HomeMy WebLinkAbout84-163 CITY OF LAKEVILLE
RESOLUTION
Date November 26, 1984 Resolution No. 84-163
Motion by Harvey Seconded by Nelson
RESOLUTION ORDERING PUBLIC IMPROVEMENT, APPROVING
PLANS AND SPECIFICATIONS AND .AUTHORIZING WORK TO PROCEED
FOR IMPROVEMENT PROJECT 84-10, LAKE MARION OUTLET CONTROL
BE IT RESOLVED by the Council of the City of Lakeville, Minnesota:
1. Such improvements are hereby ordered in accordance with the
feasibility report for the Lake Marion Outlet Control, prepared by
Consulting Engineers Diversified, dated October 8, 1984.
2. The plans and specifications for the making of such improve-
ments for phase one dated November 21, 1984, are approved.
3. The low quote .from W.G.. Rehbein Construction is hereby ap-
proved, and the Mayor and City Clerk are authorized to sign the con-
struction agreement.
4. The contractor will be authorized to proceed subject to
approval of the plans by the Minnesota Department of Natural Resources
and receipt by the City of a signed right of entry from the property
owners.
5. The City requests the Minnesota Department of Natural Resources
to set the permanent lake outlet at 982.1 M.S.L.
6. That a rough fish barrier be included in the phase two project
in the spring of 1985.
7. That the City continue to monitor the lake levels and outlet
flow.
8. That the-City Council sets as a City policy that no change be
made in the existing underground storm sewer system beginning with .the
two 15" culverts near the old Lakeville police station and going east to
the outlet near Trunk Highway 50 without first holding a public hearing
by the. City Council and submitting plans to the Vermillion River
Watershed Management Organization.
9. The City Attorney is authorized to commence condemnation to
acquire the necessary parcels of land for the project.
APPROVED AND. ADOPTED this 26th day of November, 1984.
CITY OF LAKEVILLE
BY:
Duane Zaun, Ma r
ATTEST:
Patrick E. McGarvey, City Cler
2