HomeMy WebLinkAboutItem 05a - 2027-2031 CIP1
City of Lakeville
Memorandum
To: Planning Commission
From: Justin Miller, City Administrator
Julie Stahl, Finance Director
Paul Oehme, Public Works Director
Zach Johnson, City Engineer
Joe Masiarchin, Parks & Recreation Director
Date: September 17, 2026
Subject: 2027-2031 Capital Improvement Plan (CIP)
Attached is a draft of the proposed 2027-2031 Capital Improvement Plan (CIP). The CIP is comprised of
the following components: Transportation, Utility, Environmental Resources, Parks and Recreation,
Facilities, Equipment and Technology. Included with this plan are the project descriptions, locations,
revenues and expenditures.
The 2027-2031 CIP includes public improvement projects due in large part to increased growth,
economic conditions, and the resulting increase in revenue from City permits and connection charges
to finance infrastructure improvements. The following are the more significant improvement projects
included in the 2027-2031 CIP:
Transportation
CP XX-01: Annual Pavement Management/Maintenance (2027-2031 construction)
CP XX-02: Annual Street Rehabilitation/Reconstruction (2027-2031 construction)
CP XX-03: Annual Collector Roadway Rehabilitation/Reconstruction (2027-2031 construction)
CP 22-16: Freight Rail Car Storage Facility (2027 construction)
CP 24-05: 179th St/Future CSAH 9 Bridge (2030 construction)
CP 25-04: 185th St/CSAH 60 Expansion (Kenwood Tr - Ipava Ave) (2025 construction; 2026-2028
payment to Dakota County)
CP 25-05: Holyoke Ave/Highview Ave Reconstruction (2031-2032 construction)
CP 26-04: Dodd Blvd/CSAH 9 Modernization (210th St – 202nd St/Kenwood Tr) (2027 construction)
CP 26-05: Interstate 35/CSAH 50 Interchange (2029 construction)
CP 26-15: Lake Marion Greenway (2026 construction; additional XX-15 segments in 2027-2030)
CP 27-11: CSAH 9 and Glacier Way Trail Traffic Signal (2027 construction)
CP 28-04: Dodd Blvd/CSAH 9 Modernization (215th St - 210th St) (2028 construction)
CP 28-05: CSAH 60 and Orchard Trail Traffic Signal (2028 construction)
CP 28-16: Kenrick Ave Extension (181st St-176th St) (2028 construction)
CP 29-04: CSAH 9 Improvements at 194th St and 190th St (2029 construction)
CP 31-07: CSAH 50 Expansion (CSAH 23 – Flagstaff Ave) (2030 construction)
2
Utilities
Watermain maintenance/replacement and sanitary sewer rehabilitation - in conjunction with
annual street rehabilitation/reconstruction projects (2027-2031 construction)
Fairfield Water Tower Repainting (2030 construction)
Wells 24 and 25 (2028 construction)
Parks
East Community Park (2026-2027 construction)
Voyageur Park (2027 construction)
Bunker Hill Athletic Decks (2028 construction)
Ritter Meadows Park (2028 construction)
Klamath Trail Retaining Wall (2028 construction)
Keokuk Ave/172nd St Park (2030 construction)
Skatepark (2030 construction)
Southwest corner of 210th St & I-35 Park (2031 construction)
Various trail and trail lighting projects (2027-2031 construction)
Facilities
Central Maintenance Facility (CMF) Expansion (2027 construction)
Water Treatment Plant (WTP) Satellite Plant (2027 construction)
Fire Station #2 Construction (2026-2027 construction)
Fire Station #3 Rebuild (2027 construction)
Fire Station #1 Renovations (2028 construction)
Police Station Workout Room Expansion (2029 construction)
The CIP was presented to the City Council at their September 8 meeting. The final 2027-2031 CIP will be
considered for approval at the October 5, 2026 City Council meeting.
Minnesota State Statute 462.356 provides that capital improvements are reviewed by the Planning
Commission for consistency with the Comprehensive Plan and the Planning Commission report their
findings in writing to the City Council. The Planning Commission is not responsible for reviewing the
fiscal implications of the CIP. Staff reviewed the CIP and finds it consistent with the Comprehensive
Plan. Therefore, staff recommends a motion finding that the capital improvements identified in the
2027-2031 CIP are in compliance with the Comprehensive Plan.
CAPITAL
IMPROVEMENT
PLAN
2027-2031
CITY OF LAKEVILLE
DRA
F
T
Capital Improvement Plan 2027-2031
Lakeville, MN Administrative Summary
Table of Contents
Administrative Summary
• Introduction- Page 3
• Categories- Page 3
• Debt Analysis & Tax Impact- Page 4-5
• Additional Considerations- Page 5
Cost Type Summary- Page 6
Funding Source Summary- Page 7
Projects & Funding Sources by Cost Type- Page 9
Project Details- Page 14-121
Street Reconstruction Plan- Page 122
CIP Planning Flowchart- Page 123
CIP Map- Page 124
Produced Using Plan-It CIP Software Page 2
Introduction
The Capital Improvement Plan provides a long-range framework to meet the infrastructure needs and development objectives of our community. It provides policy
makers and the community with a strategic (documented) approach to implementation and administration of improvement projects and equipment acquisitions.
The Plan identifies the allocation of the City’s financial resources and maximizes the use of non-tax revenues to finance the improvements. Municipal State Aid
Street Funds (MSA), connection charges, special assessments and other revenue sources are vital elements to financing City improvements. The use of these
revenue sources reduces the reliance on property taxes to finance these improvements.
The City intends to pursue the financing strategy as presented, but future events may require changes in both costs and revenues. The Capital Improvement Plan
represents a significant financial, engineering and development undertaking for the City in the years ahead. The Capital Improvement Plan is consistent with the
City’s Comprehensive Plan and takes into consideration projects identified in the Dakota County Capital Improvement Plan.
Categories
Transportation includes all roads, streets, street lights, bridges and traffic signals within the City with the exception of Interstate I-35 and routine maintenance of
County roads. Major funding sources include Municipal State Aid Street funds, special assessments and property taxes.
Utility infrastructure includes the construction and major maintenance of all water systems such as wells, towers and the water treatment facility. Utilities also
include sanitary sewer and storm sewer systems. The primary source of financing for developing new systems is connection charges collected when property
develops or with the issuance of a building permit. Maintenance projects are financed by user fees. The Water Treatment Plant expansion in 2027 is planned to
include a combination of bond funding (principal and interest payments to be repaid with user fees), and fund balance/net assets in the Water Trunk Fund and
Water Operating Fund, respectively.
Environmental Resources system includes lakes, wetlands, streams, prairies and woodlands. Maintenance project are financed with user fees.
Parks system includes regional, community and neighborhood parks as well as trails and recreation facilities such as the Arts Center and Heritage Center. Major
resources include park dedication fees collected when property develops, and grants. Maintenance projects are financed with property taxes and other revenue
sources. A parks bond referendum was approved in the fall of 2021 and related projects have been/are being constructed between 2022-2027.
Facilities include the city hall, police station, fire stations, central maintenance facility, arts center, FiRST Center, and other municipal buildings. Primary revenue
sources include, but are not limited to, property taxes, General Fund, Water Operating Fund, and planned bond proceeds in several years (for Fire station
renovations, CMF expansion, and Water Treatment plant expansion).
Equipment includes all major equipment acquisitions and replacement. Primary revenue sources include, but are not limited to, Liquor Fund contributions,
General Fund, Utility Funds, sale of assets and property taxes.
Technology includes all major technology-related equipment acquisitions and replacement. Primary revenue sources include, but are not limited to, Liquor Fund,
General Fund, Utility Funds, and property taxes.
Produced Using Plan-It CIP Software Page 3
Debt Analysis and Tax Impact
In reviewing the 2027-2031 Capital Improvement Plan, the City Council should consider the level of debt, the commitment of funds to repay that debt, as well as
the annual tax impact associated with the scheduled projects.
As of 12/31/2026, the City of Lakeville will have $184,455,000 in debt. The following chart reflects the type of debt that comprises the $184.5M.
EXISTING CITY DEBT AS OF 12/31/2026
BOND TYPE AMOUNT PURPOSE
GO CAPITAL
IMPROVEMENT $91,120,000 Various capital projects (Central Maintenance Facility, Police Station, First Center, Fire
Station)
GO STREET
RECONSTRUCTION $16,935,000 Street reconstruction projects
GO IMPROVEMENT $44,885,000 Various capital improvement projects; includes special assessment-supported debt
GO STATE AID STREET
REVENUE $2,815,000 Various street improvement projects
GO WATER REVENUE $8,905,000 Holyoke Ave water tower, water treatment facility improvements, wells 21 and 22,
215th St utility improvements
HRA LEASE REVENUE-
LIQUOR $280,000 Construction of liquor store (2007)
TAX ABATEMENT $14,165,000 Arenas projects 2021-2022, Keokuk liquor store construction
WATER REVENUE $5,350,000 Watermain replacement (in conjunction with street reconstruction projects)
TOTAL REMAINING
PRINCIPAL $184,455,000
The 2027-2031 CIP includes projects that will need to be funded by bond proceeds. Bonds are issued for the project costs that the City is funding through tax levies
as well as the costs that are specially assessed to property owners. The City anticipates $138,797,000 in bonding for projects in the CIP plan for 2027-2031,
including the following-
• $33,797,000 for street reconstruction/collector road rehabilitation projects in 2027-2031
• $26,000,000 for the CMF facility expansion in 2027
• $35,000,000 for the bonded portion of a Water Treatment Facility expansion project in 2027
• $20,000,000 in 2027 and $24,000,000 in 2028 for fire station remodel projects.
The anticipated bonding amount for 2027 is $88,105,260, which assumes no bonding is needed in 2027 for planned equipment expenditures. The current CIP
projections assume no bond funding will be needed for the Municipal State Aid (MSA) projects, which will be dependent on project costs and timing.
Major projects scheduled for 2027, which are planned to be funded with bonds are listed below (note that these amounts also include any bonds which will be
repaid by special assessments):
PLANNED BOND FUNDING IN 2027
PROJECT ESTIMATED BOND AMOUNT
2027 street projects $7,105,260
Central Maintenance Facility expansion 26,000,000
Water treatment satellite plant 35,000,000
Fire station #3 improvements 20,000,000
Total $88,105,260
Major projects that involve a property tax levy component in 2027 are listed below:
TAX LEVY FUNDING IN CAPITAL PROJECT FUNDS IN 2027
FUND TAX LEVY IN 2027
Building Fund $1,300,000
Equipment Fund 400,000
Park & Trail Improvement Fund 1,800,000
Pavement Management Fund 2,700,000
Technology Fund 300,000
Total $6,500,000
Project costs in the CIP may be higher than the tax levy amounts above, due to additional funding sources beyond tax levy, such as fund balance, or other sources
(as reflected in the CIP). There are sometimes transfers from General Fund balance reserve into Capital Project Funds to reduce the impact on the tax levy, and
such transfers are not reflected in the table above.
The impact of the 2027-2031 CIP and other anticipated bond payment adjustments on the debt service property tax levy are reflected in the following table:
Produced Using Plan-It CIP Software Page 4
PROJECTED CHANGE IN DEBT LEVY
2027 2028 2029 2030 2031 TOTAL 2027-2031
ANNUAL DEBT LEVY $12,297,737 12,897,185 11,984,528 10,397,856 8,547,666 $56,124,973
CHANGE FROM:
EXISTING DEBT
- 599,448 (912,657) (1,586,672) (1,850,190) (3,750,071)
NEW CIP- STREET PROJECTS - 899,000 1,891,000 2,753,000 3,416,000 8,959,000
NEW CIP-FACILITIES - 2,175,663 2,175,663 2,175,663 2,175,663 8,702,650
TOTAL CHANGE - 3,674,111 3,154,006 3,341,990 3,741,473 13,911,579
REVISED DEBT LEVY $12,297,737 $15,971,848 $16,051,191 $15,326,519 $14,139,329 $70,036,552
% CHANGE IN DEBT LEVY 30% 0% (5%) (8%)
Each year, certain bond issues mature and the corresponding debt service payments are eliminated. The amount of debt service dropping off each year as payments
are made is less than the amount that we are adding for new CIP projects through 2028. This levels out in 2029, and flips the other way in 2030 whereby the amount
of debt levy from existing debt falls at a greater rate than what is being proposed to add. This results in a significant increase in the debt service property tax levy in
2028, slight increase in 2029, and decreases in 2030 and 2031.
The proposed CIP projects will impact the debt service beginning in 2028. The anticipated bond payments on debt issued in conjunction with these new projects
will result in an increased debt service levy of approximately $3,074,000 for 2028, $4,067,000 for 2029, $4,929,000 for 2030, and $5,592,000 for 2031.
The $138.8M of bonding for projects in the 2027-2031 CIP will require significant bond payments beginning in 2028 from the following sources: tax levy, special
assessments, franchise fees, and the Water Operating Fund/Water Trunk Fund. The estimated annual payments by source are shown in the table and chart below.
Funding of New Debt from CIP (Cumulative Payments by Year)
Funding source 2028 2029 2030 2031 2032
Tax Levy $3,074,663 $4,066,663 $4,928,663 $5,591,663 $6,260,663
Special Assessments 43,791 205,645 398,642 398,642 398,642
Franchise Fees 1,673,587 3,681,891 3,681,891 3,681,891 3,681,891
Water Funds 3,486,896 3,486,896 3,486,896 3,486,896 3,486,896
Total 8,278,936 11,441,094 12,496,091 13,159,091 13,828,091
Additional Considerations
Impact of the Capital Improvement Plan on the Operating Budget
The City’s Operating Budget is affected by the Capital Improvement Plan. Capital improvements typically result in ongoing expenses for routine operation, repair
and maintenance upon completion or acquisition. Existing City facilities and equipment will eventually require rehabilitation, renovation or upgrades to
accommodate new uses or address needed improvements. Older facilities usually involve higher maintenance and repair costs as well.
Capital improvements make a positive contribution to the economic vitality, quality of life and fiscal well-being of our community in spite of potential recurring
operating costs. Capital projects such as the redevelopment of under-performing or under-used areas of the City, and the infrastructure expansion needed to
support new development, help promote the economic development and growth that generates additional operating revenues. These new revenue sources
provide the funding needed to maintain, improve and expand the City’s infrastructure.
Additional considerations
Dakota County staff continue to prepare the Dakota County’s draft 2027-2031 Transportation, Transportation Sales & Use Tax, and Regional Rail Authority Capital
Improvement Program. City and County staff continue to coordinate efforts to create CIPs that align with both local and regional transportation needs.
Produced Using Plan-It CIP Software Page 5
2027 through 2031
Cost Type Summary
Lakeville, MN Cost Type Summary
Cost Type 2027 2028 2029 2030 2031 Total
Environmental Resources 1,601,500 1,601,500 1,601,500 1,601,500 1,601,500 8,007,500
Equipment 4,116,501 5,417,938 4,469,224 6,016,451 4,503,375 24,523,489
Facilities 87,173,600 26,160,400 8,247,789 6,351,860 1,795,000 129,728,649
Parks 4,041,500 8,117,500 2,729,000 3,827,000 4,099,950 22,814,950
Technology 513,715 730,021 521,998 366,953 148,651 2,281,338
Transportation 36,360,907 23,133,352 16,277,943 14,230,307 19,765,703 109,768,212
Utility 1,932,000 3,635,000 2,105,000 2,775,000 1,945,000 12,392,000
GRAND TOTAL 135,739,723 68,795,711 35,952,454 35,169,071 33,859,179 309,516,138
Produced Using Plan-It CIP Software Page 6
2027 through 2031
Capital Improvement Plan
Lakeville, MN Funding Source Summary
Source 2027 2028 2029 2030 2031 Total
Arenas 1,534 7,599 3,628 3,696 4,384 20,841
Building Fund 938,600 1,105,400 8,027,789 1,195,000 1,705,000 12,971,789
Communications Fund 59,932 79,455 81,751 79,262 99,237 399,637
Dakota County 14,769,824 4,124,000 354,250 2,458,000 10,000 21,716,074
Dakota County- Advance funding of city
share -465,454 -2,674,000 -336,000 -3,475,454
Environmental Resources Fund 1,690,872 1,351,974 1,343,878 2,198,744 1,508,194 8,093,662
Equipment Fund 3,294,423 5,047,526 3,863,123 4,694,237 3,494,305 20,393,614
Escrows 362,029 311,046 657,600 1,330,675
General Fund 319,505 196,242 266,212 209,517 236,994 1,228,470
G.O. Improvement Bonds- Franchise
Fees (Facilities) 20,000,000 24,000,000 44,000,000
G.O. Improvement Bonds - Sp. Assess. 330,077 1,220,000 1,454,737 3,004,814
G.O. Improvement Bonds- Taxes
(Facilities) 26,000,000 26,000,000
G.O. Improvement Bonds - Taxes
(Streets) 6,775,183 7,481,056 6,497,047 4,995,932 5,043,203 30,792,421
Improvement Construction Fund 225,000 225,000
Liquor Fund 176,367 299,222 70,366 674,978 102,455 1,323,388
MSA/MSA Bonds - Sp. Assess. 350,000 350,000
Municipal State Aid 2,163,680 7,726,250 3,466,633 2,634,375 7,214,900 23,205,838
Other cost share arrangement- Credit
River (Judicial Rd) 127,000 127,000
Other funding- Federal 325,000 325,000
Other funding- State 7,229,958 7,229,958
Park Dedication Fund 2,657,000 4,515,000 1,524,791 2,912,000 3,185,000 14,793,791
Park & Trail Improvement Fund 1,889,500 3,782,500 1,394,000 1,347,000 2,314,950 10,727,950
Pavement Management Fund 2,722,500 2,750,000 2,720,000 2,790,000 2,865,000 13,847,500
Sanitary Sewer Operating Fund 1,309,376 1,303,438 1,361,704 1,240,633 1,889,643 7,104,794
Sanitary Sewer Trunk Fund 75,000 175,000 167,968 75,000 75,000 567,968
Stormwater Infrastructure Fund 585,000 600,000 582,672 205,000 1,240,000 3,212,672
Streetlight Operating Fund 10,000 50,000 60,000
Technology Fund 322,338 525,564 450,356 295,062 120,841 1,714,161
Vermillion River Watershed JPO 10,000 10,000 10,000 10,000 10,000 50,000
Water Operating Fund 10,500,479 2,293,439 2,221,704 3,710,635 1,367,473 20,093,730
Water Revenue Bonds 35,000,000 35,000,000
Produced Using Plan-It CIP Software Page 7
Source 2027 2028 2029 2030 2031 Total
Water Trunk Fund -3,635,000 2,565,000 395,845 3,440,000 315,000 3,080,845
GRAND TOTAL 135,769,723 68,795,711 35,922,454 35,169,071 33,859,179 309,516,138
Produced Using Plan-It CIP Software Page 8
2027 through 2031
Projects & Funding Sources by Cost type
Lakeville, MN Projects & Funding Sources By Cost Type
Cost Type Project # 2027 2028 2029 2030 2031 Total
Environmental Resources
East Lake Rough Fish Barrier 23-58 35,000 35,000 35,000 35,000 35,000 175,000
Forestry (Ash tree injection/removal,
reforestatio ER-05 141,500 141,500 141,500 141,500 141,500 707,500
Lake Management ER-02 110,000 110,000 110,000 110,000 110,000 550,000
Storm Water Conveyance System
Expansion ER-04 100,000 100,000 100,000 100,000 100,000 500,000
Stormwater Infrastructure Maintenance ER-03 960,000 960,000 960,000 960,000 960,000 4,800,000
Vegetation Management - City Outlots/
Public land ER-06 170,000 170,000 170,000 170,000 170,000 850,000
Water Quality and Water Conservation ER-01 85,000 85,000 85,000 85,000 85,000 425,000
Environmental Resources Total 1,601,500 1,601,500 1,601,500 1,601,500 1,601,500 8,007,500
Dakota County 10,000 10,000 10,000 10,000 10,000 50,000
Environmental Resources Fund 1,340,000 1,340,000 1,340,000 1,340,000 1,340,000 6,700,000
General Fund 141,500 141,500 141,500 141,500 141,500 707,500
Stormwater Infrastructure Fund 100,000 100,000 100,000 100,000 100,000 500,000
Vermillion River Watershed JPO 10,000 10,000 10,000 10,000 10,000 50,000
Source Grand Total 1,601,500 1,601,500 1,601,500 1,601,500 1,601,500 8,007,500
Equipment
Communications PEG-Equipment E-10 54,000 70,000 77,000 75,000 95,000 371,000
Construction Services-Equipment E-07 69,414 30,495 56,000 155,909
Environmental Resources - Equipment E-11 692,835 692,835
Facilities - Equipment E-05 45,021 46,296 91,317
Fire - Equipment E-02 421,542 1,103,344 290,000 1,537,900 99,220 3,452,006
Inspections-Equipment E-06 69,000 72,600 141,600
Liquor-Equipment E-08 34,880 34,880
Park Maintenance-Equipment E-04 551,179 732,095 768,585 604,887 457,858 3,114,604
Police-Equipment E-01 1,073,660 1,630,133 1,343,932 1,086,173 1,479,134 6,613,032
Streets-Equipment E-03 1,847,645 1,590,400 1,475,823 1,639,573 1,647,392 8,200,833
Utilities-Equipment E-12 54,040 245,670 379,509 324,083 652,171 1,655,473
Equipment Total 4,116,501 5,417,938 4,469,224 6,016,451 4,503,375 24,523,489
Communications Fund 54,000 70,000 77,000 75,000 95,000 371,000
Environmental Resources Fund 346,075 855,114 166,405 1,367,594
Equipment Fund 3,294,423 5,047,526 3,863,123 4,694,237 3,494,305 20,393,614
General Fund 138,005 54,742 114,712 68,017 95,494 470,970
Liquor Fund 34,880 34,880
Other funding- State 229,958 229,958
Sanitary Sewer Operating Fund 53,003 122,835 189,755 162,041 652,171 1,179,805
Water Operating Fund 1,037 122,835 189,754 162,042 0 475,668
Source Grand Total 4,116,501 5,417,938 4,469,224 6,016,451 4,503,375 24,523,489
Facilities
Arts Center-Maintenance/
Improvements B-05 645,000 180,000 445,000 350,000 1,620,000
City Hall Building Maintenance/
Improvements B-01 185,000 245,000 867,000 70,000 130,000 1,497,000
CMF Building Maintenance/
Improvements B-02 25,670,000 3,147,704 375,000 520,000 29,712,704
Produced Using Plan-It CIP Software Page 9
Cost Type Project # 2027 2028 2029 2030 2031 Total
Fine Arts Building-Maintenance/
Improvements B-06 100,000 570,000 670,000
Fire Station #1-Building Maintenance/
Improvements B-07 20,500,000 20,500,000
Fire Station #3-Building Maintenance/
Improvements B-09 20,000,000 3,500,000 23,500,000
Fire Station #4-Building Maintenance/
Improvements B-10 154,700 154,700
FiRST Center Facility Maintenance/
Improvements B-17 100,000 30,000 130,000
Galaxie Liquor Store- Maintenance/
Improv B-15 80,000 331,570 65,000 476,570
Heritage Center-Maintenance/
Improvements B-04 43,000 228,000 745,000 280,000 75,000 1,371,000
Heritage Liquor Store- Maintenance/
Improv B-13 15,000 95,000 200,000 25,000 335,000
Kenrick Liquor Store- Maintenance/
Improv B-14 15,000 30,290 45,290
Keokuk Liquor Store- Maintenance/
Improv B-12 70,000 70,000
Police Station- Building Maintenance/
Improvements B-03 165,600 62,400 2,963,385 25,000 600,000 3,816,385
Water Treatment Facilty-Maintenance/
Improvements B-16 40,235,000 880,000 190,000 4,525,000 45,830,000
Facilities Total 87,173,600 26,160,400 8,247,789 6,351,860 1,795,000 129,728,649
Building Fund 938,600 1,105,400 8,027,789 1,195,000 1,705,000 12,971,789
G.O. Improvement Bonds- Franchise Fees (Facilities) 20,000,000 24,000,000 44,000,000
G.O. Improvement Bonds- Taxes (Facilities) 26,000,000 26,000,000
Liquor Fund 30,000 175,000 631,860 90,000 926,860
Water Operating Fund 9,235,000 880,000 190,000 1,500,000 11,805,000
Water Revenue Bonds 35,000,000 35,000,000
Water Trunk Fund -4,000,000 3,025,000 -975,000
Source Grand Total 87,203,600 26,160,400 8,217,789 6,351,860 1,795,000 129,728,649
Parks
Bunker Hill Athletic Decks P-27 70,000 750,000 820,000
East Community Park Phase II 25-20 500,000 500,000
Future Park Land Acquisition P-04 2,000,000 100,000 100,000 100,000 2,300,000
Kensington Park Athletic Deck and
Parking Lot P-26 30,000 300,000 330,000
Keokuk Avenue/172nd St. Park P-11 75,000 825,000 900,000
Klamath Trail Retaining Wall 23-13 30,000 1,500,000 1,530,000
Other Projects P-19 67,000 430,000 355,000 325,000 330,000 1,507,000
Park Development - Adminstrative
Projects P-02 20,000 20,000 20,000 20,000 20,000 100,000
Park Development - Developer Credits P-03 435,000 435,000 435,000 435,000 435,000 2,175,000
Park Improvements (Various Parks) P-06 394,000 469,000 137,000 162,000 862,000 2,024,000
Park Parking Lot Reconstruction P-09 210,000 113,000 55,000 45,000 90,000 513,000
Parks Major Maintenance - Bldgs/
Shelters/Grounds P-17 8,000 25,000 500 24,850 0 58,350
Parks Major Maintenance - Courts P-20 30,000 22,000 12,000 51,400 60,200 175,600
Parks Major Maintenance - Fields P-16 37,000 39,000 39,000 12,000 14,000 141,000
Parks Major Maintenance - General P-01 18,500 19,500 19,500 19,750 19,750 97,000
Parks Major Maintenance - Open Space P-15 37,000 37,000 37,000 38,000 38,000 187,000
Parks - New Parking Lots & Expansions P-24 530,000 530,000
Playground Replacement P-08 340,000 650,000 384,000 384,000 390,000 2,148,000
Ritter Meadows Park P-13 60,000 870,000 930,000
Skatepark P-12 50,000 600,000 650,000
Produced Using Plan-It CIP Software Page 10
Cost Type Project # 2027 2028 2029 2030 2031 Total
S of 185th and E of Future Ixonia Ave
Ext- Park P-18 75,000 75,000
S.W. Corner of 210th Street & I-35 P-25 75,000 925,000 1,000,000
Trail Improvements (Various Trails) P-05 535,000 708,000 710,000 710,000 741,000 3,404,000
Voyageur Park P-14 720,000 720,000
Parks Total 4,041,500 8,117,500 2,729,000 3,827,000 4,099,950 22,814,950
Park Dedication Fund 2,402,000 4,335,000 1,335,000 2,480,000 1,985,000 12,537,000
Park & Trail Improvement Fund 1,639,500 3,782,500 1,394,000 1,347,000 2,114,950 10,277,950
Source Grand Total 4,041,500 8,117,500 2,729,000 3,827,000 4,099,950 22,814,950
Technology
Technology-Arenas T-04 1,534 7,599 3,628 3,696 4,384 20,841
Technology-Communications T-05 2,440 0 0 823 3,392 6,655
Technology-Environmental Resources T-07 1,946 4,255 823 1,099 8,123
Technology - General Government T-01 40,941 12,792 9,704 39,465 11,210 114,112
Technology-Liquor T-06 120,283 53,598 17,431 6,146 197,458
Technology-Network infrastructure T-10 183,513 496,879 249,660 180,720 44,389 1,155,161
Technology- Parks & recreation T-09 11,827 21,377 15,184 3,552 12,472 64,412
Technology-Public Safety T-02 127,734 120,300 221,883 102,723 46,062 618,702
Technology-Public Works T-03 6,961 5,907 20,094 16,499 18,473 67,934
Technology-Utilities T-08 16,536 7,314 1,845 1,221 1,024 27,940
Technology Total 513,715 730,021 521,998 366,953 148,651 2,281,338
Arenas 1,534 7,599 3,628 3,696 4,384 20,841
Communications Fund 5,932 9,455 4,751 4,262 4,237 28,637
Environmental Resources Fund 4,797 11,974 3,878 3,630 1,789 26,068
Liquor Fund 146,367 124,222 35,486 43,118 12,455 361,648
Sanitary Sewer Operating Fund 16,373 25,603 11,949 8,592 2,472 64,989
Technology Fund 322,338 525,564 450,356 295,062 120,841 1,714,161
Water Operating Fund 16,374 25,604 11,950 8,593 2,473 64,994
Source Grand Total 513,715 730,021 521,998 366,953 148,651 2,281,338
Transportation
195th Street Bridge Replacement 31-08 2,000,000 2,000,000
200th Street (Hamburg to Cedar) 28-05 75,000 1,600,000 1,675,000
Collector Roadway Rehabilitation XX-03 3,322,260 2,371,102 2,301,784 1,015,932 963,203 9,974,281
County Pavement Preservation/City
Utility Repairs XX-10 35,000 35,000
CSAH 23 Alignment Study (Griffon Tr -
135th St) 29-05 31,500 31,500
CSAH 23 M&O (CSAH 9 to CSAH 42) 27-09 53,568 53,568
CSAH 31 and CSAH 46 Traffic Signal 27-06 0 0
CSAH 46 and Foliage Avenue Traffic
Signal 28-06 52,031 253,125 305,156
CSAH 46 and Galaxie Avenue Traffic
Signal 28-07 59,063 253,125 312,188
CSAH 46 and Lac Lavon/Interlachen
Traffic Signal 30-05 104,062 534,375 638,437
CSAH 50 and Iberia Avenue Traffic
Safety Mgmt 31-05 140,000 67,500 207,500
CSAH 50/CSAH 60 RAB Modifications 26-08 1 1
CSAH 50 Expansion (CSAH 23 - Flagstaff
Ave) 31-07 295,000 150,000 1,910,000 2,355,000
CSAH 5 and Kenyon Avenue Traffic
Signal 27-05 141,000 141,000
CSAH 60/185th Street (Kenwood Tr-
Ipava Ave) 25-04 0 0 0 0
CSAH 60 and Judicial Road Traffic Signal 31-09 50,000 50,000
Produced Using Plan-It CIP Software Page 11
Cost Type Project # 2027 2028 2029 2030 2031 Total
CSAH 60 and Orchard Trail Traffic Signal 27-07 80,156 396,000 476,156
CSAH 9 and Glacier Way Traffic Signal 27-11 584,500 584,500
CSAH 9/Dodd Blvd Modernization
(215th St-210th St) 28-04 843,750 4,840,000 5,683,750
CSAH 9 Improvements at 194th St &
190th St 29-04 231,000 75,938 1,701,000 2,007,938
CSAH 9 Modernization (210th St -
Heritage Dr) 26-04 13,127,529 13,127,529
Freight Rail Car Storage Facility 22-16 7,475,000 7,475,000
Future CSAH 9/CSAH 31 Traffic Signal
System 23-08 0 0
Holyoke/Highview Avenue
Reconstruction 25-05 8,860,000 8,860,000
Interstate 35/CSAH 50 Interchange
Reconstruction 26-05 2,293,549 675,000 1,843,659 4,812,208
Kenrick Ave Extension (181st St-176th
St) P28-16 2,500,000 2,500,000
Lake Marion Greenway XX-15 567,500 150,000 405,000 2,880,000 4,002,500
Pavement Management - Maintenance XX-01 2,580,000 2,950,000 2,920,000 2,990,000 3,065,000 14,505,000
Street Reconstruction XX-02 4,840,000 6,670,000 6,925,000 4,710,000 4,810,000 27,955,000
Transportation Total 36,360,907 23,133,352 16,277,943 14,230,307 19,765,703 109,768,212
Dakota County 14,759,824 4,114,000 344,250 2,448,000 21,666,074
Dakota County- Advance funding of city share -465,454 -2,674,000 -336,000 -3,475,454
Escrows 362,029 311,046 657,600 1,330,675
General Fund 40,000 10,000 50,000
G.O. Improvement Bonds - Sp. Assess. 330,077 1,220,000 1,454,737 3,004,814
G.O. Improvement Bonds - Taxes (Streets) 6,775,183 7,481,056 6,497,047 4,995,932 5,043,203 30,792,421
Improvement Construction Fund 225,000 225,000
MSA/MSA Bonds - Sp. Assess. 350,000 350,000
Municipal State Aid 2,163,680 7,726,250 3,466,633 2,634,375 7,214,900 23,205,838
Other cost share arrangement- Credit River (Judicial
Rd) 127,000 127,000
Other funding- Federal 325,000 325,000
Other funding- State 7,000,000 7,000,000
Park Dedication Fund 255,000 180,000 189,791 432,000 1,200,000 2,256,791
Park & Trail Improvement Fund 250,000 200,000 450,000
Pavement Management Fund 2,722,500 2,750,000 2,720,000 2,790,000 2,865,000 13,847,500
Sanitary Sewer Operating Fund 385,000 375,000 375,000 375,000 520,000 2,030,000
Sanitary Sewer Trunk Fund 100,000 92,968 192,968
Stormwater Infrastructure Fund 485,000 500,000 482,672 105,000 1,140,000 2,712,672
Streetlight Operating Fund 10,000 50,000 60,000
Water Operating Fund 611,068 700,000 850,000 450,000 525,000 3,136,068
Water Trunk Fund 350,000 130,845 480,845
Source Grand Total 36,360,907 23,133,352 16,277,943 14,230,307 19,765,703 109,768,212
Utility
Fiber Optic Cable Connection U-10 62,000 70,000 60,000 80,000 80,000 352,000
Sanitary Sewer Inflow/Infiltration
Maintenance U-03 575,000 575,000 575,000 575,000 575,000 2,875,000
Sanitary Sewer Lift Station
Rehabilitation U-02 255,000 175,000 180,000 80,000 100,000 790,000
Sanitary Sewer Trunk Improvements U-01 75,000 75,000 75,000 75,000 75,000 375,000
Tower and Reservoir Maintenance U-08 150,000 1,000,000 1,150,000
Water Distribution Features U-06 150,000 150,000 300,000
Watermain Trunk Extensions U-05 265,000 265,000 265,000 265,000 265,000 1,325,000
Water meter replacement U-09 350,000 400,000 425,000 425,000 425,000 2,025,000
Well and Pump Rehabilitation U-07 250,000 125,000 375,000 125,000 375,000 1,250,000
Produced Using Plan-It CIP Software Page 12
Cost Type Project # 2027 2028 2029 2030 2031 Total
Well Construction U-04 100,000 1,800,000 50,000 1,950,000
Utility Total 1,932,000 3,635,000 2,105,000 2,775,000 1,945,000 12,392,000
Sanitary Sewer Operating Fund 855,000 780,000 785,000 695,000 715,000 3,830,000
Sanitary Sewer Trunk Fund 75,000 75,000 75,000 75,000 75,000 375,000
Water Operating Fund 637,000 565,000 980,000 1,590,000 840,000 4,612,000
Water Trunk Fund 365,000 2,215,000 265,000 415,000 315,000 3,575,000
Source Grand Total 1,932,000 3,635,000 2,105,000 2,775,000 1,945,000 12,392,000
GRAND TOTAL 135,739,723 68,795,711 35,952,454 35,169,071 33,859,179 309,516,138
Produced Using Plan-It CIP Software Page 13
2027 thru 2031
Project Details
Lakeville, MN
Project Name East Lake Rough Fish Barrier
Project # 23-58
Contact Zach Johnson, City Engineer Cost Type Environmental Resources
Department Environmental Resources Funding
Description
Environmental Resources Fund
Expenditures 2027 2028 2029 2030 2031 Total
Engineering/Design/Other costs 35,000 35,000 35,000 35,000 35,000 175,000
Total 35,000 35,000 35,000 35,000 35,000 175,000
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 35,000 35,000 35,000 35,000 35,000 175,000
Total 35,000 35,000 35,000 35,000 35,000 175,000
Produced Using Plan-It CIP Software Page 14
2027 thru 2031
Project Details
Lakeville, MN
Project Name Water Quality and Water Conservation
Project # ER-01
Contact Zach Johnson, City Engineer Cost Type Environmental Resources
Type Other Department Environmental Resources
Funding
Description
Environmental Resources Fund County Project # N/A
SP/SAP # N/A JPA # N/A
Description
Water Quality Best Management Practices
• Partnership projects aligning with Black Dog Watershed Water Management Organization, Dakota County Soil and Water Conservation District and
Vermillion River Watershed Joint Powers Organization restoration and protection strategies. Funding intended as City’s cost-share to meet partnership
or grant matching requirements. Emphasis on Federal Clean Water Act, Minnesota Pollution Control Agency MS4 permit and Total Maximum Daily Load
compliance.
Urban Restoration - Public System Initiatives and Improvements
• Program designed to restore and manage landscaping at public facilities and public open spaces by replacing hardscape and lawns with native plants/
low-maintenance vegetation. Best management practices include native grasses/plants, prairies, rain gardens and woodlands to provide stormwater
rate control/volume reduction or water quality improvements.
Water Conservation
• Program designed to implement water conservation strategies to reduce water use. Best management practices include water reuse and smart
irrigation systems.
Expenditures 2027 2028 2029 2030 2031 Total
Water Quality BMPs 75,000 75,000 75,000 75,000 75,000 375,000
Urban Restoration- Public System
Initiatives 10,000 10,000 10,000 10,000 10,000 50,000
Total 85,000 85,000 85,000 85,000 85,000 425,000
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 85,000 85,000 85,000 85,000 85,000 425,000
Total 85,000 85,000 85,000 85,000 85,000 425,000
Produced Using Plan-It CIP Software Page 15
2027 thru 2031
Project Details
Lakeville, MN
Project Name Lake Management
Project # ER-02
Contact Zach Johnson, City Engineer Cost Type Environmental Resources
Type Other Department Environmental Resources
Funding
Description
Environmental Resources Fund County Project # N/A
SP/SAP # N/A JPA # N/A
Description
Annual management program designed to promote and protect public water resources. Annual assessments, including aquatic plant surveys, aquatic invasive
species monitoring, fish surveys and water monitoring/sampling, guide best management practices and strategies, and prioritize and schedule treatments. Best
management practices and strategies include chemical treatments, education and outreach, and fish management.
Expenditures 2027 2028 2029 2030 2031 Total
Water Quality Assessment 60,000 60,000 60,000 60,000 60,000 300,000
Water Quality Treatment 50,000 50,000 50,000 50,000 50,000 250,000
Total 110,000 110,000 110,000 110,000 110,000 550,000
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 100,000 100,000 100,000 100,000 100,000 500,000
Dakota County 10,000 10,000 10,000 10,000 10,000 50,000
Total 110,000 110,000 110,000 110,000 110,000 550,000
Produced Using Plan-It CIP Software Page 16
2027 thru 2031
Project Details
Lakeville, MN
Project Name Stormwater Infrastructure Maintenance
Project # ER-03
Contact Zach Johnson, City Engineer Cost Type Environmental Resources
Type Maintenance Department Engineering
Funding
Description
Environmental Resources Fund
Description
Stormwater Basin Rehabilitation
• Annual maintenance program designed to extend service life/minimize life-cycle costs of public stormwater management basins. Stormwater
management basins improve water quality of stormwater runoff and reduce peak stormwater discharge rates. Public stormwater management basins
are inspected regularly to prioritize and schedule maintenance and rehabilitation projects. Best management practices include maintenance at
emergency overflow/easement areas, sediment/vegetation removal and slope restoration. Emphasis on Minnesota Pollution Control Agency Municipal
Separate Storm Sewer System (MS4) permit compliance.
Stormwater Infrastructure Maintenance/Rehabilitation
• Annual preventive maintenance program designed to protect the City’s investment in public stormwater infrastructure. Best management practices
include flared-end section repairs, sediment removal, storm sewer pipe and manhole repairs, and stormwater conveyance systems improvements.
Emphasis on Minnesota Pollution Control Agency Municipal Separate Storm Sewer System (MS4) permit compliance.
Flared-End Section (FES) Maintenance
• Annual maintenance program designed to improve the overall performance and effectiveness of the City’s stormwater management system. Best
management practices include removal of accumulated sediment that is restricting stormwater flow through flared-end sections, stormwater
infrastructure designed to convey water to/from stormwater management basins.
Stormwater Structure Sump Filling
• Annual program designed to improve the overall efficiency and effectiveness in maintaining the performance of the City's stromwater management.
Expenditures 2027 2028 2029 2030 2031 Total
Stormwater Basin Rehabilitation 450,000 450,000 450,000 450,000 450,000 2,250,000
Stormwater Infrastructure
maintenance/rehabilitation 290,000 290,000 290,000 290,000 290,000 1,450,000
Creeks- proactive/preventative
maintenance 100,000 100,000 100,000 100,000 100,000 500,000
FES Maintenance- MS4 Pond/
Outfall Insp. 85,000 85,000 85,000 85,000 85,000 425,000
Stormwater structure sump filling 35,000 35,000 35,000 35,000 35,000 175,000
Total 960,000 960,000 960,000 960,000 960,000 4,800,000
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 950,000 950,000 950,000 950,000 950,000 4,750,000
Vermillion River Watershed JPO 10,000 10,000 10,000 10,000 10,000 50,000
Total 960,000 960,000 960,000 960,000 960,000 4,800,000
Produced Using Plan-It CIP Software Page 17
2027 thru 2031
Project Details
Lakeville, MN
Project Name Storm Water Conveyance System Expansion
Project # ER-04
Contact Zach Johnson, City Engineer Cost Type Environmental Resources
Expenditures 2027 2028 2029 2030 2031 Total
Construction 100,000 100,000 100,000 100,000 100,000 500,000
Total 100,000 100,000 100,000 100,000 100,000 500,000
Funding Sources 2027 2028 2029 2030 2031 Total
Stormwater Infrastructure Fund 100,000 100,000 100,000 100,000 100,000 500,000
Total 100,000 100,000 100,000 100,000 100,000 500,000
Produced Using Plan-It CIP Software Page 18
2027 thru 2031
Project Details
Lakeville, MN
Project Name Forestry (Ash tree injection/removal, reforestatio
Project # ER-05
Contact Zach Jorgensen, City Forester Cost Type Environmental Resources
Type Maintenance Department Environmental Resources
Description
Annual maintenance program designed to manage, preserve, and protect public woodland assets. Best management practices include Emerald Ash
Borer program (tree injections, tree removal/stump grinding of infected trees and reforestation of public parks/open spaces).
Expenditures 2027 2028 2029 2030 2031 Total
Ash tree injection 60,000 55,000 55,000 55,000 55,000 280,000
Ash tree removal 53,000 56,000 56,000 56,000 56,000 277,000
Reforestation 28,500 30,500 30,500 30,500 30,500 150,500
Total 141,500 141,500 141,500 141,500 141,500 707,500
Funding Sources 2027 2028 2029 2030 2031 Total
General Fund 141,500 141,500 141,500 141,500 141,500 707,500
Total 141,500 141,500 141,500 141,500 141,500 707,500
Produced Using Plan-It CIP Software Page 19
2027 thru 2031
Project Details
Lakeville, MN
Project Name Vegetation Management - City Outlots/Public land
Project # ER-06
Contact Zach Jorgensen, City Forester Cost Type Environmental Resources
Type Maintenance Department Environmental Resources
Description
Annual maintenance program designed to help establish deep-rooted native vegetation that will help prevent erosion and filter out chemicals, and nutrients, like
phosphorous, that degrades water quality. Managing invasive and noxious weeds also helps to establish the native vegetation, increase biodiversity, and improve
habitat for local wildlife.
Expenditures 2027 2028 2029 2030 2031 Total
Vegetation maintenance-City
outlots/public land 170,000 170,000 170,000 170,000 170,000 850,000
Total 170,000 170,000 170,000 170,000 170,000 850,000
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 170,000 170,000 170,000 170,000 170,000 850,000
Total 170,000 170,000 170,000 170,000 170,000 850,000
Produced Using Plan-It CIP Software Page 20
2027 thru 2031
Project Details
Lakeville, MN
Project Name Police-Equipment
Project # E-01
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Police Department
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Police division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase - squad
vehicles 610,000 1,030,000 1,282,600 981,000 1,288,000 5,191,600
Equipment purchase - radios 345,000 351,505 9,890 96,823 45,138 848,356
Equipment Purchase -
attachments 0 172,000 0 0 0 172,000
Equipment purchase - safety
equipment 76,150 57,644 30,742 6,384 0 170,920
Equipment purchase - firearms 42,510 18,984 20,700 1,966 55,841 140,001
Equipment purchase -
supplemental equipment 0 0 0 0 90,155 90,155
Total 1,073,660 1,630,133 1,343,932 1,086,173 1,479,134 6,613,032
Funding Sources 2027 2028 2029 2030 2031 Total
Equipment Fund 1,050,090 1,621,687 1,328,715 1,074,156 1,456,240 6,530,888
General Fund 23,570 8,446 15,217 12,017 22,894 82,144
Total 1,073,660 1,630,133 1,343,932 1,086,173 1,479,134 6,613,032
Produced Using Plan-It CIP Software Page 21
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fire - Equipment
Project # E-02
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Fire
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Fire division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase - multi-year
fire equipment 0 800,000 0 1,532,000 0 2,332,000
Equipment purchase - radios 177,644 177,644 0 0 0 355,288
Equipment purchase -
supplemental equipment 243,898 34,500 0 0 38,720 317,118
Equipment Purchase - vehicle 0 0 210,000 0 60,500 270,500
Equipment purchase - safety
equipment 0 91,200 80,000 0 0 171,200
Equipment Purchase - Trailer 0 0 0 5,900 0 5,900
Total 421,542 1,103,344 290,000 1,537,900 99,220 3,452,006
Funding Sources 2027 2028 2029 2030 2031 Total
Equipment Fund 421,542 1,103,344 290,000 1,537,900 99,220 3,452,006
Total 421,542 1,103,344 290,000 1,537,900 99,220 3,452,006
Produced Using Plan-It CIP Software Page 22
2027 thru 2031
Project Details
Lakeville, MN
Project Name Streets-Equipment
Project # E-03
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Streets
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Streets division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment Purchase - plow truck 695,580 1,114,400 713,000 731,600 750,200 4,004,780
Equipment purchase - heavy
equipment 692,150 459,200 606,498 79,392 440,429 2,277,669
Equipment purchase - sweepers
(split 50-50 with Fund 7450) 459,915 0 0 324,558 332,809 1,117,282
Equipment purchase -
supplemental equipment 0 16,800 87,325 362,423 123,954 590,502
Equipment Purchase - vehicle 0 0 69,000 141,600 0 210,600
Total 1,847,645 1,590,400 1,475,823 1,639,573 1,647,392 8,200,833
Funding Sources 2027 2028 2029 2030 2031 Total
Equipment Fund 1,271,612 1,590,400 1,475,823 1,477,294 1,480,987 7,296,116
Environmental Resources Fund 346,075 0 0 162,279 166,405 674,759
Other funding- State 229,958 0 0 0 0 229,958
Total 1,847,645 1,590,400 1,475,823 1,639,573 1,647,392 8,200,833
Produced Using Plan-It CIP Software Page 23
2027 thru 2031
Project Details
Lakeville, MN
Project Name Park Maintenance-Equipment
Project # E-04
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Park Maintenance
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Park Maintenance division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase - heavy
equipment 91,898 406,911 256,450 0 151,250 906,509
Equipment Purchase - vehicle 132,488 64,614 110,469 309,687 191,710 808,968
Equipment purchase - mowers 111,289 114,352 251,796 191,802 0 669,239
Equipment purchase -
supplemental equipment 0 42,618 53,155 103,398 99,168 298,339
Equipment purchase - load & pack
refuse 215,504 0 0 0 0 215,504
Equipment Purchase - Trailer 0 72,800 34,500 0 15,730 123,030
Equipment purchase - seasonal
staff equipment 0 30,800 62,215 0 0 93,015
Total 551,179 732,095 768,585 604,887 457,858 3,114,604
Funding Sources 2027 2028 2029 2030 2031 Total
Equipment Fund 551,179 732,095 768,585 604,887 457,858 3,114,604
Total 551,179 732,095 768,585 604,887 457,858 3,114,604
Produced Using Plan-It CIP Software Page 24
2027 thru 2031
Project Details
Lakeville, MN
Project Name Facilities - Equipment
Project # E-05
Contact Tom Breeggemann, Facilities Supervisor Cost Type Equipment
Type Equipment Department General Government Facilities
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Facilities division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 45,021 46,296 0 0 0 91,317
Total 45,021 46,296 0 0 0 91,317
Funding Sources 2027 2028 2029 2030 2031 Total
General Fund 45,021 46,296 0 0 0 91,317
Total 45,021 46,296 0 0 0 91,317
Produced Using Plan-It CIP Software Page 25
2027 thru 2031
Project Details
Lakeville, MN
Project Name Inspections-Equipment
Project # E-06
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Inspections
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Inspections division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 0 0 69,000 0 72,600 141,600
Total 0 0 69,000 0 72,600 141,600
Funding Sources 2027 2028 2029 2030 2031 Total
General Fund 0 0 69,000 0 72,600 141,600
Total 0 0 69,000 0 72,600 141,600
Produced Using Plan-It CIP Software Page 26
2027 thru 2031
Project Details
Lakeville, MN
Project Name Construction Services-Equipment
Project # E-07
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Construction Services
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Construction Services division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 69,414 0 30,495 56,000 0 155,909
Total 69,414 0 30,495 56,000 0 155,909
Funding Sources 2027 2028 2029 2030 2031 Total
General Fund 69,414 0 30,495 56,000 0 155,909
Total 69,414 0 30,495 56,000 0 155,909
Produced Using Plan-It CIP Software Page 27
2027 thru 2031
Project Details
Lakeville, MN
Project Name Liquor-Equipment
Project # E-08
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Keokuk Liquor Store
Funding
Description
Liquor Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Liquor stores.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 0 0 34,880 0 0 34,880
Total 0 0 34,880 0 0 34,880
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 0 0 34,880 0 0 34,880
Total 0 0 34,880 0 0 34,880
Produced Using Plan-It CIP Software Page 28
2027 thru 2031
Project Details
Lakeville, MN
Project Name Communications PEG-Equipment
Project # E-10
Contact Tierney Helmers, Communications Manager Cost Type Equipment
Type Equipment Department Communications
Funding
Description
Equipment Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Communications division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 54,000 70,000 77,000 75,000 95,000 371,000
Total 54,000 70,000 77,000 75,000 95,000 371,000
Funding Sources 2027 2028 2029 2030 2031 Total
Communications Fund 54,000 70,000 77,000 75,000 95,000 371,000
Total 54,000 70,000 77,000 75,000 95,000 371,000
Produced Using Plan-It CIP Software Page 29
2027 thru 2031
Project Details
Lakeville, MN
Project Name Environmental Resources - Equipment
Project # E-11
Contact Bob Mach, Fleet Supervisor Cost Type Equipment
Type Equipment Department Environmental Resources
Funding
Description
Environmental Resources Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Environmental Resources division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 0 0 0 692,835 0 692,835
Total 0 0 0 692,835 0 692,835
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 0 0 0 692,835 0 692,835
Total 0 0 0 692,835 0 692,835
Produced Using Plan-It CIP Software Page 30
2027 thru 2031
Project Details
Lakeville, MN
Project Name Utilities-Equipment
Project # E-12
Contact Shane Quade, Utilities Superintendent Cost Type Equipment
Type Equipment Department Utilities
Funding
Description
Water Operating Fund
Description
The CIP includes anticipated replacement/addition of various equipment costs for the Utilities division.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment Purchase - vehicle 0 162,262 379,509 324,083 652,171 1,518,025
Equipment purchase - heavy
equipment 0 53,000 0 0 0 53,000
Equipment purchase 51,965 0 0 0 0 51,965
Equipment Purchase - Trailer 0 18,995 0 0 0 18,995
Equipment purchase -
supplemental equipment 0 11,413 0 0 0 11,413
Equipment Purchase -
attachments 2,075 0 0 0 0 2,075
Total 54,040 245,670 379,509 324,083 652,171 1,655,473
Funding Sources 2027 2028 2029 2030 2031 Total
Sanitary Sewer Operating Fund 53,003 122,835 189,755 162,041 652,171 1,179,805
Water Operating Fund 1,037 122,835 189,754 162,042 0 475,668
Total 54,040 245,670 379,509 324,083 652,171 1,655,473
Produced Using Plan-It CIP Software Page 31
2027 thru 2031
Project
Details
Lakeville, MN
Project Name City Hall Building Maintenance/
Improvements
Project # B-01
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance Department City Hall
Description
The CIP includes anticipated maintenance/repair/improvement costs at Lakeville's City Hall building at 20195 Holyoke Ave.
Expenditures 2027 2028 2029 2030 2031 Total
Roof replacement 0 0 850,000 0 0 850,000
West Wing office renovations/
Engineering Conf Room 0 200,000 0 0 0 200,000
Carpet 135,000 0 0 0 0 135,000
Lunchroom 0 0 0 0 100,000 100,000
RTU S3 Replacement 0 0 0 70,000 0 70,000
Solar farm 50,000 0 0 0 0 50,000
Wall coverings 0 45,000 0 0 0 45,000
Admin Bathrooms 0 0 0 0 30,000 30,000
Window film 0 0 17,000 0 0 17,000
Total 185,000 245,000 867,000 70,000 130,000 1,497,000
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 185,000 245,000 867,000 70,000 130,000 1,497,000
Total 185,000 245,000 867,000 70,000 130,000 1,497,000
Produced Using Plan-It CIP Software Page 32
2027 thru 2031
Project Details
Lakeville, MN
Project Name CMF Building Maintenance/Improvements
Project # B-02
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Utilities
Funding
Description
Building Fund
Description
The CIP includes anticipated maintenance/repair/improvement costs at Lakeville's Central Maintenance Facility building at 7570 179th St. W. It also includes costs
to expand the facility in 2027, which will be funded by bonds, to be repaid by tax levy in future years.
Expenditures 2027 2028 2029 2030 2031 Total
CMF Expansion 25,000,000 0 0 0 0 25,000,000
Roof replacement 0 0 3,000,000 0 0 3,000,000
Generator Replacement 0 0 0 0 425,000 425,000
Fleet storage floor coating 0 0 0 300,000 0 300,000
Boiler plant replacement 300,000 0 0 0 0 300,000
BAS automation 185,000 0 0 0 0 185,000
Building wall system 0 0 100,000 0 0 100,000
Truck Garage paint (interior) 80,000 0 0 0 0 80,000
Infrared tube heater replacement 0 0 0 75,000 0 75,000
Fire Panel (update) 65,000 0 0 0 0 65,000
Water heater replacement 0 0 0 0 55,000 55,000
Building envelope improvements 0 0 47,704 0 0 47,704
Monument sign 40,000 0 0 0 0 40,000
Carpet 0 0 0 0 30,000 30,000
Paint Exterior Doors and Trim 0 0 0 0 10,000 10,000
Total 25,670,000 0 3,147,704 375,000 520,000 29,712,704
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds- Taxes
(Facilities) 26,000,000 0 0 0 0 26,000,000
Building Fund -330,000 0 3,147,704 375,000 520,000 3,712,704
Total 25,670,000 0 3,147,704 375,000 520,000 29,712,704
Produced Using Plan-It CIP Software Page 33
2027 thru 2031
Project Details
Lakeville, MN
Project Name Police Station- Building Maintenance/Improvements
Project # B-03
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Police Department
Funding
Description
Building Fund
Description
Anticipated maintenance/repairs/improvements needed on the Police Station building.
Expenditures 2027 2028 2029 2030 2031 Total
Workout room expansion 0 0 2,500,000 0 0 2,500,000
Roof replacement 0 0 0 0 600,000 600,000
Generator Replacement 0 0 402,500 0 0 402,500
Front landscaping 80,000 0 0 0 0 80,000
Radiant panels for offices 0 0 60,885 0 0 60,885
Sit stand desks 17,600 22,400 0 0 0 40,000
Evidence fence 30,000 0 0 0 0 30,000
Fencing 30,000 0 0 0 0 30,000
Building needs study 0 30,000 0 0 0 30,000
Paint-interior 0 0 0 25,000 0 25,000
Window film 0 10,000 0 0 0 10,000
Patrol furniture 8,000 0 0 0 0 8,000
Total 165,600 62,400 2,963,385 25,000 600,000 3,816,385
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 165,600 62,400 2,963,385 25,000 600,000 3,816,385
Total 165,600 62,400 2,963,385 25,000 600,000 3,816,385
Produced Using Plan-It CIP Software Page 34
2027 thru
2031
Project
Details
Lakeville,
MN
Project Name
Heritage
Center-
Maintenance/
Improvements
Project # B-04
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Heritage Center
Funding
Description
Building Fund
Description
The Lakeville Heritage Center is located at 20110 Holyoke Ave and is home to Lakeville Area Active Adults, Lakeville Area Historical Society and Lakeville Yellow Ribbon. The CIP
includes estimated costs for maintenance/repairs/improvements at the Heritage Center building.
Expenditures 2027 2028 2029 2030 2031 Total
Interior renovation phase 1 0 0 690,000 0 0 690,000
Interior renovation phase 2 0 0 0 280,000 0 280,000
RTU MULTI 0 220,000 0 0 0 220,000
Carpet Replacement 0 0 0 0 75,000 75,000
Building envelope improvements 0 0 55,000 0 0 55,000
Fire Panel (update) 25,000 0 0 0 0 25,000
JHP-amenities 18,000 0 0 0 0 18,000
Mini Split Replacement 0 8,000 0 0 0 8,000
Total 43,000 228,000 745,000 280,000 75,000 1,371,000
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 43,000 228,000 745,000 280,000 75,000 1,371,000
Total 43,000 228,000 745,000 280,000 75,000 1,371,000
Produced Using Plan-It CIP Software Page 35
2027 thru 2031
Project Details
Lakeville, MN
Project Name Arts Center-Maintenance/Improvements
Project # B-05
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department LAAC - Performing Arts Building
Funding
Description
Building Fund
Description
The Lakeville Area Arts Center is located at 20965 Holyoke Ave, in historic downtown Lakeville. The Arts Center hosts theater and other events, community classes,
and provides rental opportunities. The CIP includes estimated costs for maintenance/repairs/improvements at the Arts Center building.
Expenditures 2027 2028 2029 2030 2031 Total
AHU 1 520,000 0 0 0 0 520,000
AHU 2 0 0 0 0 350,000 350,000
Building envelope improvements 0 0 0 320,000 0 320,000
Theater Seating Refurbishment 0 0 150,000 0 0 150,000
AHU Replacements 0 0 0 125,000 0 125,000
Light board replacement 80,000 0 0 0 0 80,000
Bleacher carpet 0 0 30,000 0 0 30,000
Fire Panel (update) 25,000 0 0 0 0 25,000
Bleacher flooring 20,000 0 0 0 0 20,000
Total 645,000 0 180,000 445,000 350,000 1,620,000
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 645,000 0 180,000 445,000 350,000 1,620,000
Total 645,000 0 180,000 445,000 350,000 1,620,000
Produced Using Plan-It CIP Software Page 36
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fine Arts Building-Maintenance/Improvements
Project # B-06
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department LAAC - Fine Arts Building
Funding
Description
Building Fund
Description
The Fine Arts Center is located at 20950 Howland Ave and is a division of the Lakeville Area Arts Center, focused on providing expanded classroom and studio
space for fine arts programming. The CIP includes estimated costs for maintenance/repairs/improvements at the Fine Arts Center building.
Expenditures 2027 2028 2029 2030 2031 Total
Roof replacement 0 570,000 0 0 0 570,000
Boiler plant replacement 100,000 0 0 0 0 100,000
Total 100,000 570,000 0 0 0 670,000
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 100,000 570,000 0 0 0 670,000
Total 100,000 570,000 0 0 0 670,000
Produced Using Plan-It CIP Software Page 37
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fire Station #1-Building Maintenance/Improvements
Project # B-07
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Fire Station #1
Description
Station 1 protects the region south of 195th Street to 220th Street, west to Judicial Road (Scott County), and east to the Farmington border. The CIP includes
anticipated maintenance/repairs and improvements to the Fire Station #1 building.
Expenditures 2027 2028 2029 2030 2031 Total
Remodel for full time 0 20,500,000 0 0 0 20,500,000
Total 0 20,500,000 0 0 0 20,500,000
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds-
Franchise Fees (Facilities) 0 20,500,000 0 0 0 20,500,000
Total 0 20,500,000 0 0 0 20,500,000
Produced Using Plan-It CIP Software Page 38
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fire Station #3-Building Maintenance/Improvements
Project # B-09
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Fire Station #3
Funding
Description
Building Fund
Description
Anticipated maintenance/repairs/improvements needed on the Fire Station #3 building.
Expenditures 2027 2028 2029 2030 2031 Total
Remodel for full time 20,000,000 3,500,000 0 0 0 23,500,000
Total 20,000,000 3,500,000 0 0 0 23,500,000
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds-
Franchise Fees (Facilities) 20,000,000 3,500,000 0 0 0 23,500,000
Total 20,000,000 3,500,000 0 0 0 23,500,000
Produced Using Plan-It CIP Software Page 39
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fire Station #4-Building Maintenance/Improvements
Project # B-10
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Fire Station #4
Funding
Description
Building Fund
Description
Built in 2002, Station 4 is currently Lakeville's newest and most centrally located station. The CIP includes anticipated maintenance/repairs/improvements needed
on the Fire Station #4 building.
Expenditures 2027 2028 2029 2030 2031 Total
RTU 1,2,4 replacement 0 0 95,000 0 0 95,000
Carpet 0 0 30,000 0 0 30,000
Building envelope improvements 0 0 29,700 0 0 29,700
Total 0 0 154,700 0 0 154,700
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 30,000 0 124,700 0 0 154,700
Total 30,000 0 124,700 0 0 154,700
Produced Using Plan-It CIP Software Page 40
2027 thru 2031
Project Details
Lakeville, MN
Project Name Keokuk Liquor Store- Maintenance/Improv
Project # B-12
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Keokuk Liquor Store
Funding
Description
Liquor Fund
Description
The CIP includes anticipated maintenance/repairs/improvement costs at the Keokuk Liquor Store building, which is located at 20880 Keokuk Ave. This facility also
includes the Emporium Room, which is a multi-purpose, 3,000 square feet room that can be rented for meetings, celebrations or classes.
Expenditures 2027 2028 2029 2030 2031 Total
Paint sales floor & office walls 0 0 0 70,000 0 70,000
Total 0 0 0 70,000 0 70,000
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 0 0 0 70,000 0 70,000
Total 0 0 0 70,000 0 70,000
Produced Using Plan-It CIP Software Page 41
2027 thru 2031
Project Details
Lakeville, MN
Project Name Heritage Liquor Store- Maintenance/Improv
Project # B-13
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Heritage Liquor Store
Funding
Description
Liquor Fund
Description
The CIP includes anticipated maintenance/repairs/improvement costs at the Heritage Liquor Store building, which is located at 20164 Heritage Dr.
Expenditures 2027 2028 2029 2030 2031 Total
Entrance door replacement 0 0 0 200,000 0 200,000
Flooring Replacement 0 65,000 0 0 0 65,000
Cooler mechanicals 0 0 0 0 25,000 25,000
LED Light Installation 0 20,000 0 0 0 20,000
Fire sprinkler system installation 15,000 0 0 0 0 15,000
Paint sales floor & office walls 0 10,000 0 0 0 10,000
Total 15,000 95,000 0 200,000 25,000 335,000
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 15,000 95,000 0 200,000 25,000 335,000
Total 15,000 95,000 0 200,000 25,000 335,000
Produced Using Plan-It CIP Software Page 42
2027 thru 2031
Project Details
Lakeville, MN
Project Name Kenrick Liquor Store- Maintenance/Improv
Project # B-14
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Kenrick Liquor Store
Funding
Description
Liquor Fund
Description
The CIP includes anticipated maintenance/repairs/improvement costs at the Kenrick Liquor Store building, which is located at 16179 Kenrick Ave.
Expenditures 2027 2028 2029 2030 2031 Total
Building envelope improvements 0 0 0 30,290 0 30,290
Cooler fire suppression
maintenance 15,000 0 0 0 0 15,000
Total 15,000 0 0 30,290 0 45,290
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 15,000 0 0 30,290 0 45,290
Total 15,000 0 0 30,290 0 45,290
Produced Using Plan-It CIP Software Page 43
2027 thru 2031
Project Details
Lakeville, MN
Project Name Galaxie Liquor Store- Maintenance/Improv
Project # B-15
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department Galaxie Liquor Store
Funding
Description
Liquor Fund
Description
The CIP includes anticipated maintenance/repairs/improvement costs at the Galaxie Liquor Store building, which is located at 16000 Galaxie Ave.
Expenditures 2027 2028 2029 2030 2031 Total
Roof replacement 0 0 0 275,000 0 275,000
Sales counter renovations 0 80,000 0 0 0 80,000
Flooring Replacement 0 0 0 0 65,000 65,000
Building envelope improvements 0 0 0 56,570 0 56,570
Total 0 80,000 0 331,570 65,000 476,570
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 0 80,000 0 331,570 65,000 476,570
Total 0 80,000 0 331,570 65,000 476,570
Produced Using Plan-It CIP Software Page 44
2027 thru 2031
Project Details
Lakeville, MN
Project Name Water Treatment Facilty-Maintenance/Improvements
Project # B-16
Contact Paul Oehme, Public Works Director Cost Type Facilities
Type Maintenance/Improvement Department Utilities
Funding
Description
Water Operating Fund
Description
Anticipated maintenance/repairs/improvements needed on the existing Water Treatment Facility building.
The City’s water demand continues to grow as new development occurs. This project would construct a satellite water treatment plant at the northeast corner of
179th Street and Granby Lane. A water treatment expansion study completed in 2026 identified the need for a satellite treatment facility to meet future water
demands. The new plant will improve the redundancy and resiliency of the City’s water system and provide additional capacity to improve water distribution and
maintain system pressure during peak-demand periods.
Expenditures 2027 2028 2029 2030 2031 Total
Satellite Water Treatment Plant
construction 40,000,000 0 0 0 0 40,000,000
Fleet garage expansion 0 0 0 3,000,000 0 3,000,000
Roof replacement 0 0 0 1,500,000 0 1,500,000
Electrical split 0 300,000 0 0 0 300,000
Parking lot mill and overlay 0 250,000 0 0 0 250,000
BAS upgrade 185,000 0 0 0 0 185,000
Dehumidifier 0 150,000 0 0 0 150,000
Filter rooms exhaust fan
replacement 0 120,000 0 0 0 120,000
AHU Replacements 0 0 115,000 0 0 115,000
Building envelope improvements 0 0 75,000 0 0 75,000
Fleet garage mechanicals 0 60,000 0 0 0 60,000
Wall coverings 30,000 0 0 0 0 30,000
Well #7 roof replacement 0 0 0 25,000 0 25,000
Main bathroom sink and
countertops 20,000 0 0 0 0 20,000
Total 40,235,000 880,000 190,000 4,525,000 0 45,830,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Revenue Bonds 35,000,000 0 0 0 0 35,000,000
Water Operating Fund 9,235,000 880,000 190,000 1,500,000 0 11,805,000
Water Trunk Fund -4,000,000 0 0 3,025,000 0 -975,000
Total 40,235,000 880,000 190,000 4,525,000 0 45,830,000
Produced Using Plan-It CIP Software Page 45
2027 thru 2031
Project Details
Lakeville, MN
Project Name FiRST Center Facility Maintenance/Improvements
Project # B-17
Contact Tom Breeggemann, Facilities Supervisor Cost Type Facilities
Type Maintenance/Improvement Department FiRST Center
Funding
Description
FiRST Center Operating Fund
Description
Construction of the FiRST Center began in early 2025 and will be located at the former Public Works site within the Airlake Industrial Park at 7777 214th Street
West. It is expected to be completed in 2026. Operational costs to maintain and operate the facility will be provided through membership fees paid by the various
agencies that will be using the facility. The CIP estimates maintenance/repair/improvements costs at this facility.
Expenditures 2027 2028 2029 2030 2031 Total
Facility improvements/
maintenance 100,000 0 0 0 0 100,000
Paint-interior 0 0 0 0 30,000 30,000
Total 100,000 0 0 0 30,000 130,000
Funding Sources 2027 2028 2029 2030 2031 Total
Building Fund 100,000 0 0 0 30,000 130,000
Total 100,000 0 0 0 30,000 130,000
Produced Using Plan-It CIP Software Page 46
2027 thru 2031
Project Details
Lakeville, MN
Project Name Klamath Trail Retaining Wall
Project # 23-13
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park & Trail Improvement Fund
Description
Two existing modular block retaining walls (totaling over 1,200 feet in length) run along the south side of Klamath Trail, west of County State Aid Highway 5. Both
were constructed in 1999.
After signs of deterioration were noticed, a third party completed a Condition Assessment Report. Based on the walls' anticipated lifespan and the assessment
findings — which identified visible staining, cracking along the face of individual blocks, and other forms of deterioration — repair is warranted.
Updated cost estimates for four repair options were obtained in 2026, ranging from $3.3 million to $4.3 million. Based on these latest estimates, staff is proposing
the evaluation of a new option, that could potentially eliminate the wall and create a new trail corridor instead. Planning and Design work is being budgeted for
2027, with construction anticipated in 2028.
Expenditures 2027 2028 2029 2030 2031 Total
Retaining Wall Reconstruction 0 1,500,000 0 0 0 1,500,000
Engineering/Design/Other costs 30,000 0 0 0 0 30,000
Total 30,000 1,500,000 0 0 0 1,530,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 30,000 1,500,000 0 0 0 1,530,000
Total 30,000 1,500,000 0 0 0 1,530,000
Map
Produced Using Plan-It CIP Software Page 47
2027 thru 2031
Project Details
Lakeville, MN
Project Name East Community Park Phase II
Project # 25-20
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Bonds
Funding
Description
Park Bonds Fund
Description
The East Community Park project was approved as part of the 2021 Park Bond Referendum and includes shelter, restrooms (year round), community garden, dog
park, water access, and fishing piers. Construction is in progress in 2026 and is anticipated to be completed in 2027.
This project also includes the trails/trailhead in East Community Park, which is part of a multi-phased County greenway project designed to provide connectivity
City and County trail system.
Expenditures 2027 2028 2029 2030 2031 Total
East Community Park 500,000 0 0 0 0 500,000
Total 500,000 0 0 0 0 500,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 500,000 0 0 0 0 500,000
Total 500,000 0 0 0 0 500,000
Map
Produced Using Plan-It CIP Software Page 48
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks Major Maintenance - General
Project # P-01
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
Includes general park amenities like benches, grills, tables and improvements completed through our Eagle Scout Program.
Expenditures 2027 2028 2029 2030 2031 Total
Park Amenities – Benches, Grills,
Tables, etc. 10,000 11,000 11,000 11,000 11,000 54,000
Eagle Scout Project Materials 8,500 8,500 8,500 8,750 8,750 43,000
Total 18,500 19,500 19,500 19,750 19,750 97,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 18,500 19,500 19,500 19,750 19,750 97,000
Total 18,500 19,500 19,500 19,750 19,750 97,000
Produced Using Plan-It CIP Software Page 49
2027 thru 2031
Project Details
Lakeville, MN
Project Name Park Development - Adminstrative Projects
Project # P-02
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
The Park Dedication Fund budget provides appropriations for many activities including planning, design and feasibility reports for park projects. On an annual basis
those project include engineering and design work for a wide variety of park projects, including rinks, playgrounds and future parks.
Expenditures 2027 2028 2029 2030 2031 Total
Engineering/Design/Other costs 20,000 20,000 20,000 20,000 20,000 100,000
Total 20,000 20,000 20,000 20,000 20,000 100,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 20,000 20,000 20,000 20,000 20,000 100,000
Total 20,000 20,000 20,000 20,000 20,000 100,000
Produced Using Plan-It CIP Software Page 50
2027 thru 2031
Project Details
Lakeville, MN
Project Name Park Development - Developer Credits
Project # P-03
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type Other Department Park Dedication
Funding
Description
Park Dedication Fund
Description
Represents credits associated with new development when the park dedication requirement is fulfilled through a land dedication.
Expenditures 2027 2028 2029 2030 2031 Total
Developer-Credits 435,000 435,000 435,000 435,000 435,000 2,175,000
Total 435,000 435,000 435,000 435,000 435,000 2,175,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 435,000 435,000 435,000 435,000 435,000 2,175,000
Total 435,000 435,000 435,000 435,000 435,000 2,175,000
Produced Using Plan-It CIP Software Page 51
2027 thru 2031
Project Details
Lakeville, MN
Project Name Future Park Land Acquisition
Project # P-04
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type Other Department Park Dedication
Funding
Description
Park Dedication Fund
Description
Represents potential costs of land acquisition where needed to fulfill future plans for parks in the City based on the 2026-2036 Parks System Master Plan.
Expenditures 2027 2028 2029 2030 2031 Total
Land acquisition for parks/trails
use 0 2,000,000 100,000 100,000 100,000 2,300,000
Total 0 2,000,000 100,000 100,000 100,000 2,300,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 2,000,000 100,000 100,000 100,000 2,300,000
Total 0 2,000,000 100,000 100,000 100,000 2,300,000
Produced Using Plan-It CIP Software Page 52
2027 thru 2031
Project Details
Lakeville, MN
Project Name Trail Improvements (Various Trails)
Project # P-05
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Reconstruction/Maintenance Department Park Maintenance
Funding
Description
Trail Improvement Fund
Description
Staff complete trail rating every three years to evaluate the condition of all trail segments in our community. Based on the evaluation results staff will refine the
current plan for either overlaying or reclaiming City trail segments, along with crack filling and fog sealing of trails.
Maintenance of sidewalks and trails along Dakota County roadways is provided in accordance with the current County and City Maintenance Agreement for County
Bikeway Trails. In 2021, the Dakota County Board of Commissioners approved the following regarding trails and sidewalks along Dakota County roadways:
Multi-Use Trails and Sidewalk Maintenance
Dakota County will participate in pavement preservation, overlay, or reconstruction of trails and sidewalks along the County highway system up to 100 percent.
The City is responsible for snow and ice removal. To be eligible for County participation in trails and sidewalks, a system-wide maintenance agreement between the
County and local agency will be required to identify system-wide trail and sidewalk roles and cost responsibilities.
Expenditures 2027 2028 2029 2030 2031 Total
Construction- Trail Rehabilitation/
Reconstruction 450,000 500,000 525,000 525,000 525,000 2,525,000
Crack Seal 85,000 85,000 85,000 85,000 90,000 430,000
Construction- New trails 0 100,000 100,000 100,000 100,000 400,000
Trail inspection and rating 0 23,000 0 0 26,000 49,000
Total 535,000 708,000 710,000 710,000 741,000 3,404,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 535,000 608,000 610,000 610,000 641,000 3,004,000
Park Dedication Fund 0 100,000 100,000 100,000 100,000 400,000
Total 535,000 708,000 710,000 710,000 741,000 3,404,000
Produced Using Plan-It CIP Software Page 53
2027 thru 2031
Project Details
Lakeville, MN
Project Name Park Improvements (Various Parks)
Project # P-06
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
The Park Improvement Fund provides funding for replacement and upgrades to shelters and buildings, improvements to hockey rinks, basketball, pickleball, tennis
courts and other park amenities.
Expenditures 2027 2028 2029 2030 2031 Total
Aronson Athletic Light
Replacement 0 0 0 0 400,000 400,000
Miracle Field surface replacement/
repairs 0 300,000 0 0 0 300,000
East Community- Tennis court
reconstruction 0 0 0 0 250,000 250,000
Dodd Trail Pickleball
reconstruction 225,000 0 0 0 0 225,000
McGuire-Rink reconstruction 110,000 110,000 0 0 0 220,000
Meadows Rink reconstruction 0 0 0 155,000 0 155,000
Rolling Oaks rink reconstruction 0 0 130,000 0 0 130,000
Parkview Rink reconstruction 0 0 0 0 130,000 130,000
East Community- BB court
reconstruction 0 0 0 0 75,000 75,000
Dodd Trail BB Reconstruction-
concrete 52,000 0 0 0 0 52,000
Prairie Lake BB reconstruction-
concrete 0 52,000 0 0 0 52,000
Ballfield dugout roof support 7,000 7,000 7,000 7,000 7,000 35,000
Total 394,000 469,000 137,000 162,000 862,000 2,024,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 394,000 469,000 137,000 162,000 862,000 2,024,000
Total 394,000 469,000 137,000 162,000 862,000 2,024,000
Produced Using Plan-It CIP Software Page 54
2027 thru 2031
Project Details
Lakeville, MN
Project Name Playground Replacement
Project # P-08
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Reconstruction/Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
The Park Improvement Fund provides funding for replacement and upgrades to playgrounds.
The Arts Center playground funding includes a $90,000 donation from QA-1.
Expenditures 2027 2028 2029 2030 2031 Total
Aronson Park 0 400,000 0 0 0 400,000
Meadows Park 0 0 0 0 130,000 130,000
Chadwick Park 0 0 0 0 130,000 130,000
Orchard Lake Park 0 0 0 0 130,000 130,000
Spyglass Park 0 0 0 128,000 0 128,000
Kenreel Park 0 0 0 128,000 0 128,000
Jaycee Park 0 0 128,000 0 0 128,000
Lakeridge Park 0 0 128,000 0 0 128,000
Rolling Oaks Park 0 0 128,000 0 0 128,000
Bassett Park 0 0 0 128,000 0 128,000
Fairfield Park 0 125,000 0 0 0 125,000
Lynwood Heights Park 0 125,000 0 0 0 125,000
Prairie Lake Park 120,000 0 0 0 0 120,000
Village Creek Park 120,000 0 0 0 0 120,000
Orchard Lake Beach 100,000 0 0 0 0 100,000
Total 340,000 650,000 384,000 384,000 390,000 2,148,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 340,000 650,000 384,000 384,000 390,000 2,148,000
Total 340,000 650,000 384,000 384,000 390,000 2,148,000
Produced Using Plan-It CIP Software Page 55
2027 thru 2031
Project Details
Lakeville, MN
Project Name Park Parking Lot Reconstruction
Project # P-09
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Reconstruction/Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
The Park Improvement Fund provides funding for replacement and rehabilitation of parking lots used to access City parks.
Expenditures 2027 2028 2029 2030 2031 Total
Orchard Lake Park 210,000 0 0 0 0 210,000
East Community Park 0 0 0 0 90,000 90,000
Greenridge Park 0 68,000 0 0 0 68,000
Prairie Lake Park 0 0 55,000 0 0 55,000
Highview Heights 0 45,000 0 0 0 45,000
Cedar Highlands 0 0 0 45,000 0 45,000
Total 210,000 113,000 55,000 45,000 90,000 513,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 210,000 113,000 55,000 45,000 90,000 513,000
Total 210,000 113,000 55,000 45,000 90,000 513,000
Produced Using Plan-It CIP Software Page 56
2027 thru 2031
Project Details
Lakeville, MN
Project Name Keokuk Avenue/172nd St. Park
Project # P-11
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
The Parks, Trails and Open Space Plan calls for a neighborhood park in the area which is proposed to be constructed in 2030. Planning/design costs are included in
2029.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 800,000 0 800,000
Planning/Design 0 0 75,000 25,000 0 100,000
Total 0 0 75,000 825,000 0 900,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 0 75,000 825,000 0 900,000
Total 0 0 75,000 825,000 0 900,000
Map
Produced Using Plan-It CIP Software Page 57
2027 thru 2031
Project Details
Lakeville, MN
Project Name Skatepark
Project # P-12
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type New construction Department Park Dedication
Description
Planning/design costs are included in 2029 with construction planned for 2030
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 600,000 0 600,000
Planning/Design 0 0 50,000 0 0 50,000
Total 0 0 50,000 600,000 0 650,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 0 50,000 600,000 0 650,000
Total 0 0 50,000 600,000 0 650,000
Map
Produced Using Plan-It CIP Software Page 58
2027 thru 2031
Project Details
Lakeville, MN
Project Name Ritter Meadows Park
Project # P-13
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
The Parks, Trails and Open Space Plan calls for a neighborhood park in the area which is proposed to be constructed in 2029.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 850,000 0 0 0 850,000
Planning/Design 60,000 20,000 0 0 0 80,000
Total 60,000 870,000 0 0 0 930,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 60,000 870,000 0 0 0 930,000
Total 60,000 870,000 0 0 0 930,000
Map
Produced Using Plan-It CIP Software Page 59
2027 thru 2031
Project Details
Lakeville, MN
Project Name Voyageur Park
Project # P-14
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
The Parks, Trails, and Open Space Plan calls for a neighborhood park East of Cedar Avenue and south of 181st Street serving the future development in this area.
The park will be approximately 2 acres in size and is proposed to be constructed in 2027.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 700,000 0 0 0 0 700,000
Planning/Design 20,000 0 0 0 0 20,000
Total 720,000 0 0 0 0 720,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 720,000 0 0 0 0 720,000
Total 720,000 0 0 0 0 720,000
Map
Produced Using Plan-It CIP Software Page 60
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks Major Maintenance - Open Space
Project # P-15
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
Includes parking lot and trail maintenance work such as crack sealing and paint striping. Funds also include ongoing maintenance and improvements at the West
Lake Marion Bike Course.
Expenditures 2027 2028 2029 2030 2031 Total
Pavement Maintenance Parking
Lots & Trails 18,000 18,000 18,000 19,000 19,000 92,000
Fence Repairs 10,000 10,000 10,000 10,000 10,000 50,000
West Lake Marion Mountain Bike
Contract Maintenance 9,000 9,000 9,000 9,000 9,000 45,000
Total 37,000 37,000 37,000 38,000 38,000 187,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 37,000 37,000 37,000 38,000 38,000 187,000
Total 37,000 37,000 37,000 38,000 38,000 187,000
Produced Using Plan-It CIP Software Page 61
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks Major Maintenance - Fields
Project # P-16
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
Includes field maintenance and improvements throughout the parks system.
Expenditures 2027 2028 2029 2030 2031 Total
Field improvements/Maintenance 12,000 12,000 12,000 12,000 14,000 62,000
Aronson – replace backstop field 4 0 27,000 0 0 0 27,000
Aronson – replace backstop field 3 0 0 27,000 0 0 27,000
Aronson – replace backstop field 2 25,000 0 0 0 0 25,000
Total 37,000 39,000 39,000 12,000 14,000 141,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 37,000 39,000 39,000 12,000 14,000 141,000
Total 37,000 39,000 39,000 12,000 14,000 141,000
Produced Using Plan-It CIP Software Page 62
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks Major Maintenance - Bldgs/Shelters/Grounds
Project # P-17
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance/Improvement Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
Includes general maintenance projects, maintenance of buildings, park shelters and grounds (examples- re-shingle park shelters, replace signs, repair fencing,
replace rubber floors, etc.).
Expenditures 2027 2028 2029 2030 2031 Total
Projects TBD - Major Maintenance
Bldgs/Shelters/Grounds 0 0 500 24,850 0 25,350
Ritter Farm Park Cistern
Restoration 0 25,000 0 0 0 25,000
Steve Michaud – HVAC
Replacement and AC 8,000 0 0 0 0 8,000
Total 8,000 25,000 500 24,850 0 58,350
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 8,000 25,000 500 24,850 0 58,350
Total 8,000 25,000 500 24,850 0 58,350
Produced Using Plan-It CIP Software Page 63
2027 thru 2031
Project Details
Lakeville, MN
Project Name S of 185th and E of Future Ixonia Ave Ext- Park
Project # P-18
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
The Parks, Trails and Open Space Plan calls for a neighborhood park in the area which is proposed to be constructed in 2032. Planning/design costs are included in
2031.
Expenditures 2027 2028 2029 2030 2031 Total
Planning/Design 0 0 0 0 75,000 75,000
Total 0 0 0 0 75,000 75,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 0 0 0 75,000 75,000
Total 0 0 0 0 75,000 75,000
Map
Produced Using Plan-It CIP Software Page 64
2027 thru 2031
Project Details
Lakeville, MN
Project Name Other Projects
Project # P-19
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Department Park Dedication Funding
Description
Park Dedication Fund
Description
This category is intended to include smaller park projects such as adding artwork in the parks, tree planting, security cameras at park facilities, Pickleball courts in
the south side of the City based on the 2026-2036 Parks System Master Plan, and the completion of an ADA Transition Plan.
Expenditures 2027 2028 2029 2030 2031 Total
Other amenities to be determined 0 100,000 300,000 300,000 300,000 1,000,000
ADA Transition Plan 0 275,000 0 0 0 275,000
Security cameras- various park
facilities 30,000 30,000 30,000 0 0 90,000
Tree Planting 15,000 15,000 15,000 15,000 20,000 80,000
Art in the Park 10,000 10,000 10,000 10,000 10,000 50,000
Aronson Park – Field 9
improvements 12,000 0 0 0 0 12,000
Total 67,000 430,000 355,000 325,000 330,000 1,507,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 67,000 430,000 355,000 325,000 330,000 1,507,000
Total 67,000 430,000 355,000 325,000 330,000 1,507,000
Produced Using Plan-It CIP Software Page 65
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks Major Maintenance - Courts
Project # P-20
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Maintenance Department Park Maintenance
Funding
Description
Park Improvement Fund
Description
Includes funding to resurface and restripe basketball, pickleball, and tennis courts.
Expenditures 2027 2028 2029 2030 2031 Total
Oak Shores Park 0 0 0 0 38,000 38,000
Bunker Hill PB & BB Resurfacing 30,000 0 0 0 0 30,000
Pinnacle Reserve Park 0 0 0 22,200 0 22,200
Knob Hill Park 0 0 0 0 22,200 22,200
Cedar Crossing Park 0 12,000 0 0 0 12,000
Jaycee Park 0 10,000 0 0 0 10,000
Chadwick Park 0 0 0 9,000 0 9,000
Fieldstone Park 0 0 0 9,000 0 9,000
Kensington Park 0 0 0 9,000 0 9,000
North Creek Park 0 0 0 2,200 0 2,200
Bassett Park 0 0 2,000 0 0 2,000
Rolling Oaks Park 0 0 2,000 0 0 2,000
Greenridge Park 0 0 2,000 0 0 2,000
Highview Heights 0 0 2,000 0 0 2,000
Foxborough Park 0 0 2,000 0 0 2,000
Hypointe Crossing Park 0 0 2,000 0 0 2,000
Total 30,000 22,000 12,000 51,400 60,200 175,600
Funding Sources 2027 2028 2029 2030 2031 Total
Park & Trail Improvement Fund 30,000 22,000 12,000 51,400 60,200 175,600
Total 30,000 22,000 12,000 51,400 60,200 175,600
Produced Using Plan-It CIP Software Page 66
2027 thru 2031
Project Details
Lakeville, MN
Project Name Parks - New Parking Lots & Expansions
Project # P-24
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Funding
Description
Park Dedication Fund
Description
Parking lot expansion at Grand Paririe Park is needed due to current high volume use estimates including Splashpad, Pickelball, Grandstand and the Athletic
Decks.
Expenditures 2027 2028 2029 2030 2031 Total
Grand Prairie Park 530,000 0 0 0 0 530,000
Total 530,000 0 0 0 0 530,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 530,000 0 0 0 0 530,000
Total 530,000 0 0 0 0 530,000
Map
Produced Using Plan-It CIP Software Page 67
2027 thru 2031
Project Details
Lakeville, MN
Project Name S.W. Corner of 210th Street & I-35
Project # P-25
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type New construction Department Park Dedication
Description
The existing Parks, Trails and Open Spaces plan calls for a future neighborhood park in the area of 210th street and I-35.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 0 900,000 900,000
Planning/Design 0 0 0 75,000 25,000 100,000
Total 0 0 0 75,000 925,000 1,000,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 0 0 75,000 925,000 1,000,000
Total 0 0 0 75,000 925,000 1,000,000
Map
Produced Using Plan-It CIP Software Page 68
2027 thru 2031
Project Details
Lakeville, MN
Project Name Kensington Park Athletic Deck and Parking Lot
Project # P-26
Contact Mark Kruse, Parks Superintendent Cost Type Parks
Type Reconstruction/Maintenance Department Park Dedication
Funding
Description
Park & Trail Improvement Fund
Expenditures 2027 2028 2029 2030 2031 Total
Parking lot 0 0 200,000 0 0 200,000
Kensington Park Athletic Deck
Improvements 0 0 100,000 0 0 100,000
Planning/Design 0 30,000 0 0 0 30,000
Total 0 30,000 300,000 0 0 330,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 0 0 200,000 0 0 200,000
Park & Trail Improvement Fund 0 30,000 100,000 0 0 130,000
Total 0 30,000 300,000 0 0 330,000
Produced Using Plan-It CIP Software Page 69
2027 thru 2031
Project Details
Lakeville, MN
Project Name Bunker Hill Athletic Decks
Project # P-27
Contact Joseph Masiarchin, Parks Director Cost Type Parks
Type Expansion Department Park Dedication
Funding
Description
Park Dedication Fund
Description
Renovate existing park conditions to create two new athletic decks, a new expansion of the parking lot, and adding irrigation to all athletic fields. Project will also
include rennovation of existing baseball field and all fencing.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 750,000 0 0 0 750,000
Planning/Design 70,000 0 0 0 0 70,000
Total 70,000 750,000 0 0 0 820,000
Funding Sources 2027 2028 2029 2030 2031 Total
Park Dedication Fund 70,000 480,000 0 0 0 550,000
Park & Trail Improvement Fund 0 270,000 0 0 0 270,000
Total 70,000 750,000 0 0 0 820,000
Produced Using Plan-It CIP Software Page 70
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology - General Government
Project # T-01
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 40,941 12,792 9,704 39,465 11,210 114,112
Total 40,941 12,792 9,704 39,465 11,210 114,112
Funding Sources 2027 2028 2029 2030 2031 Total
Technology Fund 40,941 12,792 9,704 39,465 11,210 114,112
Total 40,941 12,792 9,704 39,465 11,210 114,112
Produced Using Plan-It CIP Software Page 71
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Public Safety
Project # T-02
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 127,734 120,300 221,883 102,723 46,062 618,702
Total 127,734 120,300 221,883 102,723 46,062 618,702
Funding Sources 2027 2028 2029 2030 2031 Total
Technology Fund 127,734 120,300 221,883 102,723 46,062 618,702
Total 127,734 120,300 221,883 102,723 46,062 618,702
Produced Using Plan-It CIP Software Page 72
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Public Works
Project # T-03
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 6,961 5,907 20,094 16,499 18,473 67,934
Total 6,961 5,907 20,094 16,499 18,473 67,934
Funding Sources 2027 2028 2029 2030 2031 Total
Technology Fund 6,961 5,907 20,094 16,499 18,473 67,934
Total 6,961 5,907 20,094 16,499 18,473 67,934
Produced Using Plan-It CIP Software Page 73
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Arenas
Project # T-04
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for Lakeville Arenas.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 1,534 7,599 3,628 3,696 4,384 20,841
Total 1,534 7,599 3,628 3,696 4,384 20,841
Funding Sources 2027 2028 2029 2030 2031 Total
Arenas 1,534 7,599 3,628 3,696 4,384 20,841
Total 1,534 7,599 3,628 3,696 4,384 20,841
Produced Using Plan-It CIP Software Page 74
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Communications
Project # T-05
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 2,440 0 0 823 3,392 6,655
Total 2,440 0 0 823 3,392 6,655
Funding Sources 2027 2028 2029 2030 2031 Total
Communications Fund 2,440 0 0 823 3,392 6,655
Total 2,440 0 0 823 3,392 6,655
Produced Using Plan-It CIP Software Page 75
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Liquor
Project # T-06
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology Funding
Description
Liquor Fund
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - IT infrastructure 51,500 53,598 0 0 0 105,098
Technology - computers/hardware
acquisitions 68,783 0 0 17,431 6,146 92,360
Total 120,283 53,598 0 17,431 6,146 197,458
Funding Sources 2027 2028 2029 2030 2031 Total
Liquor Fund 120,283 53,598 0 17,431 6,146 197,458
Total 120,283 53,598 0 17,431 6,146 197,458
Produced Using Plan-It CIP Software Page 76
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Environmental Resources
Project # T-07
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 1,946 4,255 0 823 1,099 8,123
Total 1,946 4,255 0 823 1,099 8,123
Funding Sources 2027 2028 2029 2030 2031 Total
Environmental Resources Fund 1,946 4,255 0 823 1,099 8,123
Total 1,946 4,255 0 823 1,099 8,123
Produced Using Plan-It CIP Software Page 77
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Utilities
Project # T-08
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Description
The Technology Fund accounts for the accumulation and disbursement of funds for the purchase of technology equipment for the City.
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 16,536 7,314 1,845 1,221 1,024 27,940
Total 16,536 7,314 1,845 1,221 1,024 27,940
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 8,268 3,657 923 611 512 13,971
Sanitary Sewer Operating Fund 8,268 3,657 922 610 512 13,969
Total 16,536 7,314 1,845 1,221 1,024 27,940
Produced Using Plan-It CIP Software Page 78
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology- Parks & recreation
Project # T-09
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Expenditures 2027 2028 2029 2030 2031 Total
Technology - computers/hardware
acquisitions 11,827 21,377 15,184 3,552 12,472 64,412
Total 11,827 21,377 15,184 3,552 12,472 64,412
Funding Sources 2027 2028 2029 2030 2031 Total
Technology Fund 11,827 21,377 15,184 3,552 12,472 64,412
Total 11,827 21,377 15,184 3,552 12,472 64,412
Produced Using Plan-It CIP Software Page 79
2027 thru 2031
Project Details
Lakeville, MN
Project Name Technology-Network infrastructure
Project # T-10
Contact Trevor Stewart, IT Manager Cost Type Technology
Type Technology
Expenditures 2027 2028 2029 2030 2031 Total
Technology - IT infrastructure 183,513 496,879 249,660 180,720 44,389 1,155,161
Total 183,513 496,879 249,660 180,720 44,389 1,155,161
Funding Sources 2027 2028 2029 2030 2031 Total
Technology Fund 134,875 365,188 183,491 132,823 32,624 849,001
Liquor Fund 26,084 70,624 35,486 25,687 6,309 164,190
Water Operating Fund 8,106 21,947 11,027 7,982 1,961 51,023
Sanitary Sewer Operating Fund 8,105 21,946 11,027 7,982 1,960 51,020
Communications Fund 3,492 9,455 4,751 3,439 845 21,982
Environmental Resources Fund 2,851 7,719 3,878 2,807 690 17,945
Total 183,513 496,879 249,660 180,720 44,389 1,155,161
Produced Using Plan-It CIP Software Page 80
2027 thru 2031
Project Details
Lakeville, MN
Project Name Freight Rail Car Storage Facility
Project # 22-16
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Other Department Engineering
Funding
Description
Improvement Construction
Description
Programmed for 2027 construction. The City was awarded $750,000 in Federal Funding (Fiscal Year 2023) for engineering design and $7,000,000 in State Funding
for construction. Project includes construction of a 90-car storage yard, and a 30-car transload facility within the City’s industrial parks, south of CSAH 70.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 7,000,000 0 0 0 0 7,000,000
Engineering/Design/Other costs 475,000 0 0 0 0 475,000
Total 7,475,000 0 0 0 0 7,475,000
Funding Sources 2027 2028 2029 2030 2031 Total
Other funding- State 7,000,000 0 0 0 0 7,000,000
Other funding- Federal 325,000 0 0 0 0 325,000
Improvement Construction Fund 150,000 0 0 0 0 150,000
Stormwater Infrastructure Fund 0 0 0 0 0 0
Total 7,475,000 0 0 0 0 7,475,000
Map
Produced Using Plan-It CIP Software Page 81
Produced Using Plan-It CIP Software Page 82
2027 thru 2031
Project Details
Lakeville, MN
Project Name Holyoke/Highview Avenue Reconstruction
Project # 25-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Rehabilitation Department Engineering
Funding
Description
Municipal State Aid
Description
Phase I: Heritage Drive to South of 190th Street
Phase II: South of 190th Street to Dodd Boulevard/CSAH 9
Phase I programmed for 2029 construction. Project includes road rehabilitation and modernization, intersection improvements and a pedestrian
underpass. Phase II programmed for 2032 construction. Project includes road rehabilitation and modernization and intersection improvements and a
pedestrian underpass.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 0 6,155,000 6,155,000
Construction- New trails 0 0 0 0 1,200,000 1,200,000
Construction- Stormwater
infrastructure (new) 0 0 0 0 1,035,000 1,035,000
Trail costs (rehabilitation/
reconstruction) 0 0 0 0 200,000 200,000
Construction- Sanitary Sewer
infrastructure (repair/replace) 0 0 0 0 145,000 145,000
Construction- Water infrastructure
(repair/replace) 0 0 0 0 75,000 75,000
Streetlight costs 0 0 0 0 50,000 50,000
Total 0 0 0 0 8,860,000 8,860,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 0 0 5,147,400 5,147,400
Park Dedication Fund 0 0 0 0 1,200,000 1,200,000
Stormwater Infrastructure Fund 0 0 0 0 1,035,000 1,035,000
Escrows 0 0 0 0 657,600 657,600
MSA/MSA Bonds - Sp. Assess. 0 0 0 0 350,000 350,000
Park & Trail Improvement Fund 0 0 0 0 200,000 200,000
Sanitary Sewer Operating Fund 0 0 0 0 145,000 145,000
Water Operating Fund 0 0 0 0 75,000 75,000
Streetlight Operating Fund 0 0 0 0 50,000 50,000
Total 0 0 0 0 8,860,000 8,860,000
Produced Using Plan-It CIP Software Page 83
Map
Produced Using Plan-It CIP Software Page 84
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 9 Modernization (210th St - Heritage Dr)
Project # 26-04
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Modernization Department Engineering
Funding
Description
Municipal State Aid County Project # 09-065
SP/SAP # 188-020-034; 019-609-029; 019-650-026 JPA # 24020
County Billing
Contact
John Sass County Billing
Email
John.Sass@co.dakota.mn.us
Description
Modernization of CSAH 9 (Dodd Boulevard) between 210th Street and Heritage Drive. Project includes a 2-lane divided highway and trails along both sides, with
drainage and safety improvements. Includes CSAH 50 intersection and signal system replacement, with a roundabout.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 12,500,968 0 0 0 0 12,500,968
Mill and Overlay on CR50
(CSAH9-Holyoke Ave) 350,000 0 0 0 0 350,000
County to repay City ROW costs-
Scheffler property 276,561 0 0 0 0 276,561
Total 13,127,529 0 0 0 0 13,127,529
Funding Sources 2027 2028 2029 2030 2031 Total
Dakota County 12,243,000 0 0 0 0 12,243,000
Stormwater Infrastructure Fund 380,000 0 0 0 0 380,000
Escrows 292,029 0 0 0 0 292,029
Park Dedication Fund 155,000 0 0 0 0 155,000
General Fund 40,000 0 0 0 0 40,000
Streetlight Operating Fund 10,000 0 0 0 0 10,000
Sanitary Sewer Operating Fund 5,000 0 0 0 0 5,000
Water Operating Fund 2,500 0 0 0 0 2,500
Total 13,127,529 0 0 0 0 13,127,529
Map
Produced Using Plan-It CIP Software Page 85
2027 thru 2031
Project Details
Lakeville, MN
Project Name Interstate 35/CSAH 50 Interchange Reconstruction
Project # 26-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Interchange Reconstruction Department Engineering
Funding
Description
Municipal State Aid County Project # 50-033
SP/SAP # 019-650-021 JPA # 24276;
County Billing
Contact
Susan Wimberly County Billing
Email
Susan.Wimberly@CO.DAKOTA.MN.US
Description
Reconstruction of the interchange at I-35 and CSAH 5/50 (Kenwood Trail). The existing interchange is deficient in capacity, sight distance and turn lanes, resulting in
delays and safety issues. This project includes replacement of the I-35 bridges over CSAH 5/50 and construction of a northbound auxiliary lane along I-35 between
CSAH 5/50 and CSAH 46. This project is not led by the City, so only the City's share of costs is shown, other than repayment of RALF loans recently used to purchase
right of way in the project area.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 1,803,659 0 0 1,803,659
Repay RALF Loan (County share of
repayment of 2017 and 2021/2022
RALF Loans)
1,478,161 0 0 0 0 1,478,161
Right of Way- Acquisition/
Professional fees 0 675,000 0 0 0 675,000
Engineering/Design/Other costs 554,536 0 0 0 0 554,536
Repay RALF Loan (City share of
repayment of 2017 and 2021/2022
RALF Loans)
260,852 0 0 0 0 260,852
Fiber conduit (Weather Siren) 0 0 10,000 0 0 10,000
Fiber Conduit (Park Dedication
Fund) 0 0 10,000 0 0 10,000
Fiber Conduit (Lift Station) 0 0 10,000 0 0 10,000
Fiber conduit (Well/tower) 0 0 10,000 0 0 10,000
Total 2,293,549 675,000 1,843,659 0 0 4,812,208
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 815,388 675,000 1,248,133 0 0 2,738,521
Dakota County 1,478,161 0 0 0 0 1,478,161
Stormwater Infrastructure Fund 0 0 232,672 0 0 232,672
Water Trunk Fund 0 0 130,845 0 0 130,845
Park Dedication Fund 0 0 129,041 0 0 129,041
Sanitary Sewer Trunk Fund 0 0 92,968 0 0 92,968
General Fund 0 0 10,000 0 0 10,000
Total 2,293,549 675,000 1,843,659 0 0 4,812,208
Produced Using Plan-It CIP Software Page 86
Map
Produced Using Plan-It CIP Software Page 87
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 50/CSAH 60 RAB Modifications
Project # 26-08
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Maintenance/Improvement Department Engineering
Funding
Description
Municipal State Aid County Project # 50-038
SP/SAP # TBD JPA # TBD
Description
County-led safety improvement designed to improve pedestrian, bicyclist and vehicle safety. Project includes pavement markings and sign modifications.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 1 0 0 0 0 1
Total 1 0 0 0 0 1
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 1 0 0 0 0 1
Total 1 0 0 0 0 1
Map
Produced Using Plan-It CIP Software Page 88
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 5 and Kenyon Avenue Traffic Signal
Project # 27-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 05-060
SP/SAP # 019-605-037; 1980-100 JPA # 24276
County Billing
Contact
Susan Wimberly County Billing
Email
Susan.Wimberly@CO.DAKOTA.MN.US
Description
New traffic signal designed to alleviate congestion and optimize intersection operations. County-led project includes geometric improvements and pavement
markings. City cost-share per Dakota County Highway Cost Share Policy F.4.1 (Dakota County 2040 Transportation Plan),
Expenditures 2027 2028 2029 2030 2031 Total
Construction 141,000 0 0 0 0 141,000
Total 141,000 0 0 0 0 141,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 141,000 0 0 0 0 141,000
Total 141,000 0 0 0 0 141,000
Map
Produced Using Plan-It CIP Software Page 89
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 31 and CSAH 46 Traffic Signal
Project # 27-06
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 31-125
SP/SAP # TBD JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
Replacement of existing traffic signal that is approaching the end of its useful life. City cost-share per Dakota County Highway Cost Share Policy F.4.2
(Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 0 0 0
Total 0 0 0 0 0 0
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 0 0 0 0
Total 0 0 0 0 0 0
Map
Produced Using Plan-It CIP Software Page 90
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 60 and Orchard Trail Traffic Signal
Project # 27-07
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 60-029
SP/SAP # TBD JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
New traffic signal designed to alleviate congestion and optimize intersection operations. County-led project includes geometric improvements and pavement
markings. City cost-share per Dakota County Highway Cost Share Policy F.4.1 (Dakota County 2040 Transportation Plan)
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 396,000 0 0 0 396,000
Traffic signal- Design/ROW 80,156 0 0 0 0 80,156
Total 80,156 396,000 0 0 0 476,156
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 80,156 396,000 0 0 0 476,156
Total 80,156 396,000 0 0 0 476,156
Map
Produced Using Plan-It CIP Software Page 91
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 23 M&O (CSAH 9 to CSAH 42)
Project # 27-09
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Maintenance Department Engineering
Funding
Description
Pavement Management County Project # 23-088
SP/SAP # 019-623-042 JPA # 23660
County Billing
Contact
Saeed Kanwar County Billing
Email
Saeed.Kanwar@co.dakota.mn.us
Description
Mill and overlay of CSAH 23 (Cedar Avenue) from CSAH 9 (179th Street) to CSAH 42 (150th Street).The project will include pavement preservation and ADA
improvements.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 53,568 0 0 0 0 53,568
Total 53,568 0 0 0 0 53,568
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 53,568 0 0 0 0 53,568
Total 53,568 0 0 0 0 53,568
Map
Produced Using Plan-It CIP Software Page 92
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 9 and Glacier Way Traffic Signal
Project # 27-11
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 09-069
SP/SAP # 188-150-002 JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
New traffic signal designed to alleviate congestion and optimize intersection operations. City-led project includes geometric improvements and pavement
markings. City cost-share per Dakota County Highway Cost Share Policy F.4.1 (Dakota County 2040 Transportation Plan)
Expenditures 2027 2028 2029 2030 2031 Total
Construction 570,000 0 0 0 0 570,000
Engineering/Design/Other costs 14,500 0 0 0 0 14,500
Total 584,500 0 0 0 0 584,500
Funding Sources 2027 2028 2029 2030 2031 Total
Dakota County 321,475 0 0 0 0 321,475
Municipal State Aid 193,025 0 0 0 0 193,025
Escrows 70,000 0 0 0 0 70,000
Total 584,500 0 0 0 0 584,500
Map
Produced Using Plan-It CIP Software Page 93
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 9/Dodd Blvd Modernization (215th St-210th St)
Project # 28-04
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Modernization Department Engineering
Funding
Description
Municipal State Aid County Project # 09-067
SP/SAP # TBD County Billing
Contact
John Sass
County Billing
Email
John.Sass@co.dakota.mn.us
Description
Modernization of CSAH 9 (Dodd Bouelvard) between CSAH 70 (215th Street) and 210th Street. Project includes a 2-lane divided highway and trails along both sides,
with drainage and safety improvements. City cost-share per Dakota County Highway Cost Share Policy F.1 (Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 4,840,000 0 0 0 4,840,000
Right of Way- Acquisition/
Professional fees 843,750 0 0 0 0 843,750
Total 843,750 4,840,000 0 0 0 5,683,750
Funding Sources 2027 2028 2029 2030 2031 Total
Dakota County 717,188 4,114,000 0 0 0 4,831,188
Municipal State Aid 126,562 500,000 0 0 0 626,562
Escrows 0 196,000 0 0 0 196,000
Park Dedication Fund 0 30,000 0 0 0 30,000
Total 843,750 4,840,000 0 0 0 5,683,750
Map
Produced Using Plan-It CIP Software Page 94
2027 thru 2031
Project Details
Lakeville, MN
Project Name 200th Street (Hamburg to Cedar)
Project # 28-05
Contact Steve Ferraro, Public Works Coordinator Cost Type Transportation
Type Modernization Department Construction Services
Funding
Description
Improvement Construction
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 1,600,000 0 0 0 1,600,000
Engineering/Design/Other costs 75,000 0 0 0 0 75,000
Total 75,000 1,600,000 0 0 0 1,675,000
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds - Taxes
(Streets) 0 784,954 0 0 0 784,954
Water Trunk Fund 0 350,000 0 0 0 350,000
Stormwater Infrastructure Fund 0 250,000 0 0 0 250,000
Escrows 0 115,046 0 0 0 115,046
Sanitary Sewer Trunk Fund 0 100,000 0 0 0 100,000
Improvement Construction Fund 75,000 0 0 0 0 75,000
Total 75,000 1,600,000 0 0 0 1,675,000
Map
Produced Using Plan-It CIP Software Page 95
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 46 and Foliage Avenue Traffic Signal
Project # 28-06
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 46-065
SP/SAP # TBD JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
Replacement of existing traffic signal that is approaching the end of its useful life. City cost-share per Dakota County Highway Cost Share Policy F.4.2
(Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 253,125 0 0 0 253,125
Traffic signal- Design/ROW 52,031 0 0 0 0 52,031
Total 52,031 253,125 0 0 0 305,156
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 52,031 253,125 0 0 0 305,156
Total 52,031 253,125 0 0 0 305,156
Map
Produced Using Plan-It CIP Software Page 96
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 46 and Galaxie Avenue Traffic Signal
Project # 28-07
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 46-064
SP/SAP # TBD JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
Replacement of existing traffic signal that is approaching the end of its useful life. City cost-share per Dakota County Highway Cost Share Policy F.4.2
(Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 253,125 0 0 0 253,125
Traffic signal- Design/ROW 59,063 0 0 0 0 59,063
Total 59,063 253,125 0 0 0 312,188
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 59,063 253,125 0 0 0 312,188
Total 59,063 253,125 0 0 0 312,188
Map
Produced Using Plan-It CIP Software Page 97
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 9 Improvements at 194th St & 190th St
Project # 29-04
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Maintenance/Improvement Department Engineering
Funding
Description
Municipal State Aid County Project # 09-068
SP/SAP # TBD JPA # TBD
Description
Construction of new intersection control at the CSAH 9 (Dodd Boulevard) and 194th Street/Indiana Avenue intersection. City cost-share per Dakota County
Highway Cost Share Policy F.4/F.13 (Dakota County 2040 Transportation Plan).
Construction of directional access median at the CSAH 9 (Dodd Boulevard) and 190th Street intersection. City cost-share per Dakota County Highway Cost Share
Policy F.15 (Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 1,701,000 0 0 1,701,000
Engineering/Design/Other costs 231,000 0 0 0 0 231,000
Right of Way- Acquisition/
Professional fees 0 75,938 0 0 0 75,938
Total 231,000 75,938 1,701,000 0 0 2,007,938
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 231,000 75,938 1,701,000 0 0 2,007,938
Total 231,000 75,938 1,701,000 0 0 2,007,938
Map
Produced Using Plan-It CIP Software Page 98
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 23 Alignment Study (Griffon Tr - 135th St)
Project # 29-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Other Department Engineering
Funding
Description
Municipal State Aid County Project # 23-089
SP/SAP # N/A
Description
Preliminary engineering for CSAH 23 (Cedar Avenue) from Griffon Trail/Upper 164th Street to 135th Street. The corridor study will determine best practices to
manage future traffic growth, and recommend pedestrian and corridor safety improvements, and potential grade-separated intersections.
Expenditures 2027 2028 2029 2030 2031 Total
Engineering/Design/Other costs 0 0 31,500 0 0 31,500
Total 0 0 31,500 0 0 31,500
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 31,500 0 0 31,500
Total 0 0 31,500 0 0 31,500
Map
Produced Using Plan-It CIP Software Page 99
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 46 and Lac Lavon/Interlachen Traffic Signal
Project # 30-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 46-066
SP/SAP # TBD JPA # TBD
County Billing
Contact
Tyler Krage County Billing
Email
Tyler.Krage@co.dakota.mn.us
Description
Replacement of existing traffic signal that is approaching the end of its useful life. City cost-share per Dakota County Highway Cost Share Policy F.4.2
(Dakota County 2040 Transportation Plan).
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 534,375 0 534,375
Traffic signal- Design/ROW 0 104,062 0 0 0 104,062
Total 0 104,062 0 534,375 0 638,437
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 104,062 0 534,375 0 638,437
Total 0 104,062 0 534,375 0 638,437
Map
Produced Using Plan-It CIP Software Page 100
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 50 and Iberia Avenue Traffic Safety Mgmt
Project # 31-05
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Maintenance/Improvement Department Engineering
Funding
Description
Municipal State Aid County Project # 50-XXX
SP/SAP # TBD JPA # TBD
Description
Construction of traffic safety management improvements at CSAH 50 (202nd Street) and Iberia Avenue intersection.
Expenditures 2027 2028 2029 2030 2031 Total
Engineering/Design/Other costs 0 0 0 140,000 0 140,000
Right of Way- Acquisition/
Professional fees 0 0 0 0 67,500 67,500
Total 0 0 0 140,000 67,500 207,500
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 0 140,000 67,500 207,500
Total 0 0 0 140,000 67,500 207,500
Map
Produced Using Plan-It CIP Software Page 101
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 50 Expansion (CSAH 23 - Flagstaff Ave)
Project # 31-07
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Expansion Department Engineering
Funding
Description
Municipal State Aid County Project # 50-039
SP/SAP # TBD JPA # TBD
Description
Expansion of CSAH 50 between CSAH 23 (Cedar Avenue) and Flagstaff Avenue to improve traffic management safety and provide capacity for increasing traffic
volumes. The current cost projections anticipate that the County will lead the project, so only City share of costs is shown. The project includes expansion of a two-
lane road to four lanes, as well as two traffic signal replacements.The current City share of the expansion costs is 15.5%. The current City share of the signal system
costs is 25%. In Fall 2026, the County board is planning to review the cost share policy that could change the City's expansion cost from a 75%-25% cost split to an
85%-15% cost split, which would lower the City cost. The City of Farmington is also participating in the project.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 1,910,000 0 1,910,000
Engineering/Design/Other costs 0 295,000 0 0 0 295,000
Right of Way- Acquisition/
Professional fees 0 0 150,000 0 0 150,000
Total 0 295,000 150,000 1,910,000 0 2,355,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 295,000 150,000 1,910,000 0 2,355,000
Total 0 295,000 150,000 1,910,000 0 2,355,000
Map
Produced Using Plan-It CIP Software Page 102
2027 thru 2031
Project Details
Lakeville, MN
Project Name 195th Street Bridge Replacement
Project # 31-08
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Bridge Department Engineering
Funding
Description
Municipal State Aid County Project # N/A
SP/SAP # TBD JPA # TBD
Description
The 195th Street bridge crossing over I-35 (Bridge 19841) will need to be reconstructed to accommodate future traffic as development west of I-35, Kenrick Avenue
and Keokuk Avenue occurs.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 0 0 0 2,000,000 2,000,000
Total 0 0 0 0 2,000,000 2,000,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 0 0 2,000,000 2,000,000
Total 0 0 0 0 2,000,000 2,000,000
Produced Using Plan-It CIP Software Page 103
2027 thru 2031
Project Details
Lakeville, MN
Project Name CSAH 60 and Judicial Road Traffic Signal
Project # 31-09
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Traffic Signal Department Engineering
Funding
Description
Municipal State Aid County Project # 60-XXX
SP/SAP # TBD JPA # TBD
Description
• New traffic signal system designed to alleviate congestion and optimize intersection operations.
• Includes geometric improvements and pavement markings.
• City-led project
• Owned/maintained by Dakota County/Scott County
Expenditures 2027 2028 2029 2030 2031 Total
Traffic signal- Design/ROW 0 0 0 50,000 0 50,000
Total 0 0 0 50,000 0 50,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 0 0 50,000 0 50,000
Total 0 0 0 50,000 0 50,000
Map
Produced Using Plan-It CIP Software Page 104
2027 thru 2031
Project Details
Lakeville, MN
Project Name Kenrick Ave Extension (181st St-176th St)
Project # P28-16
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Extension Department Engineering
Funding
Description
Municipal State Aid
Description
Kenrick Ave will need to be extended to accomodate future traffic as development occurs. Construction would coincide with development of the parcels, and be
primarily funded by the developer.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 2,500,000 0 0 0 2,500,000
Total 0 2,500,000 0 0 0 2,500,000
Funding Sources 2027 2028 2029 2030 2031 Total
Municipal State Aid 0 2,500,000 0 0 0 2,500,000
Total 0 2,500,000 0 0 0 2,500,000
Map
Produced Using Plan-It CIP Software Page 105
2027 thru 2031
Project Details
Lakeville, MN
Project Name Pavement Management - Maintenance
Project # XX-01
Contact Steve Ferraro, Public Works Coordinator Cost Type Transportation
Type Maintenance Department Construction Services
Funding
Description
Pavement Management
Description
Annual preventive maintenance program designed to protect the City’s investment in public street/road infrastructure assets. Best management practices include
crack sealing, seal coating, surface sealing, mill and overlay and roadway patching. Associated maintenance activities such as curb and gutter repair, drain tile repair,
pavement marking painting, and stormwater infrastructure repair are included. Maintenance is financed primarily through property taxes. A portion of the City’s
annual Municipal State Aid (MSA) allotment is applied toward street/road maintenance, with the remaining MSA balance applied toward MSA-designated projects
and debt payments on previously issued bonds supporting these projects. The remaining principal and interest balances due on MSA-supported bonds at the end
of 2026 will be $2,815,000. The final principal payment will be made in 2036.
Expenditures 2027 2028 2029 2030 2031 Total
Patching & Minor Overlays 1,660,000 1,930,000 1,900,000 1,935,000 2,010,000 9,435,000
Surface Sealing 275,000 375,000 375,000 375,000 375,000 1,775,000
Crack Seal 200,000 200,000 200,000 225,000 225,000 1,050,000
Construction- Water infrastructure
(repair/replace) 100,000 100,000 100,000 100,000 100,000 500,000
Construction- Sanitary Sewer
infrastructure (repair/replace) 100,000 100,000 100,000 100,000 100,000 500,000
Sidewalk ADA 65,000 65,000 65,000 65,000 65,000 325,000
Safety Improvements 50,000 50,000 50,000 50,000 50,000 250,000
Velocity Patching 50,000 50,000 50,000 50,000 50,000 250,000
Concrete Curb & Draintile 30,000 30,000 30,000 40,000 40,000 170,000
County Road Stormwater
Infrastructure 30,000 30,000 30,000 30,000 30,000 150,000
Bridge Inspections & Repairs 20,000 20,000 20,000 20,000 20,000 100,000
Total 2,580,000 2,950,000 2,920,000 2,990,000 3,065,000 14,505,000
Funding Sources 2027 2028 2029 2030 2031 Total
Pavement Management Fund 2,380,000 2,750,000 2,720,000 2,790,000 2,865,000 13,505,000
Sanitary Sewer Operating Fund 100,000 100,000 100,000 100,000 100,000 500,000
Water Operating Fund 100,000 100,000 100,000 100,000 100,000 500,000
Total 2,580,000 2,950,000 2,920,000 2,990,000 3,065,000 14,505,000
Produced Using Plan-It CIP Software Page 106
2027 thru 2031
Project Details
Lakeville, MN
Project Name Street Reconstruction
Project # XX-02
Contact Steve Ferraro, Public Works Coordinator Cost Type Transportation
Type Reconstruction/Maintenance Department Construction Services
Funding
Description
Improvement Construction
Description
Annual program designed to extend street life, minimize total life cycle costs, and improve local streets when routine maintenance costs exceed the cost-benefit
of the investment or streets approach the end of their life cycle. Citywide OCI goal for local streets is 75. Both rehabilitation (surface sealing/mill and overlay) and
reconstruction (reclamation) practices are utilized.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 4,135,000 5,670,000 5,775,000 4,105,000 4,205,000 23,890,000
Construction- Water infrastructure
(repair/replace) 350,000 500,000 650,000 250,000 250,000 2,000,000
Construction- Sanitary Sewer
infrastructure (repair/replace) 250,000 250,000 250,000 250,000 250,000 1,250,000
Construction- Stormwater
infrastructure (new) 105,000 250,000 250,000 105,000 105,000 815,000
Total 4,840,000 6,670,000 6,925,000 4,710,000 4,810,000 27,955,000
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds - Taxes
(Streets) 4,008,000 4,450,000 4,365,000 4,105,000 4,205,000 21,133,000
G.O. Improvement Bonds - Sp.
Assess. 0 1,220,000 1,410,000 0 0 2,630,000
Water Operating Fund 350,000 500,000 650,000 250,000 250,000 2,000,000
Sanitary Sewer Operating Fund 250,000 250,000 250,000 250,000 250,000 1,250,000
Stormwater Infrastructure Fund 105,000 250,000 250,000 105,000 105,000 815,000
Other cost share arrangement-
Credit River (Judicial Rd) 127,000 0 0 0 0 127,000
Total 4,840,000 6,670,000 6,925,000 4,710,000 4,810,000 27,955,000
Produced Using Plan-It CIP Software Page 107
2027 thru 2031
Project Details
Lakeville, MN
Project Name Collector Roadway Rehabilitation
Project # XX-03
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Rehabilitation Department Engineering
Funding
Description
Improvement Construction
Description
This annual program keeps collector and arterial roads in good driving condition and helps the City avoid the higher cost of letting them fail completely. Streets are
treated before minor repairs stop being cost-effective or before a road reaches the end of its useful life, typically through a mill and overlay or, for roads in worse
condition, reclamation. The City's goal is to keep the average condition of collector and arterial roads at a rating of 75 out of 100.
Expenditures 2027 2028 2029 2030 2031 Total
Streets/Storm- Construction/
Engineering/Other 3,097,260 2,246,102 2,176,784 890,932 838,203 9,249,281
Construction- Water infrastructure
(repair/replace) 100,000 100,000 100,000 100,000 100,000 500,000
Construction- Sanitary Sewer
infrastructure (repair/replace) 25,000 25,000 25,000 25,000 25,000 125,000
Construction- New trails 100,000 0 0 0 0 100,000
Total 3,322,260 2,371,102 2,301,784 1,015,932 963,203 9,974,281
Funding Sources 2027 2028 2029 2030 2031 Total
G.O. Improvement Bonds - Taxes
(Streets) 2,767,183 2,246,102 2,132,047 890,932 838,203 8,874,467
Water Operating Fund 100,000 100,000 100,000 100,000 100,000 500,000
G.O. Improvement Bonds - Sp.
Assess. 330,077 0 44,737 0 0 374,814
Sanitary Sewer Operating Fund 25,000 25,000 25,000 25,000 25,000 125,000
Park Dedication Fund 100,000 0 0 0 0 100,000
Total 3,322,260 2,371,102 2,301,784 1,015,932 963,203 9,974,281
Produced Using Plan-It CIP Software Page 108
2027 thru 2031
Project Details
Lakeville, MN
Project Name County Pavement Preservation/City Utility Repairs
Project # XX-10
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Maintenance Department Engineering
Funding
Description
Water Operating Fund County Project # TBD
SP/SAP # N/A JPA # TBD
Description
Storm sewer, sanitary sewer and water repairs completed in conjunctions with annual Dakota County pavement preservation program.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 25,000 0 0 0 0 25,000
Construction- Water infrastructure
(repair/replace) 5,000 0 0 0 0 5,000
Construction- Sanitary Sewer
infrastructure (repair/replace) 5,000 0 0 0 0 5,000
Total 35,000 0 0 0 0 35,000
Funding Sources 2027 2028 2029 2030 2031 Total
Pavement Management Fund 25,000 0 0 0 0 25,000
Water Operating Fund 5,000 0 0 0 0 5,000
Sanitary Sewer Operating Fund 5,000 0 0 0 0 5,000
Total 35,000 0 0 0 0 35,000
Produced Using Plan-It CIP Software Page 109
2027 thru 2031
Project Details
Lakeville, MN
Project Name Lake Marion Greenway
Project # XX-15
Contact Zach Johnson, City Engineer Cost Type Transportation
Type Greenway Department Park Dedication
Funding
Description
Park Dedication Fund County Project # 2000453
SP/SAP # N/A JPA # TBD
County Billing
Contact
Tony Wotzka County Billing
Email
Tony.Wotzka@CO.DAKOTA.MN.US
Description
Trail improvements to existing local network in coordination with jurisdictional transfer to Dakota County for Lake Marion Greenway.
Expenditures 2027 2028 2029 2030 2031 Total
Segment C- Downtown to Cedar
Ave 0 0 325,000 1,800,000 0 2,125,000
Segment D- Murphy Hanrehan
Park to Ritter Farm Park 0 0 80,000 1,080,000 0 1,160,000
Segment B- Downtown 567,500 0 0 0 0 567,500
Segment E- CSAH 23 to CSAH 31 0 150,000 0 0 0 150,000
Total 567,500 150,000 405,000 2,880,000 0 4,002,500
Funding Sources 2027 2028 2029 2030 2031 Total
Dakota County 0 0 344,250 2,448,000 0 2,792,250
Park Dedication Fund 0 150,000 60,750 432,000 0 642,750
Pavement Management Fund 317,500 0 0 0 0 317,500
Park & Trail Improvement Fund 250,000 0 0 0 0 250,000
Total 567,500 150,000 405,000 2,880,000 0 4,002,500
Produced Using Plan-It CIP Software Page 110
2027 thru 2031
Project Details
Lakeville, MN
Project Name Lake Marion Greenway
Project # XX-15
Cost Type Transportation Contact Zach Johnson, City Engineer
Produced Using Plan-It CIP Software Page 111
2027 thru 2031
Project Details
Lakeville, MN
Project Name Sanitary Sewer Trunk Improvements
Project # U-01
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Type Maintenance/Improvement Department Utilities
Funding
Description
Sewer Fund
Description
The Sanitary Sewer Plan anticipates the extension of sanitary sewer trunk facilities to serve areas of anticipated/planned growth. Lift Station 26 is under construction
in 2025. Timing of sanitary sewer trunk system improvements subject to growth rate and location of planned land development.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 75,000 75,000 75,000 75,000 75,000 375,000
Total 75,000 75,000 75,000 75,000 75,000 375,000
Funding Sources 2027 2028 2029 2030 2031 Total
Sanitary Sewer Trunk Fund 75,000 75,000 75,000 75,000 75,000 375,000
Total 75,000 75,000 75,000 75,000 75,000 375,000
Produced Using Plan-It CIP Software Page 112
2027 thru 2031
Project Details
Lakeville, MN
Project Name Sanitary Sewer Lift Station Rehabilitation
Project # U-02
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Type Maintenance Department Utilities
Funding
Description
Equipment Fund
Description
Lift station service life is 12-15 years. Pumps, motors and equipment are inspected, repaired and replaced to ensure uninterrupted service. Lift stations are
inspected/cleaned annually and scheduled for rehabilitation every 12-15 years.
Expenditures 2027 2028 2029 2030 2031 Total
Lift Station 7 175,000 0 0 0 0 175,000
Lift Station 5 0 0 100,000 0 0 100,000
Lift Station 23 0 0 0 0 100,000 100,000
Lift Station 6 0 100,000 0 0 0 100,000
Lift Station 3 80,000 0 0 0 0 80,000
Lift Station 22 0 75,000 0 0 0 75,000
Lift Station 12 0 0 0 40,000 0 40,000
Lift Station 19 0 0 40,000 0 0 40,000
Lift Station 13 0 0 0 40,000 0 40,000
Lift Station 11 0 0 40,000 0 0 40,000
Total 255,000 175,000 180,000 80,000 100,000 790,000
Funding Sources 2027 2028 2029 2030 2031 Total
Sanitary Sewer Operating Fund 255,000 175,000 180,000 80,000 100,000 790,000
Total 255,000 175,000 180,000 80,000 100,000 790,000
Produced Using Plan-It CIP Software Page 113
2027 thru 2031
Project Details
Lakeville, MN
Project Name Sanitary Sewer Inflow/Infiltration Maintenance
Project # U-03
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Equipment Fund
Description
Annual program designed to manage peak discharge rates and maintain/extend the overall service life of the sanitary sewer collection system through rehabilitating
infrastructure susceptible to inflow and infiltration (groundwater). Public sanitary sewer infrastructure is inspected (televising 250,000 pipe-feet/year) and cleaned
(jetting 75 pipe-miles/year) to maintain the integrity and function of the sanitary sewer collection system.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 575,000 575,000 575,000 575,000 575,000 2,875,000
Total 575,000 575,000 575,000 575,000 575,000 2,875,000
Funding Sources 2027 2028 2029 2030 2031 Total
Sanitary Sewer Operating Fund 575,000 575,000 575,000 575,000 575,000 2,875,000
Total 575,000 575,000 575,000 575,000 575,000 2,875,000
Produced Using Plan-It CIP Software Page 114
2027 thru 2031
Project Details
Lakeville, MN
Project Name Well Construction
Project # U-04
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Equipment Fund
Description
The Water Plan provides guidance in identifying future water system facilities required to serve areas of planned land development. Well #23 is currently under
construction and will be brought online in 2025, and Wells 24 and 25 are programmed for 2028 construction. Construction timing and well location subject to
population demand/water needs. The Wellhead and Source Water Protection Plan must be amended prior to receiving a Minnesota Department of Health permit.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 1,800,000 0 0 0 1,800,000
Engineering/Design/Other costs 100,000 0 0 0 50,000 150,000
Total 100,000 1,800,000 0 0 50,000 1,950,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Trunk Fund 100,000 1,800,000 0 0 50,000 1,950,000
Total 100,000 1,800,000 0 0 50,000 1,950,000
Produced Using Plan-It CIP Software Page 115
2027 thru 2031
Project Details
Lakeville, MN
Project Name Watermain Trunk Extensions
Project # U-05
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Water Trunk Fund
Description
The Water Plan anticipates the extension of watermain trunk facilities to serve areas of planned land development. Timing of watermain trunk system improvements
subject to growth rate and location of planned land development.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 265,000 265,000 265,000 265,000 265,000 1,325,000
Total 265,000 265,000 265,000 265,000 265,000 1,325,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Trunk Fund 265,000 265,000 265,000 265,000 265,000 1,325,000
Total 265,000 265,000 265,000 265,000 265,000 1,325,000
Produced Using Plan-It CIP Software Page 116
2027 thru 2031
Project Details
Lakeville, MN
Project Name Water Distribution Features
Project # U-06
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Water Trunk Fund
Description
The Water Plan provides guidance in identifying future water system features required to serve areas of planned land development, including features to either
reduce or boost the water pressure due to the elevation of new development. New pressure reducing valves are programmed for 2026, 2028 and 2030 construction.
Construction timing and location subject to growth rate and location of planned land development.
Expenditures 2027 2028 2029 2030 2031 Total
Construction 0 150,000 0 150,000 0 300,000
Total 0 150,000 0 150,000 0 300,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Trunk Fund 0 150,000 0 150,000 0 300,000
Total 0 150,000 0 150,000 0 300,000
Produced Using Plan-It CIP Software Page 117
2027 thru 2031
Project Details
Lakeville, MN
Project Name Well and Pump Rehabilitation
Project # U-07
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Equipment Fund
Description
Pumps, motors and equipment are inspected, repaired and replaced to ensure uninterrupted, efficient service and a water system operating at maximum pumping
capacity. City wells provide water for on-demand distribution system (24 hours/day, 7 days/week). Multiple starts/stops place tremendous stress on the motors and
pump components and constant water exposure can lead to corrosion. Well and pumps are scheduled for rehabilitation every 8-10 years, based on pump type.
Expenditures 2027 2028 2029 2030 2031 Total
Well 21 125,000 0 0 0 0 125,000
Well 4 0 0 0 0 125,000 125,000
Well 11 0 0 125,000 0 0 125,000
Well 10 0 125,000 0 0 0 125,000
Well 22 125,000 0 0 0 0 125,000
Well 14 0 0 0 0 125,000 125,000
Well 8 0 0 125,000 0 0 125,000
Well 12 0 0 0 125,000 0 125,000
Well 2 0 0 0 0 125,000 125,000
Well 9 0 0 125,000 0 0 125,000
Total 250,000 125,000 375,000 125,000 375,000 1,250,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 250,000 125,000 375,000 125,000 375,000 1,250,000
Total 250,000 125,000 375,000 125,000 375,000 1,250,000
Produced Using Plan-It CIP Software Page 118
2027 thru 2031
Project Details
Lakeville, MN
Project Name Tower and Reservoir Maintenance
Project # U-08
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Type Maintenance Department Utilities
Funding
Description
Water Operating Fund
Description
Maintenance program designed to manage, preserve and protect investment in water storage tanks (interior and exterior). Maintenance removes buildup, dirt/
dust, and extends the life of the coating system, minimizing total lifecycle costs.
Expenditures 2027 2028 2029 2030 2031 Total
Fairfield Water Tower 0 0 0 1,000,000 0 1,000,000
Construction 0 0 150,000 0 0 150,000
Total 0 0 150,000 1,000,000 0 1,150,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 0 0 150,000 1,000,000 0 1,150,000
Total 0 0 150,000 1,000,000 0 1,150,000
Produced Using Plan-It CIP Software Page 119
2027 thru 2031
Project Details
Lakeville, MN
Project Name Water meter replacement
Project # U-09
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Department Utilities Funding
Description
Equipment Fund
Description
Annual program designed to replace residential and commercial water meters approaching the end of their life cycle, to ensure accurate water monitoring use
data for Minnesota Department of Natural Resources reporting. Program goal is 1,200 water meter replacements per year (based on meter age) with the intent of
meeting/maintaining a 20-year service life. Routine water meter replacement is completed by City Utilities staff.
Expenditures 2027 2028 2029 2030 2031 Total
Equipment purchase 350,000 400,000 425,000 425,000 425,000 2,025,000
Total 350,000 400,000 425,000 425,000 425,000 2,025,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 350,000 400,000 425,000 425,000 425,000 2,025,000
Total 350,000 400,000 425,000 425,000 425,000 2,025,000
Produced Using Plan-It CIP Software Page 120
2027 thru 2031
Project Details
Lakeville, MN
Project Name Fiber Optic Cable Connection
Project # U-10
Contact Shane Quade, Utilities Superintendent Cost Type Utility
Type Other Department Utilities
Funding
Description
Equipment Fund
Description
Extension of fiber optic cable to remote utility sites (lift stations, wells) for better and more reliable communication.
Expenditures 2027 2028 2029 2030 2031 Total
Fiber conduit (Well/tower) 37,000 40,000 30,000 40,000 40,000 187,000
Fiber Conduit (Lift Station) 25,000 30,000 30,000 40,000 40,000 165,000
Total 62,000 70,000 60,000 80,000 80,000 352,000
Funding Sources 2027 2028 2029 2030 2031 Total
Water Operating Fund 37,000 40,000 30,000 40,000 40,000 187,000
Sanitary Sewer Operating Fund 25,000 30,000 30,000 40,000 40,000 165,000
Total 62,000 70,000 60,000 80,000 80,000 352,000
Produced Using Plan-It CIP Software Page 121
CITY OF LAKEVILLE
STREET RECONSTRUCTION PLAN
Project # Project description:2027 2028 2029 2030 2031 Total
XX-02 Street Reconstruction 6,775,183 7,481,056 6,497,047 4,995,932 5,043,203 30,792,421
XX-03 Collector Rehabilitation 330,077 1,220,000 1,454,737 - - 3,004,814
- - - - - -
7,105,260$ 8,701,056$ 7,951,784$ 4,995,932$ 5,043,203$ 33,797,235$
Page 122
Cap
i
t
a
l
Im
p
r
o
v
e
m
e
n
t
Pl
a
n
&
O
p
e
r
a
t
i
n
g
B
u
d
g
e
t
Infrastructure
Specific Plans
Water System
Plan
Adopted 2019
Transportation
Plan
Adopted 2019
Next update 2028
Sanitary Sewer
Plan
Adopted 2019
Next update 2028
Water and
Natural
Resources
Management
Plan
Adopted 2019
Parks, Trails and
Open Space Plan
Last update 2015
Next update 2026
Citywide
Planning
20
4
0
Co
m
p
r
e
h
e
n
s
i
v
e
P
l
a
n
/
L
a
n
d
U
s
e
P
l
a
n
Ad
o
p
t
e
d
2
0
2
0
Ne
x
t
U
p
d
a
t
e
2
0
2
8
En
v
i
s
i
o
n
L
a
k
e
v
i
l
l
e
2
0
4
0
La
s
t
U
p
d
a
t
e
d
2
0
2
3
Studies & Site
Specific
Plans/REPORTS
Sanitary Sewer and Water
Rates & Fees Study
(Last Update 2017)
Water Treatment Facility
Expansion Plan
(Last Update 2022)
CMF Expansion Study
(Last Update 2015)
Dakota County East-West
Corridor Preservation Study
(Phase 1: 2003 / Phase 2: 2006)
Pedestrian Crossing Study
(2024)
Park Dedication
Fee Study
(Last update 2012)
Various Park Master Plans
(As needed)
CSAH 60/64 Alignment Study
(2026)
Downtown Development
Guide
(Last Update 2018)
Indoor Athletic Facility Study
(2017)
2027 Projects
Pavement
Maintenance
Local Street
Rehabilitation
Arterial/Collector
Rehabilitation
County Pavement
Preservation and
City Utility Repairs
215th Street
Public Improvements
Dodd Boulevard
Public Improvements
Freight Rail Car &
Transload Facility
Lake Marion
Greenway
Water Quality and
Water Conservation
Lake Management
Stormwater
Infrastructure
Maintenance
Forestry
Vegetation
Management
East Community Park
Various other park
projects
NOTES: not all
2027 CIP
projects are
listed here
(only
Highlights)
City and Dakota
County
Partnership
Projects Are
Subject to
Adopted Dakota
County 2040
Transportation
Plan Cost Share
Policies.
(Revised in 2020)
Fire Resource and Space
Needs Study
(Last Update 2020)
School Road Safety Task
(2014)
Dakota County Principal
Arterial Study
(2018)
Dakota County Pedestrian
Crossing Safety Assessment
(2022)
MnDOT I-35 Roadway Study:
Burnsville and Lakeville
(2024)
Strategic Plan for Economic
Development
(Last Update 2019)
Dakota County School Travel
Safety Assessment
(2021)
Trail Condition Review (OCI)
(2022)
Cedar Ave Environmental
Assessment
(2009)
ADA Transition
Plan
Last update 2019
Next update 2028
!H
!H
!H
!H!H!H
!H
!H
!H
!H
!H
!H
162ND ST W
KEN
W
OO
DTRL
160TH ST W
210TH ST W
DO
D
D
B
L
V
D
CE
DAR
AVE
185TH ST W
215TH ST W
179TH ST W
KENW
OOD
TRL
179TH ST W
JUNI
P
E
R
W
A
Y
DODD BLVD
185TH ST W
PI
L
O
T
K
N
O
B
R
D
KE
N
RI
C
K
A
V
E
202ND ST W
200TH ST W
28-03
28-03
27-03
27
-
0
3
27-03
29
-
0
3
29-03
30-03
25-05
27-01
27-01
27-02
27-02
27-01
27-02
27-01
28-02
28-02
28-02
28-02
28-02
28-16
26-05
29-02
29-02
29-02
29-02
22-16
27-05
27-11
27-0628-0628-07
27-07
30-05
26-05
29-04
29-04
31-08
30-02
30-02
30-02
30-02
31-02
31-02
31-02
35
5
50
23
9
31
60
46
70
Kingsley Lake
Lee
Lake
Orchard Lake
Ea
s
t
L
a
k
e
Lake Marion
27-09
26-04 27-10
26-04
28-04 31-07
City of Lakeville
2027 - 2031 CIP
P:\Projects\Construction Services\CIP Maps\CIP Maps.aprx
5
20312030
202920282027
Local Street Reconstruction
County Pavement Preservation
Collector Roadway Rehabilitation
County Roadway Expansion/
Modernization