HomeMy WebLinkAbout25-107 Authorizing Issuance of a Notice of Default and Intent to Terminate Contract for Cuase for the City Wide Trail Gap Improvements Project (Phase II) CITY OF LAKEVILLE
RESOLUTION NO.25-107
Resolution Authorizing Issuance of a Notice of Default and Intent to Terminate Contract for
Cause for the City Wide Trail Gap Improvements Project(Phase II)
WHEREAS, the City of Lakeville awarded a construction contract on Monday, January 6, 2025,
for City Wide Trail Gap Improvements Project (Phase II),City Project 23-06; and
WHEREAS,the lowest responsible bid was from UrbanEdge Solutions &Supply LLC;and
WHEREAS, UrbanEdge Solutions & Supply LLC has subsequently defaulted on the awarded
contract and has justified termination for cause.
NOW, THEREFORE, BE IT RESOLVED, that the City Council of the City of Lakeville,
Minnesota authorizes the City Administrator, or his designee to issue a notice of default and to
terminate the contract with UrbanEdge Solutions & Supply LLC, due to persistent failure to
perform the Work in accordance with the Contract Documents,failure to perform or otherwise to
comply with material terms of the Contract Documents,disregard of laws and regulations of public
bodies, and repeated disregard of the authority of the City of Lakeville.
ADOPTED by the Lakeville City Council this 4'''day of August 2025.
/�G�
e M. Hellier,Mayor
Ann Orlofs y, City Clerk
Date Change Order Request Received Amount Description
4/21/2025 Y Additional Silt Fence,curtain,bio log-SEH plan lacking NPDES compliance(Maria and Patrick)
4/29/2025 DEA Utitity Relocation Delay Claim
4/30/2025 Standby Time for Subgrade on Cedar
5/1/2025 ATLAS Foundations-Crane Mobilization and Traffic Control
5/1/2025 :SEH Staking Error-Wall A
5/1/2025 ATLAS Foundations-Material Increase(Tariffs)
5/1/2025 � = Potholing w/SEH on Highview(Equipment Hours 9:30am-12:OOpm)
5/2/2025 " Erosion Control Blanket-NPDES(Maria�,SEH plan lacking in NPDES compliance
5/28/2025 Highview Soil Corrections
6/24/2025 Highview Segment Removal
7/9/2025 Atlas Sheet Pile Removal
Denied Change Orders
Approved Change Orders • �p��`
Total Change Orders Requested $529,112
Contractor Bid For Project $992,746
Contractor Bid+Change Order Requests $1,521,858
Next Lowest Bid for Project when Awarded $1,359,609