by referendum bonds (where Note 1 is indicated). Park Bond Fund timing shows planned use of bonds, not bond
issuance year. Bond funds will be spent first, and any overage on the project will be paid by the Park Dedication Fund.
Note 2‐ This project was substantially completed during the current year or a prior year, and is included in the 2025‐2029 CIP only to reflect the related future repayment of an advance to Dakota County in one of the years presented.
Note 3‐These new trail and trail lighting costs are planned to be incurred in conjunction with a larger roadway project included in the transportation section of the 2025‐2029 CIP.
Page 37
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Escrow
23‐04 179th St/Future CSAH 9 (Highview Ave ‐ Cedar Ave) / Dodd Blvd (Gerdine Path‐ Dodd Lane)IP 690,000 ‐ ‐ ‐ ‐ 690,000
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 800,000 ‐ ‐ ‐ 800,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 116,065 ‐ ‐ ‐ ‐ 116,065
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 657,600 ‐ ‐ 657,600
26‐04 Dodd Blvd/CSAH9 (210th St ‐ Kenwood Tr/CSAH 50) IP ‐ ‐ 292,029 ‐ ‐ 292,029
28‐04 Dodd Blvd/CSAH 9 Modernization (215th St‐ 210th St.) N ‐ ‐ ‐ 196,000 ‐ 196,000
Total Escrows 806,065 800,000 949,629 196,000 ‐ 2,751,694 0
G.O. Improvement Bonds ‐ Special Assessments
XX‐02 Street Reconstruction R 645,000 ‐ ‐ 875,000 ‐ 1,520,000
XX‐03 Collector Roadway Rehabilitation R ‐ ‐ 350,000 ‐ ‐ 350,000
Total G.O. Improvement Bonds ‐ Special Assessments 645,000 ‐ 350,000 875,000 ‐ 1,870,000
G.O. Improvement Bonds ‐Property Tax Levy
XX‐02 Street Reconstruction (current year project costs) R 3,500,000 3,425,000 3,530,000 3,635,000 3,745,000 17,835,000
XX‐03 Collector Roadway Rehabilitation R 683,245 490,707 2,750,000 2,743,425 889,719 7,557,096
Total G.O. Improvement Bonds ‐ Taxes 4,183,245 3,915,707 6,280,000 6,378,425 4,634,719 25,392,096
G.O. Improvement Bonds‐ Total 4,828,245 3,915,707 6,630,000 7,253,425 4,634,719 27,262,096
Municipal State Aid/Municipal State Aid Bonds
XX‐01 Pavement Management ‐ Maintenance R 120,000 120,000 120,000 120,000 120,000 600,000
22‐03 210th St Reconstruction IP 524,000 ‐ ‐ ‐ ‐ 524,000
23‐04 179th St/Future CSAH 9 (Highview Ave ‐ Cedar Ave) / Dodd Blvd (Gerdine Path‐ Dodd Lane) IP 3,067,930 ‐ ‐ ‐ ‐ 3,067,930
24‐04 185th St/Future CSAH 60 (Dodd Blvd ‐ Highview Ave) IP 430,000 2,300,000 ‐ ‐ ‐ 2,730,000
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 2,440,200 ‐ ‐ ‐ 2,440,200
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 135,000 281,763 1,417,500 2,840,000 ‐ 4,674,263
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ 1,955,000 3,192,400 ‐ 1,255,000 6,402,400
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP 135,000 270,000 917,971 ‐ ‐ 1,322,971
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction IP ‐ 75,000 260,852 ‐ 1,605,000 1,940,852
28‐04 Dodd Blvd/CSAH 9 Modernization (215th St‐ 210th St.) N ‐ 80,325 162,435 421,610 ‐ 664,370
Total Municipal State Aid 4,411,930 7,522,288 6,071,158 3,381,610 2,980,000 24,366,986
Municipal State Aid/Municipal State Aid Bonds‐ Special Assessments
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 350,000 ‐ ‐ 350,000
Total Municipal State Aid Assessments ‐ ‐ 350,000 ‐ ‐ 350,000
Property Taxes and Fund Balance Reserves
XX‐02 Street Reconstruction R ‐ 155,000 155,000 155,000 155,000 620,000
22‐16 Freight Rail Car Storage and Transload Facility IP 150,000 ‐ ‐ ‐ ‐ 150,000
XX‐01 Pavement Management ‐ Maintenance R 2,130,500 2,195,000 2,260,000 2,330,000 2,400,000 11,315,500
XX‐10 Pavement Management ‐ County pavement preservation R 30,000 ‐ 25,000 ‐ ‐ 55,000
26‐07 Pavement Management fund‐CSAH 60 Alignment Study (CSAH 23‐ Flagstaff Ave) N ‐ 78,750 ‐ ‐ ‐ 78,750
26‐15 Pavement Management fund‐ Lake Marion Greenway IP ‐ 200,000 ‐ ‐ ‐ 200,000
Total Property Taxes and Fund Balance Reserves 2,310,500 2,628,750 2,440,000 2,485,000 2,555,000 12,419,250
City of Lakeville, Minnesota
Capital Improvements Plan
Projects by Funding Source
2025‐2029
Page 38
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Dakota County (Transportation Projects only)
Dakota County share of Project costs: ‐ ‐ ‐ ‐ ‐ ‐
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 6,850,000 ‐ ‐ ‐ 6,850,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 5,700,000 ‐ ‐ ‐ ‐ 5,700,000
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP 765,000 1,530,000 7,397,500 ‐ ‐ 9,692,500
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction IP ‐ ‐ 1,643,161 ‐ ‐ 1,643,161
26‐15 Lake Marion Greenway N 162,000 1,608,000 ‐ ‐ 345,000 2,115,000
28‐04 Dodd Blvd/CSAH 9 Modernization (215th St‐ 210th St.) N ‐ 455,175 920,465 3,499,790 ‐ 4,875,430
Total Dakota County share of project costs 6,627,000 10,443,175 9,961,126 3,499,790 345,000 30,876,091
Dakota County advance funding of city costs (City to repay three years later)
22‐03 210th St Reconstruction IP (524,000) ‐ ‐ ‐ ‐ (524,000)
23‐04 179th St/Future CSAH 9 (Highview Ave ‐ Cedar Ave) / Dodd Blvd (Gerdine Path‐ Dodd Lane) IP (4,527,875) ‐ ‐ ‐ ‐ (4,527,875)
24‐04 185th St/Future CSAH 60 (Dodd Blvd ‐ Highview Ave) IP (430,000) (2,300,000) ‐ ‐ ‐ (2,730,000)
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 2,838,935 (281,763) (1,417,500) (2,840,000) ‐ (1,700,328)
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction IP ‐ 1,605,000 3,375,000 ‐ (1,605,000) 3,375,000
Total Dakota County advances (net of repayments during years shown) (2,642,940) (976,763) 1,957,500 (2,840,000) (1,605,000) (6,107,203)
Total Dakota County (transportation contributions/advances) 3,984,060 9,466,412 11,918,626 659,790 (1,260,000) 24,768,888
Other
XX‐03 Other grant‐ Judicial Rd (Credit River)R ‐ 490,707 ‐ ‐ ‐ 490,707
25‐04 Other state funding‐ Safe Routes to School grant‐ 185th St/CSAH 60 (Kenwood Tr‐Ipava Ave) IP 704,500 ‐ ‐ ‐ ‐ 704,500
22‐16 Other state funding (project subject to grant Funding)‐ Freight Rail Car Storage Transload Facility IP ‐ 7,000,000 ‐ ‐ ‐ 7,000,000
22‐16 Other federal funding (project subject to grant Funding)‐ Freight Rail Car Storage Transload Facility IP ‐ 750,000 ‐ ‐ ‐ 750,000
22‐08 Other funding (Centerpoint Energy)IP 140,000 ‐ ‐ ‐ ‐ 140,000
Total Other 844,500 8,240,707 ‐ ‐ ‐ 9,085,207
Total Transportation Projects 17,185,300 32,573,864 28,359,413 13,975,825 8,909,719 101,004,121
Water Trunk Fund ‐ Fees
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 590,000 ‐ ‐ ‐ 590,000
25‐04 Fiber Conduit‐ 185th St/CSAH60 (Kenwood Tr‐Ipava Ave) IP 50,000 ‐ ‐ ‐ ‐ 50,000
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction‐ Fiber conduit N ‐ ‐ 10,000 ‐ ‐ 10,000
U‐4 Well Construction R ‐ ‐ 100,000 1,800,000 ‐ 1,900,000
U‐5 Watermain Trunk Extensions R 265,000 265,000 265,000 265,000 265,000 1,325,000
U‐6 Water Distribution Features R 60,000 150,000 ‐ 150,000 ‐ 360,000
Total Water Trunk Fund 375,000 1,005,000 375,000 2,215,000 265,000 4,235,000
Water Operating Fund ‐ Fees
U‐7 Well and Pump Rehabilitation R 100,000 200,000 200,000 100,000 300,000 900,000
U‐8 Tower and Reservoir Maintenance R ‐ 1,000,000 ‐ ‐ 150,000 1,150,000
U‐9 Water Meter Replacement R 150,000 300,000 300,000 300,000 300,000 1,350,000
U‐10 Fiber Optic Cable Connection N 45,000 37,000 37,000 40,000 30,000 189,000
XX‐02 Watermain Replacement/Repair (XX‐02 Street Reconstruction project) R 900,000 470,000 470,000 470,000 470,000 2,780,000
XX‐03 Watermain Replacement/Repair (XX‐03 Collector Roadway Rehab project) R 35,000 50,000 100,000 100,000 50,000 335,000
xx‐10 Watermain Replacement/Repair (XX‐10 Dakota County pavement preservation) R 10,000 5,000 5,000 ‐ ‐ 20,000
XX‐01 Watermain Replacement/Repair (XX‐01 misc street repairs project) R 100,000 100,000 100,000 100,000 100,000 500,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 150,000 ‐ ‐ ‐ ‐ 150,000
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 75,000 ‐ ‐ 75,000
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP ‐ ‐ 2,500 ‐ ‐ 2,500
Total Water Operating Fund 1,490,000 2,162,000 1,289,500 1,110,000 1,400,000 7,451,500
Total Water System 1,865,000 3,167,000 1,664,500 3,325,000 1,665,000 11,686,500
Page 39
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Sanitary Sewer Trunk Fund ‐ Fees
24‐09 Sanitary Sewer Trunk Fund ‐ Fees N 2,000,000 ‐ ‐ ‐ ‐ 2,000,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 15,000 ‐ ‐ ‐ ‐ 15,000
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction‐ Fiber conduit (lift station connectivity)‐ ‐ 10,000 ‐ ‐ 10,000
26‐15 Lake Marion Greenway‐ Fiber conduit (lift station connectivity)‐ 90,000 ‐ ‐ ‐ 90,000
xx‐03 Fiber conduit‐ lift station connectivity ‐ ‐ 50,000 ‐ ‐ 50,000 ‐
U‐1 Sanitary Sewer Trunk Extensions R 75,000 75,000 75,000 75,000 75,000 375,000
Total Sanitary Sewer Trunk Fund 2,090,000$ 165,000$ 135,000$ 75,000$ 75,000$ 2,540,000$
Sanitary Sewer Operating Fund ‐ User Fees
U‐3 Sanitary Sewer Inflow/Infiltration Repairs R 575,000 575,000 575,000 575,000 575,000 2,875,000
U‐2 Sanitary Sewer Lift Station Rehabilitation R 205,000 105,000 235,000 275,000 275,000 1,095,000
U‐10 Fiber Optic Cable Connection N 25,000 25,000 25,000 30,000 30,000 135,000
XX‐01 Sanitary Sewer Rehabilitation (XX‐01 misc street repairs project) R 100,000 100,000 100,000 100,000 100,000 500,000
XX‐02 Sanitary Sewer Rehabilitation (XX‐02 Street Reconstruction project) R 250,000 250,000 250,000 250,000 250,000 1,250,000
XX‐03 Sanitary Sewer Rehabilitation (XX‐03 Collector Roadway Rehab project) R 5,000 15,000 25,000 25,000 15,000 85,000
xx‐10 Sanitary Sewer Rehabilitation (XX‐10 Dakota County pavement preservation) R 10,000 5,000 5,000 ‐ ‐ 20,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 15,000 ‐ ‐ ‐ ‐ 15,000
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 145,000 ‐ ‐ 145,000
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP ‐ ‐ 5,000 ‐ ‐ 5,000
Total Sanitary Sewer Operating Fund 1,185,000$ 1,075,000$ 1,365,000$ 1,255,000$ 1,245,000$ 6,125,000$
Total Sanitary Sewer System 3,275,000$ 1,240,000$ 1,500,000$ 1,330,000$ 1,320,000$ 8,665,000$
Street Light Operating Fund ‐ User Fees
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 67,500 ‐ ‐ ‐ 67,500
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 10,000 ‐ ‐ ‐ ‐ 10,000
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 50,000 ‐ ‐ 50,000
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP ‐ ‐ 10,000 ‐ ‐ 10,000
26‐06 CSAH 50 Roundabout at Hamburg Ave N ‐ 30,000 ‐ ‐ ‐ 30,000
Total Street Light Operating Fund 10,000$ 97,500$ 60,000$ ‐$ ‐$ 167,500$
Stormwater Infrastructure Fund‐ Fees
20‐45 165th St Drainage System Improvements IP 275,000 ‐ ‐ ‐ ‐ 275,000
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 2,232,825 ‐ ‐ ‐ 2,232,825
24‐44 Stormwater Management Improvements at Greenridge Park N 24,000 76,000 ‐ ‐ ‐ 100,000
25‐04 185th St/CSAH60 (Kenwood Tr‐Ipava Ave)IP 1,300,000 ‐ ‐ ‐ ‐ 1,300,000
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 1,035,000 ‐ ‐ 1,035,000
26‐04 CSAH 9 Modernization (210th St‐ CSAH 50)IP ‐ ‐ 250,000 ‐ ‐ 250,000
26‐05 Interstate 35/CSAH 50 Interchange Reconstruction ‐ ‐ 135,000 ‐ ‐ 135,000
XX‐02 Storm Water Management Improvements ‐ Street Reconstruction R 105,000 105,000 105,000 105,000 105,000 525,000
ER‐4 Storm Water Conveyance System Expansion R 100,000 100,000 100,000 100,000 100,000 500,000
Total Stormwater Infrastructure Fund 1,804,000 2,513,825 1,625,000 205,000 205,000 6,352,825
Environmental Resources ‐ Fees
ER‐1 Water Quality BMPs R 75,000 75,000 75,000 75,000 75,000 375,000
ER‐1 Urban Restoration‐ Public System Initiatives R 10,000 10,000 10,000 10,000 10,000 50,000
ER‐1 Water Conservation‐ Public System Improvements R 20,000 20,000 20,000 20,000 20,000 100,000
ER‐2 Lake Management R 75,000 75,000 75,000 75,000 75,000 375,000
ER‐3 Storm Water Basin Rehabilitation R 350,000 350,000 350,000 350,000 350,000 1,750,000
ER‐3 Stormwater Infrastructure Maintenance/Rehabilitation R 190,000 190,000 190,000 190,000 190,000 950,000
ER‐3 FES Maintenance‐(MS4 Pond/Outfall Insp)R 85,000 85,000 85,000 85,000 85,000 425,000
ER‐6 Vegetation Maintenance‐City Outlots/Land R 140,000 140,000 140,000 140,000 140,000 700,000
23‐58 East Lake Rough Fish Barrier N 50,000 ‐ ‐ ‐ ‐ 50,000
Total Environmental Resources Fund 995,000 945,000 945,000 945,000 945,000 4,775,000
Page 40
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Dakota County (Utility/Environmental Resources projects only)
24‐44 Vermillion‐ Stormwater Management Improvements at Greenridge Park N ‐ 200,000 ‐ ‐ ‐ 200,000
ER‐2 Dakota County Lake Management assessment/treatment R 35,000 35,000 35,000 35,000 35,000 175,000
Total Dakota County (Environmental Resources contributions) 35,000 235,000 35,000 35,000 35,000 375,000
General Fund
ER‐5 Forestry R 130,000 130,000 130,000 130,000 130,000 650,000
26‐04 Fiber conduit (siren connection)‐ CSAH 9 Modernization (210th St‐ CSAH 50)‐ ‐ 40,000 ‐ ‐ 40,000
26‐05 Fiber conduit (siren connection)‐ Interstate 35/CSAH 50 Interchange Reconstruction ‐ ‐ 10,000 ‐ ‐ 10,000
Total General Fund 130,000 130,000 180,000 130,000 130,000 700,000
Total Utility/Natural Resources System Projects 8,114,000$ 8,328,325$ 6,009,500$ 5,970,000$ 4,300,000$ 32,721,825$
Dakota County (Park projects only)
P‐5 Eclipse Ave Trail CP25‐01 N 40,000 ‐ ‐ ‐ ‐ 40,000
25‐15 North Creek Greenway Trailhead (Park Dedication project) IP 510,000 510,000
25‐15 North Creek Greenway Trails (Trail improvement project) IP 170,000 170,000 340,000
25‐20 East Community Park Trailhead IP ‐ 400,000 ‐ ‐ ‐ 400,000
Total Dakota County (Park contributions) 720,000 570,000 ‐ ‐ ‐ 1,290,000
Park Improvement Fund ‐ Taxes
P‐1 Park Major Maintenance 217,450 136,250 159,500 169,000 153,000 835,200
P‐6 Park Improvements‐ playground replacements (Various Parks)R 226,000 346,000 236,000 489,000 372,000 1,669,000
P‐6 Park Improvements‐ parking lot improvements (at parks)R 90,000 75,000 210,000 113,000 55,000 543,000
P‐6 Park Improvements‐ other R 85,000 271,000 356,000 104,000 87,000 903,000
26‐15 Lake Marion Greenway‐Ritter Farm parking lot/roadway improvements N ‐ 225,000 ‐ ‐ ‐ 225,000
Total Park Improvement Fund 618,450 1,053,250 961,500 875,000 667,000 4,175,200
Trail Improvement Fund ‐ Taxes
P‐5 Trail improvement R 530,000 830,000 530,000 612,000 610,000 3,112,000
23‐13 Klamath Trail Retaining Wall IP ‐ ‐ 1,500,000 ‐ ‐ 1,500,000
26‐15A Trail Reconstruction CP26‐15A / Ritter to Dodd Blvd ‐ 53,000 ‐ ‐ ‐ 53,000
26‐15B Trail Reconstruction CP26‐15B / Dodd Blvd To 208th St Cul de Sac ‐ 57,000 ‐ ‐ ‐ 57,000
25‐05 Trail Reconstruction CP25‐05 / Highview Ave ‐ ‐ 200,000 ‐ ‐ 200,000
25‐15A Trail Reconstruction CP25‐15A / North Creek Trail, 173rd to East Park 30,000 ‐ ‐ ‐ ‐ 30,000
25‐15B Trail Reconstruction CP25‐15B / North Creek Trail, East Park to 160th ‐ 30,000 ‐ ‐ ‐ 30,000
Total Trail Improvement Fund 560,000 970,000 2,230,000 612,000 610,000 4,982,000
Park Bonds Fund
24‐20 Grand Prairie Park (Avonlea) Note 1 (referendum bonds)IP 2,102,625 ‐ ‐ ‐ ‐ 2,102,625
25‐20 East Community Park Phase II ‐ Note 1 (referendum bonds)IP 350,000 2,025,000 ‐ ‐ ‐ 2,375,000
2,452,625 2,025,000 ‐ ‐ ‐ 4,477,625
Page 41
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Park Dedication Fund ‐ Fees
P‐2 Park Development ‐ Adminstrative Projects R 20,000 35,000 20,000 170,000 20,000 265,000
P‐3 Park Development ‐ Developer Credits R 435,000 435,000 435,000 435,000 435,000 2,175,000
P‐4 Future Park Land Acquisition R ‐ ‐ ‐ 100,000 100,000 200,000
P‐5 Other New Trails IP ‐ ‐ ‐ 100,000 100,000 200,000
P‐7 Pedestrian Crossing Projects IP 55,000 ‐ ‐ ‐ ‐ 55,000
P‐8 Ritter Meadows Park IP ‐ 58,000 770,000 ‐ ‐ 828,000
P‐9 Voyager Park IP 720,000 ‐ ‐ ‐ ‐ 720,000
P‐10 Spyglass Park‐Phase II IP 45,000 420,000 ‐ ‐ ‐ 465,000
P‐11 Keokuk Ave/ 172nd St. Park IP ‐ ‐ ‐ ‐ 65,000 65,000
P‐12 Grand Prairie Skatepark N ‐ ‐ 50,000 600,000 ‐ 650,000
P‐13 Other projects IP/N 145,000 225,000 200,000 325,000 325,000 1,220,000
23‐04 179th St/Future CSAH9 Trail & Trail Lights‐ Note 3 IP 769,945 ‐ ‐ ‐ ‐ 769,945
24‐05 179th St Bridge and Future CSAH 9 IP ‐ 67,313 ‐ ‐ ‐ 67,313
25‐04 185th St (Kenwood Tr‐Ipava Ave)‐ Trail & trail lights‐ Note 3 IP 200,000 ‐ ‐ ‐ ‐ 200,000
25‐05 Holyoke/Highview Avenue Reconstruction IP ‐ ‐ 1,200,000 ‐ ‐ 1,200,000
25‐15 North Creek Greenway Trail/Trailhead IP 90,000 90,000
25‐20 East Community Park Phase II ‐Note 1 (excess costs beyond referendum bonds)IP ‐ 150,000 ‐ ‐ ‐ 150,000
26‐04 Dodd Blvd/CSAH 9 (210th St‐Kenwood Trl/CSAH 50)‐ Trail & trail lights‐ Note 3 IP ‐ ‐ 97,500 ‐ ‐ 97,500
27‐03 Fiber conduit (new) for park connectivity‐ Kenyon Ave N of CR60; 205th St N ‐ ‐ 100,000 ‐ ‐ 100,000
26‐05 Fiber conduit (new) for park connectivity‐ I35 interchange; Klamath to Kenrick N ‐ ‐ 10,000 ‐ ‐ 10,000
26‐15 Lake Marion Greenway‐ Fiber conduit (parks connectivity) N ‐ 90,000 ‐ ‐ ‐ 90,000
26‐15 Lake Marion Greenway‐ Trails N 28,000 2,050,000 ‐ ‐ 60,000 2,138,000
P‐5 Eclipse Ave Trail CP25‐01 N 40,000 ‐ ‐ ‐ ‐ 40,000
28‐04 Dodd Blvd/CSAH 9 Modernization (215th St‐ 210th St.) N ‐ ‐ ‐ 30,000 ‐ 30,000
Total Park Dedication Fund 2,547,945 3,530,313 2,882,500 1,760,000 1,105,000 11,825,758
Total‐ Parks Projects 6,899,020$ 8,148,563$ 6,074,000$ 3,247,000$ 2,382,000$ 26,750,583$
Page 42
Total
CIP #Financing / Project Status* 2025 2026 2027 2028 2029 2025‐2029
Equipment Plan‐ Totals by funding source below
Equipment Fund Interest Earnings 53,566 18,021 9,639 9,498 8,453 99,177
Equipment Fund Balance use (surplus)1,777,225 419,121 7,052 52,237 (316,247) 1,939,388
General Fund 125,472 102,825 98,100 ‐ 89,674 416,071
Tax Levy‐ Equipment 500,000 2,000,000 3,400,000 1,700,000 1,600,000 9,200,000
Liquor Fund contribution 500,000 500,000 500,000 780,000 780,000 3,060,000
Environmental Resources Fund‐ contribution 40,500 40,500 74,256 40,500 40,500 236,256
Communications Fund 33,000 45,000 45,000 40,000 52,000 215,000
Water & Sewer Operating Funds 124,579 366,743 127,705 128,494 389,674 1,137,195
Auction/Sale Proceeds 300,000 300,000 300,000 300,000 300,000 1,500,000
Total Planned Equipment Purchases 3,454,342 3,792,210 4,561,752 3,050,729 2,944,054 17,803,087
‐ ‐ ‐ ‐ ‐ ‐
Facilities Plan‐ Totals by funding source below
Facilities Fund Balance use/(surplus)397,924 355,557 926,642 500,952 242,769 2,423,844
Facilities Fund interest earnings 51,355 43,396 36,285 17,752 7,733 156,521
Tax Levy‐ Facilities 100,000 200,000 250,000 300,000 350,000 1,200,000
General Fund contribution ‐ ‐ ‐ ‐ ‐ ‐
Antenna Rental 482,113 497,247 512,873 531,236 571,356 2,594,825
Liquor Fund 10,000 40,000 ‐ 65,000 ‐ 115,000
Water Operating Fund 1,125,000 488,000 9,875,000 85,000 147,480 11,720,480
Water Trunk Fund/Water Revenue Bonds 3,375,000 375,000 11,500,000 ‐ ‐ 15,250,000
Sewer Operating Fund ‐ ‐ 375,000 55,000 32,480 462,480
Franchise Fees ‐ 4,238,250 4,671,184 3,356,387 ‐ 12,265,821
Bond Proceeds 17,792,608 15,761,750 32,328,816 16,643,613 ‐ 82,526,787
Other/Partnership 7,170,000 ‐ ‐ ‐ ‐ 7,170,000
Total Planned Facility Expenditures 30,504,000$ 21,999,200$ 60,475,800$ 21,554,940$ 1,351,818$ 135,885,758
Technology Plan‐ Totals by funding source below
Technology Fund Balance use/(surplus)145,379 (92,557) (18,746) (29,258) (50,666) (45,848)
Technology Fund interest earnings 4,308 1,400 3,251 3,626 4,211 16,796
Tax Levy‐ Technology Plan 300,000 300,000 500,000 550,000 450,000 2,100,000
Communications Fund contribution 4,260 5,822 9,547 11,078 1,047 31,754
Liquor Fund contribution 67,605 51,981 144,520 83,330 7,817 355,253
Environmental Resources Fund contribution 2,385 3,676 9,810 9,630 854 26,355
Utility (Water/Sewer) Fund contribution 86,128 16,655 40,790 59,185 9,840 212,598
Lakeville Arenas 1,843 1,337 3,402 1,497 1,500 9,579
Total Planned Technology Expenditures 611,908 288,314 692,574 689,088 424,603 2,706,487
‐$ ‐$ ‐$ ‐$ ‐$
TOTAL‐ ALL PROJECTS 66,768,570$ 75,130,476$ 106,173,039$ 48,487,582$ 20,312,194$ 316,871,861
*Status Key
R These are recurring annual projects. The costs may have changed slightly from the prior year CIP due to revised estimates, and a subsequent year added to the CIP.
IP These projects were included in a prior year CIP. The costs and funding sources may have been revised due to more accurate estimates since the prior CIP.
N These projects are new to the CIP this year.
Note 1‐ The majority of this project is anticipated to be funded with bonds. Park projects funded primarily by referendum bonds (where Note 1 is indicated). Park Bond Fund timing shows planned use of bonds, not bond issuance year.
Bond funds will be spent first, and any overage on the project will be paid by the Park Dedication Fund.
Note 2‐ This project was substantially completed during the current year or a prior year, and is included in the 2025‐2029 CIP only to reflect the related future repayment of an advance to Dakota County in one of the years presented.
Note 3‐These new trail and trail lighting costs are planned to be incurred in conjunction with a larger roadway project included in the transportation section of the 2025‐2029 CIP.
Page 43
CITY OF LAKEVILLE
STREET RECONSTRUCTION PLAN
Project # Project description: 2025 2026 2027 2028 2029 Total
XX‐02 Street Reconstruction 4,145,000 3,580,000 3,685,000 4,665,000 3,900,000 19,975,000
XX‐03 Collector Rehabilitation 683,245 490,707 3,100,000 2,743,425 889,719 7,907,096
‐ ‐ ‐ ‐ ‐ ‐
4,828,245$ 4,070,707$ 6,785,000$ 7,408,425$ 4,789,719$ 27,882,096$
CITY OF LAKEVILLE Council Work Session
2025 - 2034 FACILITY PLAN 8/26/2024
2024 2023 CF +2025 - 2034
Adopted 2024 Est'd 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Totals
Use of Funds:
Art Center- Performing Arts 14,500$ 64,500$ 210,000$ 90,000$ 135,000$ -$ 2,368$ 125,000$ 250,000$ -$ -$ -$ 812,368$
Art Center- Fine Arts (ALC building) 40,000 40,000 20,000 - 570,000 - - - - - - - 590,000
Heritage Center 29,000 29,000 748,000 - - 108,000 96,160 40,000 75,000 40,000 - - 1,107,160
Central Maintenance Facility 473,850 325,842 458,000 356,000 17,660,000 300,000 797,704 - 40,000 21,000 - - 19,632,704
City Hall 539,110 689,110 105,000 100,000 - 135,000 17,051 70,000 30,000 125,000 - - 582,051
Fire Station #1 20,000 - 275,000 - - 20,791,940 - - - - - - 21,066,940
Fire Station #2 32,000 12,000 - 20,268,200 - - - - - - - - 20,268,200
Fire Station #3 28,000 8,000 - - 20,330,800 - - - - - - - 20,330,800
Fire Station #4 20,000 100,000 48,000 7,000 30,000 - 124,700 - - 120,000 - - 329,700
Police Station 80,000 67,500 80,000 275,000 - 15,000 133,875 25,000 600,000 165,000 - - 1,293,875
Heritage Liquor Store 108,300 108,300 - - - 65,000 - 8,000 25,000 65,000 - - 163,000
Galaxie Liquor Store 93,500 222,220 - - - - - 331,570 65,000 50,000 - - 446,570
Kenrick Liquor Store 62,000 62,000 - 40,000 - - - 31,629 - 120,000 26,000 - 217,629
Keokuk Liquor Store 31,000 31,000 60,000 - - - - - 10,000 45,000 65,000 - 180,000
Public Safety Training Facility 14,000,000 - 24,000,000 - - - - - - - - - 24,000,000
Water Treatment Facility 452,500 444,500 4,500,000 863,000 21,750,000 140,000 179,960 65,000 - 15,000 - - 27,512,960
Total Use of Funds 16,023,760$ 2,203,972$ 30,504,000$ 21,999,200$ 60,475,800$ 21,554,940$ 1,351,818$ 696,199$ 1,095,000$ 766,000$ 91,000$ -$ 138,533,957$
Source of Funds:
Interest Earnings (2%) 13,257$ 13,257$ 51,355$ 43,396$ 36,285$ 17,752$ 7,733$ 2,878$ 17,542$ 10,171$ 13,518$ 26,736$ 227,366$
Annual Levy (Building Fund) - - 100,000 200,000 250,000 300,000 350,000 400,000 1,600,000
General Fund Contribution - - - - - - - - - - - - -
Antenna Rental 502,341 502,341 482,113 497,247 512,873 531,236 571,356 590,347 608,875 628,198 647,373 650,175 5,719,793
Liquor Fund 1 244,800 373,520 10,000 40,000 - 65,000 - 371,199 100,000 280,000 91,000 - 957,199
Water & Sewer Operating Funds 452,500 444,500 1,125,000 488,000 10,250,000 140,000 179,960 65,000 - 15,000 - - 12,262,960
Water & Sewer Trunk Funds / Bonds 1 - - 3,375,000 375,000 11,500,000 - - - - - - - 15,250,000
Franchise Fees (reduce Fire station bonds)- - - 4,238,250 4,671,184 3,356,387 - - - - - - 12,265,821
Energy Rebates 50,000 50,000 - - - - - - - - - - -
Other/Partnership 14,000,000 800,000 7,170,000 - - - - - - - - - 7,170,000
Bond Proceeds - Ice Arena 1 - - - - - - - - - - - - -
Bond Proceeds - CMF/Fire/First - - 17,792,608 15,761,750 32,328,816 16,643,613 - - - - - - 82,526,787
Other Ice Arena - - - - - - - - - - - - -
Total Source of Funds 15,262,898$ 2,183,618$ 30,106,076$ 21,643,643$ 59,549,158$ 21,053,988$ 1,109,049$ 1,429,424$ 726,417$ 933,369$ 751,891$ 676,911$ 137,979,926$
Change in Fund Balance (760,862)$ (20,354)$ (397,924)$ (355,557)$ (926,642)$ (500,952)$ (242,769)$ 733,225$ (368,583)$ 167,369$ 660,891$ 676,911$ (554,031)$
Beginning Fund Balance 998,001$ 2,588,094$ 2,567,740$ 2,169,816$ 1,814,259$ 887,617$ 386,665$ 143,896$ 877,121$ 508,538$ 675,907$ 1,336,798$
Ending Fund Balance 237,139$ 2,567,740$ 2,169,816$ 1,814,259$ 887,617$ 386,665$ 143,896$ 877,121$ 508,538$ 675,907$ 1,336,798$ 2,013,709$
1. The Liquor Fund, Water/Sewer Funds and the Ice Arena sources/uses NET to zero.
2. The fund balance shown is for the Building Fund (Which does not include Liquor, Water/Sewer and Ice Arena)
2024-2033 CIP Adopted 15,509,650 15,509,650 3,462,900 1,483,500 33,057,800 760,800 1,679,758 732,199 1,222,000 1,162,000 91,000 - 59,161,607
Variance 514,110 (13,305,678) 27,041,100 20,515,700 27,418,000 20,794,140 (327,940) (36,000) (127,000) (396,000) - - 79,372,350
CITY OF LAKEVILLE Council Work session
2025 - 2034 EQUIPMENT PLAN 8/26/2024
2024 2023 CF+2025 - 2034
Funding ADOPTED 2024 Est'd 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Totals
Use of Funds:
Facilities GEN FUND -$ -$ 59,977$ 33,401$ -$ -$ -$ -$ -$ -$ -$ -$ 93,378$
Arts Center GEN FUND 36,000 - - - - - - - - - - - -
City Clerk EQ FUND 20,003 20,003 - 318,000 - - - 23,604 - - - - 341,604
Comm. Develop Code GEN FUND 30,900 - - - - - - - - - - - -
Inspections GEN FUND 34,245 34,245 - - 43,600 - - 47,200 48,400 49,600 50,800 52,000 291,600
Police EQ FUND 946,035 820,983 572,934 663,800 969,023 724,890 1,264,623 822,659 970,720 985,189 604,558 601,073 8,179,469
PD Equipment delay EQ FUND (188,238) - (20,208) 95,172 557,560 632,524
Fire EQ FUND 775,563 55,463 943,963 2,390,300 34,880 157,920 172,500 5,900 536,437 - 82,550 136,500 4,460,950
Fire Equipment delay EQ FUND (720,100) - (750,000) (1,957,000) 375,000 2,332,000 -
Engineering GEN FUND - - - - - - 57,500 59,000 - - - - 116,500
Construction Services GEN FUND - - 65,495 69,425 54,500 - 32,174 59,000 - - - - 280,593
Streets EQ FUND 1,137,139 1,183,081 1,364,179 1,098,925 1,578,395 1,282,726 635,618 961,260 1,247,361 1,362,155 852,324 795,939 11,178,883
Forestry EQ FUND - 54,044 57,287 - - - - - 33,644 - - 144,974
Parks EQ FUND 420,240 496,879 593,647 611,157 742,333 716,699 339,965 249,892 394,081 299,126 746,870 488,647 5,182,417
Env. Resources ENV RES - - - - 33,756 - - - - - 36,596 - 70,353
Communications COMM 41,500 41,500 33,000 45,000 45,000 40,000 52,000 80,400 45,000 25,000 40,000 45,000 450,400
Utilities UTILITY 120,433 120,433 124,579 366,743 127,705 128,494 389,674 332,537 668,751 407,629 1,397 - 2,547,509
Liquor LIQUOR - - - - - - - - 30,250 25,142 40,640 - 96,032
Vehicle contingency (PD+Parks) EQ FUND - - 412,732 - - - - - - - - - 412,732
Total Use of Funds 2,653,720 2,772,587 3,454,342 3,792,209 4,561,752 3,050,729 2,944,053 4,973,452 3,941,000 3,187,485 2,455,736 2,119,159 34,479,918
Source of Funds:
Interest Earnings (2%) 103,172 103,172 53,566 12,021 6,519 9,316 8,267 14,589 16,188 15,509 16,288 12,649 164,912
Annual Levy - - 200,000 2,000,000 3,400,000 1,700,000 1,600,000 1,000,000 2,000,000 1,600,000 1,000,000 1,000,000 15,500,000
Transfers in:
General Fund Contribution - - - - - - - - - - - - -
Liquor Fund Contribution 500,000 500,000 500,000 650,000 650,000 780,000 780,000 780,000 780,000 780,000 780,000 780,000 7,260,000
Env Res Fund Contribution 40,500 40,500 40,500 40,500 40,500 40,500 40,500 48,700 48,700 48,700 48,700 48,700 446,000
Utility Fund Contribution - - - - - - - - - - -
Coded directly to another fund:
Funding outside Equipment Fund
General Fund 121,148 34,245 125,472 102,825 98,100 - 89,674 165,200 48,400 49,600 50,800 52,000 782,071
Communications Fund 41,500 41,500 33,000 45,000 45,000 40,000 52,000 80,400 45,000 25,000 40,000 45,000 450,400
Environmental Res Fund - - - - 33,756 - - - - - 36,596 - 70,353
Water & Sewer Funds 120,433 120,433 124,579 366,743 127,705 128,494 389,674 332,537 668,751 407,629 1,397 - 2,547,509
Lakeville Arenas - - - - - - - - - - - - -
Other financing sources
Intergovernmental Grants - - - - - - - - - -
Auction/Sale Proceeds 448,000 324,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 300,000 3,000,000
Donations - - - - - - - - - - - - -
Equipment Certificates - - - - - - 2,332,000 - - - - 2,332,000
Total Source of Funds 1,374,753 1,163,850 1,377,116 3,517,089 4,701,581 2,998,310 3,260,115 5,053,426 3,907,039 3,226,438 2,273,781 2,238,349 32,553,245$
Change in Fund Balance (1,278,967) (1,608,737) (2,077,226) (275,119) 139,828 (52,419) 316,061 79,974 (33,961) 38,953 (181,955) 119,190 (1,926,674)$
Beginning Fund Balance 2 5,158,608 4,287,037 $2,678,300 601,074 325,955 465,783 413,364 729,425 809,399 775,438 814,391 632,436
Ending Fund Balance 2 $3,879,641 $2,678,300 $601,074 $325,955 $465,783 $413,364 $729,425 $809,399 $775,438 $814,391 $632,436 $751,626
0
1. "Funding outside the Equipment Fund" Individual fund's sources/uses NET to zero.
2. The fund balance shown is for the Equipment Fund (Which does not include any funding from the other funds listed under "Funding outside Equipment Fund)
3. Fire engines are estimated to be 24 months out from delievery; estimating 1/2 cost in 12 months from date of order and balance at the end of 24 months; ladder truck is estimated to be 27 months (i.e. order in 2024, 1/2 payment in 2025 remainder in 2
2024-2033 CIP Adopted 3,592,958 4,780,024 3,533,332 3,310,006 2,819,026 3,063,335 3,827,972 3,291,268 3,421,306 2,386,532 - 34,025,759
Variance (820,371) (1,325,682) 258,877 1,251,746 231,703 (119,282) 1,145,480 649,732 (233,821) 69,204 2,119,159 454,159
CITY OF LAKEVILLE Council Work session
2025 - 2034 TECHNOLOGY PLAN 8/26/2024
2024 2024 2025 - 2034
ADOPTED Estimate 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 Totals
Use of Funds:
Administration -$ -$ 8,141$ 7,454$ 10,046$ 2,280$ -$ 3,467$ 2,492$ 5,312$ 2,643$ -$ 41,836$
Arts Center - - 1,298 1,493 - 6,144 2,349 1,505 1,730 - 7,122 2,723 24,364
Building Inspection - - 7,280 4,657 18,845 - - 8,440 5,399 21,847 - - 66,468
Comm/Econ Development - 8,753 1,660 3,254 - - 10,147 1,924 3,773 1,362 351 31,222
Engineering 7,300 6,899 2,448 9,908 3,254 9,019 10,401 2,838 10,844 4,433 10,456 3,290 66,892
Facilities Maintenance 2,153 7,003 537 1,660 - - 1,866 623 1,924 - - 2,163 8,773
Finance - - 8,753 6,674 3,446 4,923 - 17,936 6,132 3,995 6,388 - 58,246
Fire 8,786 9,432 24,043 13,956 8,155 13,694 1,153 27,873 5,357 31,141 4,338 1,336 131,047
Forestry 2,152 1,404 1,075 3,319 570 1,174 - - 5,131 - 681 1,402 13,353
Heritage Center - - 2,747 4,167 - 4,945 - 3,185 4,831 - 5,733 - 25,609
Human Resources - 10,271 652 2,053 - 7,563 11,907 - 1,601 - 826 34,874
Information Technology - 2,112 2,142 14,572 - - 2,137 2,483 16,892 - 1,052 41,390
Construction Services 9,659 5,497 5,866 1,660 - - 3,443 6,177 1,924 - - 5,315 24,384
Park & Rec Administration - - 1,449 - 7,384 2,534 7,563 1,680 - 8,560 5,661 - 34,831
Parks Maintenance 515 - 3,224 6,305 1,627 7,109 2,419 1,869 5,385 3,869 2,796 5,609 40,211
Police 236,885 82,579 330,953 18,914 137,119 41,171 317,682 3,817 171,606 4,788 41,150 139,973 1,207,172
Streets Maintenance 7,869 4,817 8,576 2,675 5,451 3,523 8,684 9,319 3,101 5,659 681 12,872 60,539
Arenas - - 1,843 1,337 3,402 1,497 1,500 2,137 1,550 3,944 1,736 1,739 20,686
Communications - - 3,687 2,675 2,589 - - 4,274 3,101 3,001 - - 19,326
Liquor - - 63,319 28,475 92,550 587 - 49,523 7,129 81,295 1,361 701 324,940
Environmental Resources 1,448 - 1,917 1,107 4,130 587 - 1,599 642 6,109 - 701 16,792
Utilities 3,183 1,130 83,465 2,046 8,491 7,760 4,981 5,386 1,730 10,504 5,592 5,774 135,730
ERP** 275,000 275,000 - - - - - - - - - - -
Network Infrastructure 150,849 150,000 25,000 160,076 360,171 582,140 55,000 246,727 86,837 314,191 666,099 55,000 2,551,240
Miscellaneous - 33,333 5,150 5,305 5,464 - - - - - - - 15,918
Total Use of Funds 705,799$ 577,094$ 611,908$ 288,314$ 692,574$ 689,088$ 424,603$ 422,565$ 331,252$ 530,914$ 763,800$ 240,828$ 4,995,846$
Source of Funds:
Interest Earnings (2%) 10,058$ 10,058$ 4,308$ 1,400$ 3,251$ 3,626$ 4,211$ 5,225$ 7,444$ 9,711$ 11,050$ 7,699$ 57,925$
Annual Levy - - 300,000 300,000 500,000 550,000 450,000 400,000 400,000 400,000 400,000 400,000 4,100,000
Transfers in:
General Fund 215,000 215,000 - - - - - - - - - -
Communications Fund 7,300 7,300 4,260 5,822 9,547 11,078 1,047 8,969 4,753 8,980 12,675 1,047 68,178
Liquor Fund 59,500 59,500 67,605 51,981 144,520 83,330 7,817 84,592 19,472 125,952 96,038 8,519 689,826
Environmental Resources 4,600 4,600 2,385 3,676 9,810 9,630 854 5,432 1,991 10,990 10,347 1,555 56,670
Utility Billing (share of ERP)59,537 59,537 - - - - - - - - - - -
Utility (Water/Sewer) Fund 28,400 28,400 86,128 16,655 40,790 59,185 9,840 27,181 9,401 38,259 64,434 10,633 362,507
Coded directly to another fund:
Lakeville Arenas - - 1,843 1,337 3,402 1,497 1,500 2,137 1,550 3,944 1,736 1,739 20,686
Other financing sources
- - - - - - - - - - - - -
Total Source of Funds 384,395$ 384,395$ 466,530$ 380,871$ 711,320$ 718,346$ 475,269$ 533,536$ 444,612$ 597,836$ 596,280$ 431,193$ 5,355,792$
Change in Fund Balance (321,404)$ (192,699)$ (145,378)$ 92,557$ 18,746$ 29,258$ 50,667$ 110,971$ 113,359$ 66,922$ (167,520)$ 190,365$ 359,947$
Beginning Fund Balance 502,905$ 408,084$ 215,385$ 70,007$ 162,564$ 181,310$ 210,568$ 261,235$ 372,205$ 485,565$ 552,487$ 384,967$
Ending Fund Balance 181,501$ 215,385$ 70,007$ 162,564$ 181,310$ 210,568$ 261,235$ 372,205$ 485,565$ 552,487$ 384,967$ 575,332$
2024-2033 CIP 705,798 369,338 160,121 547,476 635,924 388,363 333,234 316,024 515,843 692,888 n/a 4,665,009
Change (128,704) 242,570 128,193 145,098 53,164 36,240 89,331 15,228 15,071 70,912 240,828 330,837
Ca
p
i
t
a
l
Im
p
r
o
v
e
m
e
n
t
Pl
a
n
&
O
p
e
r
a
t
i
n
g
B
u
d
g
e
t
Infrastructure
Specific Plans
Water System
Plan
Adopted 2019
Transportation
Plan
Adopted 2019
Next update 2028
Sanitary Sewer
Plan
Adopted 2019
Next update 2028
Water and
Natural
Resources
Management
Plan
Adopted 2019
Next update 2028
Parks, Trails and
Open Space Plan
Last update 2015
Next update 2025
Citywide
Planning
20
4
0
C
o
m
p
r
e
h
e
n
s
i
v
e
Pl
a
n
/
L
a
n
d
U
s
e
P
l
a
n
Ad
o
p
t
e
d
2
0
2
0
En
v
i
s
i
o
n
L
a
k
e
v
i
l
l
e
2
0
4
0
La
s
t
U
p
d
a
t
e
d
2
0
2
3
Studies & Site
Specific
Plans/REPORTS
(2024)
(2024)
Water Rates & Fees Study
Last U date 2017
Water Treatment Facility
Expansion Plan
Last U date 2022
Sewer Rates & Fees Study
Last U date 2017
CMF Expansion Study
Last Update ~2015
Dakota County East-West
Corridor Preservation Study
(Phase 1: 2003 / Phase 2: 2006)
NPDES MS4 Permit
Implementation
Last U date 2023
Park Dedication
Fee Study
Last u date 2012
Various Park Master Plans
(As needed
ADA Transition Plan
Last u date 2019
Downtown Development
Guide
U dated 2018/ Next u date 5-10 rs
Indoor Athletic Facility Study
(2017
2025 Projects
Pavement Maintenance
Local Street
Rehabilitation
Arterial/Collector
Roadway Rehabilitation
179th St (Future CSAH 9)
Bridge
185th St (CSAH 60)
Expansion
(Kenwood Tr - Ipava Ave)
Stormwater
management Initiatives
and Water
Conservation
Lake Management
Stormwater
Infrastructure
Maintenance
Upland/Woodland
Vegetation Management
Lift Station #26
construction
North Creek Greenway
Phase I Improvements
Grand Prairie Park
Various other park
projects
NOTES: not all
2025 CIP
projects are
listed here (only
highlights)
City and Dakota
County
Partnership
Projects Subject
to Adopted Dakota
County 2040
Transportation
Plan Cost Share
Policies. (Revised
in 2020)
Fire Resource/Space Needs
Study
Update 2020
School Road Safety Task
Force (Last Update~2014)
Dakota County Principal
Arterial Stud (2018
Pedestrian Crossing Study
(2024)
Interstate 35 Corridor Study
(Lakeville – Burnsville)
(2024)
Strategic Plan for Economic
Development
Updated 2019/ Next update 2024
Strategic GIS Plan
U dated 2023
Trail Condition Review (OCI)
(2022
Dakota County Pedestrian
Crossing Safety Assessment
(2022
#I
!H
"J
#I
$K
!H
Kingsley
Lake
Lee
Lake
Orchard Lake
Ea
s
t
La
k
e
Lake Marion
5
50
60
9
31
23
46
70
35
162ND ST W
KE
N
W
O
O
D
T
R
L
160TH ST W
185TH ST W
210TH ST W
DO
D
D
B
L
V
D
CEDAR
AVE
185TH ST W
215TH ST W
179TH ST W
KENW
O
O
D
T
R
L
DO
D
D
B
L
V
D
179TH ST W
JUNI
P
E
R
W
A
Y
PI
L
O
T
K
N
O
B
R
D
DODDBLVD
185TH ST W
KENRICK
AVE
202ND ST W
200TH ST W
29-02
29-03
29-03
29-02 29-
0
2
28-02
28-02
28-02 28-03
28-03
28
-
0
2
28-03
28
-
0
2
27
-
0
3
27-02
27-02
27-02
27-03
23-13
27-02
27-03
25
-
0
5
26-02
26-02
26-02
24-05
26
-
0
3
25-03
25-02
25-02
25-0
2
25-03
20-4
5
27
-
X
X
27
-
X
X
27-10
25
-
1
0
25-10
28
-
0
4
26
-
0
4
25-04
27-10
26-15A
26-15A
25-15B
26
-
1
0
25-15A
26-07
26-05
28-XX
25-15B
XX-XX
26-06
24-44
U-8
XX-XX
2025 - 2029
Capital Improvement Projects
0 1 20.5
Miles
²
2025
2026
2027
2028
2029
P:
\
P
r
o
j
e
c
t
s
\
C
o
n
s
t
r
u
c
t
i
o
n
S
e
r
v
i
c
e
s
\
C
I
P
M
a
p
s
\
C
I
P
M
a
p
s
.
a
p
r
x
Parks & Recreation"J
Transportation#I
Utility!H
Environmental&J
Local Street Reconstruction
Dakota County Pavement Preservation
Trail Construction/Rehabilitation
Collector Roadway Rehabilitation
Roadway Studies
County Roadway Expansion/Modernization5